1 Waverley Elementary School Feasibility Study FREDERICK COUNTY PUBLIC SCHOOLS Feasibility Study Meeting #6 January 18,
2 AGENDA 1. PROJECT OVERVIEW schedule 2. 1/11 COMMUNITY MEETING recap of Community Meeting, review of Community feedback/ overall response 3. FEASIBILITY STUDY OPTIONS a. Miscellaneous follow up items b. Updated schemes 1019 Waverly Building Renovation/ Addition w/ L shaped classroom wing 1019 Replacement Building w/ split primary-intermediate classroom wings c. Construction phasing/ swing space strategies 2
3 FEASIBILITY SCHEDULE NOV DEC JAN FEB MAR Building/ Site Analysis Community Visioning Session (12/11/17) Develop Concept Options 50% Community Presentation (1/11/18) Refine Concept Options 95% Community Presentation (2/15/18) Feasibility Study Report 3
4 COMMUNITY MEETING #2 4
5 COMMUNITY MEETING #2 5
6 COMMUNITY MEETING FEEDBACK Building Layout Site Plan Process Comments / Questions 2 Story building would be difficult for Teachers to maneuver with mobile carts Compact floor plan provides better access for Special Ed teaching Bigger area may need more surveillance Smaller ground floor footprint will not make building feel like a High School Larger building could lead to too many students in the future Adequate Community Use space Adult use Restrooms in all parts of school Location of building in proximity to surrounding houses adequate distance away for safety, sound Parking close to street rather than far into site Building at back of site would be more of a distance for walkers from East Outdoor congregation space play and evacuation areas Green space vs. hardscape surfaces field at back of site away from entrance drive Redistricting fears of being relocated Length of Construction the shorter the better Costs cheaper to build new? When do Rock Creek students get relocated, where are they going? 6
7 COMMUNITY MEETING #2 Community Meeting #2 Questions: 49 responses 1. Do you prefer a large school or a small school? Large = 45 (92%) Small = 4 (8%) 2. Do you want to keep your existing school and renovate it or do you want a replacement school? Renovate = 7 (14%) Replace = 42 (86%) 3. Is it worthwhile to you to reuse parts of the Waverley or Rock Creek building even if construction will take an additional 6 to 12 months? Yes = 21 (43%) *note, some of the Yes responses also preferred a Replacement school in Question #2 No = 25 (51%) Depends = 3 (6%) 4. Do you prefer the building to be closer to the street or closer to the back of the site (near the homes)? Close to street = 22 (45%) Back by homes = 24 (49%) In the middle / no preference = 3 (6%) 5. Do you prefer to have parking near the street or behind the building? Near the street = 26 (53%) Behind the building = 17 (35%) Both sides = 3 (6%) No response, no preference = 3 (6%) 6. Do you like the idea of a more spread-out one-story building or a more compact two-story building? One story = 10.5 (21%) Two story = 37.5 (77%) PreK 2nd Grades, 1 story. 3 5th Grades, 2 story = 1 (2%) 7
8 CLASSROOM TEST FIT STUDY Reuse for swing space during Waverley building renovation/ addition work in lieu of additional portables Minimal renovation clean and repaint SF (not counting Toilet Room) SWING SPACE SAMPLE CLASSROOM LAYOUT DEMOLISHED WALLS Renovate as part of the Rock Creek renovation/ addition option Demolish non-bearing walls as necessary for new layout SE RES PLAN For reference Typical classrooms in Butterfly Ridge range between SF (not counting Toilet Room) and are approximately 25 x 34 ROCK CREEK KEYPLAN RENOVATION SAMPLE CLASSROOM LAYOUT 710 SF (not counting Toilet Room) 8
9 DESIGN OPTIONS Waverley Building Renovation-Addition Option 2 (1019 Students) Demolish west classroom wing Reconfigure cafeteria/ gym wing Reconfigure central classroom wing New two-story classroom addition New gym addition Demolition 9,500 GSF (+/-) Reconfigured/ renovated 44,500 GSF (+/-) New construction 92,500 GSF (+/-) SWM Existing Addition Addition Car parking (80) Car parking (100) Field SITE PLAN 9
10 DESIGN OPTIONS Waverley Building Renovation-Addition Option 2 (1019 Students) Community Entry Entry Pros: Reuses 2 of 3 existing wings New construction allows for second floor expansion Addition has better ceiling height for classes New right sized gym SECOND FLOOR PLAN Cons: Inefficiencies due to renovation of existing spaces Classrooms in existing wing lack natural light without major renovation of the façade Complex phasing because of the need to renovate kitchen/dining area while it is being used Longer distance from some classrooms to cafeteria/ gym Longest distance in existing Waverley is 280 Layout may prohibit use of Rock Creek building as swing space 525 FIRST FLOOR PLAN 10
11 DESIGN OPTIONS Replace Waverley Building Option 3 (1019 Students) Demolish Rock Creek building New building on former Rock Creek building location Demolish Waverley building and redevelop site as outdoor play areas and additional parking Ground Floor 104,500 GSF (+/-) Second Floor 31,500 GSF (+/-) SWM Car parking (130) Car parking (50) New School Service Field SITE PLAN 11
12 DESIGN OPTIONS Replace Waverley Building Option 3 (1019 Students) Entry Community Entry Entry Pros: Classroom wings clustered by primary and intermediate grades Common spaces centrally located between classroom wings New right sized program means more efficient building Very defined public-private area. Allows for easy closing of classroom wing so that the community can use the rest building Centered Main Entry w/ secondary entry to PK-1 wing Can be built while the students are still using the Waverley building FIRST FLOOR PLAN Cons: Demolishing 2 schools Longer distance from some classrooms to cafeteria/ gym SECOND FLOOR PLAN 12
13 CONSTRUCTION PHASING Replace Waverley Building Option 1 (725 Students) 32 Parking Spaces Phase 1 Demolish Rock Creek building Phase 2 Build replacement school and associated site work 45 Parking Spaces Phase 3 Demolish Waverley building and complete sitework Construction Schedule: Months Approximate Line of Construction Area 77 Parking Spaces CONSTRUCTION PHASING DIAGRAM 13
14 CONSTRUCTION PHASING Replace Waverley Building 74 Parking Spaces Option 2 (725 Students) 64 Parking Spaces Phase 1 Demolish Rock Creek building Phase 2 Build replacement school and associated site work 45 Parking Spaces Phase 3 Demolish Waverley building and complete sitework Construction Schedule: Months Approximate Line of Construction Area CONSTRUCTION PHASING DIAGRAM 14
15 CONSTRUCTION PHASING Waverley Building Renovation-Addition 74 Parking Spaces Option 1 (725 Students) (1019 Student Option would have similar phasing) Phase 1 Add new portables Demolish existing west classroom wing Build new two-story classroom addition 45 Parking Spaces Phase 3 Phase 2 Phase 4 Phase 2 Build new entry vestibule Build new gym addition Phase 3 Reconfigure cafeteria/ gym wing Reconfigure central classroom wing Approximately 8 CR Portables to be added for Swing Space Phase 1 Phase 4 Demolish Rock Creek building Complete sitework Construction Schedule: Months 32 Parking Spaces CONSTRUCTION PHASING DIAGRAM 15
16 CONSTRUCTION PHASING Rock Creek Building Renovation-Addition Option 1 (725 Students) 32 Parking Spaces Phase 1 Renovation/ Addition to Rock Creek building and associated site work 45 Parking Spaces Phase 2 Demolish Waverley building and complete sitework Construction Schedule: Months Approximate Line of Construction Area 77 Parking Spaces CONSTRUCTION PHASING DIAGRAM 16
17 CONSTRUCTION PHASING Replace Waverley Building Option 1 (1019 Students) 32 Parking Spaces Phase 1 Demolish Rock Creek building Phase 2 Build replacement school and associated site work 45 Parking Spaces Phase 3 Demolish Waverley building and complete sitework Construction Schedule: Months Approximate Line of Construction Area 77 Parking Spaces CONSTRUCTION PHASING DIAGRAM 17
18 CONSTRUCTION PHASING Replace Waverley Building 74 Parking Spaces Option 2 (1019 Students) 60 Parking Spaces Phase 1 Demolish Rock Creek building Phase 2 Build replacement school and associated site work 40 Parking Spaces Phase 3 Demolish Waverley building and complete sitework Construction Schedule: Months Approximate Line of Construction Area CONSTRUCTION PHASING DIAGRAM 18
19 CONSTRUCTION PHASING Replace Waverley Building Option 3 (1019 Students) 46 Parking Spaces Phase 1 Demolish Rock Creek building Phase 2 Build replacement school and associated site work 40 Parking Spaces Phase 3 Demolish Waverley building and complete sitework Construction Schedule: Months Approximate Line of Construction Area No access to rear parking Lot CONSTRUCTION PHASING DIAGRAM 19
20 CONSTRUCTION PHASING Waverley-Rock Creek Building Renovation-Addition Option 1 (1019 Students) 10 Parking Spaces 62 Parking Spaces Phase 1 Renovation/ Addition to Rock Creek building and associated site work Phase 2 Reconfigure central classroom wing Reconfigure west classroom wing Build connecting link between Rock Creek and Waverley buildings 45 Parking Spaces Phase 3 Phase 2 Phase 1 Phase 3 Demolish Waverley building gym/ cafeteria and complete sitework Construction Schedule: Months No access to rear parking Lot Approximate Line of Construction Area CONSTRUCTION PHASING DIAGRAM 20
Tisbury Elementary School
SLIDE TITLE Slide Sub Title Building Committee Presentation for: Tisbury Elementary School MAY 10, 2017 AGENDA 1. Discussion of Options 1. Addition / Renovation (Site, Phasing, Plans) 2. New 2 Story School
More informationAshby, Pepperell, Townsend North Middlesex Regional High School. Preferred Schematic Report Update
Ashby, Pepperell, Townsend North Middlesex Regional High School Preferred Schematic Report Update June 3, 2013 AGENDA Preferred Schematic Report (PSR) Options Review Criteria and Goals Project Costs Factors
More informationPOTOMAC ELEMENTARY SCHOOL MODERNIZATION STUDY PTA PRESENTATION MAY 15, 2013
Montgomery County Public Schools POTOMAC ELEMENTARY SCHOOL MODERNIZATION STUDY PTA PRESENTATION MAY 15, 2013 Jim Henderson, AIA, LEED BD+C Managing Principal Meeting Schedule Work Session #1 February 6,
More informationM E E T I N G NOT E S
M E E T I N G NOT E S April 17, 2013 DATE PROJECT : Wayside Elementary School Modernization Schematic Design - Community Meeting #3 PROJECT NO. : 530275.000 CC : Shawn Benjaminson Cindy Ponafala Phill
More informationMISSOULA COUNTY PUBLIC SCHOOLS STRATEGIC FACILITIES PLAN DRAFT ASSESS/EXPLORE REPORT December 3, 2013
EX 12 Subcommittee Review of Undeveloped Sites, Leased Facilities and District Administration Buildings A subcommittee of the Steering Committee reviewed the undeveloped sites, leased facilities and District
More informationGREAT FALLS HIGH SCHOOL MASTER PLAN. GFHS Master Plan Task Force
GREAT FALLS HIGH SCHOOL MASTER PLAN GFHS Master Plan Task Force Serving our community for over 80 years! Overriding premise: Retain GFHS Architectural Integrity Infrastructure Issues 1) Heat, ventilation,
More informationProfessional Building. Seneca, SC 1765 BLUE RIDGE BOULEVARD
1st CHOICE REALTY and JESSE YOUNCE, REALTOR PRESENT Professional Building Seneca, SC 1765 BLUE RIDGE BOULEVARD Seneca, SC Professional Building Multi Use Building 3 Lots Seneca, SC 29672 ONE GREAT OPPORTUNITY
More informationHardwick State of the Town Forum & Charrette Summary
Hardwick State of the Town Forum & Charrette Summary May 2014 Introduction The purpose of this report is to summarize the positions of approximately 50 residents of Hardwick provided at a State of the
More informationUpper Dublin Public Library. Master Plan Presentation for: 520 Virginia Drive
Master Plan Presentation for: 520 Virginia Drive May 22, 2018 Design Presentation Agenda Master Plan Design for 520 Virginia Drive Existing Conditions & Opportunities Project Goals Site Plan & Floor Plans
More informationNew Hope-Solebury School District Campus Revitalization Plan
Campus Revitalization Plan 20 January 2016 GODSHALL KANE O ROURKE ARCHITECTS, LLC 12 East Butler Avenue, Suite 205, Ambler, PA 19002 T: 215.646.2003 F: 215.646.5707 www.gkoarchitects.com Site Rendering
More informationRGM Architects. Eduardo Mata Elementary School
Insert Google Map Image Overall Scope ADA Improvements Exterior site upgrades Roof replacement Restroom upgrades Kitchen upgrades Mechanical, electrical, and plumbing upgrades Fire alarm and Life Safety
More informationHousing Conservation District Advisory Group
Housing Conservation District Advisory Group Inaugural Meeting January 31, 2018 Welcome and Thank You! Purpose of the HCDAG: Help County staff assess and refine proposed Housing Conservation District incentives.
More informationHIGHTSTOWN MUNICIPAL COMPLEX
HIGHTSTOWN MUNICIPAL COMPLEX THE HISTORY Hurricane Irene hits Hightstown Borough on August 27 th 2011 Major Flooding and Flood Damage Downtown Local Businesses Fire Department Municipal Building Police
More informationHopkinton Public Library Feasibility Study
The Center School [parcel U17-42-0] which is separated into two roughly equivalent areas by parcels U17-49-0 and U17-50-0, which make up a 100 foot right-of-way. The front portion of the site, southwesterly,
More informationOPTION 1 MAX RENOVATION/ADDITION
OPTION 1 MAX RENOVATION/ADDITION MASSING TWO STORY NEW ADDITION OUTDOOR CLASSROOM ON ROOF MULTI PURPOSE ROOM ADDITION PARKING PLAY AREA 1886 HISTORIC BUILDING 12TH PLACE NE C ST NE 13TH ST NE CONSTITUTION
More informationFUMC Research Task Force Site Visit Report Westminster Presbyterian Church, Alexandria April 14, 2015
FUMC Research Task Force Site Visit Report Westminster Presbyterian Church, Alexandria April 14, 2015 General Westminster Presbyterian Church was built in three phases, like Fairlington UMC: original sanctuary
More informationProperty Acquisition 56 Grove Avenue
Property Acquisition 56 Grove Avenue Background In 2016, discussion before the Council as to the current condition of Fire Station #2 created discussion about the current deteriorating condition of the
More informationQuestions and Answers about Neighborhood Conservation Districts
Questions and Answers about Neighborhood Conservation Districts NEIGHBORHOOD CONSERVATION Planning Department Housing and Neighborhood Services NCD@townofchapelhill.org (919) 968-2728 Questions about Neighborhood
More informationAvalonBay Communities + BRIDGE Housing. Mission Housing Habitat for Humanity Pacific Union Development Corporation
AvalonBay Communities + BRIDGE Housing Mission Housing Habitat for Humanity Pacific Union Development Corporation CAC Workshop #3 Agenda Recap of discussion from 12/11/17 CAC meeting Housing types and
More informationCrenshaw/LAX Transit Project Joint Development Fairview Heights Community Workshop #2 April 30, 2016
Crenshaw/LAX Transit Project Joint Development Fairview Heights Community Workshop #2 April 30, 2016 1 Agenda 1. Introduction 2. What is Joint Development? 3. Community Input Process 4. What We ve Heard
More informationPurpose of Workshop. Scope project to be included in a Design Build RFP Review Program Needs Site Analysis Concept Plans
Purpose of Workshop Scope project to be included in a Design Build RFP Review Program Needs Site Analysis Concept Plans Workshop Process Second Workshop Present Preferred Scheme Revisions Solicit Comment
More informationYMCA Property Discussion. City Council Study Session April 10,
YMCA Property Discussion City Council Study Session April 10, 2018 1 Council Discussion Items Questions for City Council: 1. Shall the City Council authorize staff to re-negotiate the terms of the Recreational
More informationHOUSING ELEMENT GOALS, OBJECTIVES, & POLICIES
HOUSING ELEMENT GOALS, OBJECTIVES, & POLICIES GOAL H-1: ENSURE THE PROVISION OF SAFE, AFFORDABLE, AND ADEQUATE HOUSING FOR ALL CURRENT AND FUTURE RESIDENTS OF WALTON COUNTY. Objective H-1.1: Develop a
More information224 South Allen Street Reuse or Redevelopment Update on the site, proposals and process for discussion
224 South Allen Street Reuse or Redevelopment Update on the site, proposals and process for discussion Joint meeting of State College Borough Council, Planning Commission and Redevelopment Authority March
More informationApproval of Takoma Amended Joint Development Agreement
Planning, Program Development and Real Estate Committee Item IV- A October 10, 2013 Approval of Takoma Amended Joint Development Agreement Washington Metropolitan Area Transit Authority Board Action/Information
More informationCITY OF VANCOUVER POLICY REPORT DEVELOPMENT AND BUILDING
P2 CITY OF VANCOUVER POLICY REPORT DEVELOPMENT AND BUILDING Report Date: May 1, 2007 Author: Michael Naylor Phone No.: 604.871.6269 RTS No.: 06621 VanRIMS No.: 11-3600-10 Meeting Date: May 15, 2007 TO:
More informationEquality and Access Plan The Abbey School, Reading
Equality and Access Plan 2017-2020 The Abbey School, Reading , Reading Accessibility Plan Scope The School recognises the benefits of a diverse School Community, with individuals who value one another
More informationUpdate on the New Avondale Public School
Community Meeting Update on the New Avondale Public School Monday, May 26, 2014 Agenda. Time: 7:00 8:30 p.m. Moderator: Manon Gardner 1. Welcome, Introductions and Purpose of Meeting Manon Gardner TDSB,
More informationApproval of Takoma Amended Joint Development Agreement and Compact Public Hearing
Planning, Program Development and Real Estate Committee Item IV - B March 13, 2014 Approval of Takoma Amended Joint Development Agreement and Compact Public Hearing Washington Metropolitan Area Transit
More informationTruax Park Apartments
Truax Park Apartments Master Planning and Site Development Study Prepared by The Community Development Authority of the City of Madison In association with SMITH & SMITH ASSOCIATES, Inc CONSTRUCTION COST
More informationASBESTOS PERIODIC SURVEILLANCE CHECK LIST
DATE OF SCHOOL: Effingham County Board Office SURVEILLANCE 1. SURFACING: 2010 Plaster in hallway NO This building has been completely renovated for the board office. The plaster has been covered with paneling
More information1 Application Form 4
1 Application Form 4 5 2 Project Summary Location The proposed development is located at 216 Cobequid Road in Sackville, Nova Scotia. Site Characteristics The mixed-use development is situated on the corner
More informationDiscussion Paper 2: Lot Sizes and Housing Affordability. Township of Lake of Bays Official Plan Review
Discussion Paper 2: Lot Sizes and Housing Affordability Township of Lake of Bays Official Plan Review 1 Context The Township of Lake of Bays has strong policies in the Official Plan to avoid the inefficient
More informationPocatello High School New Building Addition Board Interview
Pocatello High School New Building Addition Board Interview 9.6.2018 Agenda Introduction The Team Project Team Expectations Related Experience The Scope Building Site(s) The Site The Building / Site The
More informationGlendale Municipal Golf Courses Glen Lakes Analysis. City Council Workshop November 13, 2018
Glendale Municipal Golf Courses Glen Lakes Analysis City Council Workshop November 13, 2018 Today s Presentation Notice of Violation Temporary Golf Course Operations Maintenance Building & Irrigation System
More informationSubject: Addendum No. 2 Request for Expressions of Interest (RFEI) for Development of Brooklyn College School of Business.
Subject: Addendum No. 2 Request for Expressions of Interest (RFEI) for Development of Brooklyn College School of Business. Date: August 9, 2018 Facilities Planning, Construction, and Management Office
More informationFLAG LOT PILOT
FLAG LOT PILOT 2017 1 BACKGROUND Action 10 in Edmonton s Infill Roadmap (2014) is to Identify and support a range of pilot projects that explore creative and new forms of infill in order to provide learning
More informationZoning Options. Key Questions:
Zoning Options This section explores zoning options to encourage Character Home retention and improve size and compatibility of new homes in the study areas. Options being explored include: A Floor Area
More informationSt. Charles High School Emergency Plan Instructions. Fire Drill Evacuation Procedures
Keep the following items in this folder: St. harles High School Emergency Plan Instructions urrent class rosters (student names only, update quarterly) School Emergency Plan for St. harles High School
More informationLINCOLN CORRIDOR REDEVELOPMENT PROJECT UPDATE FOR DOWNTOWN GATEWAY FOCUS AREA
ITEM: 51 BACKGROUND: Staff Report LINCOLN CORRIDOR REDEVELOPMENT PROJECT UPDATE FOR DOWNTOWN GATEWAY FOCUS AREA March 27, 2018 The City has been working for two years to develop, adopt, and implement the
More informationIn your opinion, what opportunities do you think should be considered in this process? (Describe up to 3)
Working Group Meeting #1: Orientation June 21, 2014 (Comments updated 7.9.14) Thanks for your help and your ideas! In your opinion, what opportunities do you think should be considered in this process?
More informationMemorial Northwest Homeowners Association Master Plan Project Phasing
Memorial Northwest Homeowners Association Master Plan Project Phasing October 2011 Contents Master Plan Key Learning s Construction Phasing Construction Phasing Issues Project Estimates Project Financing
More informationWashington Municipal Building- Feasibility Study
Existing Municipal Building Existing Former Library 1 Washington Municipal Building- Feasibility Study February 11, 2014 Table of Contents Option Summary.............................. 3 Option 1...................................
More informationVillage of Glenview Plan Commission
Village of Glenview Plan Commission STAFF REPORT March 24, 2015 TO: Chairman and Plan Commissioners CASE #: P2015-012 FROM: Community Development Department CASE MANAGER: Michelle House, Planner SUBJECT:
More informationDowntown Development Focus Area: I. Existing Conditions
Downtown Development Focus Area: I. Existing Conditions The Downtown Development Focus Area is situated along Route 1, south of the train tracks, except for the existing Unilever property. It extends west
More informationReal Estate Strategic Plan: Port Commission Final Presentation
Item No. 7a_supp Date of Meeting October 25 th, 2016 Real Estate Strategic Plan: Port Commission Final Presentation October 25 th, 2016 1 Overview I. Real Estate Plan Objectives II. Real Estate Development
More informationFREEHOLD BOROUGH SCHOOL DISTRICT. Proposed Referendum Schematic Designs & Preliminary Costs
FREEHOLD BOROUGH SCHOOL DISTRICT Proposed Referendum Schematic Designs & Preliminary Costs Introduction The foundation of every state is the education of its youth. - Diogenes Laertius Greek Philosopher
More informationTO MEMBERS OF THE FINANCE AND CAPITAL STRATEGIES COMMITTEE: DISCUSSION ITEM
F13 Office of the President TO MEMBERS OF THE FINANCE AND CAPITAL STRATEGIES : For Meeting of DISCUSSION ITEM ORCHARD PARK FAMILY HOUSING AND GRADUATE STUDENT HOUSING REDEVELOPMENT PROJECT AND WEST VILLAGE
More informationChairman Schreiber noted there was a sign up sheet at the back of the room for anyone wishing to sign up for library activities and s.
Page 1 of 6 The held a Public Informational Meeting on Saturday, January 11, 2014, at the Chester Meeting House, 4 Liberty Street, Chester, Connecticut. Chairman Terry Schreiber called the meeting to order
More informationTriangle Special Planning Area Update. Community Workshop #5 September 17, 2018
Triangle Special Planning Area Update Community Workshop #5 September 17, 2018 Welcome and Introductions Recap of the Project and Discussion to Date Meeting Agenda Review Draft SPA Revisions Discuss Outstanding
More informationCapital Placement and Approach to Value Creation. Real Estate Strategy and Leasing Conference
Capital Placement and Approach to Value Creation Real Estate Strategy and Leasing Conference Industrial Property, Brampton ON Adding Value Through Redevelopment & Excess Land Severance EXCESS LANDS LaSalle
More informationThe University of Massachusetts Campus Master Plan. Faculty Senate April 21st
The University of Massachusetts Campus Master Plan Faculty Senate April 21st Update on process and schedule 2011 Summer 2012 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
More information3928 Lorain Avenue. Cleveland, Ohio 44113
3928 Lorain Avenue Cleveland, Ohio 44113 9,441 SF building plus 3,882 SF basement Mixed Use building for Sale or Lease In line retail space with excellent frontage and visibility on Lorain Avenue 2nd and
More informationCounter urbanisation
Counter urbanisation Population Movement Urbanisation Counter - Urbanisation Gentrification / Suburbanisation What is it? The process of people moving away from urban areas to smaller settlements and rural
More informationGym Capacity: 710. Stage. Auditeria Capacity: 390. New Bleachers
New Bleachers Gym Capacity: 710 Stage Auditeria Capacity: 390 Enlarged plan of new stage configuration showing greater seating capacity of the gym vs. that of the auditeria Proposed 2018 Bond Projects
More informationFAQs: Living or developing in a Historic District
FAQs: Living or developing in a Historic District Q. How do I know if the historic district guidelines apply to my property? A. The guidelines apply if you have a contributing structure and may apply if
More informationSARPY COUNTY BOARD OF ADJUSTMENT MINUTES OF MEETING May 14, 2015
l. CALL MEETING TO ORDER SARPY COUNTY BOARD OF ADJUSTMENT MINUTES OF MEETING May 14, 2015 A meeting of the Board of Adjustment of Sarpy County, Nebraska was convened in open and public session at the call
More informationCOMMITTEE OF ADJUSTMENT CASE
COMMITTEE OF ADJUSTMENT CASE 30 Clubhouse Road, Woodbridge October 19, 2017 Prepared for: Jason Gabriele 78 Rushworth Cres Kleinburg, Ontario LOJ1C0 Prepared by: FRANKFRANCO ARCHITECTS T 647.749.0557 E
More informationThe Effective Analyst: From Research to Execution. Contents are subject to change. For the latest updates visit
The Effective Analyst: From Research to Page 1 of 8 Why Attend Solving problems in the business world is essential to keeping things moving along smoothly. While problems differ in complexity, almost all
More information100% LEASED OFFICE BUILDING FOR SALE 450 GRANT STREET AKRON, OHIO ADJACENT TO UNIVERSITY OF AKRON
OFFICE BUILDING FOR SALE 450 GRANT STREET AKRON, OHIO ADJACENT TO UNIVERSITY OF AKRON 100% LEASED Property Highlights 2-Floor Professional Office Building adjacent to University of Akron and downtown Akron.
More informationINTRODUCTION TO HOUSING LDC AMENDMENTS
INTRODUCTION TO HOUSING LDC AMENDMENTS August 6, 2018 BACKGROUND The City is participating in a regional affordable housing initiative Staff presented the City s overall strategy at the March 2018 MPB
More informationYolo County Workshop October 27, 2003
Yolo County Workshop October 27, 2003 WHAT YOU WILL DO TONIGHT Learn results of Yolo County Neighborhood Workshops Analyze pro and cons of four scenarios for Yolo County s future through 2050 Choose the
More informationHARRISON COUNTY BOARD OF EDUCATION BOND ELECTION ORDER
HARRISON COUNTY BOARD OF EDUCATION BOND ELECTION ORDER AN ORDER OF THE BOARD OF EDUCATION OF THE COUNTY OF HARRISON DIRECTING THAT A SPECIAL ELECTION BE HELD FOR THE PURPOSE OF SUBMITTING TO THE VOTERS
More informationPartnership Pro Forma
Partnership Pro Forma Property: The RealData Building 612 Old Post Road Southport, CT 06824 Prepared For: Patricia G. Partner Prepared By: Northwood Development, LLC 16554 Maple Street Southport, CT 06890
More informationSummary of Findings. Community Conversation held November 5, 2018
Summary of Findings Housing and the Future of Lebanon: What types of homes do we need in Lebanon to have a thriving community for all who live or work here? Community Conversation held November 5, 2018
More informationIf the address on this form is different than the address of the building, submit a written explanation.
ILLINOIS DEPARTMENT OF PUBLIC HEALTH AHERA THREE YEAR REINSPECTION ASBESTOS ABATEMENT PROGRAM SCHOOL INFORMATION FORM SECTION I NAME OF SCHOOL DISTRICT: SCHOOL ID NUMBER: ADDRESS OF SCHOOL: CITY: CHICAGO
More informationHOUSING ELEMENT. 3. group and foster home construction. 1. increase the supply of new affordable housing with: a regional housing trust fund;
Goal 8.0. Facilitate an adequate supply of decent, safe, and sanitary housing in suitable neighborhoods, including housing for special needs populations; available in a range of housing types, architectural
More informationRule of corner may need to be flexible i.e. context school, park. With a clustered approach. Should row housing go where fourplexes are?
Fourplex Privacy Traffic issues by school (don t locate next to school) Highest density is furthest from park and school. Is this best? Family friendly (i.e. private green space, nicely designed, etc.)
More informationSTAFF SUMMARY OF Z17-10 CONDITIONAL ZONING DISTRICT APPLICATION
STAFF SUMMARY OF Z17-10 CONDITIONAL ZONING DISTRICT APPLICATION APPLICATION SUMMARY Case Number: Z17-10 Request: Conditional B-2 Zoning District in order to expand an existing retail and warehousing business
More informationCUMBERLAND SCHOOLS WORK PROPOSED 2018
Cost Ashton Elementary School 2 2 Replace HVAC $ 375,000.00 5 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 2 3 Various Technological Improvements $ 191,258.00 2 4 Replace Plumbing Fixtures
More informationBUILDING STATISTICS SUMMARY Period From: Jan Year: 2018
Period From: Jan 01-31 There were 23 completed. There were 42 issued with a total construction value of SINGLE FAMILY DWELLINGS 8 $4,440,000.00 CARRIAGE HOUSES 0 $0.00 SECONDARY SUITES 2 $65,000.00 Construction
More information2018 APPLICATION FOR URBAN DESIGN REVIEW BOARD City of Des Moines, Iowa
2018 APPLICATION FOR URBAN DESIGN REVIEW BOARD City of Des Moines, Iowa Date Submitted: 3/16/18 Project Information PROJECT NAME & ADDRESS: 418 East Grand Mixed Use Development OWNER/DEVELOPER: Nelson
More informationEIA Model Test 7: R-O to R-O
1 ECONOMIC COST & BENEFIT COMPARISON WORKSHEET 2 Title 21 Land Use Code CELL Cells requiring direct input. 3 Current Code vs. Proposed Code (2007 Public Hearing Draft) COLOR Cells calculated by the model;
More informationBOARD OF ZONING APPEALS MINUTES OF THE PROCEEDINGS OF THE PUBLIC HEARING APRIL 25, 2017
BOARD OF ZONING APPEALS MINUTES OF THE PROCEEDINGS OF THE PUBLIC HEARING APRIL 25, 2017 The hearing was called to order at 7:30 P.M. by Chairman Jones PRESENT: ABSENT: ALSO PRESENT: Board Members Matthew
More information70 Parker Hill Avenue Development. 70 Parker Hill Avenue Mission Hill. Application for Small Project Review Submitted to the
70 Parker Hill Avenue Development 70 Parker Hill Avenue Mission Hill Application for Small Project Review Submitted to the Boston Redevelopment Authority 1 70 Parker Hill Avenue, Mission Hill Application
More informationMembers of the Public in attendance are asked to be recognized by the Mayor before participating in any discussions of the Town Board AGENDA
TOWN BOARD WORK SESSION August 27, 2018 // 5:30 p.m. // First floor conference room 301 Walnut Street, Windsor, CO 80550 GOAL of this Work Session is to have the Town Board receive information on topics
More informationDesign & Access Statement 704 Woolwich Road, London SE7 8LQ February 2018
Design & Access Statement 704 Woolwich Road, London SE7 8LQ February 2018 Moji Karami, BA(hons)Arch CONTENTS 1.0 Introduction 2.0 Executive Summary 3.0 Existing Site and Surrounding Area 4.0 Transport
More informationPort Chester, NY. April 15, 2014 INTRODUCTION.
Port Chester, NY UNITED HOSPITAL SITE Port Chester, NY INTRODUCTION. 1 Project Precedents. Great Place Strategy Example Great Neighborhoods. One. CREATING A NEW, GREAT, MIXED-USE, PORT CHESTER NEIGHBORHOOD...
More informationThe Sharing Economy s Impact on Rural Tourism Case Sample: Estacada Alternative Lodging Project
Photo courtesy of Clackamas River Outfitters 2016 Oregon Governor s Conference on Tourism Terra Wilcoxson, Economic Development Manager City of Estacada, www.cityofestacada.org wilcoxson@cityofestacada.org
More informationLUCAS COUNTY. Downtown Site Analysis. 26 March 2018
LUCAS COUNTY Downtown Site Analysis 26 March 2018 PROGRAM BLOCKING & STACKING A: FACILITY COMMON 01 Entry Area 1,775 02 Staff Services & Training 8,308 Subtotal 10,083 Total CGSF B: SHERIFF'S OFFICE 03
More informationUrban Redevelopment Through Adaptive Reuse: From Blight to Bright
Urban Redevelopment Through Adaptive Reuse: From Blight to Bright The Case for Adaptive Reuse in Pinellas County: Adaptive Reuse is the process of revitalizing older structures for purposes other than
More informationTown of Clinton, Connecticut Action Plan for the Historic Unilever Property and Area. Steering Committee Meeting #5 Implementation Strategies
Town of Clinton, Connecticut Action Plan for the Historic Unilever Property and Area Steering Committee Meeting #5 Implementation Strategies Wednesday, March 19, 2014 6:30pm Steering Committee Meeting
More informationTENANT RELOCATION POLICY
TENANT RELOCATION POLICY Spring 2016 Table of Contents Section 1: Introduction 1 Section 2: Background 2 Section 3: Tenant Relocation Policy 3 Application of the Tenant Relocation Policy 3 Requirements
More informationBOARD OF ZONING APPEALS MINUTES OF THE PROCEEDINGS OF THE PUBLIC HEARING FEBRUARY 27, 2018
BOARD OF ZONING APPEALS MINUTES OF THE PROCEEDINGS OF THE PUBLIC HEARING FEBRUARY 27, 2018 The hearing was called to order at 7:30 P.M. by Chairman Jones PRESENT: ABSENT: ALSO PRESENT: Board Members Matthew
More informationBOARD WORK SESSION Construction Projects Discussion & Superintendent Evaluation MINUTES
District Office 471 NE Ochoco Plaza Dr., Prineville, OR 97754 (541) 447-5664 August 16, 2014 BOARD WORK SESSION Construction Projects Discussion & Superintendent Evaluation DISTRICT ADMINISTRATION OFFICE
More informationBREWERYTOWN CORNER DEVELOPMENT OPPORTUNITY Cecil B. Moore Avenue Philadelphia, PA. Property Rendering CORNER LOCATION
BREWERYTOWN CORNER DEVELOPMENT OPPORTUNITY 2623-25 Cecil B. Moore Avenue Philadelphia, PA. Property Rendering CORNER LOCATION property details Property Overview ADDRESS: 2623-25 Cecil B. Moore Ave. Philadelphia
More informationCHAPTER 7 HOUSING. Housing May
CHAPTER 7 HOUSING Housing has been identified as an important or very important topic to be discussed within the master plan by 74% of the survey respondents in Shelburne and 65% of the respondents in
More informationWorking Group Kick-Off Meeting
June 21, 2014 Wilson School Kick-Off Meeting Study Process Orientation & Walking Tour Presentation Overview 2 of Our Effort Examine planning issues and develop a Vision, Policies, and Recommendations Prepare
More informationCounty Lot C Redevelopment
County Lot C Redevelopment La Crosse County La Crosse, WISCONSIN 03.20.14 Orientation What is the purpose of this process? La Crosse County is exploring ways to maximize the value of Lot C by completing
More informationRBC-Pembina Home Location Study. Understanding where Greater Toronto Area residents prefer to live
RBC-Pembina Home Location Study Understanding where Greater Toronto Area residents prefer to live RBC-Pembina Home Location Study: Understanding where Greater Toronto Area residents prefer to live July
More informationTHE AREA PLAN COMMISSION OF ST. JOSEPH COUNTY, IN AGENDA
THE AREA PLAN COMMISSION OF ST. JOSEPH COUNTY, IN AGENDA Tuesday, June 20, 2017 Fourth-Floor Council Chambers 3:30 p.m. County-City Building, South Bend, IN PUBLIC HEARINGS: 1. Rezonings: A. A combined
More informationCommunity Advisory Committee (CAC) Meeting #7 West Anaheim Youth Center May 26, 2016
Community Advisory Committee (CAC) Meeting #7 West Anaheim Youth Center May 26, 2016 1 Project Team City: David Belmer Planning and Building Director Jonathan Borrego, AICP Planning Services Manager Gustavo
More informationLOT AREA AND FRONTAGE
LOT AREA AND FRONTAGE Lot Area & Frontage for the R2.1 Zone Lot Area & Frontage for the R2.4 Zone Minimum Lot Minimum Lot Zone Area Width R2.1 700 sq m 18 m R2.4 600 sq m 16 m Lot Area means the total
More informationTOWN OF ROCKINGHAM ZONING APPLICATION FORMS INFORMATION SHEET
TOWN OF ROCKINGHAM ZONING APPLICATION FORMS INFORMATION SHEET Rockingham Zoning-Planning Office P.O. Box 370 Bellows Falls VT 05101 Tel. 802-463-1229 www.rockbf.org GENERAL INFORMATION 1. This application
More informationMichigan State University Barrier-Free/Accessibility Project Status Summary December 2017
Projects Completed FY16, FY17 and FY18 (arranged alphabetically) Abrams Planetarium Install automatic door opener on main doors of the Planetarium. Completed: Summer 2016 Cost: $13,000 Bessey Hall 1 st
More informationPLANNING AND DEVELOPMENT SERVICES. Planning Cases. Case Type
PLANNING AND DEVELOPMENT SERVICES Planning Cases Case Type 27 28 29 21 211 Plats 26 13 15 19 3 Site Plans 32 28 1 8 Rezonings 9 4 6 2 1 PDs 1 3 4 1 1 SUPs 3 4 8 8 1 Annexations 4 2 1 Ordinances 17 15 12
More informationTHE REDEVELOPMENT PLAN
PAGE 37 THE REDEVELOPMENT PLAN FUTURE LAND USE The Silver Terrace Redevelopment Area is currently designated as Redevelopment Area #4 on the City of Delray Beach Future Land Use Map (FLUM). This designation
More informationMemorandum. Kenneth Johnstone, Community Development Director. November 25, 2015 (for December 3 Study Session)
Memorandum TO: THROUGH: FROM: DATE: SUBJECT: Planning Commission Kenneth Johnstone, Community Development Director Lisa Ritchie, Planner II November 25, 2015 (for December 3 Study Session) Accessory Dwelling
More informationATTACHMENT A REQUEST/BACKGROUND INFORMATION VENTURA/TYRONE REDEVELOPMENT PROJECT PROJECT OVERVIEW/REQUEST BACKGROUND Ventura Boulevard
Revised October 28, 2016 ATTACHMENT A REQUEST/BACKGROUND INFORMATION VENTURA/TYRONE REDEVELOPMENT PROJECT Sherman Oaks, CA 91423 PROJECT OVERVIEW/REQUEST The Applicant, 14311 Ventura Development, LLC,
More information2016 Annual Report. Enid Public Schools 2016 Bond. February 2017
2016 Annual Report Enid Public Schools 2016 Bond February 2017 Enid Public Schools Strategic Action Plan The initial goals of the Enid Public Schools Strategic Action Plan have been met, and we are well
More information