Facilities Construction
|
|
- Jennifer Gilmore
- 5 years ago
- Views:
Transcription
1 NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction May 2014 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION Bernal Middle School
2 BERNAL MIDDLE SCHOOL (Formerly STEVENS RANCH AREA MIDDLE SCHOOL) Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager Jim Berg Contractor Bartlett Cocke, Inc. Construction Budget - $41,408, Construction Period - January 2013 May 2014 Project Scope New 1200 Student Middle School (93% Complete) MEP infrastructure in progress. Interior Finishes in progress. Site work and play fields in progress. Site paving (parking and drives) are complete. Landscaping in progress. Technology infrastructure in progress. Punch lists are being generated.
3 BERNAL MIDDLE SCHOOL (Aerial May 5, 2014)
4 BERNAL MIDDLE SCHOOL (Perspective of Front Entrance)
5 BERNAL MIDDLE SCHOOL (May 6, 2014)
6 BERNAL MIDDLE SCHOOL (May 6, 2014)
7 BERNAL MIDDLE SCHOOL (May 6, 2014)
8 BERNAL MIDDLE SCHOOL (May 6, 2014)
9 BERNAL MIDDLE SCHOOL (May 6, 2014)
10 ELLISON ELEMENTARY SCHOOL (Formerly CIELO VISTA SOUTH ELEMENTARY) Architect Garza Bomberger Architects Project Architect Roy Lewis, AIA NISD Project Manager Marilyn Sevedge Risk Contractor Joeris General Contractor Construction Budget - $19,877, Construction Period - February 2013 May 19, 2014 (95% Complete) Project Scope 800 Student Elementary School AHJ Inspections, Intrusion Detection, Lock Cores completing punch lists and misc. PR s and controls.
11 ELLISON ELEMENTARY SCHOOL (Aerial March 20, 2014)
12 ELLISON ELEMENTARY SCHOOL (Perspective of Front Entrance)
13 ELLISON ELEMENTARY SCHOOL (May 12, 2014)
14 ELLISON ELEMENTARY SCHOOL (May 12, 2014)
15 ELLISON ELEMENTARY SCHOOL (May 12, 2014)
16 ELLISON ELEMENTARY SCHOOL (May 12, 2014)
17 ELLISON ELEMENTARY SCHOOL (May 12, 2014)
18 REDBIRD RANCH ELEMENTARY SCHOOL Architect Noonan Rittimann Project Architect John Rittimann NISD Project Manager Thomas Curiel Contractor Joeris General Contractor Construction Budget - $20,000, Construction Period February 2014 May 22, 2015 Project Scope New 800 Student Elementary School Site clearing and building layout in progress. Building pad in progress.
19 REDBIRD RANCH ELEMENTARY SCHOOL Aerial View (April 18, 2014)
20 REDBIRD RANCH ELEMENTARY SCHOOL Front Entrance Perspective
21 REDBIRD RANCH ELEMENTARY SCHOOL (May 6, 2014)
22 INSELMANN BASEBALL FIELD (Replacement of Existing Facilities) Architect Garza Bomberger & Associates Project Architect Roy Lewis, AIA NISD Project Manager Christopher Parker Contractor D. Wilson Construction Construction Budget - $2,700, Construction Period May 2014 December 2014 Project Scope Replacement of Existing Field and associated Facilities. Contractor awarded; Negotiations in progress.
23 INSELMANN BASEBALL FIELD (Entry View)
24 INSELMANN BASEBALL FIELD (Bird s Eye View)
25 INSELMANN BASEBALL FIELD (May 6, 2014)
26 KALLISON RANCH HIGH SCHOOL Architect Garza Bomberger & Associates Project Architect Roy Lewis NISD Project Manager Jim Berg Contractor Joeris General Contractor Estimated Construction Budget - $105,000, Tenative Construction Period September 2014 May 2017 Project Scope New 2800 Student High School Design only project at this time. Construction Budget - $105,000, in 2014 Bond
27 KALLISON RANCH HIGH SCHOOL Aerial Plan
28 KALLISON RANCH HIGH SCHOOL Schematic Design Site Plan
29 KALLISON RANCH HIGH SCHOOL Schematic Design Front Entry
30 KALLISON RANCH HIGH SCHOOL Schematic Design Windows
31 KALLISON RANCH HIGH SCHOOL Schematic Design Auditorium
32 SPORTS GYM Architect Marmon Mok Project Architect Monty Howard NISD Project Manager Thomas Curiel Contractor TBD Construction Budget - $19,000, Construction Period - October 2014 October 2015 Project Scope Provide a District-Wide Sports Gymnasium at the Farris Complex. Design only project at this time. Funding - Project to be funded from 2010 Bond Savings.
33 SPORTS GYM Site Plan
Facilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction February 2014 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction August 2015 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT BOND 2010 Facilities Construction Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
More informationKyle Seale MS. Lesile Road ES. Ward ES. Alamo Ranch ES. Potranco West Area HS. Rayburn MS
Kyle Seale MS Lesile Road ES Ward ES Alamo Ranch MS Alamo Ranch ES Potranco West Area HS Stevens Ranch ES John Jay HS Rayburn MS BRENNAN HIGH SCHOOL a. Name and Location of Building: Brennan High School
More informationKyle Seale MS. Kuentz Road ES. Ward ES. Hoffmann ES. Brennan HS. Rayburn MS
Kyle Seale MS Kuentz Road ES Ward ES Alamo Ranch MS Hoffmann ES Brennan HS Langley ES John Jay HS Rayburn MS BRENNAN HIGH SCHOOL a. Name and Location of Building: Brennan High School Potranco West San
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT BOND 2010 Facilities Construction Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction February 2018 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction February 2019 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction January 2019 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction August 2018 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction December 2018 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction October 2017 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction September 2018 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
More informationWednesday, December 6, 2017 Central Office Board Room 6:00 PM
Wednesday, December 6, 2017 Central Office Board Room 6:00 PM OVERVIEW v Updates on: v Scope & Schedule v Contracting of Architects v Staffing v Contractor selection v Master Plan: 2030 2 UPDATE: SCOPE
More information11.79 Acres Prime Development Property
14530 West FM 471, San Antonio, Texas 78254 LOCATION Corner of Culebra Road (FM 471) and Kallison Bend; fronts Culebra Rd (FM 471) west of Loop 1604, between Talley Rd and Hwy 211 in Bexar County, Texas;
More informationLA Unified Real Estate Report
LA Unified Real Estate Report LA Unified Advisory Task Force March 2018 Los Angeles Unified School District Advisory Task Force The LA Unified Advisory Task Force was created to help the Superintendent
More information±19.2 ACRES OF COMMERCIAL TRACTS AND PADS:: FOR SALE
TBPE FIRM REGISTRATION #470 I TBPLS FIRM REGISTRATION #10028800 DR. PAT HENDERSON ELEMENTARY SCHOOL JOHN MARSHALL HARLAN HIGH SCHOOL ±5.9 ACRES ±4.5 ACRES ±8.8 ACRES TALLEY RD FM 471 W SAN ANTONIO I AUSTIN
More informationPOTOMAC ELEMENTARY SCHOOL MODERNIZATION STUDY PTA PRESENTATION MAY 15, 2013
Montgomery County Public Schools POTOMAC ELEMENTARY SCHOOL MODERNIZATION STUDY PTA PRESENTATION MAY 15, 2013 Jim Henderson, AIA, LEED BD+C Managing Principal Meeting Schedule Work Session #1 February 6,
More information2016 Annual Report. Enid Public Schools 2016 Bond. February 2017
2016 Annual Report Enid Public Schools 2016 Bond February 2017 Enid Public Schools Strategic Action Plan The initial goals of the Enid Public Schools Strategic Action Plan have been met, and we are well
More information9.426 AC on Cielo Vista Drive & Babcock Road
Property Highlights Secluded Northwest Hill Country land available for sale Residential Development Land For Sale Frontage on Cielo Vista Drive Easy access from IH-10 & Cielo Vista Drive Situated less
More informationUMass Amherst Design Building Leading the Way with Mass Timber Solutions
UMass Amherst Design Building Leading the Way with Mass Timber Solutions Tom S. Chung, AIA LEED BD+C Principal, Leers Weinzapfel Associates Disclaimer: This presentation was developed by a third party
More informationREQUEST FOR COUNCIL ACTION
COUNCIL AGENDA ITEM L-7 COUNCIL MEETING OF 11/19/13 REQUEST FOR COUNCIL ACTION SUBJECT: Resolution No. 7347 determining that pursuant to Section 15162 of the State s Guidelines implementing the California
More informationPERIODIC PROGRESS REPORT
PERIODIC PROGRESS REPORT Name and Address of Applicant or Certificate Holder: Boys and Girls Home and Family Services, Inc. (dba Boys and Girls Home of Alaska, Inc.) 2101 Court Street PO Box 1197 Sioux
More informationFOCUS ENGINEERING, inc.
FEASIBILITY REPORT for OLD VILLAGE PHASE 3 STREET, DRAINAGE AND UTILITY IMPROVEMENTS RESOULTION RECEIVING REPORT AND CALLING FOR PUBLIC HEARING OLD VILLAGE CIP PHASING PLAN Phase 3 2017. Amount: $ 2,557,000.
More informationTri-Party School Mitigation Agreement between the Enumclaw School District, City of Black Diamond and Yarrow Bay. December 6, 2010
Tri-Party School Mitigation Agreement between the Enumclaw School District, City of Black Diamond and Yarrow Bay December 6, 2010 Review of Timeline Agreement October 26, 2009: Joint announcement of the
More information$65,000,000 PRINCE GEORGE S COUNTY, MARYLAND SPECIAL OBLIGATION BONDS (National Harbor Project) SERIES 2004
$65,000,000 PRINCE GEORGE S COUNTY, MARYLAND SPECIAL OBLIGATION BONDS (National Harbor Project) SERIES 2004 DEVELOPER S CONTINUING DISCLOSURE STATEMENT Attn: Keenan Rice MuniCap 8340 Governor Ridgley Lane
More informationRGM Architects. Eduardo Mata Elementary School
Insert Google Map Image Overall Scope ADA Improvements Exterior site upgrades Roof replacement Restroom upgrades Kitchen upgrades Mechanical, electrical, and plumbing upgrades Fire alarm and Life Safety
More information$92,850,000 PENINSULA TOWN CENTER COMMUNITY DEVELOPMENT AUTHORITY SPECIAL OBLIGATION BONDS, SERIES 2007 DEVELOPER S CONTINUING DISCLOSURE STATEMENT
$92,850,000 PENINSULA TOWN CENTER COMMUNITY DEVELOPMENT AUTHORITY SPECIAL OBLIGATION BONDS, SERIES 2007 DEVELOPER S CONTINUING DISCLOSURE STATEMENT Attn: Keenan Rice MuniCap, Inc. 6760 Alexander Bell Drive,
More informationAshby, Pepperell, Townsend North Middlesex Regional High School. Preferred Schematic Report Update
Ashby, Pepperell, Townsend North Middlesex Regional High School Preferred Schematic Report Update June 3, 2013 AGENDA Preferred Schematic Report (PSR) Options Review Criteria and Goals Project Costs Factors
More informationSCHOOL BOARD ACTION REPORT
SCHOOL BOARD ACTION REPORT DATE: January 3, 2018 FROM: Dr. Larry Nyland, Superintendent LEAD STAFF: Dr. Lester Herndon, Associate Superintendent, Facilities and Operations (206) 252-0644 ltherndon@seattleschools.org
More informationBallpark at Potomac Town Center A Partnership between Prince William County, the Potomac Nationals and The JBG Companies
A Partnership between Prince William County, the Potomac Nationals and The JBG Companies Spring 2017 PROJECT SUMMARY The Potomac Nationals is a family-owned small business that has been providing affordable
More informationRecreation and Park Commission Capital Committee. Angelo J. Rossi Playground Restroom Replacement Conceptual Plan Approval
DATE: March 23, 2012 TO: THRU: FROM: RE: Recreation and Park Commission Capital Committee Philip A. Ginsburg, General Manager Dawn Kamalanathan, Capital and Planning Manager Mary Hobson, Project Manager
More informationREQUEST FOR QUALIFICATIONS AND PROPOSAL NEW POLICE STATION, LEDYARD, CONNECTICUT Bid # (Due: 2:00pm on August 30, 2013)
Principal August 26, 2013 Town of Ledyard Mayor s Office 741 Colonel Ledyard Hwy. Ledyard, CT 06339 Re: REQUEST FOR QUALIFICATIONS AND PROPOSAL NEW POLICE STATION, LEDYARD, CONNECTICUT Bid # 2014-1 (Due:
More information$92,850,000 PENINSULA TOWN CENTER COMMUNITY DEVELOPMENT AUTHORITY SPECIAL OBLIGATION BONDS, SERIES 2007 DEVELOPER S CONTINUING DISCLOSURE STATEMENT
$92,850,000 PENINSULA TOWN CENTER COMMUNITY DEVELOPMENT AUTHORITY SPECIAL OBLIGATION BONDS, SERIES 2007 DEVELOPER S CONTINUING DISCLOSURE STATEMENT Attn: Keenan Rice MuniCap, Inc. 6760 Alexander Bell Drive,
More informationM E E T I N G NOT E S
M E E T I N G NOT E S April 17, 2013 DATE PROJECT : Wayside Elementary School Modernization Schematic Design - Community Meeting #3 PROJECT NO. : 530275.000 CC : Shawn Benjaminson Cindy Ponafala Phill
More informationJacksonville ISD Facilities Use Agreement
Facilities Use Agreement Updated 09/01/2014 CAMPUS: FACILITY: FEE: $ per (see current JISD Rental Fee Schedule) RENTAL DATE: Notes/Comments: HOURS: From: To: NAME: (Renter Organization / Group / Individual)
More informationSMITH PUBL I C SC H OO L S. Terry Morawski, Ed. D. Deputy Superintendent
FORT @ SMITH PUBL I C SC H OO L S Terry Morawski, Ed. D. Architecture Plus, Inc. Attn: Michael G. Johnson Nlichael@archplusinc.net 907 South 21st Street Fort Smith, AR 72901 RE: Limited Letter of Intent
More informationDesign Phase Award Structural Steel (Early Package) Award Final GMP for Remaining Project Construction Phase
Eastlake H.S. Phase III Architect: Mijares Mora Architects CM@Risk: Buford Thompson Company Award Structural Steel (Early Package) Award Final GMP for Remaining Project Occupancy of Classrooms 20 May 11
More informationPINNACLE PROPERTIES ANNEXATION AND ADOPTION OF PROPOSED ZONING REGULATIONS
Submitted by Pierce County On Behalf of the City of Auburn PINNACLE PROPERTIES ANNEXATION AND ADOPTION OF PROPOSED ZONING REGULATIONS Ballot Title: The City Council of the City of Auburn, Washington, adopted
More informationCaleb Dustin Hunking School Haverhill, MA
Caleb Dustin Hunking School Haverhill, MA Meeting Minutes School Building Committee (SBC) Date: November 26, 2013 Location: Haverhill City Hall, School Department Conf. Room Time: 8:30 AM Attendees: Name
More informationCOMMERCIAL LOTS WESTOVER TOWN CENTER NORTHWEST SAN ANTONIO, TEXAS
COMMERCIAL LOTS WESTOVER TOWN CENTER NORTHWEST SAN ANTONIO, TEXAS LOCATION: SIZE/ INVESTMENT: FRONTAGE: The lots are located at the southeast quadrant of Highway 151 and Westover Hills Boulevard. See Lot
More informationCOMMERCIAL LOTS WESTOVER TOWN CENTER NORTHWEST SAN ANTONIO, TEXAS
COMMERCIAL LOTS WESTOVER TOWN CENTER NORTHWEST SAN ANTONIO, TEXAS LOCATION: SIZE/ INVESTMENT: FRONTAGE: The lots are located at the southeast quadrant of Highway 151 and Westover Hills Boulevard. See Lot
More informationPocatello High School New Building Addition Board Interview
Pocatello High School New Building Addition Board Interview 9.6.2018 Agenda Introduction The Team Project Team Expectations Related Experience The Scope Building Site(s) The Site The Building / Site The
More informationFleming Island Office, Retail, Land Available
Fleming Island Office, Retail, Land Available INC Property Features Beautiful retail or office space for sale or lease Multiple units available for lease in both buildings, between 1,320± SF and 2,615±
More information6 LOT RECORDED FINAL MAP WITH CONSTRUCTION DRAWINGS
Grading can Commence upon Posting of Bonds 10,000 SF Min. Lot Size House Sizes of 2,950-2,956 SF Construction Drawings Included $825,000 - $950,000 New Home Area ASKING PRICE: $1,500,000 Guajome Regional
More informationSAMER NESSIEM P O T F O L I O SAMER NESSIEM P O R T F O L I O. Architecture is creation of balanced environment for human ARCHIECT
P O T F O L I O Skilled at working with multiple stakeholders and gathering detailed information necessary to convert complex functional programs into efficient architectural solutions. I pay attention
More informationSauk Prairie School District Facility User Manual
Sauk Prairie School District Table of Contents Sections Page Responsibility, Facility Use & Application 1 Facility Use Fees and Charges 1 General Facility Procedures 1-2 Bridges Elementary 3 Community
More informationTulsa Development Authority Board of Commissioners Meeting Executive Director s Report. July 2017
Tulsa Development Authority Board of Commissioners Meeting Executive Director s Report July 2017 1. Project Status Update A. Morton s Reserve Properties, LLC, formerly Pine Place Development, LLC 605 East
More informationSUBJECT: Board Approval: 1/18/07
1255 Imperial Avenue, Suite 1000 San Diego, CA 92101-7490 619/231-1466 FAX 619/234-3407 Policies and Procedures No. 18 SUBJECT: Board Approval: 1/18/07 JOINT USE AND DEVELOPMENT OF PROPERTY PURPOSE: It
More informationStevens Ranch Mixed Use Development San Antonio, Texas
Stevens Ranch Mixed Use Development San Antonio, Texas DRAKE COMMERCIAL GROUP DEBORAH BAUER TRAVIS BAUER 4630 N LOOP 1604 W, SUITE 510 SAN ANTONIO, TEXAS 78249 T: 210.402.6363 F: 210.402.6767 www.drakecommercial.com
More informationTANAMERA. Biography September Longley Lane - Reno, NV (775)
TANAMERA Biography September 2016 5560 Longley Lane - Reno, NV 89511 (775) 850-4200 www.tanamera.info/ COMPANY OVERVIEW Tanamera is a unique association of real property companies working in total harmony
More informationP3 for Procurement Practitioners. Alfiya Mirzagalyamova and Scott Baker AECOM
P3 for Procurement Practitioners Alfiya Mirzagalyamova and Scott Baker AECOM The Motivation Demystify P3 procurement Draw from experiences of transit P3s in North America Compare DBB and DBFOM - Availability
More informationPlease consider my architectural firm, Thomas McInerney Architect, for design services of the Slater Hall Renovations.
Page1 September 9, 2010 Hello, Please consider my architectural firm,, for design services of the Slater Hall Renovations. Our office is only 2 miles from the project site. We will bring trust, honesty,
More information36 ACRES RESIDENTIAL LAND FOR SALE GRIFFIN ROAD SOUTHWEST RANCHES, FL 33330
FOR SALE 36 ACRES RESIDENTIAL LAND FOR SALE SOUTHWEST RANCHES, FL 33330 VISTA VIEW PARK NEW TESTAMENT CHURCH + K-8 SCHOOL PALOMINO DRIVE HANCOCK ROAD CONTACT US CHRISTOPHER WOOD MICHAEL K. SILVER,SIOR
More informationSteven McCormack. Professional Portfolio
Steven McCormack Mont Pleasant Middle School 1-6 Pine Plains Bus Maintenance Facility 7-8 Simpson Residence Construction Documents 9-18 Bollengier Residence Preliminary Design 19-20 Agro Residence Preliminary
More informationThe Nuts & Bolts of Public-Private Partnerships
The Nuts & Bolts of Public-Private Partnerships Presented by: Dr. Calvin Jamison, UT Dallas Vice President for Administration Mr. Kirk Tames, UT System Executive Director of Real Estate ABOUT UT DALLAS
More informationRequest for Proposals (RFP) for. The construction of a new pole barn addition for the AuSable Township Department of Public Works
Request for Proposals (RFP) for The construction of a new pole barn addition for the AuSable Township Department of Public Works Issued: Monday February 26, 2018 Deadline for Final Submission of Questions:
More informationFLOWCHART #3 - NEW BUILDING CONSTRUCTION AND MAJOR RENOVATION PLANNING MILESTONES
1 NEW CONSTRUCTION AND MAJOR RENOVATION 2 Letter of Intent (LOI) to Bishop See note 3 Start developing: Financial plan Stakeholder list Communications plan 4 Implement: Financial plan Stakeholder list
More informationPROPOSITION S BOND PROGRAM REBUILDING ST. LOUIS PUBLIC SCHOOLS MONTHLY REPORT
PROPOSITION S BOND PROGRAM REBUILDING ST. LOUIS PUBLIC SCHOOLS MONTHLY REPORT October 2013 TABLE OF CONTENTS 1.0 EXECUTIVE SUMMARY 2.0 PROGRAM OVERVIEW 3.0 DETAILS 4.0 COST REPORT OVERALL PROGRAM SUMMARY
More informationARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of July 14, 2018
save ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of July 14, 2018 DATE: July 10, 2018 SUBJECT: Increase to Contract 178-07 with Donald R. Hoover, transacting as OCULUS for Professional
More informationAGENDA. Next Board Meeting: March 23, 2017
March 3, 2017 To: Columbia Association Board of Directors Advisory Committee Chairpersons Village Board Chairs Village Managers Members of the Press CA Management From: Andrew C. Stack, Board Chair The
More informationSAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT
SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT Issued By: Clifford Gorman Date Issued: February 1, 2016 BID NO.: 16-1250 FORMAL INVITATION FOR BIDS ANNUAL CONTRACT FOR LAWN MAINTENANCE SERVICES FOR ASR
More information1322 E 12th St Austin, TX 78702
FOR SALE $400 PSF East Austin 8500 SF retail/ office / walk-up restaurant 1322 E 12th St Austin, TX 78702 Property Highlights Highly visible 8500 SF ground floor retail/ office / walk-up restaurant space
More informationImpact Fee Funding Criteria Checklist
Project Name: Date: Description: Impact Fee Funding Criteria Checklist Total Project Cost $ IFAC Funding Request $ In accordance with Chapter 15.66, Missoula Municipal Code. Impact fees collected pursuant
More informationthe home you like is never within budget, the one within budget you never like?
Why is it that the home you like is never within budget, the one within budget you never like? It s perhaps the biggest irony of life The things that we want to own seem to be always beyond our reach.
More informationDISTRICT ADMINISTRATIVE RULE
DISTRICT ADMINISTRATIVE RULE FEAE-R Construction on District Property Funded by Others 7/25/16 GSBA Reference: FEAE (Community Involvement in Project Planning) RATIONALE/OBJECTIVE: The Cobb County School
More informationCurriculum Vitae. Profession
6950 SW Hampton Street Suite 203 Portland, Oregon 97223 TEL: 503-747-8644 FAX: 503-430-1980 www.nickpriest.com EMAIL: info@nickpriest.com California Contractor s License No. 828296 Oregon Contractor s
More informationShaenfield Outparcel Retail
Retail Leasing Shaenfield Outparcel Retail Opportunity 7907 W. Loop 1604 N., San Antonio, TX 78254 Dominion Advisory Group is pleased to present for lease 5,400 SF of Retail / Service space, including
More informationAlternative Project Delivery Strategies for Expansion and Renovation
Alternative Project Delivery Strategies for Expansion and Renovation UNIVERSITY OF CALIFORNIA, SAN FRANCISCO PUBLIC PRIVATE DEVELOPMENT 2015 Urban Land Institute: Private Public Product Council ESTHER
More information15 Finished Single Family Lots
Aerials Maps TRACT MAP project info Photos Plat Map lot BREAKDOWN Malabar Ranch LISTINGS/Sales lot site plans OFFERS DUE THURSDAY, MAY 24 Highest quality gated community in Fallbrook 2.0-2.12 gross lot
More informationConsortium West Builders 611 Anton Boulevard, Suite 675, Costa Mesa CA P F
Consortium West Builders 611 Anton Boulevard, Suite 675, Costa Mesa CA 92626 P 949 748-7556 F 949 748-7557 CONSORTIUM WEST BUILDERS ABOUT US PROJECT EXPERIENCE COMPANY STRUCTURE 3 4 17 611 Anton Boulevard,
More informationMagnolia Public Schools
Magnolia Public Schools Board Of Directors Board Agenda Item # II. H Date: 06/28/2016 To: From: Staff Lead: RE: Magnolia Board of Directors Caprice Young, Ed.D. CEO & Superintendent Frank Gonzalez, Chief
More informationF A C I L I T I E S P L A N N I N G & C O N S T R U C T I O N
F A C I L I T I E S P L A N N I N G & C O N S T R U C T I O N Planning & Building Schools of Excellence o NORWALK HIGH SCHOOL ATHLETIC FIELDS AND POSSIBLE STADIUM PROJECT (ARCHITECT: RACHLIN PARTNERS,
More informationPAD AVAILABLE FOR HOTEL DEVELOPMENT 1321 N COLUMBIA CENTER BLVD #100 KENNEWICK, WA 99336
PAD AVAILABLE FOR HOTEL DEVELOPMENT 1321 N COLUMBIA CENTER BLVD #100 KENNEWICK, WA 99336 Taylor Gibbons Director of Operations Associate Advisor 509.939.1741 taylor.gibbons@svn.com SVN CORNERSTONE 1311
More informationVISTA TERRACE LOT 8 RIDGWAY, COLORADO 1.14± ACRES $145,500
VISTA TERRACE LOT 8 RIDGWAY, COLORADO 1.14± ACRES $145,500 This 1.14 acre lot is located in the hillside subdivision of Vista Terrace overlooking the beautiful Uncompahgre River Valley. This corner lot
More informationDue Diligence for Property Acquisitions
Due Diligence for Property Acquisitions Presenters: Mary Guinee Principal, Due Diligence Services Ray Sinagra, AIA Sr. Project Manager, Property Condition Assessment Services April 28, 2009 Conference
More informationMemo. DATE: 20 September 2018 City Planning Commission John Rahaim, Director of Planning RE: HOUSING BALANCE REPORT No. 7 1 July June 2018
DATE: 20 September 2018 TO: FROM: City Planning Commission John Rahaim, Director of Planning RE: HOUSING BALANCE REPORT No. 7 1 July 2008 30 June 2018 STAFF CONTACT: Teresa Ojeda, 415 558 6251 SUMMARY
More information*Times for meetings are subject to modifications within the September 18-19, 2014 time frame.
Board of Regents Thursday, *2:00 p.m. 5:00 p.m. UAS Student Recreation Center, Room 115 University of Alaska Southeast *Times for meetings are subject to modifications within the September 18-19, 2014
More informationREQUEST FOR PROPOSALS Professional Engineering Services for Lift Station In the Rural Municipality of Wellington
REQUEST FOR PROPOSALS Professional Engineering Services for Lift Station In the Rural Municipality of Wellington Issue Date: March 2, 2018 Prepared By: Rural Municipality of Wellington Wellington, PEI
More informationCalifornia Commercial Properties
California Commercial Properties MAIL: P.O. BOX 181, ALAMO, CA 94507-0181 OFFICE: 3195 DANVILLE BOULEVARD, SUITE 2, ALAMO, CA TEL: 415-860-5000 RETAIL BUILDING FOR LEASE IMAGINE YOUR BUSINESS IN VISALIA,
More informationThe following is a list of assumptions on which this Term Sheet is based:
NONBINDING TERM SHEET BETWEEN CITY OF LAS VEGAS, CITY PARKWAY V, THE CORDISH COMPANIES, AND FINDLAY SPORTS AND ENTERTAINMENT, LLC This Nonbinding Term Sheet ( Term Sheet ) dated this day of September,
More informationPrevailing Wages in California Relevant Law and Case Updates Ethan Walsh
Prevailing Wages in California Relevant Law and Case Updates Ethan Walsh Best Best & Krieger LLP League of California Cities Annual Conference San Francisco What are prevailing wages? The prevailing wage
More information15 Finished Single Family Lots
Aerials Highest quality gated community in Fallbrook 2.0-2.12 gross lot sizes 0.25-0.31 acre pads 11 miles to coast Easy access to I-15 Panoramic views Via Monserate 15 LOTS at MALABAR RANCH www.malabarranch.com
More informationSan Francisco 2015 Affordable Housing General Obligation Bond CGOBOC Report March 2018
San Francisco 2015 Affordable Housing General Obligation Bond CGOBOC Report March 2018 1 P a g e Table of Contents Affordable Housing Bond Overview... 3 History of Bond Approval... 3 Need for the Bond...
More informationHERSHEY COMMUNITY CENTER
HERSHEY COMMUNITY CENTER 1 Frequently asked questions 5 Learn more about the new Hershey Community Center process 8 Understand the proposed Community Center solution 10 Read about how the Derry Township
More informationMiami Beach, FL KITCHEN RENOVATION
Miami Beach, FL 9 KITCHEN RENOVATION PERMIT SET 07..0 EoA, Inc. 0 Minorca Avenue. Suite 7 C EoA, Inc. 0 State of Florida Architect of Record Malcolm Berg, AIA License No. AR9 KEY PLAN N REV. # DATE NARRATIVE
More informationOffering Memorandum THE TIKI APARTMENTS Market Street Kirkland, WA. Exclusively offered by Paragon Real Estate Advisors
Offering Memorandum THE TIKI APARTMENTS 1124 Market Street Exclusively offered by Paragon Real Estate Advisors 1 Offering Summary The Tiki Apartments present a unique investment opportunity with an excellent
More informationTulsa Development Authority Board of Commissioners Meeting Executive Director s Report. May 2018
Tulsa Development Authority Board of Commissioners Meeting Executive Director s Report May 2018 1. Project Status Update A. First Place, LLC 419 South Main Street, Parking Garage No new information B.
More informationCalifornia Commercial Properties
California Commercial Properties MAIL: P.O. BOX 181, ALAMO, CA 94507-0181 OFFICE: 3195 DANVILLE BOULEVARD, SUITE 2, ALAMO, CA TEL: 415-860-5000 RETAIL BUILDING FOR LEASE SACRAMENTO, CALIFORNIA GREAT VISIBILITY
More informationREQUEST FOR QUALIFICATIONS
REQUEST FOR QUALIFICATIONS FOR EXECUTIVE ARCHITECT/ARCHITECT OF RECORD SERVICES FOR HOMECOMINGS INC. WESTVIEW VILLAGE REDEVELOPMENT Issued February 4, 2016 SUBMITTAL DEADLINE Wednesday, February 17, 2016
More informationWelcome. Primer program Please review the additional materials It has a LOT of additional detail, samples and links to other materials
Welcome Primer program Please review the additional materials It has a LOT of additional detail, samples and links to other materials There are many kinds of leases Single and multi-tenant office Single
More informationWestside Creeks Restoration Oversight Committee (WCROC) Meeting
Westside Creeks Restoration Oversight Committee (WCROC) Meeting I. Welcome & Introductions Committee Co Chairs II. Approval of Meeting Minutes (3/10/2009) Tuesday, April 14, 2009 6:00 PM San Antonio River
More informationAttachment 2 Civil Engineering
A. Phase 1, Programming and Schematic Design: The CONSULTANT shall for each project: 1. Ascertain the project s requirements through a meeting with the COUNTY, and a review of an existing schematic layout
More informationTANAMERA CONSTRUCTION & DEVELOPMENT
TANAMERA CONSTRUCTION & DEVELOPMENT Company Biography May 2018 COMPANY OVERVIEW Tanamera is a unique real property construction and development company that provides high-end commercial and residential
More informationAcres Briggs Ranch State Hwy 211 & Hwy 90 San Antonio, Texas
42.903 Acres Briggs Ranch State Hwy 211 & Hwy 90 San Antonio, Texas DRAKE COMMERCIAL GROUP DEBORAH BAUER TRAVIS BAUER 4630 N LOOP 1604 W, STE. 510 SAN ANTONIO, TEXAS 78249 T: 210.402.6363 F: 210.402.6767
More informationMICHAEL BARDIN ARCHITECT
education Harvard University Graduate School of Design 99 MArch I University of Pittsburgh 95 Masters of Arts in English Literature Swarthmore College 91 Bachelor of Arts with High Honors in English Lit
More informationCORNELL University, Ithaca, New York B.Arch Colegio San José, Río Piedras Registered Licensed Architect PR #16929
ALBERTO LASTRA POWER, AIA ARCHITECT COLLEGE EDUCATION CORNELL University, Ithaca, New York B.Arch. 1993 HIGH SCHOOL EDUCATION Colegio San José, Río Piedras 1988 REGISTRATION Registered Licensed Architect
More informationDMITRI J. KAPALIS AIA, LEED AP
DMITRI J. KAPALIS AIA, LEED AP EXPERIENCE & QUALIFICATIONS An active and accomplished licensed Architect with exceptional technical skills in conceptual planning and 3D design formulation. Balanced with
More informationAdministrative Regulation
Administrative Regulation CODE: IG.AR TOPIC: Community Use of District Buildings EFFECTIVE DATE: (12-02-1998) ISSUE DATE: (11-16-1998) REVIEW YEAR: (2003) REGULATION A. JOINT USE AGREEMENT In accordance
More informationAttachment 10 Structural Engineering
A. Phase 1, Preliminary Design: The CONSULTANT shall: Attachment 10 Structural Engineering 1. Ascertain the requirements for each project through a meeting with the Capital Projects Division Manager or
More information