1 F A C I L I T I E S P L A N N I N G & C O N S T R U C T I O N Planning & Building Schools of Excellence o NORWALK HIGH SCHOOL ATHLETIC FIELDS AND POSSIBLE STADIUM PROJECT (ARCHITECT: RACHLIN PARTNERS, CONSTRUCTION MANAGER: BALFOUR BEATTY CONSTRUCTION) DSA APPLICATION # Tuesday, June 13, 2017, Facilities, along with the Environmental Consultant (Ninyo and Moore), performed the site walk at Norwalk High School, to mark the boring locations for the underground utility locator in preparation for Preliminary Endangerment Assessment (PEA) Workplan Implementation, which is required as a part of the Department of Toxic Substances Control approval process. Tuesday, 6/13/17 In the week of June 19, 2017, Facilities, along with the Environmental Consultant (Ninyo and Moore), performed the soil sampling at Norwalk High School, as part of the PEA Workplan Implementation. Monday, 6/19/17 - Friday, 6/23/17

2 Board Update Page 2

3 Board Update Page 3 Monday, June 19, 2017, Facilities, along with the Architect (Rachlin Partners) and their electrical engineering team, performed the site walk at Norwalk High School, to gather the information on the existing system on site. o GLENN HIGH SCHOOL ATHLETIC FIELDS AND POSSIBLE STADIUM PROJECT (ARCHITECT: RACHLIN PARTNERS, CONSTRUCTION MANAGER: BERNARDS) DSA APPLICATION # Environmental Due Diligence At the June 26, 2017 Board meeting, the Board of Education certified the Mitigated Negative Declaration Study Report in accordance with the California Environmental Quality Act. Friday, August 25, 2017 Facilities along with our environmental consultant, Ninyo & Moore and the DTSC conducted a public hearing for the final Draft Preliminary Environmental Assessment (PEA) report. o LA MIRADA HIGH SCHOOL GYM & LOCKER RM BLDGS MODERNIZATION & EXPANSION (ARCHITECT: DLR GROUP, CONSTRUCTION MANAGER: BALFOUR BEATTY CONSTRUCTION) Wednesday, June 14, 2017, Facilities met with the Architect (DLR Group) and Construction Manager (Balfour Beatty), to review the value engineering suggestions and determine next steps for each value engineering item being presented by the design team. Thursday, June 15, 2017, Facilities met with the Stakeholders at La Mirada High School, to fine-tune the details of the use and the locker requirements for the team rooms in the Gymnasium and Locker Room Buildings. Thursday, August 3, 2017, Facilities, along with the Construction Manager (Balfour Beatty) performed a site walk at La Mirada High School, to check the existing conditions of the Gymnasium and Locker Room Buildings. Thursday, 8/3/17 SITE VISIT OF GYM & LOCKER ROOM BUILDINGS AT LA MIRADA HS Wednesday, August 9, 2017, Facilities met with the Stakeholders at La Mirada High School, to discuss the possible value engineering options being discussed. The comments from the Stakeholders were shared with the design team to be incorporated into the design.

4 Board Update Page 4 o LA MIRADA HIGH SCHOOL INTERIM PE LOCKER BUILDINGS (ARCHITECT: WESTGROUP DESIGN) Thursday, June 15, 2017, Facilities, along with the Architect (Westgroup), met with the Stakeholders at La Mirada High School to gather the Stakeholder s input for the Interim Locker Building Project. The project is scheduled to be submitted to the Division of State Architect for Over-The-Counter plan check in late September On Friday, June 23, 2017 and on Monday, June 26, 2017, Facilities joined the Architect (Westgroup), and the Civil Engineer (FPL), to perform a site walk-through of the potential building sites for the interim PE locker buildings. The team checked the existing accessibility, available utilities, and the grading of the site to determine the exact building location. Friday, 6/23/17 INTERIM PE LOCKER AT LA MIRADA HS Monday, 6/26/17 o LA MIRADA HIGH SCHOOL CAMPUS-WIDE RENOVATION OF HARD/SOFT SCAPE (ARCHITECT: NAC ARCHTIECTURE)

5 Board Update Page 5 Thursday, June 29, 2017, Facilities, along with the Architect (NAC Architecture) and their Landscape Architect (SALT), met with the Stakeholders to review the schematic design and objectives of the project based on Stakeholder s input received at the previous Stakeholder meeting. Thursday, 6/29/17 Friday, July 21, 2017, Facilities, along with the Landscape Architect (SALT), met with the M&O Department, to discuss the irrigation system issues at La Mirada High School with the design team. The meeting was followed by the site walk at La Mirada High School, where the landscape architect obtained the detailed information from the site irrigation personnel regarding the existing conditions of the irrigation system at different parts of the campus. Friday, 7/21/17

6 Board Update Page 6 O BENTON MIDDLE SCHOOL CAMPUS-WIDE RENOVATION W/ ACCESSORY STRUCTURES PROJECT (ARCHITECT: DLR GROUP, LANDSCAPE ARCHITECT: LYNN CAPOUYA INC, CONSTRUCTION MANAGER: CUMMING) DSA APPLICATION # Status: DSA Approve / Bidding Phase Anticipated Construction Start Date: Fall 2017 Project drawings and specifications have been prepared for bidding this month. Thursday, June 22, the Contractor performed the utilities disconnect at the leased portable restroom building in preparation for its return to the portable building manufacturer.

7 Board Update Page 7 Monday, July 17, 2017, the leased portable restroom building has been dismantled and returned to the portable building manufacturer, Williams Scotsman.

8 Board Update Page 8 O CORVALLIS MIDDLE SCHOOL CAMPUS-WIDE RENOVATION W/ ACCESSORY STRUCTURES PROJECT (ARCHITECT: DLR GROUP, LANDSCAPE ARCHITECT: LYNN CAPOUYA INC, CONSTRUCTION MANAGER: CUMMING) DSA APPLICATION # Status: DSA Approved / Project Bidding Phase Anticipated Construction Start Date: Fall 2017 Project drawings and specifications have been prepared for bidding this month. o MORRISON ES AND LOS ALISOS MS HVAC/MODERNIZATION OF ADMIN. & MPR BUILDINGS PROJECTS (ARCHITECT: RACHLIN PARTNERS, CONSTRUCTION MANAGER: BERNARDS) DSA APPLICATION # & # Status: The project received approval from the Division of the State Architect O GARDENHILL ES AND HUTCHINSON MS HVAC/MODERNIZATION OF ADMIN. & MPR BUILDINGS PROJECTS (ARCHITECT: DLR GROUP, CONSTRUCTION MANAGER: BALFOUR BEATTY CONSTRUCTION) DSA APPLICATION # & # Status: Plan Check Review - Division of the State Architect. Wednesday, June 14, 2017, Facilities, along with the M&O and ITS Departments, met with the Architect (DLR Group) and Construction Manager (Balfour Beatty) to provide the constructability review comments to the 90% Construction Documents submitted by the Architect. The design team is incorporating the comments received from the meeting. The project is currently undergoing a plancheck review under the Division of State Architect, the state regulatory agency. Wednesday, June 28, 2017, Facilities met with the Architect (DLR Group) and Construction Manager (Balfour Beatty), to review the value engineering suggestions and determine next steps for each value engineering item being presented by the design team. Following the meeting, the Construction Manager (Balfour Beatty) performed a site walk to check the existing condition. o MEASURE G AND S CITIZENS OVERSIGHT COMMITTEE MEETING Tuesday, June 27, 2017, the Facilities conducted the Measure G and S Citizens Oversight Committee Meeting at La Mirada High School. The meeting was followed by the site walk of the existing Gymnasium and Locker Room Buildings.

9 Board Update Page 9 MEASURE G AND S CITIZENS OVERSIGHT COMMITTEE MEETING o DULLES ELEMENTARY SCHOOL KINDERGARTEN PLAYGROUND RENOVATION (ARCHITECT: DOUGHERTY ARCHITECTS) DSA APPLICATION # Bids for the Dulles Elementary Playground Project were opened on August 3, 2017 and a recommendation has been made to award the project to the contractor at the August 21, 2017 Board meeting. Construction is scheduled to start in early September and to be completed by the end of October. o ESCALONA ELEMENTARY SCHOOL PLAYGROUND ADDITION (ARCHITECT: DOUGHERTY ARCHITECTS) DSA APPLICATION # Bids for the Escalona Elementary Playground Project were opened on August 3, 2017 and a recommendation has been made to award the project to the contractor at the August 21, 2017 Board meeting. Construction is scheduled to start in early September and to be completed by the end of October. o SANCHEZ ES PLAYGROUND ADDITION AND KINDERGARTEN PLAYGROUND RENOVATION (ARCHITECT: DOUGHERTY ARCHITECTS) DSA APPLICATION # Status: Construction

10 Board Update Page 10 Construction started on Thursday, July 6, 2017 and the project is 95% complete. Both the playground in the K-Yard and the addition to the main yard was open in time for the first day of school. The contractor will be returning to install updated gates which were part of an accessibility upgrade. KINDERGARTEN YARD KINDERGARTEN YARD MAIN YARD

11 Board Update Page 11 MAIN YARD o HUERTA ES SHADE STRUCTURE FOR HEADSTART (ARCHITECT: DOUGHERTY ARCHITECTS) DSA APPLICATION # Status: DSA APPROVED The project was approved by the Division of the State Architect (DSA) on July 18, Next step, Facilities staff is in the process of determining if this project will require an informal bid. o RAMONA SHADE STRUCTURE (ARCHITECT: DOUGHERTY ARCHITECTS) DSA APPLICATION # Status: DSA APPROVED The project was approved by Division of the State Architect (DSA) on July 18, Next step, Facilities staff is in the process of determining if this project will require an informal bid. o LOS ALISOS MIDDLE SCHOOL ELECTRONIC MARQUEE PROJECT (ARCHITECT: DONALD KROTEE PARTNERSHIP) DSA APPLICATION # Status: Under Construction Installation of pole in preparation for electronic sign to be installed.

12 Board Update Page 12 o LOS COYOTES MIDDLE SCHOOL ELECTRONIC MARQUEE PROJECT (ARCHITECT: DONALD KROTEE PARTNERSHIP) DSA APPLICATION # Status: Under Construction Demolition of existing monument sign and completion of pole in preparation of new electronic marquee. o LA MIRADA HIGH SCHOOL TEAM PORTABLE BUILDING REPLACEMENT PROJECTS (ARCHITECT: WESTGROUP DESIGNS) Monday, June 26, 2017, the Facilities conducted a mandatory pre-bid job walk with the prospective bidders at La Mirada High School. The Purchasing Department has conducted a bid opening on Monday, July 17, 2017, and the bid was awarded to R. Jensen Co. Inc. at the Board of Education Meeting on Monday, August 7, Next Steps: The Pre-Construction Meeting was scheduled for Wednesday, August 23, 2017, to introduce the team, and discuss the logistics and communication protocol during construction, which is scheduled to start in September 2017.

13 Board Update Page 13 Monday, 6/26/17 TEAM PORTABLE BUILDING REPLACEMENT AT LA MIRADA HS o LA MIRADA HS SYNTHETIC TURF SPORT FIELD AND TRACK REPLACEMENT PROJECT (ARCHITECT: TBD) Monday, August 7, 2017, Facilities met with the Geotechnical Engineer (Converse Consultants) to mark-up the boring locations for the percolation testing. On Wednesday, August 9, 2017, Facilities met with the synthetic turf vendor FieldTurf to open the (2) - 3 x 3 areas of the field, in preparation of the percolation testing. On Friday, August 11, 2017, Facilities, along with Converse Consultants, conducted a percolation testing to check the permeability rate of the existing soil under the football field. On Friday, August 18, 2017, FieldTurf patched the opened turf back to its original condition. Wednesday, 8/9/17 Monday, 8/7/17

14 Board Update Page 14 o NORWALK HS CTE CULINARY ARTS CLASSROOM CONVERSION (ARCHITECT: RACHLIN PARTNERS) On the following three days, Monday, June 19, 2017, Thursday, June 29, 2017, and August 7, 2017, Facilities, along with the Architect Rachlin Partners and their engineering team, performed the site walk at Norwalk High School, to gather the information on the existing system on site. Monday, 6/19/17 Thursday, 6/29/17

15 Board Update Page 15 Recently completed and upcoming projects include: o HUTCHINSON MIDDLE SCHOOL RENNOVATION OF PORTABLES AND CLASSROOM CONVERSION UPGRADES TO THREE PORTABLE CLASSROOMS AND CONVERSION OF BOOK STORAGE ROOM To accommodate the growing student population, two rooms were recently converted into classrooms. Additional power, data and interior work was completed to convert the space into a classroom.

16 Board Update Page 16 The ASB room was also converted into a classroom with the addition of A/C units and additional interior upgrades to provide additional teaching space. o BENTON MIDDLE SCHOOL ADMINISTRATION OFFICE SWINGING GATE A Site Modification Request was received from the site to install a barrier to help control access into the reception area in the administration office. On August 3 rd 2017 a pony wall with a swinging gate was installed.

17 Board Update Page 17 Since our last report, Facilities Staff, in collaboration with our consultants, have certified one (1) project through the Division of the State Architect (DSA). School Site included: o Foster Road & Corvallis ( ) Project completed in 2000 We currently have two (2) projects left to certify, one of which is under review at DSA. o Various Sites ( ) Project completed in 2001 o Various Sites ( ) Project completed in 2001 Facilities Staff continue to work toward having the final project certified by the DSA Office. o Nuffer Elementary School RETURN OF THREE (3) LEASED PORTABLE CLASSROOMS It was determined that three (3) portable classrooms made up of seven leased units were no longer needed at Nuffer Elementary for capacity. During the week of June 7, 2017, contractors arrived to disconnect the utilities and began the demolition needed for the return. A crane was brought out to the site to remove the buildings and stage them for transportation. Once the buildings were removed the work began to fill the hole left behind and repair the blacktop in

18 Board Update Page 18 time for the first day of school. Facilities Staff would like to thank the Principal and Lead Custodian for their patience over the summer break. o La Mirada High School CARPET REPLACEMENT IN SIX (6) LEASED PORTABLES Monday, June 19, 2017, contractors were sent out to replace the carpet in six (6) portable buildings at La Mirada High School.

19 Board Update Page 19 o Dolland Elementary School CARPET REPAIR AND PAINT IN SIX (6) LEASED PORTABLES Friday, June 23, 2017, contractors were sent out to repair the carpet in six (6) portable classrooms. The exterior door along with the ramps & railing was also painted as requested by the Principal. o Los Alisos Middle School CARPET REPAIR IN TWELVE (12) LEASED PORTABLE BUILDINGS During the week of June 21, 2017 contractors repaired the carpet in twelve (12) leased portables at Los Alisos Middle School. o Gardenhill Elementary School CARPET REPLACEMENT IN LEASED PORTABLE BUILDING Thursday, June 22, 2017, contractors were sent to Gardenhill Elementary to replace the carpet in the leased portable building that is used for the music program.

2016 Annual Report. Enid Public Schools 2016 Bond. February 2017

2016 Annual Report. Enid Public Schools 2016 Bond. February 2017 2016 Annual Report Enid Public Schools 2016 Bond February 2017 Enid Public Schools Strategic Action Plan The initial goals of the Enid Public Schools Strategic Action Plan have been met, and we are well

More information

Ashby, Pepperell, Townsend North Middlesex Regional High School. Preferred Schematic Report Update

Ashby, Pepperell, Townsend North Middlesex Regional High School. Preferred Schematic Report Update Ashby, Pepperell, Townsend North Middlesex Regional High School Preferred Schematic Report Update June 3, 2013 AGENDA Preferred Schematic Report (PSR) Options Review Criteria and Goals Project Costs Factors

More information

Tisbury Elementary School

Tisbury Elementary School SLIDE TITLE Slide Sub Title Building Committee Presentation for: Tisbury Elementary School MAY 10, 2017 AGENDA 1. Discussion of Options 1. Addition / Renovation (Site, Phasing, Plans) 2. New 2 Story School

More information

New Hope-Solebury School District Campus Revitalization Plan

New Hope-Solebury School District Campus Revitalization Plan Campus Revitalization Plan 20 January 2016 GODSHALL KANE O ROURKE ARCHITECTS, LLC 12 East Butler Avenue, Suite 205, Ambler, PA 19002 T: 215.646.2003 F: 215.646.5707 www.gkoarchitects.com Site Rendering

More information

FREEHOLD BOROUGH SCHOOL DISTRICT. Proposed Referendum Schematic Designs & Preliminary Costs

FREEHOLD BOROUGH SCHOOL DISTRICT. Proposed Referendum Schematic Designs & Preliminary Costs FREEHOLD BOROUGH SCHOOL DISTRICT Proposed Referendum Schematic Designs & Preliminary Costs Introduction The foundation of every state is the education of its youth. - Diogenes Laertius Greek Philosopher

More information

RGM Architects. Eduardo Mata Elementary School

RGM Architects. Eduardo Mata Elementary School Insert Google Map Image Overall Scope ADA Improvements Exterior site upgrades Roof replacement Restroom upgrades Kitchen upgrades Mechanical, electrical, and plumbing upgrades Fire alarm and Life Safety

More information

EXHIBIT A FULL TEXT OF BOND PROPOSITION HILMAR UNIFIED SCHOOL DISTRICT CLASSROOM SAFETY, RENOVATION AND CONSTRUCTION MEASURE

EXHIBIT A FULL TEXT OF BOND PROPOSITION HILMAR UNIFIED SCHOOL DISTRICT CLASSROOM SAFETY, RENOVATION AND CONSTRUCTION MEASURE EXHIBIT A FULL TEXT OF BOND PROPOSITION 4152-6874-3188.6 HILMAR UNIFIED SCHOOL DISTRICT CLASSROOM SAFETY, RENOVATION AND CONSTRUCTION MEASURE This proposition may be known and referred to as the Hilmar

More information

SAN MATEO UNION HIGH SCHOOL DISTRICT. Site Recommendation Alternative High School Program December 13, 2017

SAN MATEO UNION HIGH SCHOOL DISTRICT. Site Recommendation Alternative High School Program December 13, 2017 SAN MATEO UNION HIGH SCHOOL DISTRICT Site Recommendation Alternative High School Program December 13, 2017 AGENDA o Background o Original Property Search Criteria o Current Property Search Criteria o Properties

More information

SOLANO COMMUNITY COLLEGE DISTRICT GOVERNING BOARD AGENDA ITEM. Members of the Governing Board

SOLANO COMMUNITY COLLEGE DISTRICT GOVERNING BOARD AGENDA ITEM. Members of the Governing Board SOLANO COMMUNITY COLLEGE DISTRICT GOVERNING BOARD AGENDA ITEM AGENDA ITEM 13.(e) --~~---------- MEETING DATE April 15, 2015 TO: SUBJECT: REQUESTED ACTION: Members of the Governing Board LEASE AGREEMENT

More information

Michigan State University Barrier-Free/Accessibility Project Status Summary December 2017

Michigan State University Barrier-Free/Accessibility Project Status Summary December 2017 Projects Completed FY16, FY17 and FY18 (arranged alphabetically) Abrams Planetarium Install automatic door opener on main doors of the Planetarium. Completed: Summer 2016 Cost: $13,000 Bessey Hall 1 st

More information

RM.com. Community Recreation and Aquatic Center Ad Hoc Committee Status Report & Preliminary Proposal/Recommendations

RM.com. Community Recreation and Aquatic Center Ad Hoc Committee Status Report & Preliminary Proposal/Recommendations Community Recreation and Aquatic Center Ad Hoc Committee Status Report & Preliminary Proposal/Recommendations July 19, 2011 PRELIMINARY AMENITIES SELECTED GUIDED BY COMMUNITY ON-LINE SURVEY RESULTS 1 During

More information

CUMBERLAND SCHOOLS WORK PROPOSED 2018

CUMBERLAND SCHOOLS WORK PROPOSED 2018 Cost Ashton Elementary School 2 2 Replace HVAC $ 375,000.00 5 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 2 3 Various Technological Improvements $ 191,258.00 2 4 Replace Plumbing Fixtures

More information

PINNACLE PROPERTIES ANNEXATION AND ADOPTION OF PROPOSED ZONING REGULATIONS

PINNACLE PROPERTIES ANNEXATION AND ADOPTION OF PROPOSED ZONING REGULATIONS Submitted by Pierce County On Behalf of the City of Auburn PINNACLE PROPERTIES ANNEXATION AND ADOPTION OF PROPOSED ZONING REGULATIONS Ballot Title: The City Council of the City of Auburn, Washington, adopted

More information

Final RRISD Bond 2018/19 Project List 3 Yr Sale

Final RRISD Bond 2018/19 Project List 3 Yr Sale Capital Renewal Anderson Mill ES ELEC Replace electric panels, Capital Renewal Anderson Mill ES ELEC Replace Main Switch Gear 97,200 Capital Renewal Anderson Mill ES Controller Replacement/Programming

More information

Americans with Disabilities Act Transition Plan Barrier Removal Database Project Listed by Type

Americans with Disabilities Act Transition Plan Barrier Removal Database Project Listed by Type Americans with Disabilities Act Transition Plan Barrier Removal Database Project Listed by Type Parking Lot Priorities Type 1 Program na Use 1 Severity na New Parking Lots and restriping / regradeing existing

More information

ASBESTOS PERIODIC SURVEILLANCE CHECK LIST

ASBESTOS PERIODIC SURVEILLANCE CHECK LIST DATE OF SCHOOL: Effingham County Board Office SURVEILLANCE 1. SURFACING: 2010 Plaster in hallway NO This building has been completely renovated for the board office. The plaster has been covered with paneling

More information

DTSC BROWNFIELDS Services

DTSC BROWNFIELDS Services DTSC BROWNFIELDS Services Maryam Tasnif-Abbasi California Environmental Protection Agency Department of Toxic Substances Control Brownfields Coordinator RESOURCES FOR SUSTAINABLE REDEVELOPMENT AND LAND

More information

Local Ballot Measure: E. Enterprise Elementary School District Bond Measure

Local Ballot Measure: E. Enterprise Elementary School District Bond Measure E Enterprise Elementary School District Bond Measure Ballot question To improve educational quality; upgrade/renovate/construct classrooms, restrooms and facilities; repair/replace leaky roofs; upgrade

More information

Design Development Presentation New North Richland Middle School // Birdville ISD

Design Development Presentation New North Richland Middle School // Birdville ISD Design Development Presentation New North Richland Middle School // Birdville ISD ARCHITECTURE // ENGINEERING // PLANNING // TECHNOLOGY // FACILITY CONSULTING 972-233-1323 // PBK.COM ACKNOWLEDGEMENT The

More information

COORDINATING COMMITTEE

COORDINATING COMMITTEE COORDINATING COMMITTEE 100 West Washington Street, Room 320 Hagerstown, MD 21740-4748 P: 240.313.2330 F: 240.313.2331 www.washco-md.net PUR-1331 NOTICE TO PROSPECTIVE BUYERS REQUEST FOR PROPOSALS FOR THE

More information

Relocation Plan Colonial Village West

Relocation Plan Colonial Village West Relocation Plan Colonial Village West AHC Inc. Draft 3/6/18 Relocation Plan, Page 1 of 19 Table of Contents OVERVIEW AND RESIDENT PROFILE... 4 Property Profile... 4 Resident Profile... 5 Affordable Apartments...

More information

SCHOOL BOARD ACTION REPORT

SCHOOL BOARD ACTION REPORT SCHOOL BOARD ACTION REPORT DATE: May 31, 2018 FROM: Dr. Larry Nyland, Superintendent LEAD STAFF: Dr. Lester Herndon, Associate Superintendent, Facilities and Operations (206) 252-0644, ltherndon@seattleschools.org

More information

ATTACHMENT 3 NOTICE OF EXEMPTION. Clerk of the Board County of Santa Barbara 105 E. Anapamu Street, Room 407 Santa Barbara, CA

ATTACHMENT 3 NOTICE OF EXEMPTION. Clerk of the Board County of Santa Barbara 105 E. Anapamu Street, Room 407 Santa Barbara, CA ER11-0012 - Annual Maintenance & Operations Plan, fiscal year 2011-2012 Operations, Repair and Maintenance Activities Maintenance activities to be performed by the s Public Works, Utilities and Parks and

More information

PROPOSED BOND PROJECT DETAILS. New School Facilities to Prevent Overcrowding

PROPOSED BOND PROJECT DETAILS. New School Facilities to Prevent Overcrowding PROPOSED BOND PROJECT DETAILS New School Facilities to Prevent Overcrowding New High School - Phase I What: First phase of a 2,000 student comprehensive high school. Capacity of Phase I - 1,000 students.

More information

Corvallis School District 2002 Long Range Facilities Master Plan Projects Update

Corvallis School District 2002 Long Range Facilities Master Plan Projects Update Corvallis School District 2002 Long Range Facilities Master Plan Projects Update Phase 1 (Each estimate includes contingency, indirect and inflation costs) 1. Replacement School for Existing Corvallis

More information

SAMER NESSIEM P O T F O L I O SAMER NESSIEM P O R T F O L I O. Architecture is creation of balanced environment for human ARCHIECT

SAMER NESSIEM P O T F O L I O SAMER NESSIEM P O R T F O L I O. Architecture is creation of balanced environment for human ARCHIECT P O T F O L I O Skilled at working with multiple stakeholders and gathering detailed information necessary to convert complex functional programs into efficient architectural solutions. I pay attention

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction September 2018 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS FOR EXECUTIVE ARCHITECT/ARCHITECT OF RECORD SERVICES FOR HOMECOMINGS INC. WESTVIEW VILLAGE REDEVELOPMENT Issued February 4, 2016 SUBMITTAL DEADLINE Wednesday, February 17, 2016

More information

Proposed East Liberty TRID Phase II. November 2, 2015 School District, Business Committee Meeting

Proposed East Liberty TRID Phase II. November 2, 2015 School District, Business Committee Meeting Proposed East Liberty TRID Phase II November 2, 2015 School District, Business Committee Meeting What is TRID Spur Transit Oriented Development and Community Revitalization Establishes value capture areas

More information

ProgID Title Description FY18 FY19 MOF

ProgID Title Description FY18 FY19 MOF AIEA HIGH SCHOOL, OAHU PLANS AND DESIGN FOR A NEW BUILDING, AND RENOVATION AND EXPANSION FOR A GIRLS' ATHLETIC LOCKER ROOM, WEIGHT TRAINING FACILITY, AND OTHER ATHLETIC FACILITIES; GROUND AND SITE IMPROVEMENTS;

More information

The ABC s of New Buildings: Architects, Bonds and Construction

The ABC s of New Buildings: Architects, Bonds and Construction The ABC s of New Buildings: Architects, Bonds and Construction 2016 NASB/NASA State Education Conference F6 - Friday, November 18, 2016 10:30 to 11:30 a.m. Presented by: Rex R. Schultze, Perry, Guthery,

More information

SCHOOL BOARD ACTION REPORT

SCHOOL BOARD ACTION REPORT SCHOOL BOARD ACTION REPORT DATE: January 3, 2018 FROM: Dr. Larry Nyland, Superintendent LEAD STAFF: Dr. Lester Herndon, Associate Superintendent, Facilities and Operations (206) 252-0644 ltherndon@seattleschools.org

More information

PEDESTRIAN OVERLAY DISTRICT. November 6, 2013 Charlotte-Mecklenburg Planning Department

PEDESTRIAN OVERLAY DISTRICT. November 6, 2013 Charlotte-Mecklenburg Planning Department Midtown Morehead Cherry PEDESTRIAN OVERLAY DISTRICT November 6, 2013 Charlotte-Mecklenburg Planning Department Meeting Purpose To provide a background on the Pedestrian Overlay District Zoning text amendment

More information

The property lends itself to additional housing units along Dover and Potter Streets provided the new units are welldesigned

The property lends itself to additional housing units along Dover and Potter Streets provided the new units are welldesigned (ATTACHMENT 1) AUTHOR RIZATION TO O WAIVE ADM MINISTRATIV VE POLICY 5.01 5 AND ACTION ON A REQUEST R TO SELL L A PROPERT TY LOCATED D AT 619 EA AST DOVER STREET S Req quest For Pro oposal; Dove er Elementarry

More information

MISSOULA COUNTY PUBLIC SCHOOLS STRATEGIC FACILITIES PLAN DRAFT ASSESS/EXPLORE REPORT December 3, 2013

MISSOULA COUNTY PUBLIC SCHOOLS STRATEGIC FACILITIES PLAN DRAFT ASSESS/EXPLORE REPORT December 3, 2013 EX 12 Subcommittee Review of Undeveloped Sites, Leased Facilities and District Administration Buildings A subcommittee of the Steering Committee reviewed the undeveloped sites, leased facilities and District

More information

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of July 14, 2018

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of July 14, 2018 save ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of July 14, 2018 DATE: July 10, 2018 SUBJECT: Increase to Contract 178-07 with Donald R. Hoover, transacting as OCULUS for Professional

More information

EARLY PLANNING - SCHOOL SITE SELECTION

EARLY PLANNING - SCHOOL SITE SELECTION EARLY PLANNING - SCHOOL SITE SELECTION CASH / CCFC Workshop January 14, 2003 Michael O'Neill - Calif. Dept. of Education School Facilities Planning Division ASSUMPTIONS (Already done?) Identified need

More information

Public Inspection for the Kuala Lumpur-Singapore High Speed Rail Frequently Asked Questions (FAQ)

Public Inspection for the Kuala Lumpur-Singapore High Speed Rail Frequently Asked Questions (FAQ) Public Inspection for the Kuala Lumpur-Singapore High Speed Rail Frequently Asked Questions (FAQ) Public Inspection 1. What is the purpose of Public Inspection? The Public Inspection is a mandatory process

More information

REQUEST FOR PROPOSALS FOR EQUITY INVESTOR FEDERAL AND STATE 4% LOW INCOME HOUSING TAX CREDITS BOULDER HOUSING PARTNERS OAK PARK AND

REQUEST FOR PROPOSALS FOR EQUITY INVESTOR FEDERAL AND STATE 4% LOW INCOME HOUSING TAX CREDITS BOULDER HOUSING PARTNERS OAK PARK AND 4800 N. Broadway, Boulder, CO 80304 Phone: 720-564-4610 Fax: 303-939-9569 www.boulderhousing.org Hearing Assistance: 1-800-659-3656 REQUEST FOR PROPOSALS FOR EQUITY INVESTOR FEDERAL AND STATE 4% LOW INCOME

More information

Design Phase Award Structural Steel (Early Package) Award Final GMP for Remaining Project Construction Phase

Design Phase Award Structural Steel (Early Package) Award Final GMP for Remaining Project Construction Phase Eastlake H.S. Phase III Architect: Mijares Mora Architects CM@Risk: Buford Thompson Company Award Structural Steel (Early Package) Award Final GMP for Remaining Project Occupancy of Classrooms 20 May 11

More information

PROPOSAL JANITORIAL SERVICES LAKELAND ELEMENTARY SCHOOL OAKSEED LN LAKELAND, TN FEBRUARY 11, 2015

PROPOSAL JANITORIAL SERVICES LAKELAND ELEMENTARY SCHOOL OAKSEED LN LAKELAND, TN FEBRUARY 11, 2015 PROPOSAL JANITORIAL SERVICES LAKELAND ELEMENTARY SCHOOL 10050 OAKSEED LN LAKELAND, TN 38002 FEBRUARY 11, 2015 A Service Mark of COMMUNITY REHABILITATION AGENCIES OF TENNESSEE 40 Rutledge Street Nashville,

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction October 2017 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING

More information

Waverley Elementary School Feasibility Study

Waverley Elementary School Feasibility Study Waverley Elementary School Feasibility Study FREDERICK COUNTY PUBLIC SCHOOLS Feasibility Study Meeting #6 January 18, 2018 1 AGENDA 1. PROJECT OVERVIEW schedule 2. 1/11 COMMUNITY MEETING recap of Community

More information

NOTICE OF ADDENDUM #1

NOTICE OF ADDENDUM #1 Page #1 NOTICE OF ADDENDUM #1 Invitation to Bid No. 2017/18-02 This one (1) page must be completed and submitted with all other documents in the Proposal Package By signing this page and submitting a proposal,

More information

Gym Capacity: 710. Stage. Auditeria Capacity: 390. New Bleachers

Gym Capacity: 710. Stage. Auditeria Capacity: 390. New Bleachers New Bleachers Gym Capacity: 710 Stage Auditeria Capacity: 390 Enlarged plan of new stage configuration showing greater seating capacity of the gym vs. that of the auditeria Proposed 2018 Bond Projects

More information

Request Conditional Use Permits (Craft Brewery, Assembly Use & Open-Air Market) Staff Recommendation Approval. Staff Planner Robert Davis

Request Conditional Use Permits (Craft Brewery, Assembly Use & Open-Air Market) Staff Recommendation Approval. Staff Planner Robert Davis Applicant Property Owner Weathersby Properties, LLC Public Hearing January 9, 2019 City Council Election District Bayside Agenda Item 4 Request Conditional Use Permits (Craft Brewery, Assembly Use & Open-Air

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction August 2015 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction August 2018 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING

More information

PASSAIC BOARD OF EDUCATION IMPROVEMENT OF FACILITIES REPORT

PASSAIC BOARD OF EDUCATION IMPROVEMENT OF FACILITIES REPORT PASSAIC BOARD OF EDUCATION IMPROVEMENT OF FACILITIES REPORT School No.10 Annex Renovations Contractor: Malanga Construction (Employed by Archdiocese) Architectural Firm: Kellen Chapin Architects Start

More information

Christopher J. Blunk, Deputy Public Works Director/ City Engineer

Christopher J. Blunk, Deputy Public Works Director/ City Engineer STAFF REPORT DATE: March 27, 2018 TO: FROM: PRESNTER: City Council Gosia Woodfin, Project Engineer Christopher J. Blunk, Deputy Public Works Director/ City Engineer 922 Machin Avenue Novato, CA 94945 415/

More information

Request for Proposal(RFP) for Planning Services

Request for Proposal(RFP) for Planning Services Request for Proposal(RFP) for Planning Services Issued December 18, 2017 Population (2010 census) 2,454 Area.55 square miles No. of Households 731 SUMMARY The Charter Township of Royal Oak requests proposals

More information

TOWN MANAGER S WEEKLY REPORT

TOWN MANAGER S WEEKLY REPORT TOWN MANAGER S WEEKLY REPORT UPCOMING MEETINGS & EVENTS Town Offices Closed: Monday, January 19 th, in observation of Martin Luther King Day Planning Commission: Wednesday, January 21 st, 6:00 PM, Town

More information

Oxford Central School District Referendum Fact Sheet

Oxford Central School District Referendum Fact Sheet Introduction To better accommodate the Oxford Central School District s current and future students, it looks to do necessary safety and security upgrades, to replace the current HVAC system and to complete

More information

HARRISON COUNTY BOARD OF EDUCATION BOND ELECTION ORDER

HARRISON COUNTY BOARD OF EDUCATION BOND ELECTION ORDER HARRISON COUNTY BOARD OF EDUCATION BOND ELECTION ORDER AN ORDER OF THE BOARD OF EDUCATION OF THE COUNTY OF HARRISON DIRECTING THAT A SPECIAL ELECTION BE HELD FOR THE PURPOSE OF SUBMITTING TO THE VOTERS

More information

The Agenda for the April 20, 2016 Meeting is as Follows:

The Agenda for the April 20, 2016 Meeting is as Follows: PUBLIC NOTICE April 15, 2016 Public notice is hereby given that the Board of Park Commissioners of the Wheaton Park District, DuPage County, Illinois (the Park Board ) will hold a meeting at 7 pm on Wednesday,

More information

EVENT INFO. Pavilion Egg Harbor Library. Donald & Carol Kress. Professionally Managed By

EVENT INFO. Pavilion Egg Harbor Library. Donald & Carol Kress. Professionally Managed By EVENT INFO Donald & Carol Kress Pavilion Egg Harbor Library 7845 CHURCH STREET - PO BOX 175 - EGG HARBOR, WI 54209 920.868.3334 ext. 3 - www.kresspavilion.org Professionally Managed By DONALD & CAROL KRESS

More information

NEIGHBORHOOD MEETING

NEIGHBORHOOD MEETING NEIGHBORHOOD MEETING Community Development Department 8101 Ralston Road Arvada, Colorado 80002 NEIGHBORHOOD MEETINGS The City of Arvada promotes citizen participation in the development review process.

More information

Interstate 35 Community School District Board of Education January 29, (pictures as of )

Interstate 35 Community School District Board of Education January 29, (pictures as of ) Interstate 35 Community School District Board of Education January 29, 2018 (pictures as of 1-26-18) East end of CTE building (note outside entrances to both classrooms) Front entrance to CTE and east

More information

HERSHEY COMMUNITY CENTER

HERSHEY COMMUNITY CENTER HERSHEY COMMUNITY CENTER 1 Frequently asked questions 5 Learn more about the new Hershey Community Center process 8 Understand the proposed Community Center solution 10 Read about how the Derry Township

More information

?10 /S-- 0 & ENDORSED FILED

?10 /S-- 0 & ENDORSED FILED SAN FRANCISCO Notice of Exemption Approval Date: February 5, 2015 Case No.: 2013.0862E Project Title: The Urban School of San Francisco Zoning: P.M-i (Residential - Mixed, Low Density) District I 40-X

More information

BALLOT MEASURE SUBMITTAL FORM. Jurisdiction Name: San Leandro Unified School District Election Date: 8 November 2016

BALLOT MEASURE SUBMITTAL FORM. Jurisdiction Name: San Leandro Unified School District Election Date: 8 November 2016 Official Use Only: Date Stamp BALLOT MEASURE SUBMITTAL FORM Jurisdiction Name: San Leandro Unified School District Election Date: 8 November 2016 BALLOT TITLE & QUESTION TO BE PRINTED Note: The information

More information

EMERGING ALTERNATE DELIVERY LEASE LEASEBACK FOR COMMUNITY COLLEGES CCFC 21 ST ANNUAL CONFERENCE SEPT 9 TH, TUESDAY 10:25 AM 11:40 AM WORKSHOP #1 (CC

EMERGING ALTERNATE DELIVERY LEASE LEASEBACK FOR COMMUNITY COLLEGES CCFC 21 ST ANNUAL CONFERENCE SEPT 9 TH, TUESDAY 10:25 AM 11:40 AM WORKSHOP #1 (CC EMERGING ALTERNATE DELIVERY LEASE LEASEBACK FOR COMMUNITY COLLEGES CCFC 21 ST ANNUAL CONFERENCE SEPT 9 TH, TUESDAY 10:25 AM 11:40 AM WORKSHOP #1 (CC ROOM 202) agenda LEGAL PERSPECTIVE & FRAMEWORK OWNERS

More information

CHAPTER SCHOOL PROPERTY

CHAPTER SCHOOL PROPERTY CHAPTER 393 - SCHOOL PROPERTY CARE, MANAGEMENT AND CONTROL OF SCHOOL PROPERTY NRS 393.010 NRS 393.020 NRS 393.030 NRS 393.051 Management, control and custody of school property. Insurance; use of proceeds.

More information

Glendale Municipal Golf Courses Glen Lakes Analysis. City Council Workshop November 13, 2018

Glendale Municipal Golf Courses Glen Lakes Analysis. City Council Workshop November 13, 2018 Glendale Municipal Golf Courses Glen Lakes Analysis City Council Workshop November 13, 2018 Today s Presentation Notice of Violation Temporary Golf Course Operations Maintenance Building & Irrigation System

More information

M E E T I N G NOT E S

M E E T I N G NOT E S M E E T I N G NOT E S April 17, 2013 DATE PROJECT : Wayside Elementary School Modernization Schematic Design - Community Meeting #3 PROJECT NO. : 530275.000 CC : Shawn Benjaminson Cindy Ponafala Phill

More information

JKL Bahweting School. Request for Proposal. Classroom and Hallway Carpet

JKL Bahweting School. Request for Proposal. Classroom and Hallway Carpet JKL Bahweting School Request for Proposal Classroom and Hallway Carpet Theresa Kallstrom School Superintendent Date: September 10, 2018 RFP # 20180910.1 1.0 GENERAL INFORMATION 1.1 Scope of the Project

More information

REPORT. DATE ISSUED: December 19, 2014 REPORT NO: HCR Chair and Members of the San Diego Housing Commission For the Agenda of January 16, 2015

REPORT. DATE ISSUED: December 19, 2014 REPORT NO: HCR Chair and Members of the San Diego Housing Commission For the Agenda of January 16, 2015 REPORT DATE ISSUED: December 19, 2014 REPORT NO: HCR15-008 ATTENTION: SUBJECT: Chair and Members of the San Diego Housing Commission For the Agenda of January 16, 2015 COUNCIL DISTRICT: 9 REQUESTED ACTION

More information

1. Question: In regards to the facilities are they all Monday thru Friday cleaning? Any facilities Saturday and or Sunday cleaning?

1. Question: In regards to the facilities are they all Monday thru Friday cleaning? Any facilities Saturday and or Sunday cleaning? Proposal No. P18/9957 Custodial Services Answers to Vendor Questions Questions are in black, Answers are in red 1. Question: In regards to the facilities are they all Monday thru Friday cleaning? Any facilities

More information

CONSIDERATION OF THE MINUTES OF THE INFORMATIONAL AND REGULAR MEETINGS OF MAY 18, 2017

CONSIDERATION OF THE MINUTES OF THE INFORMATIONAL AND REGULAR MEETINGS OF MAY 18, 2017 JUNE 22, 2017 The regular meeting of the Planning Commission of the Township of Upper St. Clair, duly advertised and posted in accordance with the law, was called to order by the Chairperson at 7:30 PM,

More information

LONSDALE FARM, FRIZINGTON, CUMBRIA

LONSDALE FARM, FRIZINGTON, CUMBRIA Preliminary particulars of sale of: LONSDALE FARM, FRIZINGTON, CUMBRIA An opportunity to acquire a 140 acre holding with quality agricultural land suitable for mowing and grazing, farm buildings, allotments

More information

Request Conditional Use Permit (Craft Brewery) Staff Planner Jimmy McNamara

Request Conditional Use Permit (Craft Brewery) Staff Planner Jimmy McNamara Applicant Property Owner Juan Suarez, Arch Dixon & Jalaladin Mansourzadeh Public Hearing August 10, 2016 City Council Election District Rose Hall Agenda Item 1 Request Conditional Use Permit (Craft Brewery)

More information

NAPA COUNTY BOARD OF SUPERVISORS Board Agenda Letter

NAPA COUNTY BOARD OF SUPERVISORS Board Agenda Letter Agenda Date: 5/1/2012 Agenda Placement: 7H NAPA COUNTY BOARD OF SUPERVISORS Board Agenda Letter TO: FROM: Board of Supervisors Lederer, Steven - Interim Director of Public Works Public Works REPORT BY:

More information

Facilities. A Brief Overview: How to Secure a Facility for Your. Charter School

Facilities. A Brief Overview: How to Secure a Facility for Your. Charter School Charter School Facilities A Brief Overview: How to Secure a Facility for Your Charter School Contents 1. Forming a Facilities Team 2. Creating a Timeline 3. Identifying Your Need 4. Searching for the Ideal

More information

DWR REAL ESTATE COORDINATION PLAN

DWR REAL ESTATE COORDINATION PLAN DWR REAL ESTATE COORDINATION PLAN Exhibit E DWR PROPERTY ACQUISTION PLAN EXHIBIT E Revised Date: 5 10 18 DWR PROPERTY ACQUISTION PLAN EXHIBIT E Revised Date: 5-10-2018 California WaterFix Real Estate Coordination

More information

Due diligence - Hits & Misses. CA Rajesh S Shetty January 2018

Due diligence - Hits & Misses. CA Rajesh S Shetty January 2018 Due diligence - Hits & Misses CA Rajesh S Shetty January 2018 Contents Need of due diligence What is due diligence? Types of due diligence The process Focus areas Key benefits Limitations 2 Need of Due

More information

City of Riverside. Board of Public Utilities. Agenda 6:30 PM MISSION STATEMENT

City of Riverside. Board of Public Utilities. Agenda 6:30 PM MISSION STATEMENT Public Utilities Administrative Office 3750 University Ave. 3 Fl. Riverside, CA 92501 951-826-2135 Meeting Date: Monday, Publication Date: Wednesday, December 28, 2016 6:30 PM Art Pick Council Chamber

More information

Community Development Department Planning Division 1600 First Street + P.O. Box 660 Napa, CA (707)

Community Development Department Planning Division 1600 First Street + P.O. Box 660 Napa, CA (707) Community Development Department Planning Division 1600 First Street + P.O. Box 660 Napa, CA 94559-0660 (707) 257-9530 PLANNING COMMISSION STAFF REPORT MARCH 3, 2016 AGENDA ITEM # 7.B. File No. 15-0158

More information

The East Jordan Civic Center Contract. City of East Jordan 201 Main Street PO BOX 499 East Jordan, MI THE CIVIC CENTER IS A NO SMOKING FACILITY

The East Jordan Civic Center Contract. City of East Jordan 201 Main Street PO BOX 499 East Jordan, MI THE CIVIC CENTER IS A NO SMOKING FACILITY The East Jordan Civic Center Contract City of East Jordan 201 Main Street PO BOX 499 East Jordan, MI 49727 THE CIVIC CENTER IS A NO SMOKING FACILITY Please Circle the day of scheduled event(s): Monday

More information

IMPERIAL VALLEY COLLEGE Citizens Oversight Committee for Measure L Unadopted Minutes Thursday, September 20, 2007

IMPERIAL VALLEY COLLEGE Citizens Oversight Committee for Measure L Unadopted Minutes Thursday, September 20, 2007 IMPERIAL VALLEY COLLEGE Citizens Oversight Committee for Measure L Unadopted Minutes Thursday, September 20, 2007 Members Present Dr. Barbara Macci-Trethewey, Chair John Anderson Terence Donovan Kathy

More information

REAL ESTATE CAREER INFORMATION SESSION

REAL ESTATE CAREER INFORMATION SESSION 7:00 a.m. Personal time Sunday 9:00 a.m. Drive around targeted areas to locate industrial properties for lease or sale. Identify contact information for follow-up 11:00 a.m. Family time 1 4:00 p.m. Organize

More information

Magnolia Public Schools

Magnolia Public Schools Magnolia Public Schools Board Of Directors Board Agenda Item # II. H Date: 06/28/2016 To: From: Staff Lead: RE: Magnolia Board of Directors Caprice Young, Ed.D. CEO & Superintendent Frank Gonzalez, Chief

More information

PC RESOLUTION NO. 15~11-10~01 CONDITIONAL USE PERMIT (CUP)

PC RESOLUTION NO. 15~11-10~01 CONDITIONAL USE PERMIT (CUP) PC RESOLUTION NO. 15~11-10~01 CONDITIONAL USE PERMIT (CUP) 15-005 A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF SAN JUAN CAPISTRANO, CALIFORNIA APPROVING A MUSIC EDUCATION FACILITY IN EXISTING

More information

EXHIBIT F NON- MONETARY COMPENSATION SERVICES AND PUBLIC BENEFITS TO BE PROVIDED BY TENANT

EXHIBIT F NON- MONETARY COMPENSATION SERVICES AND PUBLIC BENEFITS TO BE PROVIDED BY TENANT EXHIBIT F NON- MONETARY COMPENSATION SERVICES AND PUBLIC BENEFITS TO BE PROVIDED BY TENANT Section 1: General Requirements The Tenant shall provide the services and benefits established in this Section

More information

Recreation and Park Commission Capital Committee. Angelo J. Rossi Playground Restroom Replacement Conceptual Plan Approval

Recreation and Park Commission Capital Committee. Angelo J. Rossi Playground Restroom Replacement Conceptual Plan Approval DATE: March 23, 2012 TO: THRU: FROM: RE: Recreation and Park Commission Capital Committee Philip A. Ginsburg, General Manager Dawn Kamalanathan, Capital and Planning Manager Mary Hobson, Project Manager

More information

THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS:

THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS: Page 1 ORDINANCE NO. An ordinance amending Sections 12.03 and 12.22 and repealing portions of Section 12.24 of Chapter 1 of the Los Angeles Municipal Code (LAMC) for the purpose of regulating Accessory

More information

MINUTES FOR NOVEMBER 7, 2018

MINUTES FOR NOVEMBER 7, 2018 MINUTES FOR NOVEMBER 7, 2018 The regular monthly meeting of the Valley Township Board of Supervisors was held on Wednesday, November 7, 2018, at 7:30 p.m. at the Township Municipal Building, 890 West Lincoln

More information

Pam N asstrom Tiz Beretta. Matthew Yanko Ming Chang

Pam N asstrom Tiz Beretta. Matthew Yanko Ming Chang PACIFIC QUORUM Properties Inc. HARBOUR REACH STRATA PLAN VR1330 COUNCIL MEETING MINUTES WEDNESDAY, APRIL 4, 2012, 7:00 P.M. COUNCIL PRESENT: ABSENT: Brad Keller Pam N asstrom Tiz Beretta Matthew Yanko

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction February 2014 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION

More information

NACS and PEI Member 2017 Booth Selection Details

NACS and PEI Member 2017 Booth Selection Details NACS and PEI Member 2017 Booth Selection Details CONTENTS: 2017 NACS Show Basic Information (Dates/Location/Pricing/Contacts) How to Reserve a Booth Important Notices Assignment Process Exhibitor FAQs

More information

Dear Fair Concessionaires:

Dear Fair Concessionaires: JEFFERSON COUNTY FAIR AUTHORITY GPS Address: 1514 Route 28N, Brookville, PA 15825 ~Website: http://www.jeffcofair.com Mailing Address: c/o Jim Grant, Secretary, 1709 Arch Street Ext., Brockway, PA 15824

More information

INDUSTRIAL BUILDING AND LOT

INDUSTRIAL BUILDING AND LOT INDUSTRIAL BUILDING AND LOT 9550-70 SOUTH GENOA AVENUE CHICAGO, IL 60643 David Makowski Senior Vice President 847.509.2757 davem@svn.com SVN AUCTIONWORKS 707 SKOKIE BLVD., SUITE 601, NORTHBROOK, IL 60062

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction February 2019 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING

More information

MUNICIPAL HOUSING REHABILITATION PROGRAM HANDBOOK

MUNICIPAL HOUSING REHABILITATION PROGRAM HANDBOOK MUNICIPAL HOUSING REHABILITATION PROGRAM HANDBOOK For further information or inquiries please write or call your municipality s Small Cities Consultants: Lisa Low & Associates 293 Riggs Street Oxford,

More information

FOR LEASE ±9,940 Square Foot Industrial Building

FOR LEASE ±9,940 Square Foot Industrial Building FOR LEASE ±9,940 Square Foot Industrial Building 4810 Brooks Street Montclair, California 91763 Contact only Listing Agents below for additional information to Qualified Tenant(s) Carlos Rodriguez Senior

More information

Housing Information Session Housing Contracts, Online Room Selection, Building Layout

Housing Information Session Housing Contracts, Online Room Selection, Building Layout Housing Information Session Housing Contracts, Online Room Selection, Building Layout Office of Housing & Residence Life Spring 2018 No deposits are required for any of our contracts Space is available

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction January 2019 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING

More information

ADUs in San Francisco May 2017

ADUs in San Francisco May 2017 ADUs in San Francisco May 2017 sf-adu Handbook The handbook project was developed to define: various physical forms for small scale residential infill; when investment in small scale residential infill

More information

DEKALB COUNTY ENTERPRISE ZONE APPLICATION. Project Information

DEKALB COUNTY ENTERPRISE ZONE APPLICATION. Project Information DEKALB COUNTY ENTERPRISE ZONE APPLICATION Project Information Project Name: Street Address: City/State/Zip: Mailing Address: City/State/Zip: (the exact legal name under which the business is applying for

More information

Meruelo Maddux Properties

Meruelo Maddux Properties Meruelo Maddux Properties Key milestones for senior management in 2007 Meruelo Maddux Properties, Inc. is a self-managed, full-service real estate company that develops, redevelops and owns commercial

More information

MOTION NO. M Property Exchange Agreement with the University of Washington for the Northgate Link Extension

MOTION NO. M Property Exchange Agreement with the University of Washington for the Northgate Link Extension MOTION NO. M2012-93 Property Exchange Agreement with the University of Washington for the Northgate Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: PHONE: Board 12/20/12 Final Action Ahmad

More information