NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD RESETTLEMENT PLAN (RP) SUBPROJECT:

Size: px
Start display at page:

Download "NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD RESETTLEMENT PLAN (RP) SUBPROJECT:"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD RESETTLEMENT PLAN (RP) SUBPROJECT: TRANSMISSION EFFICIENCY PROJECT 500KV TAN UYEN SUBSTATION AND CONNECTION LINES PREPARED BY POWER ENGINEERING CONSULTING JOINT STOCK COMPANY 3 Ho Chi Minh city, March 2014

2 TABLE OF CONTENTS 1. INTRODUCTION Transmission Efficiency Project (TEP) Subproject of 500kV Tan Uyen substation and connection lines Technical specification of substation Technical specification of connection lines Objectives of Resettlement Plan LEVEL OF IMPACTS OF THE SUBPROJECT Determination of the subproject's impacts Determination of affected scope/area of the subproject Determination of affected people (APs) by the subproject Types of the subproject's impacts Productive land Residential land Houses Graves Crops Trees Temporary impacts LEGAL FRAMEWORK AND COMPENSATION POLICY Legal framework Policies of Vietnam Policies of WB Compatibility between policies of Government and the World Bank and require wavers Compensation policy Principles Policies on compensation, assistance and resettlement applied to the subproject COMPENSATION, ASSISTANCE AND RESETTLEMENT Compensation Compensation unit prices for land Compensation unit prices for houses and structures Compensation unit prices for trees and crops Assistances and rehabilitation Power Engineering Consulting Joint Stock Company 3 2

3 4.3 Resettlement PUBLIC CONSULTATION AND PEOPLE S PARTICIPATION Public consultation and people s participation Disclosure Grievance redress mechanism SUPERVISION, MONITORING AND VALUATION Internal monitoring and supervision Independent monitoring Reporting condition IMPLEMENTATION SCHEDULE Implementation responsibility Implementation schedule COSTS Basis of cost calculations Replacement Cost Survey Cost estimation for implementation of RP Cost of detail measurement survey Cost of compensation Cost of assistances Cost for CRC Cost of monitoring cost of RP implementation ANNEXES Annex 1 Annex 2 Annex 3 Annex 4 Annex 5 Annex 6 Map of site area Entitlement Matrix Site agreement Minutes and pictures of meetings on public consultation Questionnaires form Inventory of subproject affected households Power Engineering Consulting Joint Stock Company 3 3

4 ABBREVIATION AND DEFINITION Abbreviations are applied on the following principles: - Using popular abbreviations For example: PC: People s Committee, CRC: Compensation and Resettlement Committee - Using the shortest form for particular phrases For example: RP: Resettlement Plan APs: Affected persons by the subproject AHs APs CPC CRC DMS DPC EVN GRM HCM HH NPT PECC3 PPC ROW RP SPPMB SS TEP T/L VND WB Affected households by the subproject Affected persons by the subproject Commune People s Committee Compensation and Resettlement Council Detail measurement survey District People s Committee Vietnam Electricity Grievance redress administrative Ho Chi Minh Household National Power Transmission Corporation Power Engineering and Consulting joint-stock company No.3 Provincial People s Committee Right of way Resettlement Plan Southern Power Project Management Board Substation Transmission Efficiency Project Transmission line Viet Nam Dong World Bank Temporarily affected land: land in ROW of high voltage transmission line (according to Decree No.81/2009/ND-CP dated Oct. 12, 2009) will be restricted usability, and also affected during construction by stretching the line. Temporarily affected houses/structures: houses/structures in ROW of high voltage transmission line (according to Decree No.81/2009/ND-CP dated Oct. 12, 2009) will be restricted usability, and and owners' daily activities are also affected. Power Engineering Consulting Joint Stock Company 3 4

5 LIST OF TABLES Table 1.1 Items of the subproject Table 2.1 Number of AHs by the subproject Table 2.2 Number of AHs and APs based on the local boundary Table 2.3 Productive land acquisition Table 2.4 Residential land acquisition Table 2.5 Dismantled houses (relocated) Table 2.6 Removed graves Table 2.7 Permanently affected crops Table 2.8 Permanently affected trees Table 2.9 Temporary impacts on productive land Table 2.10 Temporary impacts on residential land Table 2.11 Temporarily affected houses and structures (no relocation) Table 2.12 Temporarily affected crops Table 2.13 Temporarily affected trees Table 3.1 Comparison of Vietnam s and World Bank s Policies related to Involuntary Resettlement Table 4.1 Compensation unit prices for land Table 4.2 Compensation unit prices for houses and structures Table 4.3 Compensation unit prices for trees and crops Table 4.4 Assistance unit prices for land in the ROW (restricted usability) Table 4.5 Assistance unit prices for houses in the ROW (restricted usability) Table 5.1 Public consultation Table 6.1 Main activities for internal monitoring and evaluation Table 8.1 Compensation cost - Thanh Phuoc commune Tan Uyen district Table 8.2 Compensation cost - Thai Hoa township Tan Uyen District Table 8.3 Compensation cost - Tan Binh ward Di An town Table 8.4 Compensation cost - Tan Hanh commune Bien Hoa city Table 8.5 Compensation cost - Hoa An commune Bien Hoa city Table 8.6 Compensation cost - Buu Hoa ward Bien Hoa city Table 8.7 compensation cost of the subproject Table 8.8 Allowance cost - Thanh Phuoc commune Tan Uyen district Table 8.9 Allowance cost - Thai Hoa township Tan Uyen district Table 8.10 Allowance cost - Tan Binh ward Di An town Table 8.11 Allowance cost - Tan Hanh commune Bien Hoa city Table 8.12 Allowance cost - Hoa An commune Bien Hoa city Table 8.13 Allowance cost - Buu Hoa ward Bien Hoa city Table 8.14 allowance cost of the subproject Table 8.15 cost for RP implementation Power Engineering Consulting Joint Stock Company 3 5

6 SUMMARY Subproject of 500kV Tan Uyen substation and connection lines belongs to Transmission Efficiency Project (TEP). The subproject will go through Thanh Phuoc commune and Thai Hoa township Tan Uyen district, Tan Binh ward Di An town Binh Duong province; Tan Hanh, Hoa An communes and Buu Hoa ward Bien Hoa city Dong Nai province. The subproject includes 2 items: (1) construction and installation of Tan Uyen 500kV substation with capacity of 900MVA, 250MVA and access road, (2) construction and installation of 220kV connection lines to the 220kV Long Binh - Thu Duc T/L with 12.4 km in length, in which 10.5 km of overhead connection lines and 1.9 km of underground cables. Construction time of subproject is estimated about 18 months. The construction is expected to start in Jan The subproject will affect 334 households (1,375 persons), including 211 households (891 persons) in Binh Duong province and 123 households (484 persons) in Dong Nai province, in which: Permanent affected persons Content 1. AHs have productive land required permanently less than 20% of the total area of the landholding, or less than 10% for the poor and vulnerable group 2. AHs have productive land required permanently from 20% to 70% the total area of the landholding, or more than 10% for the poor and vulnerable group 3. AHs have productive land required permanently more than 70% of the total area of the landholding Number of HHs Number of persons AHs have residential land required permanently AHs have houses/structures to be dismantled and relocated AHs have graves to be dismantled and relocated AHs have trees, crops required permanently Temporary affected persons 1. AHs have productive land affected temporarily AHs have residential land affected temporarily AHs have house/structure in the ROW (27m in width) AHs have trees, crops affected temporarily by the subproject Permanent impacts: No. Permanent impact Unit Tan Uyen district Di An district Bien Hoa city 1 Productive land required permanently m 2 121,299 2,858 8, , Annual crop land m 2 107,382 2,858 6, , Perennial tree land m 2 12,830-2,067 14,897 Power Engineering Consulting Joint Stock Company 3 6

7 No. Permanent impact Unit Tan Uyen district Di An district Bien Hoa city 1.3 Pond land m 2 1, ,849 2 Residential land m 2 1, ,302 3 Houses are dismantled unit Graves are removed unit Paddy and crops m 2 107,382 2,858 6, ,345 6 Trees tree , Cajuput tree , Rubber tree Banana tree No. Temporary impacts: Temporary impact Unit Tan Uyen District Di An District Bien Hoa city 1 Productive land affected temporarily m 2 102,849 38, , , Annual crop land m 2 91,023 30,591 53, , Perennial tree land m 2 11,178-3,105 14, Pond land m ,452 11,718 19, Quarry land m ,304 33,304 2 Residential land m 2 6,218 1,755 9,014 16,986 3 Houses affected temporarily unit House grade 4 (brick wall, tiled roof) House grade 4 (brick wall, metal roof) Temporary house (thatched wall, thatched roof) unit unit unit Paddy and crops m 2 91,023 30,591 53, ,120 5 Trees 5.1 Pomelo tree Cajuput tree 5, , Mango tree Banana tree The Resettlement Plan of the subproject 500kV Tan Uyen substation and connection lines is prepared on the basis of the WB s OP 4.12 Involuntary Resettlement (OP/BP 4.12) and Power Engineering Consulting Joint Stock Company 3 7

8 Resettlement Policy Framework of the Transmission Efficieny Project (TEP). Compensation for affected households expected to start in June cost of the resettlement plan is estimated as 66,559,960,957 VND (this amount shall be updated at the time of the subproject implementation to ensure the compensation on the principle of replacement price). Budget for RP implementation shall be provided by NPT. Power Engineering Consulting Joint Stock Company 3 8

9 1. INTRODUCTION 1.1 Transmission Efficiency Project (TEP) 1. The National Power Transmission Cooperation (NPT) is developing Efficient Transmission Project (TEP) with funding from the World Bank (WB). The Project Development Objective (PDO) for TEP is to support the implementation of an investment programs to increase capacity of Vietnam s electricity transmission grid, improve efficiency and reliability of electricity services and strengthen the institutional capacity of the National Power Transmission Company. The direct beneficiary of the project would be Vietnam s electricity transmission company NPT. Indirect beneficiaries would include all segments of population. They would benefit from: (i) Improved reliability, which will reduce unserved demand and the number and duration of power outages; and (ii) Increased energy efficiency, which will reduce overall costs and GHG emissions. The project would also bring direct temporary benefits for skilled and unskilled workers that would be employed for the construction of the project. The proposed project is comprised of the following three components: (a) The Transmission Infrastructure Component will finance transmission lines and substations at voltage levels of 220kV and 500kV. The investments will target three areas that are key to the overall economic development of Vietnam, namely the Greater Hanoi Area, the Greater Ho Chi Minh City Area and the Mekong Delta. Investments at the 500kV level will help increase the transport capacity of the main 500kV trunk system while increasing its reliability. Investments at the 220kV level are aimed at increasing the capacity of the supply points to the distribution utilities and improve the reliability of the network that serves these points. (b) The Smart Grid Component will support modernization of monitoring, control, and protection equipment in 500kV and 220kV substations to improve the reliability of the interconnected power system as a whole and of some bulk-supply points in the distribution network. Today, 60 percent of the faults in substations are a consequence of faulty operations of monitoring, control, and protection equipment. Aided by monitoring and control gear, protection equipment: (i) detects - among other things - the locations and intensity of faults and, based on such information, determines what equipment should be disconnected to protect the system from damage; and (ii) decides when disconnected equipment should be reconnected to ensure that interruptions in the provision of electricity services are minimized. (c) The Capacity Building and Institutional Strengthening Component will contribute to the gradual development of NPT to become an independent transmission company with revenues from the application of cost-of-service regulation in the transmission sector. The steps to be supported in this operation include the definition of technical and financial performance indicators, the introduction of enterprise asset management systems and strategies. 2. Component 1 and Component 2 will be implemented by three management boards of NPT, Component 3 and a part of the component 2 will be implemented by NPT and ERAV. 1.2 Subproject of 500kV Tan Uyen substation and connection lines The subproject of 500kV Tan Uyen S/S and connection lines is in the area of Thanh Phuoc commune and Thai Hoa township Tan Uyen district, Tan Binh ward Di An town Binh Duong province; Tan Thanh and Hoa An communes and Buu Hoa ward Bien Hoa city Dong Nai province (Pls. see Appendix 1: Map of site area). Power Engineering Consulting Joint Stock Company 3 9

10 The subproject is invested and built to increase power supply to loads in Binh Duong region (area of Thuan An, Di An, Tan Uyen), and one part of HCM city (Thu Duc district and district 9); besides reducing the system losses and increasing the reliability of power system in case of the surrounding substations and T/L (500kV Song May SS or the 500kV Tan Dinh SS, the 220kV Tan Dinh - Binh Hoa T/L or the 220kV Binh Hoa - Thuan An T/L) are out of service. The subproject includes 02 items: - Substation: construction and installation of Tan Uyen 500kV substation with capacity of 900MVA, 250MVA and access road kV connection lines: construction and installation of 220kV connection lines with total length of 12.4km including 10.5km overhead connection lines and 1.9km underground cables. No. Province/district/ commune 1 Binh Duong province 1.1 Tan Uyen District Thanh Phuoc commune Table 1.1 Items of the subproject Capacity (MVA) 900MVA and 250MVA Overhead connection lines Thai Hoa township Di An town 2.4 Length (km) Underground cables Tan Binh ward Dong Nai province 2.1 Bien Hoa City Tan Hanh commune Hoa An Commune Buu Hoa Ward MVA and 250MVA Technical specification of substation Location - Cay Da village, Thanh Phuoc commune, Tan Uyen district, Binh Duong province Capacity - Installed 03 transformers 500/220kV-900MVA and 03 transformers 220/110kV - 250MVA. Phase 1, it will be installed 01 transformer 500/220kV 1x900MVA and 01 transformer 220/110kV 1x250MVA. The next phases, it will be installed 500kV and 220kV transformers. Power Engineering Consulting Joint Stock Company 3 10

11 - Connecting diagram: using diagram 3/2, with 03 outgoing feeders as follows: Song May 1, Song May 2, 3AT Transformer. Expected to extend feeders for 2AT transformer, 3AT transformer and redundancy for two new 500kV feeders. - Connecting diagram of 220kV side: double busbar with transfer busbar system. Maximum number of outgoing feeders is 20, is expected as follows: 03 incoming feeders of 500/220kV transformers, this scope will be installed 01 incoming feeder for 3AT transformer. 11 outgoing feeders, with 06 outgoing feeders to Thuan An (1 & 2), Thu Duc (1 & 2), Long Binh (1 & 2). Redundancy for extension 05 feeders. 03 incoming feeders for 500/220kV transformers, in this scope will be installed 01 incoming feeder (3AT transformer). 02 feeders for the bus-coupler circuit breaker and transfer circuit breaker. Redundancy for installation of bus-couplers. - Connecting diagram of 110kV side: double bus bar without transfer busbar. Maximum number of outgoing feeders is 18, is arranged as follows: 03 incoming feeders 220/110kV transformer, in this scope will be installed 01 incoming feeder (4AT transformer); 14 outgoings feeders. This scope will be installed 06 feeders, including the feeders to Binh Hoa, Nam Tan Uyen, Thu Duc (Tan Binh in future), Binh An (Binh Duong), Long Binh (Quang Vinh-in future), Dong Nai (Bien Hoa city). There are 08 spare positions for future. 01 bus-coupler feeder. There is 01 spare position for bus-coupler Communication - The Optical Communication is expected to make this solution would be: + 500kV side: 500kV Tan Uyen substation - 500kV Song May substation - 500kV Phu My Substation - 500kV Phu Lam substation - A2. 500kV Tan Uyen substation - 500kV Song May substation - Tan Dinh 500kV substation - 500kV Di Linh substation - A kV side: 500kV Tan Uyen Substation - 220kV Thuan An substation. 500kV Tan Uyen Substation - 220kV Binh Long substation. 500kV Tan Uyen Substation - 220kV Thu Duc substation. - And Phone line and exchange information systems; WAN connection; SCADA system and hotline Technical specification of connection lines Connection lines of the subproject will go through Thanh Phuoc commune and Thai Hoa township Tan Uyen district, Tan Binh commune Di An district Binh Duong province; Tan Thanh, Hoa An communes and Buu Hoa ward Bien Hoa city Dong Nai province. Power Engineering Consulting Joint Stock Company 3 11

12 kV-1 connection line - Voltages: 220kV. - Numbers of circuit: 02 circuits (layout to the left, shared towers with the 220kV-2 connection line). - The start point: 500kV Tan Uyen substation. - The end point: DDN.1 belonging to 220/110kV Long Binh - Thu Duc transmission line in T.42A tower (new tower) between 2 towers T.21 and T The length: km (not included the G5D.2-G8B.2 underground cable which is mentioned below). - steering angle: Conductor: ACSR 400/51. - Overhead Ground Wires: PHLOX-181,6,1 - Optical Overhead Ground Wire: OPGW Insulator: suspended insulator by glass or polymer, manufactured based on standard IEC. - Tower: tower with 4 circuits, shared towers with the 220kV-2 connection line. Spot casting reinforced concrete foundation. - Foundation: spot casting reinforced concrete foundation. - Earthing: Rod join grounding bar G5D.2-G8B.2 underground cable belonging to the 220kV-1 connection line - Voltage level: 220kV. - Number of circuit: 02 circuits. - The start point: G5D.2. - The end point: G8B.2. - The length: 1,920 m. - Number of connection box: Conductor: 220kV-XLPE-2000mm 2. - Cable output: outdoor, insulated SF 6 gas. - Lightning arresters: 192kV, 1 phase, outdoor. - Earthing: all sites of connection box and commutation of cable cover. - Cable pipe: HDPE 260/200 (and 01 standby pipe) kV-2 connection line - Voltages: 220kV. - Numbers of circuit: 02 circuits (layout to the right, shared towers with the 220kV-1 connection line). - The start point: 500kV Tan Uyen substation. Power Engineering Consulting Joint Stock Company 3 12

13 - The end point: DDN.2 belonging to 220/110kV Long Binh - Thu Duc transmission line in T.42B tower (new tower) between 2 towers T.21 and T The length: km (not included the G5D.2-G8B.2 underground cable which is mentioned below). - steering angle: Conductor: 2xACSR-400/51. - Overhead Ground Wires: shared with the 220kV-1 connection line. - Insulator: suspended insulator by glass or polymer, manufactured based on standard IEC - Tower: tower with 4 circuits, shared towers with the 220kV-1 connection line. Spot casting reinforced concrete foundation. - Foundation: spot casting reinforced concrete foundation (shared foundations with the 220kV-1 connection line). - Earthing: Rod join grounding bar (shared with the 220kV-1 connection line) G5D.2-G8B.2 underground cable belonging to the 220kV-2 connection line - Voltage level: 220kV. - Number of circuits: 02 circuits. - The start point: G5D.2. - The end point: G8B.2. - The length: 1,920m. - Number of connection box: Conductor: 220kV-XLPE-2000mm 2. - Cable output: outdoor, insulated SF 6 gas. - Lightning arresters: 192kV, 1 phase, outdoor. - Earthing: shared with the underground cable of the 220kV-1 connection line. - Cable pipe: HDPE 260/200 (and 01 standby pipe). 1.3 Objectives of Resettlement Plan The Resettlement Plan is established for the following objectives: - Involuntary resettlement must be avoided where possible, or be reduce to the lowest possible extent by selecting appropriate design options. - Where involuntary resettlement is unavoidable, the resettlement activities must be prepared and executed with sustainable development programs and sufficiently provided investment supports, enabling displaced people to benefit from the subproject. - The displaced people will be fully consulted and allowed to participate in preparatory and implementing activities of Resettlement Plan.APs must be supported in terms of Power Engineering Consulting Joint Stock Company 3 13

14 their capacity to improve their living conditions and to rehabilitate their living standards higher than or at least equal to that before constructing the subproject. 2. LEVEL OF IMPACTS OF THE SUBPROJECT 2.1 Determination of the subproject's impacts Determination of affected scope/area of the subproject The subproject will affect Phuoc Thanh commune and Thai Hoa township Tan Uyen district; Tan Binh ward Di An town Binh Duong province; Tan Hanh, Hoa An communes and Buu Hoa ward Bien Hoa city Dong Nai province. Scope and areas affected by the subproject include: Component with land acquisition - The area at location of substation and access road: 115,503 m 2. - The area at location of underground cables: for safety of the underground cables, the subproject will require permanently land within the ROW: 1,920m x 4.5m = 8,640 m 2. - The area at location of tower foundations of the overhead connection lines: m 2 per foundation Component with temporary impacts - ROW of the overhead connection lines will be affected due to restricted usability and construction activities (from 1 to 2 months): 10,490m x 27m = 283,230 m 2. - Temporary land acquisition for access roads during construction is not necessary because existing roads, alleys and lane will be used in the construction process Determination of affected people (APs) by the subproject Determination of affected people and eligibility criteria The Tan Uyen 500kV substation subproject has only impacts covered in paragraph 3a of OP The eligibility criteria for compensation will include: (a) those who have formal legal rights to land or other assets; (b) those who initially do not have formal legal rights to land or other assets but have a claim to legal rights based upon the laws of the country; upon the possession of documents such as land tax receipts and residence certificates; or upon the permission of local authorities to occupy or use the project affected plots; and (c) those who have no recognizable legal right or claim to the land they are occupying. Persons covered under (a) and (b) are provided compensation for the land they lose, and other assistance. Persons covered under (c) are provided resettlement assistance, in lieu of compensation for the land they occupy, and other assistance, as necessary Number of affected persons and households According to the survey result, there are 334 HHs (1,375 persons) affected by the subproject, including the following types of impact: - Household has residential land/ productive land affected partially or fully (temporarily or permanently). - Household has house/structure affected partially or fully (temporarily or permanently). - Household has trees, crops affected partially or fully (temporarily or permanently). Power Engineering Consulting Joint Stock Company 3 14

15 Summarized result is shown in the following tables (Please see more details in Appendix 6: Inventory of APs by the subproject). Permanent affected persons Table 2.1 Number of AHs by the subproject Content 1. AHs have productive land required permanently less than 20% of the total area of the landholding, or less than 10% for the poor and vulnerable group 2. AHs have productive land required permanently from 20% to 70% the total area of the landholding, or more than 10% for the poor and vulnerable group 3. AHs have productive land required permanently more than 70% of the total area of the landholding Number of HHs Number of persons AHs have residential land required permanently AHs have houses/structures to be dismantled and relocated AHs have graves to be dismantled and relocated AHs have trees, crops required permanently Temporary affected persons 1. AHs have productive land affected temporarily AHs have residential land affected temporarily AHs have house/structure in the ROW (27m in width) AHs have trees, crops affected temporarily by the subproject Note: It is noted that 1 AH may fall into more than 1 impact category. No. Table 2.2 Number of AHs and APs based on the local boundary Province/ district/ commune 1 Binh Duong province 1.1 Tan Uyen district Affected households and persons Number of AHs (household) Number of APs (person) Thanh Phuoc commune Thai Hoa township Di An town Tan Binh ward Dong Nai province 2.1 Bien Hoa city Tan Hanh commune Hoa An commune Power Engineering Consulting Joint Stock Company 3 15

16 No. Province/ district/ commune Affected households and persons Number of AHs (household) Number of APs (person) Buu Hoa ward Impact level 334 1,375 According to the survey result, impact level of the subproject is as follows: - 05 AHs (21 persons) have to dismantle their houses/structures and relocate AHs (9 persons) have to remove their graves AHs (355 persons) are required permanently land from 4.0% to 100% of the total area of the landholding, in which: + 44 AHs will lose less than 10% of total productive land area + 08 AHs who belong to the vulnerable group will lose less than 10% of total productive land area AHs will lose from 20-70% of total productive land area AHs will lose more than 70% of total productive land area. Please see more details in Appendix 6: Inventory of AHs by the subproject Vulnerable groups According to the survey result, there are 77 female headed households (315 persons). There is no AH belonging to poor household or ethnic minorities. 2.2 Types of the subproject's impacts The subproject can cause some impacts as: Permanent impacts: - Productive land acquisition for substation, access road, underground cables and tower foundations of the overhead connection lines. - Residential land acquisition for substation - Dismantling houses on permanently acquired land. - Removing graves on permanently acquired land. - Cutting down crops on permanently acquired land. - Cutting down trees on permanently acquired land. Temporary impacts: - Restricting usability of land in the ROW for safety of the overhead line and temporarily affected by construction activities. - Improving and installing fireproof materials and lightning arrestors for all houses and structures in the ROW to meet regulations in Decree No.106/2005/ND-CP and Decree No.81/2009/ND-CP of the Government (width is 27m, it is 13.5m from center of the T/L to sides). Power Engineering Consulting Joint Stock Company 3 16

17 - Installing fireproof materials and lightning arrestors for all houses and structures in earthing corridor to meet regulations in Circular No.03/TT-BCT dated Jan. 22nd, 2010 of Ministry of Industry and Trade (with distance of 30m from center of the T/L to sides). - Cut down trees, crops in the ROW for construction activities. The subproject does not impact on public structures and business Productive land For construction of substation, access road, tower foundations of overhead connection lines and underground cables, the subproject will permanently require 133,092m 2 productive land area of AHs, including 121,299m 2 land area of Tan Uyen district, 2.858m 2 land area of Di An town and 8,934 m 2 land area of Bien Hoa city. No. Province/ district/ commune 1 Binh Duong province Table 2.3 Productive land acquisition Annual tree land Perennial tree land Pond land Unit: m Tan Uyen district 107,382 12,830 1, , Thanh Phuoc commune 102,804 12,372 1, , Thai Hoa township 4, , Di An town 2, , Tan Binh ward 2, ,858 2 Dong Nai province 2.1 Bien Hoa city 6,105 2, , Tan Hanh commune 1, , Hoa An commune 2,315 1,791-4, Buu Hoa ward 2, , Residential land 116,345 14,897 1, ,091 In order to minimize the impact on the lives of APs, the items which need to recover permanent land as substation, access road, tower foundations of overhead connection lines and underground cables, will be selected design in productive land. However, the construction site is expected for the substation, despite selection, design and implementation of mitigation measures, the subproject still needs to permanently require 1,302m 2 in area of residential land. The total area of the landholding belongs to 5 households in Cay Da hamlet, Thanh Phuoc commune, Tan Uyen district, Binh Duong province. Table 2.4 Residential land acquisition No. Province/ district/ commune Residential land 1 Binh Duong province Unit: m 2 Power Engineering Consulting Joint Stock Company 3 17

18 No. Province/ district/ commune Residential land 1.1 Tan Uyen district 1, Thanh Phuoc commune 1, Thai Hoa township Di An town Tan Binh ward - 2 Dong Nai province 2.1 Bien Hoa city Tan Hanh commune Hoa An commune Buu Hoa ward Houses 1,302 On the 1,302m 2 area of permanently required residential land for the substation, the subproject will dismantle and relocate 5 houses of 5 AHs belonging to Cay Da hamlet, Thanh Phuoc commune, Tan Uyen district, Binh Duong province. No. Province/ district/ commune 1 Binh Duong province Table 2.5 Dismantled houses (relocated) House grade 4 (Brick wall, metal roof) Unit m Tan Uyen district Thanh Phuoc commune Thai Hoa township Di An town Tan Binh ward Dong Nai province 2.1 Bien Hoa city Tan Hanh commune Hoa An commune Buu Hoa ward Graves Also on the 1,302m 2 area of permanently required residential land for the substation, besides relocating houses, the subproject will remove 6 graves of 2 AHs belonging to Cay Da hamlet, Thanh Phuoc commune, Tan Uyen district, Binh Duong province. Power Engineering Consulting Joint Stock Company 3 18

19 Table 2.6 Removed graves No. Province/ district/ commune Grave (unit) 1 Binh Duong province 1.1 Tan Uyen district Thanh Phuoc commune Thai Hoa township Di An town Tan Binh ward - 2 Dong Nai province 2.1 Bien Hoa city Tan Hanh commune Hoa An commune Buu Hoa ward Crops 6 On the 133,092m 2 area of permanently required productive land, the subproject will cut annual crops for construction of items. area of paddy and crops will be cut is 116,345 m 2, mainly concentrated in the substation area and along the connection lines of 6 communes belonging to Binh Duong and Dong Nai provinces. Table 2.7 Permanently affected crops No. Province/ district/ commune Paddy and crops (m 2 ) 1 Binh Duong province 1.1 Tan Uyen district 107, Thanh Phuoc commune 102, Thai Hoa township 4, Di An town 2, Tan Binh ward 2,858 2 Dong Nai province 2.1 Bien Hoa city 6, Tan Hanh commune 1, Hoa An commune 2, Buu Hoa ward 2, Trees 116,345 Similar to crops, on the 133,092m 2 area of permanently required productive land, the subproject will cut trees for construction of items. number of trees will be cut is 1,217 Power Engineering Consulting Joint Stock Company 3 19

20 trees including 1,125 cajuput trees, 19 rubber trees and 73 banana trees, belonging to Thanh Phuoc commune and Thai Hoa township, Tan Uyen district, Binh Duong province and Hoa An commune, Bien Hoa city, Dong Nai province. No. Province/ district/ commune 1 Binh Duong province Table 2.8 Permanently affected trees Cajuput (tree) Rubber (tree) Banana (tree) (tree) 1.1 Tan Uyen district Thanh Phuoc commune Thai Hoa township Di An town Tan Binh ward Dong Nai province Bien Hoa city Tan Hanh commune Hoa An commune Buu Hoa ward Temporary impacts 1, , Temporary impacts on productive land Land in the ROW of the overhead connection lines will be restricted usability and affected by construction activities (called temporary impact). area of temporarily affected productive land is 242,524 m 2, including 175,120m 2 of annual crop land, 14,283m 2 of perennial tree land, 19,818m 2 of pond land and 33,304m 2 of quarry land. The entire productive land goes along the connection lines belonging to 6 communes of Binh Duong and Dong Nai provinces. Table 2.9 Temporary impacts on productive land Unit: m 2 No. Province/ district/ commune Annual crop land Perennial tree land Pond land Quarry land 1 Binh Duong province 1.1 Tan Uyen district 91,023 11, , Thanh Phuoc commune 32,390 1, , Thai Hoa township 58,633 9, , Di An town 30,591-7,452-38, Tan Binh ward 30,591-7,452-38,043 Power Engineering Consulting Joint Stock Company 3 20

21 No. Province/ district/ commune Annual crop land Perennial tree land Pond land Quarry land 2 Dong Nai province 2.1 Bien Hoa city 53,506 3,105 11,718 33, , Tan Hanh commune 13,315 3,105 9,909-26, Hoa An commune 30, ,706 42, Buu Hoa ward 10,148-1,809 20,597 32, ,120 14,283 19,818 33, , Temporary impacts on residential land Similar to productive land, residential land in the ROW of the 220kV overhead connection lines will be affected due to restricted usability (called "temporarily affected"). The total temporarily affected residential land area is 16,986 m 2, including 6,218 m 2 of Tan Uyen District and 1,755 m 2 of Di An town, Binh Duong province and 9,014 m 2 of Bien Hoa city, Dong Nai province. Table 2.10 Temporary impacts on residential land No. Province/ district/ commune Residential land (m 2 ) 1 Binh Duong province 1.1 Tan Uyen district 6, Thanh Phuoc commune Thai Hoa township 5, Di An town 1, Tan Binh ward 1,755 2 Dong Nai province 2.1 Bien Hoa city 9, Tan Hanh commune 1, Hoa An commune 6, Buu Hoa ward 1, Temporary impacts on houses and structures: 16,986 According to Decree No.106/2005/ND-CP dated Aug.17, 2005 and Decree No.81/2009/ND-CP dated Oct.12, 2009, all houses and structures in the ROW of 220kV T/Ls still exist if they meet safety conditions, whereby: - House/structure with tile roof and brick wall is still existed. - House/structure made by metal materials in the ROW will be required to install lightning arrestors. - House/structure made by wooden or leaf will be required to improve and install fireproof materials and lightning arrestors. Power Engineering Consulting Joint Stock Company 3 21

22 Besides, all houses and structures in the ROW will be restricted usability, and owners' daily activities are also affected. The survey results showed that a total of 119 houses in the ROW belonging to 6 communes of Binh Duong and Dong Nai provinces, including: No houses grade 4 with structure of brick wall and tiled roof (they are allowed to exist without improvement or installing fireproof materials and lightning arrestors) houses grade 4 with structure of brick wall and metal roof (they must be installed fireproof materials and lightning arrestors to exist). - 3 temporary houses with wooden walls or thatched roof (they need to be improved and installed fireproof materials and lightning arrestors to exist). Table 2.11 Temporarily affected houses and structures (no relocation) Province/district/ commune 1 Binh Duong province 1.1 Tan Uyen district House Cat. 4 (brick wall, tiled roof) Temporarily affected houses and structures House Cat. 4 (Brick wall, metal roof) House Cat. temporary (thatched wall) Unit m 2 Unit m 2 Unit m 2 Unit m Thanh Phuoc Thai Hoa township 18 1, , , Di An town Tan Binh ward , ,755 2 Dong Nai province 2.1 Bien Hoa city Tan Hanh commune , , Hoa An commune , , Buu Hoa ward , , , , , Temporary impacts on crops For construction and stretching the overhead connection line, 175,120m 2 of rice and crops of all kinds in the ROW may be temporarily affected by the subproject. After stretching wire, local people can continue cultivating the same as before subproject construction. The whole area of of rice and crops along the overhead connection line belongs to 6 communes of Binh Duong and Dong Nai provinces. Power Engineering Consulting Joint Stock Company 3 22

23 Table 2.12 Temporarily affected crops No. Province/ district/ commune Paddy and crops (m 2 ) 1 Binh Duong province 1.1 Tan Uyen district 91, Thanh Phuoc commune 32, Thai Hoa township 58, Di An town 30, Tan Binh ward 30,591 2 Dong Nai province 2.1 Bien Hoa city 53, Tan Hanh commune 13, Hoa An commune 30, Buu Hoa ward 10, Temporary impacts on trees 175,120 For construction and stretching the overhead connection wire, 4,594 trees of all kinds in the ROW may be temporarily affected by the subproject, including 4,220 cajuputs, 112 pomelo trees, 73 mango trees, 189 banana trees in Thanh Phuoc commune and Thai Hoa township, Tan Uyen district, Binh Duong province and Tan Hanh commune, Bien Hoa city, Dong Nai province. After stretching wire, local people can continue planting trees, however it needs to ensure the safety distance from the lowest point of the line to the highest of tree is over or equal to 6m. No. Province/ district/ commune 1 Binh Duong province Table 2.13 Temporarily affected trees Cajuput Pomelo Mango Banana tree tree tree tree tree 1.1 Tan Uyen district 4, , Thanh Phuoc commune 1, , Thai Hoa township 3, , Di An town Tan Binh ward Dong Nai province 2.1 Bien Hoa city Tan Hanh commune Hoa An commune Power Engineering Consulting Joint Stock Company 3 23

24 No. Province/ district/ commune 1 Binh Duong province Cajuput Pomelo Mango Banana tree tree tree tree tree 1.1 Tan Uyen district 4, , Buu Hoa ward , ,594 Power Engineering Consulting Joint Stock Company 3 24

25 3. LEGAL FRAMEWORK AND COMPENSATION POLICY 3.1 Legal framework Policies of Vietnam Regulations of the Government of Vietnam on compensation, assistance and resettlement shall be applied to this subproject as follows: - The Constitution of Vietnam The Land Law 2003, No.13/2003/QH11, issued on November 26, 2003 (to be replaced by the Land Law 2013 which become effective from July 1, 2014) - Decree No.181/2004/ND-CP issued on October 29, 2004 guiding the implementation of the Land Law revised Decree No.188/2004/ND-CP issued on November 16, 2004 providing the method of land price calculation and the tariff for all types of land; - Decree No.197/2004/ND-CP issued on December 3, 2004 on compensation, support and resettlement when land is recovered by the state. - Decree No.188/2004/ND-CP issued on November 16, 2004 on methods to determine land prices and assorted land price brackets. - Decree No.123/2007/ND-CP dated July 27, 2007, on revision and supplementation of some regulations in decree 188/2004/ND-CP of November 16, 2004 on methods to determine land prices and assorted land price brackets. - Decree No.17/2006/ND-CP dated January 27, 2006 on revision and supplementation of some regulations in decrees guiding the implementation of the Land Law and Decree No.187/2004/ND-CP on transformation of state companies into joint-stock companies. - Decree No.84/2007/ND-CP dated May 25, 2007 on revision of issuing LURC, land acquisition, implementation of land use right, procedure for compensation, resettlement when land acquired by State and grievance redress. - Decree No.69/2009/ND-CP, effective October 1, 2009; an amendment to Decree No.197/2004/ND-CP; supplementary regulations on land use planning, land prices, land acquisition, compensation, support and resettlement. - Circular No.116/2004/TT-BTC dated December 17, 2004 providing guidance for the implementation of Decree No.197/2004/ND-CP dated December 3, 2004 on compensation, assistance and resettlement upon the State recovery of land; - Circular No.14/TT-BTNMT dated October 1, 2009 providing detailed regulations on compensation, assistances, relocation and process and procedures for land acquisition, land hand-over and land lease. - Circular No.57/2010/TT-BTC issued on April 16, 2010 prescribing the estimation, use and settlement of funds for compensation, support and resettlement upon recovery by the State. - Circular No.02/2010/TTLT-BTNMT-BTC dated January 8, 2010 issued by the Ministry of Natural Resource and Environment and Ministry of Finance guiding the preparation appraisal, and issuance and revision of land prices revision and the competence of the city/province PC under the National Government control. Power Engineering Consulting Joint Stock Company 3 25

26 - Decision No.1956/2009/QD-TTg, dated November 17, 2009 by the Prime Minister approving the Master Plan on vocational training for rural labors by Decision No.52/2012/QD-TTg, dated November 16, 2012 on the support policies on employment and vocational training to farmers whose agricultural land has been recovered by the State. - The Electricity Law 2004, No.28/2004/QH11, ratified on December 3, Decree No.106/2005/ND-CP (and its associated guiding circulars) dated August 17, 2005, guiding the implementation of a number of articles under the Electricity Law regarding safety protection of high-voltage power grid. - Decree No.81/2009/ND-CP (and its associated guiding circulars) dated October 12, 2009, amending or supplementing a number of articles of the government s decree No.106/205/ND-CP of August 17, 2005 which details and guide a number of articles of the electricity law regarding the safe protection of high-voltage power grid works. - Circular No.03/2010/TT-BCT dated on January 22, 2010 of Ministry of Industry and Trade, regulating a number of articles under decrees 106/2005/ND-CP and decree 81/2009/ND-CP. The following are current regulations on compensation, allowance, and resettlement of Dong Nai and Binh Duong provinces would be applied in RP of this subproject: Dong Nai province: - Decision No.12/2012/QD-UBND dated Feb. 23, 2012 of Dong Nai PPC promulgating the regulations on compensation unit prices of properties in the area of Dong Nai province. - Decision No.14/2012/QD-UBND dated Feb. 24, 2012 of Dong Nai PPC promulgating the regulations on compensation unit prices of houses when the State recovers land in the area of Dong Nai province. - Decision No.25/2012/QD-UBND dated April 3, 2012 of Dong Nai PPC promulgating regulations on compensation, assistance and resettlement when the State recovers land in the area of Dong Nai province. - Decision No.76/2012/QD-UBND dated Dec.19, 2012 of Dong Nai PPC promulgating the regulations on land prices in 2013 in the area of Dong Nai province. Binh Duong province: - Decision No.87/2009/QD-UBND dated Dec. 21, 2009 of Binh Duong PPC promulgating regulations on compensation, assistance and resettlement when the State recovers land in the area of Binh Duong province. - Decision No.58/2011/QD-UBND dated Dec. 19, 2011 of Binh Duong PPC promulgating the regulations on compensation unit prices of houses, structures, trees and crops in land when the State recovers land. - Decision No.58/2012/QD-UBND dated Dec. 18, 2012 of Binh Duong PPC promulgating the regulations on land prices in 2013 in the area of Binh Duong province Policies of WB The World Bank s OP 4.12 Involuntary Resettlement includes the following principles: Power Engineering Consulting Joint Stock Company 3 26

27 - Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs; - Where it is not feasible to avoid resettlement, resettlement activities should be conceived and executed as sustainable development programs, providing sufficient investment resources to enable the persons displaced by the project to share in project benefits. Project affected persons should be meaningfully consulted and should have opportunities to participate in planning and implementing resettlement programs; - Project affected persons should be assisted in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher Compatibility between policies of Government and the World Bank and require wavers Although the recent legislation on resettlement of Vietnam tends to be more consistent with that of the World Bank, there still exists some discrepancies required particular attention. The differences between the Government s Laws and Decrees and World Bank Policy with regard to resettlement and compensation, and how to address these gaps are shown in Table below: Table 3.1 Comparison of Vietnam s and World Bank s Policies related to Involuntary Resettlement Subjects Bank s OP 4.12 Policy objectives Support for affected households who have no recognizable legal right or claim to the land they are occupying DPs should be assisted in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to predisplacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher Financial assistance to all project affected persons to achieve the policy objective (to improve their livelihoods and standards of living or at least to restore them, in real terms, to predisplacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher) Land Property Government of Vietnam Resettlement site and its infrastructure should have equal or better development conditions than the existing one. Financial assistance provided at different levels depending on the legal status of affected persons Project Measures Livelihoods and income sources will be restored in real terms, at least, to the pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher. Financial assistance of an agreed amount will be given to all DPs, regardless of their legal status, until their livelihoods and standards of living restore in real terms, at least, to predisplacement levels. Power Engineering Consulting Joint Stock Company 3 27

28 Compensation for illegal structures Methods for determining compensation rates Compensation for loss of income sources or means of livelihood Compensation for indirect impact caused by land or structures taking Livelihood restoration and assistance Consultation and disclosure Compensation at full cost for all structures regardless of legal status of the DP s land and structure. Compensation for lost land and other assets should be paid at full replacement costs, Loss of income sources should be compensated (whether or not the affected persons must move to another location) It is good practice for the borrower to undertake a social assessment and implement measures to minimize and mitigate adverse economic and social impacts, particularly upon poor and vulnerable groups. Provision of livelihood restoration and assistance to achieve the policy objectives. Participation in planning and implementation, specially confirming the eligibility criteria for Compensation Provided to cover the new structure costs. Depending on the illegality status attributed, covering between 80% and 0% of the total costs Compensation for lost assets is calculated at price close to transferring the assets in local markets or the cost of newly-built structures. Provincial governments are granted to annually set up compensation prices for different categories of assets Assistance in respect of income loss is given only for registered businesses. For affected persons losing agricultural land, additional financial support will be provided. Not addressed. Livelihood restoration and assistance measures are provided. No followup for full livelihood restoration after resettlement completion. Limited mostly to information sharing and disclosure. Compensation at full replacement cost will be given for all structures affected, regardless of legal status of the land and structure. Independent appraiser identifies replacement costs for all types of assets affected. Provincial government will use this assessment to establish the compensation rates at full replacement. All income losses are to be compensated and, where necessary to achieve the objectives of the policy, development assistance in addition to compensation will be provided. Socio-economic assessment has been undertaken and measures identified and being implemented to minimize and mitigate adverse impacts, particularly upon poor and vulnerable groups. Provision of livelihood restoration and assistance measures to achieve the policy objectives. These will be monitored as detailed in the RP Consultation and participation incorporated into RP design, along with Power Engineering Consulting Joint Stock Company 3 28

29 compensation and assistance, and access to Grievances Redress Mechanisms Grievance redress mechanism should be independent Grievance redress mechanism Internal and independent monitoring are required Monitoring & Evaluation The same governmental body makes decisions on compensation and resettlement, and also handles grievances at the first step; There is no explicit requirements on monitoring, including both internal and independent (external) monitoring information sharing with DPs and stakeholders. Priority will be given to the participation of women in the consultation processes. Independent Grievance and Redress mechanisms are to be established, built on the existing governmental system, with monitoring by an independent monitor Both internal and external (independent) monitoring is to be regularly maintained (on a monthly basis for internal and biannual basis for independent monitoring). An endof-project report will be done to confirm whether the objectives of OP 4.12 were achieved. As a World Bank member country, the Government of Vietnam has committed that, should the international agreements signed or acceded to by Vietnam with the World Bank contain provisions different from those in the present resettlement legal framework in Vietnam, the provisions of the international agreements with the World Bank shall prevail. The RPF of the TEP confirms that in approving this instrument, the Government of Vietnam and the Province/City People s Committee, grant the waivers to the relevant articles in various Vietnamese laws that contradict or are not consistent with the objectives set forth in the RPF. The measures taken to address the differences and comply with World Bank involuntary resettlement policies are addressed under the RPF. 3.2 Compensation policy Principles All DPs who have assets within or reside within the area of project land-take before the cut-off date are entitled to compensation or assistance for their losses. Those who have lost their income and/or subsistence will be eligible for livelihood rehabilitation assistance, based Power Engineering Consulting Joint Stock Company 3 29

30 on the criteria of eligibility defined by the project and in consultation with the DPs.1 If, by the end of the project, livelihoods have been shown not to be restored to pre-project levels, additional measures will be provided. - The compensation rates will be determined based on the results of independent land/assets appraisal in a timely and consultative fashion. All fees and taxes on land and/or house transfers will be waived or otherwise included in a compensation package for land and structures/houses or businesses. The local authorities will ensure that DPs choosing relocation on their own obtain, without additional cost, the necessary property titles and official certificates commensurate with similar packages provided to those who choose to move to the project resettlement sites. - Land will be compensated land for land or in cash according to the DP s choice whenever possible. The choice of land for land must be offered to those losing 20% or more of their productive land. If land is not available, the borrower must assure itself that this is indeed the case. Those losing 20% or more of their land will have to be assisted to restore their livelihood. The same principles apply for the poor and vulnerable people losing 10% or more of their productive landholding. - DPs that prefer land for land will be provided with land plots with the equivalent productive capacity for lost lands or a combination of land (a standard land plot) in a new residential area nearby for residential land, and cash adjustment for the difference between their lost land and the land plots provided. The resettlement area will be planned properly and implemented in consultation with the DPs. All basic infrastructures, such as paved roads, sidewalks, drainage, water supply, and electricity and telephone lines, will be provided. - DPs that prefer cash for land will be compensated in cash at the full replacement cost. These DPs will be assisted in rehabilitating their livelihoods and making their own arrangements for relocation. - Compensation for all residential, commercial, or other structures will be offered at the replacement cost, without any depreciation of the structure and without deduction for salvageable materials. Structures shall be evaluated individually. Any rates set by category of structure must use the highest value structure in that group (not the lowest). - The DPs will be provided full assistance (including a transportation allowance) for transportation of personal belongings and assets, in addition to the compensation at replacement cost of their houses, lands, and other properties. - Plans for acquisition of land and other assets and provision of rehabilitation measures will be carried out in consultation with the DPs (with particular attention to vulnerable DPs), to minimize the disturbance and shorten the resettlement transition period. The rehabilitation measures will be provided to the DP's prior to the expected start-up date of works in the respective project sites. - If, by the end of the project, livelihoods have been shown not to be restored to preproject levels, additional measures should be considered. - 1 For impacts (other than involuntary resettlement) on ethnic minority communities, refer to Ethnic Minority Planning Framework (EMPF) developed under TEP for appropriate instructions. Power Engineering Consulting Joint Stock Company 3 30

31 - Financial services (such as loans or credits) will be provided to DPs, if necessary. The installment amounts and the schedule of payments will be within the repayment capacity of DPs. - Additional efforts, such as economic rehabilitation assistance, training and other forms of assistance, should be provided to DPs losing income sources, especially to vulnerable groups in order to enhance their future prospects toward livelihood restoration and improvement. - The previous level of community services and resources, encountered prior to displacement, will be maintained or improved for resettlement areas. - Contractors can only commence civil works after (i) the governmental competent agency has satisfactorily completed compensation payments and rehabilitation assistances in accordance to approved RP for that sub-project; (ii) alreadycompensated DPs have cleared the area in a timely manner; and (iii) the area is free from any encumbrances. Temporary Resettlement: relocation of any households more than once should be avoided, because it leads to DPs being impacted twice or more and will slow down the livelihood restoration time. If it must happen, these households should be considered for additional benefits as they have been impacted twice. If the implementing agency has verified that temporary resettlement is unavoidable for such reasons as the final resettlement is subject to the temporary resettlement (e.g., construction of the resettlement site will not take place until the DPs are temporarily relocated) and an implementation plan for the final resettlement is agreed by the DPs and approved by District People s Committee (DPC) or Provincial People s Committee (PPC) and the Bank, then an additional assistance package is offered Policies on compensation, assistance and resettlement applied to the subproject Compensation for Loss of Agricultural Land Legal and Legalized Land Users If the lost area represents less than 20% of a Household s (HH s) land holding (or less than 10% for poor and vulnerable groups), and the remaining area is economically viable, compensation in cash will be at 100% replacement cost for the lost area. If the lost area represents 20% or more of the HHs land holding, (or 10% or more for the poor and vulnerable groups) or the remaining area is economically not viable, then land for land compensation should be considered as the preferred option. a. If no land is available, then implementing agencies (IAs) must demonstrate this to the World Bank s satisfaction before proceeding. b. If land is not available, or if the DP prefers cash compensation, then cash compensation will be provided for the lost area at 100% of land replacement cost, and the DP will be provided with rehabilitation measures to restore the lost income sources, such as agricultural extension, job training, credit access, provision of non-agricultural land at a location appropriate for running off-farm business or services. c. If the DPs wish, and there is land of similar value elsewhere, the project should also assist these DPs to visit these areas and help with legal transactions should they wish to acquire them. d. For agricultural land lying intermixed with residential areas, and garden and pond land lying adjacent to residential areas, apart from compensation at the price of agricultural Power Engineering Consulting Joint Stock Company 3 31

32 land having the same use purpose, monetary support shall also be provided; with the prices for such support being equal to between 50% and 70% of the prices of adjacent residential land; and with the specific support levels being decided by the Provincial People's Committees (PPC) to suit local conditions. Users with temporary or leased rights to use communal/public land (DPs who rent communal or public land) Cash compensation at the amount corresponding to the remaining investment put on the land or corresponding to the remaining value of the land rental contract, if it exists. For DPs currently using land assigned by State-owned agricultural or forestry farms on a contractual basis for agricultural, forestry, or aquaculture purposes (excluding land under special use forests and protected forests), compensation shall be provided for investments made on the land, but not for the land itself, and these DPs may also receive additional support according to the following provisions: a. Additional monetary support shall be provided for DPs that receive land on a contractual basis and are public employees or workers of State-owned agricultural or forestry farms, or who are former employees of such farms and who are now receiving an allowance related to their former employment. The highest level of additional monetary support shall be equal to the price of land to be compensated, calculated on the basis of the value of the affected land area which shall, however, not exceed the local agricultural land assignment limits. The PPC shall decide on the specific support levels to suit the local conditions but the additional monetary support shall not be less than 70% of the compensation value for the land actually acquired. b. Where DPs receive land on a contractual basis but are other than the individuals specified at (a) above, they shall only receive compensation for investments made on the land. Land Users without formal or customary recognized rights to the affected land Instead of compensation, these DPs will receive rehabilitation assistance up to 100% of the land value in cash. DPs will be entitled to rehabilitation measures mentioned above to ensure their living standards are restored. In case the land is rented through civil contract between individuals, households, or organizations, then the compensation for crops, trees, or aquaculture products will be paid to the affected land users and the project client shall assist the renter to find similar land to rent. In cases when DPs utilize public land (or protected areas), with an obligation to return the land to the Government when requested, the DPs will not be compensated for the loss of use of the land. However, these DPs will be compensated for crops, trees, structures and other assets they own or use, at full replacement cost. Although they cannot reside in such public safety-hazard areas, if access has not been denied previously through well-documented signs and such things as fences, the social and baseline assessment should consider if such a physical impediment (like a newly restricted public safety area) is causing loss of livelihood due to people no longer being able to get to jobs and other assets associated with their subsistence as a result of restricted safety zone definition, which may for example add significant cost to traveling from home to business, schools, etc Compensation for Loss of Residential Land Losing of residential land without associated structures: Compensation for loss of land in cash at replacement cost to legal and/or legalizable land users. For land users who have Power Engineering Consulting Joint Stock Company 3 32

33 no recognizable land use right, financial assistance of an agreed amount will be provided. The amount will be determined by the respective Provincial People s Committee. Loss of residential land with associated structures and the remaining land is sufficient to rebuild the structure (reorganizing DP): Compensation for loss of land will be made in cash at (i) full replacement cost for legal and legalizable land users; (ii) Financial assistance of an agreed amount will be provided to land users who do not have recognizable land use rights. If DPs have to rebuild their houses, they will be provided with a rental allowance for a period of 3 months while their houses are being rebuilt. Loss of residential land with associated structures and the remaining land is insufficient to rebuild the structure (relocating DP): other than specific provisions listed below, in case where relocated DPs belong to vulnerable groups, the project will consider providing them with additional assistance (in cash and kind) to ensure that they can afford to relocated to a new site. (i) For DPs who have legal or legalizable rights to the affected land: - A land plot of equivalent size and quality, in a well-developed resettlement site. Where land is not available, an apartment will be provided to the DP. The will be done in consultation with the DP. Full ownership title to the land or apartment will be given at no cost to the DP. OR, - On request of and with full consultation with the DP, cash compensation at full replacement cost, plus the amount equivalent to the value of the infrastructure investments calculated as an average for each household in a resettlement site. In this case, the household will be expected to relocate themselves. In the event that the compensation (or assistance) amount accounts less than the cost of a land plot in the project s resettlement site, DPs will be supported with the difference required for the acquisition of the land plot. If a land plot in the project resettlement site is not the chosen DP s option, cash assistance will be provided equivalent to difference required to acquire a chosen land plot. (ii) DPs who do not have formal or customary rights to the affected land: - An identified assistance amount will be provided based on the level of legality of the land and on a case by case basis. - If the DP has no place to move, a land plot or an apartment satisfactory to them will be provided in the resettlement site Compensation Policy for Loss of Houses/Structures Houses Compensation or assistance in cash will be made for all affected private-owned houses/structures, at 100% of the replacement costs for materials and labor, regardless of whether or not they have title to the affected land or a construction permit for the affected structure. The compensation will be sufficient to rebuild the affected house/structure of the same quality. As per OP 4.12 cash compensation will be at full replacement cost in local markets. No deductions will be made for depreciation or salvageable materials. If the house/structure is partially affected, a financial assistance will be provided to enable DPs to repair the affected house/structures to restore it to the former condition, or better, at no additional cost to them. Power Engineering Consulting Joint Stock Company 3 33

34 Graves Compensation for the removal of graves/ tombs will include the cost of excavation, relocation, reburial and other related costs which are necessary to satisfy customary requirements. Compensation in cash will be paid to each affected family or to the affected group as a whole as is determined through a process of consultation with the affected community. The level of compensation will be decided in consultation with the affected families/communities. Household and individual graves are considered physical cultural resources (PCR) and even though the costs associated with their relocation may be covered in the resettlement plan, the WB OP 4.11 on Physical Cultural Resources should be triggered and relevant cross references should be made to the Environmental Management Plan or project implementation manual. Tenants The tenants of state or organization s houses will be: (i) entitled to rent or buy a new apartment of the area at least equal to their affected one if they/he/she have a demand for; or (ii) provided an assistance equal 60% of replacement cost of the affected land and houses. The structure created by the DPs themselves will be compensated at their full replacement costs. The tenants who are leasing a private house for living purposes will be provided with transportation allowance for moving assets, as well as will be assisted in identifying alternative accommodation Compensation Policy for Loss of Standing Crops and Trees For annual and perennial standing crops, regardless of the legal status of the land, compensation will be paid to the affected persons, who cultivate the land, according to the full market value of the affected crops and/or at replacement cost for affected perennial trees. Regarding the removable affected trees, the compensation will be equal the transportation cost plus actual loss. Perennial crops will be compensated for at the calculated value of their life time productivity Compensation Policy for Loss of Income and/or Business/Productive Assets For DPs losing income and/or business/productive assets as a result of land acquisition, the mechanism for compensating will be: - The registered non-farm producer/business DPs, who have income-generating and/or business/productive assets affected, will be given cash business assistance for the loss of business income, equivalent to 50% of the annual average for the last 3 years net income. (This amount is equivalent to 100% of monthly net income for 6 months). - The non-registered business or non-farm producer DPs, whose operations are recognized by local authority and who have income and/or business/productive assets affected, will be given assistance in cash for the income losses for three months at the minimum - If the business has to be relocated, then, a priority to provide a replacement business site accessible to customers, or, compensation in cash for the affected area at a replacement cost, plus transportation allowance to remove movable attached assets. If there is no land available, then the business/non-farm producer DPs will be entitled for rehabilitation measures such as job training, credit access to help restore the income sources Compensation Policy for Temporary Impact during Construction Power Engineering Consulting Joint Stock Company 3 34

35 In the event of temporary impact during construction, DPs are entitled to the following: - Compensation for all affected assets/investments made on the land, including trees, crops etc., at full replacement cost; - Cash compensation for land temporarily acquired in the form of rent which is at least equivalent to the net income that would have been derived from the affected property during the period of disruption; Damages to Private or Public Structures Damaged property by contractor will be restored by contractors immediately at full replacement value, after completion of civil works, to its former condition. Under their contract specifications, the contractors will be required to take extreme care to avoid damaging property during their construction activities. Where damages do occur, the contractor will be required to pay compensation immediately to affected families, groups, communities, or government agencies at the same compensation rates that are applied to all other assets affected by the subproject. Compensation for loss of community assets: In cases where community infrastructure such as schools, bridges, factories, water sources, roads, sewage systems is damaged, the project will ensure that these will be restored or repaired at no cost for the community and to the community s satisfaction Secondary DPs This applies to those affected by development of individual resettlement or group resettlement sites. Because all secondary DPs are likely to be affected in similar ways as primary ones, they will be entitled to compensation and rehabilitation assistance in accordance with the same respective provisions for all other DPs Allowances and Rehabilitation Assistance Besides the compensation for affected assets, DPs will be provided with financial assistance to cover their expenses during the transition period. The assistance levels will be adjusted, taking into account inflation factor and price increase to be appropriate to the payment time. They include: 1) Transportation allowance: will be given to relocating DPs. The amount will be determined by local authority. 2) House renting allowance or temporary accommodation will be provided for relocating DPs during the time when the DPs are waiting for the land plot or apartment to be ready plus for the period of building the new house. 3) Removal Support: Organizations and DPs that are allocated or leased land by the state or are lawfully using land and have to relocate their productive and/or business establishments are entitled to financial support for dismantling, relocating and re-installation of the establishment. Support levels will be determined by actual costs at the time of removal, based on self-declaration of the organizations and verification by the agency in charge of compensation. This will then be submitted to the relevant authorities for approval. 4) Subsistence allowance for relocating: All DPs (i) relocating within province shall receive a cash allowance equal to 30 kg of rice per month in uninterrupted 03 months; (ii) relocating out of province shall receive a cash allowance equal to 30 kg of rice per month in uninterrupted 06 months; (iii) who are in a severe socioeconomic difficulty or who relocating Power Engineering Consulting Joint Stock Company 3 35

36 to areas of socioeconomic difficulty shall be receive cash allowance equal to 30 kg of rice per month in uninterrupted 12 months. 5) Support for living stabilization: (a) DPs losing 20-70% of their agricultural landholding (or 10-70% for the poor and vulnerable groups) will be provided with the amount equivalent to 30 kg of rice/person/month for 6 months if they do not have to relocate and 12 months in case of relocation. In some special cases, in extremely difficult areas, the compensation may be provided for a maximum of 24 months; (b) DPs losing more than 70% of their agricultural landholding will be assisted for 12 months if they do not have to relocate and 24 months in case of relocation. In some special cases, in extremely difficult areas, the compensation may be provided upto a maximum of 36 months; (c) Households affected by loss of less than 20% of land, where the remaining land is rendered unviable for continued use, will be assisted with the above support plus any additional support as determined, for a period of 12 months. In case of land-for-land compensation, DPs will be assisted with seedlings, agricultural-forestry extension programs, husbandry etc. 6) Support for job changing (with several options provided depending on the interest of the DPs): The support amount is 2-5 times of the agricultural land price for the whole acquired agricultural area but not exceeding the local land allocation limit at the moment of handing over land. 7) Support for training, apprenticeships on vocational training establishments in the province and exemption from tuition fees for the training courses for those of working age (not applicable for those who enroll for a vocational training outside the province). After finishing training courses, they will be given priorities to be recruited in local manufacturers/businesses. 8) Support for the poor and vulnerable groups: Additional support will be provided to the poor and vulnerable groups to ensure they will be able to restore the losses and livelihood at least at pre-project level. 9) Relocation bonus: A bonus of maximum 5 million VND will be awarded to DPs who dismantle their houses and vacate their premises in accordance with the resettlement schedule. 10) Allowance for land in the ROW - Residential land in the ROW of the T/L: According to Item 2 - Clause 6 - Article 1 of Decree No.81/2009/ND-CP of the Government dated Oct. 12, 2009, residential land area in of the T/L will be compensated, supported due to restricted usability. The assistance cost will not exceed 80 % of compensation cost. - Agricultural land in the ROW of the T/L: According to Item 3 - Clause 6 - Article 1 of Decree No.81/2009/ND-CP of the Government dated Oct. 12, 2009, on the same parcel including residential land and other land of the same owner when the ROW of the T/L occupies a space which is larger than the limit of residential land so the other land area on the same parcel in the ROW will be also compensated, supported due to restricted usability. The assistance cost will not exceed 80 % of compensation cost. 11) Allowance for houses/structures in the ROW: According to Item 1 - Clause 5 - Article 1 of Decree No.81/2009/ND-CP of the Government dated Oct. 12, 2009, houses/structures in the ROW of the T/L will be Power Engineering Consulting Joint Stock Company 3 36

37 compensated and supported due to restricted usability and affected on owners' daily activities. The assistance cost will not exceed 70 % of value of houses/structures. Power Engineering Consulting Joint Stock Company 3 37

38 4. COMPENSATION, ASSISTANCE AND RESETTLEMENT 4.1 Compensation Cut-off date: The cut-off date has been fixed during the socio-economic survey and inventory, Oct. 01, The cut-off date has been notified to the competent local authorities when working with the locality performing public consultation. Persons who encroach and move into the area that proposed to be affected area after the subproject s cut-off date will not be entitled to compensation and resettlement. These people will be requested to dismantle affected structures, cut trees or harvest crops for land clearance of the subproject; however, they will not have to pay any fine. The subproject s cut-off date and terms no compensation for the encroachers have been announced clearly in the public meetings. Replacement cost: according to the survey result, the substation, connection lines will be built in the rural area, almost land is used for permanent agricultural production and the land unit price has been relatively steady for 3 years. Through consultation with local authorities and residents, compensation unit prices for land, houses, structures, crops of other projects in the region were applied equivalent to the unit prices issued by PPC and accepted by affected households. Hence, this RP applies the unit prices issued by PPC for estimation. Dong Nai province: - Decision No.12/2012/QD-UBND dated Feb. 23, 2012 of Dong Nai PPC promulgating the regulations on compensation unit prices of properties in the area of Dong Nai province. - Decision No.14/2012/QD-UBND dated Feb. 24, 2012 of Dong Nai PPC promulgating the regulations on compensation unit prices of houses when the State recovers land in the area of Dong Nai province. - Decision No.25/2012/QD-UBND dated April 3,, 2012 of Dong Nai PPC promulgating regulations on compensation, assistance and resettlement when the State recovers land in the area of Dong Nai province. - Decision No.76/2012/QD-UBND dated Dec.19, 2012 of Dong Nai PPC promulgating the regulations on land prices in 2013 in the area of Dong Nai province. Binh Duong province: - Decision No.87/2009/QD-UBND dated Dec. 21, 2009 of Binh Duong PPC promulgating regulations on compensation, assistance and resettlement when the State recovers land in the area of Binh Duong province. - Decision No.58/2011/QD-UBND dated Dec. 19, 2011 of Binh Duong PPC promulgating the regulations on compensation unit prices of houses, structures, trees and crops in land when the State recovers land. - Decision No.58/2012/QD-UBND dated Dec. 18, 2012 of Binh Duong PPC promulgating the regulations on land prices in 2013 in the area of Binh Duong province. It should be noted that land unit prices applied in this RP is only for estimation (at the time of compiling this RP). At the time of implementation of RP (expected to start in Jun. Power Engineering Consulting Joint Stock Company 3 38

39 2014), land compensation unit price will be updated to ensure that APs will be compensated at replacement cost for their losses Compensation unit prices for land Table 4.1 Compensation unit prices for land Unit: VND/m 2 No. Province/district/ commune Residential land Annual crop land Perennial tree land 1 Binh Duong province (Decision No.58/2012/QD-UBND dated Dec. 18, 2012 of Binh Duong PPC) Pond land 1.1 Tan Uyen district Thanh Phuoc 330,000 65,000 75,000 80, Thai Hoa township 330,000 65,000 75,000 80, Di An town Tan Binh ward 440,000 80,000 90,000 90,000 2 Dong Nai province (Decision No.76/2012/QD-UBND dated Dec.19, 2012 of Dong Nai PPC) 2.1 Bien Hoa city Tan Hanh commune 1,200, , , , Hoa An commune 1,600, , , , Buu Hoa ward 5,000, , , , Compensation unit prices for houses and structures Table 4.2 Compensation unit prices for houses and structures No. Province/district/ commune House grade 4 (Brick wall, metal roof) Grave VND/m 2 VND/m 2 1 Binh Duong province (Decision No.58/2011/QD-UBND dated Dec. 19, 2011of Binh Duong PPC) 1.1 Tan Uyen district Thanh Phuoc 2,000,000 4,800, Thai Hoa township 2,000,000 4,800, Di An town Tan Binh ward 2,000,000 4,800,000 2 Dong Nai province (Decision No.12/2012/QD-UBND dated Feb and Decision No.14/2012/QD- UBND dated Feb of Dong Nai PPC) 2.1 Bien Hoa city Tan Hanh commune 1,977,000 6,916,000 Power Engineering Consulting Joint Stock Company 3 39

40 No. Province/district/ commune House grade 4 (Brick wall, metal roof) Grave VND/m 2 VND/m Hoa An commune 1,977,000 6,916, Buu Hoa ward 1,977,000 6,916, Compensation unit prices for trees and crops No. Province/district/ commune Table 4.3 Compensation unit prices for trees and crops Paddy and crops Pomelo Cajuput Rubber Mango Banana VND/m 2 VND/tree VND/tree VND/tree VND/tree VND/tree 1 Binh Duong province (Decision No.58/2011/QD-UBND dated Dec. 19, 2011of Binh Duong PPC) 1.1 Tan Uyen district Thanh Phuoc 3, ,000 60, , ,000 30, Thai Hoa township 3, ,000 60, , ,000 30, Di An town Tan Binh ward 3, ,000 60, , ,000 30,000 2 Dong Nai province (Decision No.12/2012/QD-UBND dated Feb of Dong Nai PPC) 2.1 Bien Hoa city Tan Hanh commune 3, ,000 26, , ,000 20, Hoa An commune 3, ,000 26, , ,000 20, Buu Hoa ward 3, ,000 26, , ,000 20, Assistances and rehabilitation Besides the direct compensation for the losses, severely AHs by the subproject are as follows: According to the survey result, impact level of the subproject is as follows: - 05 AHs (21 persons) have to dismantle their houses/structures and relocate AHs who belong to the vulnerable group will lose less than 10% of total productive land area AHs will lose from 20-70% of total productive land area AHs will lose more than 70% of total productive land area. In addition to direct compensation for damages, the above severely AHs will also receive allowance for transportation, relocation, production and living rehabilitation, vocational training and job creation, bonus, etc. These assistances will help APs recover their livelihood. Power Engineering Consulting Joint Stock Company 3 40

41 Details of these assistances are as follows: 1) Transportation allowance: 4,000,000 VND/HH. 2) House renting allowance: 2,000,000 VND/HH/month x 6 months. 3) Subsistence allowance for relocating: 30 kg of rice per person per month for 03 consecutive months is equivalent to 900,000 VND/HH (relocating within province). 4) Support for living stabilization: + AHs losing 20-70% of their agricultural landholding (or 10-70% for the poor and vulnerable groups): 1,800,000 VND/person if they do not have to relocate (equivalent to 30 kg of rice/person/month for 6 months); 3,600,000 VND/person in case of relocation (equivalent to 30 kg of rice/person/month for 12 months). + AHs losing more than 70% of their agricultural landholding: 3,600,000 VND/person if they do not have to relocate (equivalent to 30 kg of rice/person/month for 12 months); 7,200,000 VND/person in case of relocation (equivalent to 30 kg of rice/person/month for 24 months). 5) Support for job changing (with several options provided depending on the interest of the AHs): the support amount is 2 times of the agricultural land price for the whole acquired agricultural area but not exceeding the local land allocation limit at the moment of handing over land. 6) Support for training, apprenticeships on vocational training establishments in the province: 3,000,000 VND/person in the working ages. 7) Support for the poor and vulnerable groups: 5,000,000 VND/HH. 8) Relocation bonus: 5,000,000 VND/HH. 9) Allowance for land in the ROW of the overhead connection lines: Table 4.4 Assistance unit prices for land in the ROW (restricted usability) - VND/m 2 No. Province/district/ commune Residential land Annual crop land Perennial tree land Pond land 1 Binh Duong province 1.1 Tan Uyen district Thanh Phuoc 99,000 19,500 22,500 24, Thai Hoa township 99,000 19,500 22,500 24, Di An town Tan Binh ward 132,000 24,000 27,000 27,000 2 Dong Nai province 2.1 Bien Hoa city Tan Hanh commune 360,000 66,000 66,000 56, Hoa An commune 480,000 66,000 66,000 56, Buu Hoa ward 1,500,000 94,800 94,800 56,100 Power Engineering Consulting Joint Stock Company 3 41

42 No. 10) Allowance for houses/structures in the ROW of the overhead connection lines: Table 4.5 Assistance unit prices for houses/structures in the ROW (restricted usability) Province/district/ commune 1 Binh Duong province 1.1 Tan Uyen district House Cat. 4 (brick wall, tiled roof) House Cat. 4 (Brick wall, metal roof) - VND/m 2 House Cat. temporary (thatched wall) VND/m 2 VND/m 2 VND/m Thanh Phuoc 750, , , Thai Hoa township 750, , , Di An town Tan Binh ward 750, , ,000 2 Dong Nai province 2.1 Bien Hoa city Tan Hanh commune 697, , , Hoa An commune 697, , , Buu Hoa ward 697, , , Resettlement Power Engineering Consulting Joint Stock Company 3 42

43 As presented, the subproject will relocate 5 households in Cay Da hamlet, Thanh Phuoc commune, Binh Duong province. Of these, only one household whose land has to be cleared entirely, the remaining 4 households whose a portion of land will be required, the remaining land of them are sufficient to rebuild houses/structures. Details are as follows: - Le Thanh Binh entirely required land - Nguyen Hoang Sang partially required land - Le Van Hung partially required land - Bui Xuan Phuong partially required land - Quang Thi Ghe partially required land For 4 AHs whose land required partially, during survey and consultation, these AHs would like to be compensated in cash for land and house to arrange resettlement themselves at the remaining land plot around the substation. For household Le Thanh Binh, this AH would also like to be compensated in cash for land and house to arrange resettlement themselves. According to consultation, this AH reported that they will relocate in Cay Cham hamlet Thanh Phuoc commune (where their relatives are living). Power Engineering Consulting Joint Stock Company 3 43

44 5. PUBLIC CONSULTATION AND PEOPLE S PARTICIPATION 5.1 Public consultation and people s participation Public consultants are carried out by sending summary document of the subproject and organized community meetings. This summary document was described subproject s components, resettlement policy, frequently asked questions of AHs, prevented methods for risk of shock and protect measures for the ROW, potential impacts and minimized methods, etc. PECC3 held community meetings at People s Committee of affected communes in Oct Minutes of public consultant meetings and photos are presented in Annex 4 of the RP. Participant components who invited to the public consultation meeting consist of representatives of subproject affected households, local authorities, Fatherland Front Committee and local mass organizations (Women Union, Farmers Associations, etc.) (Please see details in Annex 4). In the consultation meetings, representatives of the subproject owner as the consultant presented some major issues as follows: - Introduction of the subproject and implementation schedule. - Impacts on land, houses, structures, trees; mitigation measures for land acquisition; principles and policy of compensation; the grievance procedure. - Impacts on air quality, noise, water quality, socio-economic activities and mitigation measures. In the community meetings, AHs queries on RP related issues such as entitlement, compensation, etc., will be answered and recorded by representatives of the subproject owner; and updated in the RP. Power Engineering Consulting Joint Stock Company 3 44

45 Table 5.1 Public consultation No. Location/ Time/ Participants Method of public consultation Questions of APs and local authorities Answers of representative of the subproject owner Summary of issues discussed and opinions 1 Location: Cultural Center in Cay Da Village, Thanh Phươc commune, Tan Uyen Dist. Date: Oct. 13, 2013 Participants: 45 persons Representative of People s Committee of commune Commune's Environment and cadastral Staff Head of Cay Da Village Meeting - Will compensation for losses of land, houses and trees be implemented before conducting land acquision? - Will unit prices of compensation be applied to subproject the same as the current unit prices or at the time of land acquisition? - The payment of compensation and allowances will be completed prior to conducting land acquisition and clearance of at least 01 months - Unit price of compensation applied will be unit price at the time of land acquisition. 1. Environment issue: - Subproject owners should fully implement the mitigation measures to minimize impacts on the environmental quality during construction. - During the operation phase, the subproject owner must ensure thorough treatment of waste, especially hazardous waste. - Propose the subproject design to ensure safety and electromagnetic fields not affect people who work on the cultivated land near the station area (or in the ROW). 2. Social and resettlement issue: Party committee Secretary of Cay Da Village - Suggest that the subproject owner appropriately compensates and supports the APs to stabilize life and production after land acquisition. - In the compensation process, the subproject owner should notify and consult with local residents to minimize disagreements when implementing the subproject. - Complete the compensation payment prior to land acquisition and subproject construction. 3. Conclusion: - All participants agreed with the implementation policy of the subproject. Power Engineering Consulting Joint Stock Company 3 45

46 No. Location/ Time/ Participants Method of public consultation Questions of APs and local authorities Answers of representative of the subproject owner Summary of issues discussed and opinions 2 Location: People s Committee of Tan Binh Ward, Di An town Date: Oct. 14, 2013 Participants: 6 persons Representative of People s Committee Representative of Fatherland Front Committee. Representative of Farmers' Association Representative of Women's Union Environment and cadastral Staff Economical Staff Meeting - How much is the amount of allowance for land in the ROW? According to Decree No.81/2009/ND-CP maximum support level for land in the ROW is 80% compared with the compensation cost. The actual support level applied to the subproject will be proposed by the compensation committee and submitted to the PPC for approval at the time of subproject implementation 1. Environment issue - Ensure implementation of environmental protection measures. - Make sure the electromagnetic field intensity not affect people who work on the cultivated land in the transmission line. 2. Social and resettlement issue: - Cooperate closely with local authorities in all activities of the subproject to address the arisen problems. - Consider support level for the HHs whose affected lands are in the power grid safety corridors (ROW) and reduced ability to use. 3. Conclusion: - Agree with the implementation policy of the subproject. 3 Location: People s Committee of Tan Hanh commune, Bien Hoa city Date: Oct. 14, 2013 Participants: 11 persons Representative of People s Committee Representative of Fatherland Front Committee. Meeting - Will land in the ROW be compensated? - Land in the ROW will not be compensated but supported, with maximum allowance level will be 80% compared with the compensation cost, according to Decree No.81/2009/ND-CP. 1. Environment issue - The subproject design must ensure full implementation of environmental protection measures. - The subproject design must ensure the electromagnetic field intensity does not cause any impact during power line operating. 2. Social and resettlement issue: - Full announcement on the subproject to the Power Engineering Consulting Joint Stock Company 3 46

47 No. Location/ Time/ Participants Method of public consultation Questions of APs and local authorities Answers of representative of the subproject owner Summary of issues discussed and opinions Representative of Farmers' Association Representative of Women's Union Environment and cadastral Staff Representative of the AHs affected households. - Inventory and full support for land and housing in the ROW before stretching high voltage line. 3. Conclusion: - Fully agree with investment policy of the subproject. 4 Location: People s Committee of Hoa An commune, Bien Hoa city Date: Oct. 15, 2013 Participants: 29 persons Representative of People s Committee Representative of Fatherland Front Committee. Representative of Farmers' Association Representative of Women's Union Environment and cadastral Staff Representative of the AHs Meeting - How will land in the ROW be compensated and supported? - Will trees/crops affected by the construction activities and stretching cables be compensated? - According to Decree No.81/2009/ND-CP maximum support level for land in the ROW is 80% compared with the compensation cost. The actual support level applied to the subproject will be proposed by the compensation committee and submitted to the PPC for approval at the time of subproject implementation - Trees/crops affected by the construction activities and stretching the line will be compensated. 1. Environment issue: - Construction Team must not discharge the waste to the environment. - Tidy up the ground after construction. - Make sure the electromagnetic field intensity not affect local people 2. Social and resettlement issue: - Information disclosure and full announcement on the subproject to the related local area. - Consider compensation for the affected land in the ROW. - Compensation for all plants and crops damaged during construction. 3. Conclusion: - Agreed with implementation policy of the subproject. Power Engineering Consulting Joint Stock Company 3 47

48 No. Location/ Time/ Participants Method of public consultation Questions of APs and local authorities Answers of representative of the subproject owner Summary of issues discussed and opinions 5 Location: People s Committee of Buu Hoa Ward, Bien Hoa city Date: Oct. 15, 2013 Participants: 11 persons Representative of People s Committee Representative of Fatherland Front Committee. Representative of Farmers' Association Representative of Women's Union Economical Staff Environment and cadastral Staff Representative of the AHs Meeting Environment issue: The construction materials transported must be covered suitably to avoid spillage. - Arrange and organize the properly implementation schedule to avoid traffic disruption, especially section crossing Highway 1K. - Tidy up the ground after construction. 2. Social and resettlement issue: - Cooperate closely with local authorities in inventory of effects on the ward. 3. Conclusion: - Agreed with implementation policy of the subproject. 6 Location: People s Committee of Thai Hoa township, Tan Uyen Dist. Date: Oct. 26, 2013 Participants: 63 persons Representative of People s Committee Representative of Meeting - Will houses/structures in the ROW be removed? - According to Decree No.81/2009/ND-CP, houses/structures in the ROW will be allowed to exist if the safety conditions are met fully, then they will not be relocated. Therefore, if houses/structures which 1. Environment issue: -Ensure mitigation measures are implemented by the construction units. - Tidy up the ground after construction. - Ensure the electromagnetic field intensity not affect people living under the T/L. 2. Social and resettlement issue: Power Engineering Consulting Joint Stock Company 3 48

49 No. Location/ Time/ Participants Method of public consultation Questions of APs and local authorities Answers of representative of the subproject owner Summary of issues discussed and opinions Fatherland Front Committee. Representative of Farmers' Association Representative of Women's Union Environment and cadastral Staff Representative of the AHs - Will houses/structures in the ROW be repaired? - Please explain width of the ROW of 27m. - How far is the safety distance from the top of house/structure to the lowest of the transmission line? are made by flammable materials such as leaves, wood have to be improved and grounded to the metal materials. Cost for improvement and grounding implementation will be provided by the subproject owner. - Houses/structures in the ROW will be allowed to repair but the safety distance from the top of house to the lowest of the transmission line must be ensured over 6m (220kV network). - Width of the ROW is 27m i.e. 13.5m from the center of T/L to sides - According to Decree No.81/2009/ND-CP, the safety distance from the top of house to the lowest of the transmission line is 6m (220kV network). - Cooperate closely with local authorities in detailed design and inventory of losses due to the subproject. - For permanent required land, compensation for the whole impacted plot if the remaining plot is not economically viable. 3. Conclusion: - Agreed with implementation policy of the subproject. Power Engineering Consulting Joint Stock Company 3 49

50 5.2 Disclosure Per requirement of Bank s policy, the Vietnamese version of this draft report was publically disclosed at subproject communes, SPPMB, and VDIC of the World Bank office in Hanoi (Jan. 2014). English version was also disclosed in InfoShop of the World Bank in Washington D.C. Final versions (English and Vietnamese) will also be re-disclosed at project sites, SPPMB, VDIC and InfoShop. 5.3 Grievance redress mechanism DPs are entitled to the complaints regarding their interests and responsibilities in the subproject implementation including but not limited to entitlements, compensation policy, unit prices, land acquisition, resettlement and other entitlements related to the recovery support programs. Complaints can also concern issues related to construction safety and nuisances caused by construction. Grievance procedures should be affordable and accessible procedures for third party settlement of disputes arising from resettlement; such grievance mechanisms should take into account the availability of judicial recourse and community and traditional dispute settlement mechanisms. The mechanism of complaint and complaint and grievances resolution steps are as below: First Stage - At Commune People s Committee (CPC) An aggrieved DP may bring his/her complaint to any member of the CPC, in writing or verbally. It is incumbent upon said member of CPC to notify the CPC about the complaint. The CPC will meet personally with the aggrieved DP and will have 15 days following the lodging of the complaint to resolve it. The CPC secretariat is responsible for documenting and keeping file of all complaints that it handles. Second Stage - At District People s Committee (DPC) If after 15 days the aggrieved DP does not hear from the CPC, or if the CPC gives its solutions, but DP is not satisfied with the decision taken on his/her complaint, the DP may bring the case, either in writing or verbally, to any member of DPC or DCB. The DCB in turn will have 30 days to resolve the case. The DPC is responsible for documenting and keeping file of all complaints that it handles. Third Stage - At Provincial People s Committee (PPC) If after 30 days the aggrieved DP does not hear from the DCB, or if the DP is not satisfied with the decision taken on his/her complaint, the DP may bring the case, either in writing or verbally, to any member of the PPC. The PPC has 45 days within which to resolve the complaint to the satisfaction of all concerned. The PPC secretariat is also responsible for documenting and keeping file of all complaints that it handles. Final Stage - Court of Law Decides If after 45 days following the lodging of the complaint with the PPC, the aggrieved DP does not hear from the PPC, or if he/she is not satisfied with the decision taken on his/her complaint, the case may be brought to a court of law for adjudication. Under no circumstance, can the DP be evicted from his/her property nor can the Government take over his/her property without the explicit permission of the court. In order to minimize complaints, SPPMB (via their assigned grievance focal point or grievance facilitation unit GFU) will cooperate with the District Compensation Board/ Center for Land Development Fund to participate in and consult on settling complaints. Power Engineering Consulting Joint Stock Company 3 50

51 Names and contact details of Grievance Focal Points and/or the Grievance Facilitation Unit (GFU) will be made publically available in information brochures and at subproject areas. Local mass organizations such as Fatherland Front, Farmer s Union, Women s Union will be mobilized to participate actively in the process of resolving complaints, questions. The independent monitoring agency will be responsible for checking the procedures for and resolutions of grievances and complaints. The independent monitoring agency may recommend further measures to be taken to redress unresolved grievances. DPs will be exempted from all administrative and legal fees. Besides that, an escrow accounts for resettlement payments should be used when grievance is resolving to avoid excessive delay of the project while ensuring compensation payment after the grievance has been resolved. SPPMB should maintain a system to register queries, suggestions and grievances of the DPs. All queries, suggestions and grievances and their resolution should be recorded and forwarded to the PC and its functioning monitored monthly. SPPMB will formulate and maintain a database of the DPs grievances related to the subproject to ensure that all complaints are recorded, recognized and processed by the functional units at all levels. 6. SUPERVISION, MONITORING AND VALUATION Implementation of RP will be periodically supervised and monitored by the respective PMBs in a close coordination with the respective Peoples' Committees at different administrative units and independent monitoring agencies. The findings will be recorded in quarterly reports to be furnished to NPT, SPPMB, and World Bank. 6.1 Internal monitoring and supervision Internal monitoring and supervision will: - Verify that the baseline information of all DPs has been carried out and that the valuation of assets lost or damaged, and the provision of compensation, resettlement and other rehabilitation entitlements has been carried out in accordance with the provisions of this Policy Framework and the respective RP. - Oversee that the RP are implemented as designed and approved. - Verify that funds for implementing the RP are provided to the respective SPPMB in a timely manner and in amounts sufficient for their purposes, and that such funds are used by the respective SPPMB s in accordance with the provisions of the RP and policy framework. - Record all grievances and their resolution and ensure that complaints are dealt with in a timely manner. A staff in charge of resettlement, compensation and clearance of this subproject is responsible to update information and maintain records based on the following main activities. Table 6.1 Main activities for internal monitoring and evaluation No. Activities in RP 1. Inform to Local People and Authorities about the Subproject Implementation Yes No Describe Power Engineering Consulting Joint Stock Company 3 51

52 No. 2. Inventory of Loss 3. Survey Replacement Cost 4. Make RP report 5. Approve RP - SPPMB Activities in RP - Provincial People s Committee - World Bank 6. Disclosure RP - Subproject location: - SPPMB - VDIC/Infoshop 7. Inventory and Measurement 8. Apply compensation prices (transfer from RP) 9. Make detail compensation plan 10. Approve compensation plan 11. Proclaim compensation plan 12. Amend and approval (if any) 13. Pay compensation (included updates on RP s estimation for example number of AHs, expense, level of impact, etc) 14. Internal monitoring 15. Independent Monitoring 16. Report Implement Plan 17. Record and solve claims 18. Public consultation and participate of people - Community meeting - Provide Information Booklet 19. Coordinate with other agencies (especially Compensation Resettlement Committee) 20. Evaluate middle-term and final-term (up to subproject schedule) Implementation Yes No Describe 6.2 Independent monitoring An independent agency or agencies or individual consultant will be retained by SPPMB to periodically carry out external monitoring and evaluation of the implementation of RP. The independent agencies will be academic or research institutions, non-governmental Organizations (NGO) or independent consulting firms, all with qualified and experienced staff and terms of reference acceptable to the World Bank. Independent monitoring begins Power Engineering Consulting Joint Stock Company 3 52

53 about the same time as implementation activities and continues until the end of subproject. The independent monitoring agency will: - Determine whether the procedures for DPs participation and delivery of compensation and other rehabilitation entitlements has been done in accordance with the Policy Framework; and - Assess if the Policy Framework objective of enhancement or at least restoration of living standards and income levels of DPs have been met. - Gather qualitative indications of the social and economic impact of subproject implementation on the DPs. - Suggest modification in the implementation procedures of as the case may be, to achieve the principles and objectives of the Policy Framework. 6.3 Reporting condition Internal monitoring will make report quarterly with detail schedule of RP implementation. These reports will be sent to SPPMB, NPT and WB. Terms of Reference (TOR) for independent monitoring will be presented fully in contract between SPPMB and such independent monitoring. A Resettlement Plan cannot be considered complete until a completion audit or survey confirms that all entitlements have been received by beneficiaries and livelihood restoration is progressing on schedule. Power Engineering Consulting Joint Stock Company 3 53

54 7. IMPLEMENTATION SCHEDULE 7.1 Implementation responsibility Southern Power Project Management Board (SPPMB) SPPMB, representing NPT, have following responsibilities: - Prepare RPs in accordance with the RPF. Coordinate with the provincial People s Committees and local authorities to obtain consensus from provincial People s Committee for the RPs and submit them to the WB for review and clearance. - Develop and implement a training program for the provincial and district People s Committee s, relevant stakeholders involved in RP implementation and Grievance Redress. - Where relevant, provide technical support (e.g. consultation mobilization) in identifying the replacement cost to inform compensation rate during the RP implementation. - Secure timely availability of required budget for RP preparation and implementation; - Conduct internal monitoring of RP implementation as per requirements set out in the project s RPF and the RPs. - Prepare bi-annual progress reports and submit to WB - Designate staff with solid experience in resettlement and familiar with Bank s safeguard policies as a social focal point for PMB. - Take part in compensation, support and resettlement council at local level and ensure that the agreed RPs are properly implemented, documented and reported. - Work closely with competent governmental agencies to address concern, grievances related to resettlement in their managed subprojects. Provincial People s Committees (PPC) Provincial People s Committees have responsibilities as follows: - To direct, organize, propagate and mobilize all organizations and individuals concerning compensation, support and resettlement policies and ground clearance according to the land recovery decisions of competent State bodies; - To direct the provincial/municipal services, departments, branches and district-level People's Committees: (i) To draw up resettlement and resettlement area plans in service of the land recovery; (ii) To draw up compensation, support and resettlement plans according to their competence; - To approve or assign the district-level People's Committees to approve compensation, support and resettlement plans; - To approve land prices; promulgate the property price tables for compensation calculation; prescribe support levels and supporting measures according to their competence; resettlement arrangement plans, job change training plans according to their assigned competence; - To direct the concerned agencies to settle citizens' complaints, denunciations related to compensation, support and resettlement according to their law-prescribed competence; Power Engineering Consulting Joint Stock Company 3 54

55 - To guarantee impartiality and equity when considering and deciding on the compensation, support and resettlement when land is recovered by the State according to their competence prescribed in this Decree; - To decide or assign the district-level People's Committees to apply coercion to cases of deliberately failing to abide by the State's land recovery decisions according to their competence; - To direct the examination and handling of violations in the compensation, support and resettlement domain. District People s Committees The District People s Committees have responsibilities as follows: - To direct, organize, propagate and mobilize all organizations and individuals concerning compensation, support and resettlement policies and ground clearance according to the land recovery decisions of competent State bodies; - To direct the compensation, support and resettlement councils of the same level to draw up, and organize the implementation of, the compensation, support and resettlement plans; approve the compensation, support and resettlement plans according to the responsibility assignment by the provincial-level People's Committees; - To coordinate with the provincial/municipal services, departments and branches, organizations and investors in executing investments projects to build and plans to create resettlement areas in their localities according to the assignment of the provincial-level People's Committees; - To settle citizens' complaints, denunciations related to compensation, support and resettlement according to their assigned competence; issue coercive decisions and organizing coercion in the cases falling under their competence; coordinate with the functional agencies in organizing coercion according to the decisions of competent bodies. Compensation, support and resettlement councils The compensation, support and resettlement councils shall assist the People's Committees of the same level in making, and organizing the implementation of, compensation, support and resettlement arrangement plans; work on the collective principle and decide by majority; where the numbers of votes for and against are equal, the opinion of the side joined by the council chairman shall be followed. Responsibilities of council members are as follow: - The council chairman shall direct the council members to make, submit for approval and organize the implementation of, the compensation, support and resettlement plan; - The investor shall be responsible for assisting the council chairman in making the compensation, support and resettlement plan, ensuring sufficient funds for timely payment of compensation, support and resettlement money; - Representatives of persons who have land recovered shall be responsible for reflecting the aspirations of persons who have land recovered, persons who must be relocated; mobilizing persons who have land recovered to move and clear the ground according to schedule; - Other members shall perform the tasks as assigned and directed by the council chairman, suitable to their respective branches. Power Engineering Consulting Joint Stock Company 3 55

56 - The compensation, support and resettlement councils shall be responsible for the accuracy and rationality of inventory statistics, the legality of land and property eligible or ineligible for compensation, supports in the compensation, support and resettlement Center for Land Fund Development The Center for Land Fund Development has main responsibilities related to resettlement as follows: - To assume the prime responsibility for, or coordinate the with the compensation and ground clearance council in, organizing compensation and ground clearance; - To work and coordinate closely with project s stakeholders to update and implement RP as per project s RPF. - To provide compensation and ground clearance services; - To develop resettlement areas; - To build infrastructure on land funds assigned to it for management in order to organize auction; - To provide information on land prices and land funds to organizations and individuals upon request; - To assist the District People s Committee and Provincial People s Committee in disseminating information related to Resettlement Plan. - To assist the District People s Committee in handling complaints at district level. - To perform other tasks under decisions of the provincial-level People's Committee. Commune People's Committees The Commune People's Committees shall have the responsibilities: - To organize propaganda on the land recovery purposes, compensation, support and resettlement polices of the projects; - To coordinate with the compensation, support and resettlement councils in certifying land and property of persons who have land recovered; - To join in, and create conditions for, the payment of compensation and support money to, and arrange resettlement for, persons who have land recovered, and create conditions for the ground clearance. Displaced persons (DPs) DPs are ready with their necessary RP related papers i.e. LURC, ownership of other assets. DPs are responsible for carefully checking on their lost assets and respective entitlements and clear land in a timely manner once DPs receive full entitlements. Independent Monitoring An independent agency is responsible to supervise and evaluate implementation of RP for the subproject. This agency will submit monitoring reports periodically during implementation of RP and suggest solving measures for all identified issues to SPPMB and WB. Power Engineering Consulting Joint Stock Company 3 56

57 7.2 Implementation schedule The following is proposed RP implementation schedule Schedule for SPPMB and CRC: 1. Set up RP 12/ Commencement of public information 01/ Review and clear of RP by the WB 03/ Establishment of subproject CRC 05/ Commencement of field works (detail measures survey) 06/ Commencement of payment of compensation 07/2014 Schedule for DPs 1. Commencement of declaration of quantity and status of properties 06/ Commencement of receiving compensation and ground clearance 07/2014 Bidding Commencement of bidding for equipment and civil works 06/2014 Civil works 01/ /2016 Monitoring 06/ /2016 All modifications introduced to the RP after issuing the Non-Objection Letter requires review and agreement of the WB before proceeding. Power Engineering Consulting Joint Stock Company 3 57

58 8. COSTS 8.1 Basis of cost calculations Compensation cost estimate for affected land, houses or structures based on: - Resettlement Policy Framework (RPF) of the Transmission Efficiency Project (TEP). - Decree No.197/2004/ND-CP on December 3,, 2004 of the Government on compensation, support and resettlement when land is requisitioned by the state. - Decree No.106/2005/ND-CP on August 17, 2005 regulates details and guides to implement some matters under the Electricity Law regarding safety protection for high-voltage power networks. - Decree No.69/2009/ND-CP dated August 13, 2009 of the Government additionally regulates on land use planning, land prices, land requisition, compensation, support and resettlement. - Decree No.81/2009/ND-CP on October 12, 2009, on revision and supplement of some articles of the government s decree No.106/205/ND-CP of August 17, Survey on the replacement cost and the market price for land, houses, structures done by PECC3 in Oct Related decisions of Binh Duong and Dong Nai provinces: Dong Nai province: - Decision No.12/2012/QD-UBND dated Feb. 23, 2012 of Dong Nai PPC promulgating the regulations on compensation unit prices of properties in the area of Dong Nai province. - Decision No.14/2012/QD-UBND dated Feb. 24, 2012 of Dong Nai PPC promulgating the regulations on compensation unit prices of houses when the State recovers land in the area of Dong Nai province. - Decision No.25/2012/QD-UBND dated April 3, 2012 of Dong Nai PPC promulgating regulations on compensation, assistance and resettlement when the State recovers land in the area of Dong Nai province. - Decision No.76/2012/QD-UBND dated Dec. 19, 2012 of Dong Nai PPC promulgating the regulations on land prices in 2013 in the area of Dong Nai province. Binh Duong province: - Decision No.87/2009/QD-UBND dated Dec. 21, 2009 of Binh Duong PPC promulgating regulations on compensation, assistance and resettlement when the State recovers land in the area of Binh Duong province. - Decision No.58/2011/QD-UBND dated Dec. 19, 2011 of Binh Duong PPC promulgating the regulations on compensation unit prices of houses, structures, trees and crops in land when the State recovers land. - Decision No.58/2012/QD-UBND dated Dec. 18, 2012 of Binh Duong PPC promulgating the regulations on land prices in 2013 in the area of Binh Duong province. 8.2 Replacement Cost Survey According to the survey result, the substation, connection lines will be built in the rural Power Engineering Consulting Joint Stock Company 3 58

59 area, almost land is used for permanent agricultural production and the land unit price has been relatively steady for 3 years. Through consultation with local authorities and residents, compensation unit prices for land, houses, structures, crops of other projects in the region were applied equivalent to the unit prices issued by PPC and accepted by affected households. Hence, this RP applies the unit prices issued by PPC for estimation. At the time of implementation of RP (expected to start in Jun. 2014), compensation unit prices will be updated to ensure that AHs will be compensated at replacement cost for their losses. 8.3 Cost estimation for implementation of RP Source of financing for RP implementation is from counterpart fund of NPT and SPPMB. The funds will be transferred to CRC who is responsible for: Payment of compensation and all entitled allowances directly to AHs, and Payment to cover costs of overall RP activities. The contingency component would cover such differences by the time of actual RP implementation. This cost was included in provision costs of the subproject Cost of detail measurement survey - Land survey fees: 5,000,000VND - Land survey cost: 100,000,000 VND - Cost of setting up landmarks for clearance: 100,000,000 VND : 205,000,000 VND Cost of compensation Based on impact types and scale of impacts are described in above sections, the compensation cost of the subproject includes: - Compensation for permanently required land. - Compensation for dismantled houses and removed graves. - Compensation for damaged trees and crops Compensation cost for Thanh Phuoc commune Tan Uyen district Table 8.1 Compensation cost - Thanh Phuoc commune Tan Uyen district No. Content Unit Quantity Unit price (VND) (VND) I Compensation for land 8,126,780,000 1 Residential land m 2 1, , ,660,000 2 Annual crop land m 2 102,804 65,000 6,682,260,000 3 Perennial tree land m 2 12,372 75, ,900,000 4 Pond land m 2 1,087 80,000 86,960,000 II Compensation for houses, structures 1,173,800,000 1 House cat.4 (brick wall, metal roof) m 2 572,5 2,000,000 1,145,000,000 Power Engineering Consulting Joint Stock Company 3 59

60 No. Content Unit Quantity Unit price (VND) (VND) 2 Grave unit 6 4,800,000 28,800,000 III Compensation for trees and crops 543,949,000 1 Paddy and crops m 2 135,194 3, ,179,000 2 Cajuput tree 1,048 60,000 62,880,000 3 Rubber tree ,000 5,700,000 4 Banana tree 73 30,000 2,190,000 IV 9,844,529, Compensation cost for Thai Hoa township Tan Uyen district Binh Duong province Table 8.2 Compensation cost - Thai Hoa township Tan Uyen District No. Content Unit Quantity Unit price (VND) (VND) I Compensation for land 331,920,000 1 Annual crop land m 2 4,578 65, ,570,000 2 Perennial tree land m ,000 34,350,000 II Compensation for trees and crops 465,618,500 1 Paddy and crops m 2 63,211 3, ,238,500 2 Pomelo tree ,000 40,320,000 3 Cajuput tree 3,401 60, ,060,000 III 797,538, Compensation for Tan Binh ward Di An town Binh Duong province Table 8.3 Compensation cost - Tan Binh ward Di An town No. Content Unit Quantity Unit price (VND) (VND) I Compensation for land 228,640,000 Annual crop land m 2 2,858 80, ,640,000 II Compensation for trees and crops 117,071,500 Paddy and crops m 2 33,449 3, ,071,500 III 345,711, Compensation for Tan Hanh commune Bien Hoa city Dong Nai province Table 8.4 Compensation cost - Tan Hanh commune Bien Hoa city No. Content Unit Quantity Unit price (VND) (VND) I Compensation for land 367,400,000 1 Annual crop land m 2 1, , ,680,000 Power Engineering Consulting Joint Stock Company 3 60

61 2 Perennial tree land m ,000 60,720,000 II Compensation for trees and crops 90,612,000 1 Paddy and crops m 2 14,709 3,000 44,127,000 2 Mango cây ,000 42,705,000 3 Banana cây ,000 3,780,000 III 458,012, Compensation Hoa An commune Bien Hoa city Dong Nai province Table 8.5 Compensation cost - Hoa An commune Bien Hoa city No. Content Unit Quantity Unit price (VND) (VND) I Compensation for land 903,320,000 1 Annual crop land m 2 2, , ,300,000 2 Perennial tree land m 2 1, , ,020,000 II Compensation for trees and crops 120,370,000 1 Paddy and crops m 2 32,358 3,000 97,074,000 2 Cajuput cây ,000 23,296,000 III 1,023,690, Compensation Buu Hoa ward Bien Hoa city Dong Nai province Table 8.6 Compensation cost - Buu Hoa ward Bien Hoa city No. Content Unit Quantity Unit price (VND) Value (VND) I Compensation for land 899,630,000 1 Annual crop land m 2 2, , ,136,000 2 Pond land m , ,494,000 II Compensation for trees and crops 37,632,000 Paddy and crops m 2 12,544 3,000 37,632,000 III 937,262, compensation cost of the subproject Power Engineering Consulting Joint Stock Company 3 61

62 No. Province/district/ commune 1 Binh Duong 1.1 Tan Uyen district Table 8.7 compensation cost of the subproject Compensation for land Compensation for houses/ structures Compensation for trees and crops Unit: VND Thanh Phuoc com. 8,126,780,000 1,173,800, ,949,000 9,844,529, Thai Hoa township 331,920, ,618, ,538, Di An town Tan Binh ward 228,640, ,071, ,711,500 2 Dong Nai 2.1 Bien Hoa city Tan Hanh com. 367,400,000 90,612, ,012, Hoa An com. 903,320, ,370,000 1,023,690, Buu Hoa ward 899,630,000 37,632, ,262,000 10,857,690,000 1,173,800,000 1,375,253,000 13,406,743, Cost of assistances Based on impact types and scale of impacts are described in above sections, the assistance cost of the subproject includes: - Transportation allowance. - House renting allowance. - Subsistence allowance for relocating. - Support for living stabilization. - Support for job changing. - Support for training, apprenticeships on vocational training establishments in the province. - Relocation bonus. - Assistance for land in the ROW due to reducing usability. - Assistance for houses/structures in the ROW due to reducing usability and impacts on daily activities. - Support for improving and installing fireproof materials and lightning arrestors of houses and structures in the ROW which not meet safety conditions as stipulated in Decree No.106/2005/ND-CP and Decree No.81/2009/ND-CP of the Government Allowance cost for Thanh Phuoc commune Tan Uyen district Power Engineering Consulting Joint Stock Company 3 62

63 Table 8.8 Allowance cost - Thanh Phuoc commune Tan Uyen district No. Content Unit Quantity Unit price (VND) (VND) 1 Transportation allowance HH 5 4,000,000 20,000,000 2 House renting allowance HH 5 12,000,000 60,000,000 3 Subsistence allowance for relocating HH ,000 18,900,000 4 Support for living stabilization 352,800, AHs losing 20-70% of their agricultural landholding (or 10-70% for the poor and vulnerable groups) - no relocation AHs losing 20-70% of their agricultural landholding (or 10-70% for the poor and vulnerable groups) - relocation AHs losing more than 70% of their agricultural landholding - no relocation AHs losing more than 70% of their agricultural landholding - relocation Per. 96 1,800, ,800,000 Per. 9 3,600,000 32,400,000 Per. 33 3,600, ,800,000 Per. 4 7,200,000 28,800,000 5 Support for job changing 15,394,240, Support in cash for required annual tree land Support in cash for required perennial tree land m 2 102, ,000 13,364,520,000 m 2 12, ,000 1,855,800, Support in cash for required pond land m 2 1, , ,920,000 6 Support for training, apprenticeships on vocational training establishments Per. 81 3,000, ,000,000 7 Relocation bonus HH 45 5,000, ,000,000 8 Assistance for land in the ROW 746,197, Residential land m ,000 57,123, Annual crop land m 2 32,390 19, ,605, Perennial tree land m 2 1,863 22,500 41,917, Pond land m ,000 15,552, Assistance for houses/structures in the ROW Allowance for reducing usability and impacts on daily activities 352,200,000 House cat. 4 (brick wall, metal roof) m , ,200,000 Support for installing fireproof materials and lightning arrestors set 3 2,000,000 6,000,000 17,412,337,500 Power Engineering Consulting Joint Stock Company 3 63

64 Allowance cost for Thai Hoa township Tan Uyen district Binh Duong province Table 8.9 Allowance cost - Thai Hoa township Tan Uyen district Unit price No. Content Unit Quantity (VND) (VND) 1 Support for job changing 663,840, Support in cash for required annual tree land m 2 4, , ,140, Support in cash for required perennial tree land m ,000 68,700,000 2 Support for training, apprenticeships on vocational training establishments Per. 25 3,000,000 75,000,000 3 Relocation bonus HH 12 5,000,000 60,000,000 4 Assistance for land in the ROW 1,911,340, Residential land m 2 5,641 99, ,409, Annual crop land m 2 58,633 19,500 1,143,343, Perennial tree land m 2 9,315 22, ,587, Assistance for houses/structures in the ROW Allowance for reducing usability and impacts on daily activities 3,951,675,000 House cat. 4 (brick wall, tiled roof) m 2 1,461,5 750,000 1,096,125,000 House cat. 4 (brick wall, metal roof) m 2 4, ,000 2,420,400,000 House temp. (leaf wall, leaf roof) m ,000 39,150, Support for improving house m ,000, ,000, Support for installing fireproof materials and lightning arrestors set 53 2,000, ,000,000 6,661,855, Allowance cost for Tan Binh ward Di An town Binh Duong province Table 8.10 Allowance cost - Tan Binh ward Di An town Unit price No. Content Unit Quantity (VND) (VND) 1 Support for living stabilization 5,400,000 AHs losing 20-70% of their agricultural landholding (or 10-70% for the poor and vulnerable groups) - no relocation Per. 3 1,800,000 5,400,000 2 Support for job changing 457,280,000 Support in cash for required annual tree land m 2 2, , ,280,000 3 Support for training, apprenticeships on vocational training establishments Per. 15 3,000,000 45,000,000 4 Relocation bonus HH 8 5,000,000 40,000,000 5 Assistance for land in the ROW 965,844, Residential land m 2 1, , ,660,000 Power Engineering Consulting Joint Stock Company 3 64

65 No. Content Unit Quantity Unit price (VND) (VND) 5.2 Annual crop land m 2 30,591 24, ,184, Assistance for houses/structures in the ROW Allowance for reducing usability and impacts on daily activities 1,055,000,000 House cat. 4 (brick wall, metal roof) m 2 1, ,000 1,053,000,000 Support for installing fireproof materials and lightning arrestors set 1 2,000,000 2,000,000 2,568,524, Allowance cost for Tan Hanh commune Bien Hoa city Dong Nai province Table 8.11 Allowance cost - Tan Hanh commune Bien Hoa city Unit price No. Content Unit Quantity (VND) (VND) 1 Support for living stabilization 5,400,000 AHs losing 20-70% of their agricultural landholding (or 10-70% for the poor and vulnerable groups) - no relocation Per. 3 1,800,000 5,400,000 2 Support for job changing 734,800, Support in cash for required annual tree land m 2 1, , ,360, Support in cash for required perennial tree land m , ,440,000 3 Support for training, apprenticeships on vocational training establishments Per. 9 3,000,000 27,000,000 4 Relocation bonus HH 5 5,000,000 25,000,000 5 Assistance for land in the ROW 2,085,294, Residential land m 2 1, , ,680, Annual crop land m 2 13,315 66, ,790, Perennial tree land m 2 3,105 66, ,930, Pond land m 2 9,909 56, ,894, Assistance for houses/structures in the ROW Allowance for reducing usability and impacts on daily activities 766,107,400 House cat. 4 (brick wall, metal roof) m 2 1, , ,906,200 House temp. (leaf wall, leaf roof) m ,600 9,849, Support for improving house m ,100 21,351, Support for installing fireproof materials and lightning arrestors set 11 2,000,000 22,000,000 3,643,602,300 Power Engineering Consulting Joint Stock Company 3 65

66 Allowance cost for Hoa An commune, Bien Hoa city, Dong Nai province Table 8.12 Allowance cost - Hoa An commune Bien Hoa city Unit price No. Content Unit Quantity (VND) (VND) 1 Support for living stabilization 25,200,000 AHs losing 20-70% of their agricultural landholding (or 10-70% for the poor and vulnerable groups) - no relocation Per. 14 1,800,000 25,200,000 2 Support for job changing 1,806,640, Support in cash for required annual tree land m 2 2, ,000 1,018,600, Support in cash for required perennial tree land m 2 1, , ,040,000 3 Support for training, apprenticeships on vocational training establishments Per. 18 3,000,000 54,000,000 4 Relocation bonus HH 10 5,000,000 50,000,000 5 Assistance for land in the ROW 4,946,838, Residential land m 2 6, ,000 2,964,000, Annual crop land m 2 30,043 66,000 1,982,838, Assistance for houses/structures in the ROW Allowance for reducing usability and impacts on daily activities 3,804,559,100 House cat. 4 (brick wall, tiled roof) m ,800 54,428,400 House cat. 4 (brick wall, metal roof) m 2 6, ,100 3,616,130,700 Support for installing fireproof materials and lightning arrestors set 67 2,000, ,000,000 10,687,237, Allowance cost for Buu Hoa ward Bien Hoa city Dong Nai province Table 8.13 Allowance cost - Buu Hoa ward Bien Hoa city Unit price No. Content Unit Quantity (VND) (VND) 1 Support for living stabilization 7,200,000 AHs losing 20-70% of their agricultural landholding (or 10-70% for the poor and vulnerable groups) - no relocation Per. 4 1,800,000 7,200,000 2 Support for job changing 36,000, Support in cash for required annual tree land m 2 2, ,000 1,514,272, Support in cash for required pond tree land m , ,988,000 3 Support for training, apprenticeships on vocational training establishments Per. 12 3,000,000 36,000,000 4 Relocation bonus HH 6 5,000,000 30,000,000 Power Engineering Consulting Joint Stock Company 3 66

67 No. Content Unit Quantity Unit price (VND) (VND) 5 Assistance for land in the ROW 3,464,640, Residential land m 2 1,601 1,500,000 2,401,125, Annual crop land m 2 10,148 94, ,030, Pond land m 2 1,809 56, ,484, Assistance for houses/structures in the ROW Allowance for reducing usability and impacts on daily activities 971,404,825 House cat. 4 (brick wall, metal roof) m 2 1, , ,404,825 Support for installing fireproof materials and lightning arrestors set 11 2,000,000 22,000,000 4,545,245,125 Power Engineering Consulting Joint Stock Company 3 67

68 allowance cost of the subproject Table 8.14 allowance cost of the subproject No. Province/district/ commune Transportation allowance House renting allowance Subsistence allowance for relocating Support for living stabilization Support for job changing Support for training Relocation bonus Assistance for land in the ROW Assistance for houses/structures in the ROW 1 Binh Duong 1.1 Tan Uyen dist Thanh Phuoc 20,000,000 60,000,000 18,900, ,800,000 15,394,240, ,000, ,000, ,197, ,200,000 17,412,337, Thai Hoa 663,840,000 75,000,000 60,000,000 1,911,340,500 3,951,675,000 6,661,855, Di An town Tan Binh ward 5,400, ,280,000 45,000,000 40,000, ,844,000 1,055,000,000 2,568,524,000 2 Dong Nai 2.1 Bien Hoa city Tan Hanh com. 5,400, ,800,000 27,000,000 25,000,000 2,085,294, ,107,400 3,643,602, Hoa An com. 25,200,000 1,806,640,000 54,000,000 50,000,000 4,946,838,000 3,804,559,100 10,687,237, Buu Hoa ward 7,200,000 36,000,000 36,000,000 30,000,000 3,464,640, ,404,825 4,545,245,125 20,000,000 60,000,000 18,900, ,000,000 19,092,800, ,000, ,000,000 14,120,155,200 10,900,946,325 45,518,801,525 Power Engineering Consulting Joint Stock Company 3 68

69 8.3.4 Cost for CRC Cost for CRC is estimated maximum at 2% of total cost of compensation and rehabilitation Cost of monitoring Cost of the independent external monitoring of RP implementation is estimated as 200,000,000 VND. The external monitoring agencies concerned will prepare technical and financial proposals for bidding and actual cost will be determined after bidding cost of RP implementation cost for RP implementation is estimated as below: Table 8.15 cost for RP implementation No. Content Amount (VND) A Preparation cost (detailed measurement survey) 205,000,000 B Compensation cost 13,406,743,000 1 Compensation for land 10,857,690,000 2 Compensation for houses/structures 1,173,800,000 3 Compensation for trees/crops 1,375,253,000 C Allowances 45,518,801,525 1 Transportation allowance 20,000,000 2 House renting allowance 60,000,000 3 Subsistence allowance for relocating 18,900,000 4 Support for living stabilization 396,000,000 5 Support for job changing 19,092,800,000 6 Support for training, apprenticeships on vocational training establishments 480,000,000 7 Relocation bonus 430,000,000 6 Assistance for land in the ROW 14,120,155,200 7 Assistance for houses/structures in the ROW 10,900,946,325 D Cost for CRC = 2% *(B+C) 1,178,510,891 E Cost for external monitoring agency 200,000,000 F Contingency (10%) 6,050,905,542 (A+B+C+D+E) 66,559,960,957 Power Engineering Consulting Joint Stock Company 3 69

70 ANNEXES Annex 1 Map of site area Annex 2 Entitlement Matrix Annex 3 Site agreement Annex 4 Minutes and pictures of meetings on public consultation Annex 5 Questionnaires form Annex 6 Inventory of subproject affected households Power Engineering Consulting Joint Stock Company 3 70

71 ANNEX 1 MAP OF SITE AREA Power Engineering Consulting Joint Stock Company 3 71

72 Transmission Efficiency Project, Subproject: 500kV Tan Uyen SS and connection lines ANNEX 1: MAP OF SITE AREA Power Engineering Consulting Joint Stock Company 3 72

73 ANNEX 2 ENTITLEMENT MATRIX Type of Loss/ Impacts Application Entitlements Implementation Arrangements 1. Productive land (Agricultural, garden, pond land, etc.) either in or out of the residential area. Legal land users 1.1. Marginal loss (<20% of land holding or <10% for vulnerable group) The remaining area of affected plot is still economically viable for use or meets the expected personal yield. Cash compensation at replacement cost (free from taxes and transaction costs) at 100% replacement cost for the lost area. - Affected households to be notified at least ninety days before land recovery by the Project. - The owner of land will hand over the land within 20 days from the date District Compensation Board fully pays compensation for land. - For vulnerable and severely affected households, affected farmers, including landless, allocation of arable land equal per capita arable land in commune. If there no land available for allocation or, on the DPs request through informed choice, training/ rehabilitation programs will be provided to at least restore, if not improve, their income and living standards Loss >20% or >10% for vulnerable groups Land for land compensation should be as the preferred option. If land is not available, or at the DP s choice, cash compensation can be provided for the lost area at 100% of land replacement cost. The DP will be provided with the additional rehabilitation measures to restore the lost income sources - Other assistance options which each province could decide based on the locality conditions. - Affected households to be notified at least ninety days before land recovery by the Project (Land law-2003; Article 39- Item 2). - The owner of land will hand over the land within 20 days from the date District Compensation Board/ Land Fund Development Center has paid compensation and other allowances in full. - For poor, vulnerable and severely affected farmers, including landless, allocation of arable land equal to per capita arable land in commune, or if there no land available for allocation or, on the DPs request through informed choice, training/ rehabilitation programs will be provided to at least restore, if not improve, their income and living standards. Land Users with temporary or leased rights to use land. Cash compensation at the amount corresponding to the remaining investment on the land or corresponding to the remaining value of the land rental contract. Land Users who do not have formal or customary rights to the affected land DPs will receive assistance corresponding up to 100% of the land value in cash. In addition to above, rehabilitation/training assistance will be provided. In case the DP uses public land where there was previous agreement to return the land to the Government when so requested, they will not be compensated for the acquired public land but will be compensated for structures, crops, trees and other assets on the land at 100% of the Power Engineering Consulting Joint Stock Company 3 73

74 Type of Loss/ Impacts 2. Residential land 2.1. Marginal loss (i.e., land is still viable for use and not requiring relocation). Application Entitlements Implementation Arrangements replacement cost. Compensation for loss of land in cash at (i) replacement cost to the legal and legalizable land users; (ii) An financial assistance of an agreed amount to the land users not having recognizable land use right. If DPs have to rebuild their houses, they will receive a house rental allowance for 3 months in recognition of the time needed to rebuild their houses Relocated DPs (i) Legal or legalizable land users: It land is not available, a land plot in a resettlement site or apartment will be provided to the DP, in consultation with them. They will have full land title or apartment ownership title without any cost to them. Or, on request of the DPs through informed choice, cash compensation at full replacement cost plus the amount equivalent to the value of the infrastructure investments calculated averagely for each household in a resettlement site. In this case, they will be expected to relocate themselves. If the compensation amounts to less than the cost of a land plot in the project s resettlement site, DPs will be provided additional supported to enable them to acquire the land plot (or cash assistance will be provided equivalent to this difference for self-relocated DPs). (ii) DPs who do not have formal, or customary rights to the affected land: An identified assistance amount will be provided based on the level of legality of the land and on a case by case basis. If the DP has no place to move, a land plot or an apartment satisfactory to them will be provided in the resettlement site. In case the relocated DP belong to vulnerable groups, the project will consider providing them with additional assistance (in cash and kind) to ensure that they can afford to relocated to a new site. - Affected household to be notified at least 180 days before land recovery by the Project. - The owner of land will hand over the land within 20 days from the date District Compensation Board/ Land Fund Development Center has paid compensation in full. - Affected household to be notified at least 180 days before land recovery by the Project. - The owner of land will hand over the land within 20 days from the date District Compensation Board/ Land Fund Development Center has paid compensation in full. The process of compensation for a plot at the resettlement site will be as follows: - If the selling cost of plot(s) at the new site is more than the value of the affected residential land, DPs receive new plot at no additional cost. - If the plot(s) at the new site is equal the value of affected residential land, DPs receive new plot at the new site without any balance. - If the plot(s) at the new site is less than the value of affected residential land, DPs will receive plot and the difference in cash. The planning and detailed design for the relocation sites will be done by consultant of DCB/ CLDF in consultation with stakeholders and then approved by the PPC. Detailed regulation on plot allocation will be developed by DCB/CLDF through consultation with commune and DPs, followed by approval of PPC. For relocating households, assistance is in form of land-for-land of similar characteristics with title at no cost. The replacement land is no less than 40m2, or compensation in cash with equal value if DP opts for selfrelocation. Area and number of resettlement sites will be decided in consultation with DPs. Power Engineering Consulting Joint Stock Company 3 74

75 Type of Loss/ Impacts Application Entitlements Implementation Arrangements 3. Houses 3.1. Partial impact: Unaffected portion of the house is still viable for use and could be remained from the technical viewpoints, therefore, require no relocation Full impact (i.e., house is partially acquired by the project but no longer viable for continued use or the entire structure is acquired). - If house/structure is partially affected and the remaining structure is viable for continued use, the project will provide a house/structure repair cost, in addition to the compensation for affected portion at replacement cost, to enable DPs to restore it to former or better conditions. - Compensation for other structures/fixed assets will be at full replacement cost and will be in cash. - Compensation in cash for entire affected structures will be provided at 100% of the full replacement cost for materials and labor, regardless of whether or not they have title to the affected land or permit to build the affected structure. The amount will be sufficient to rebuild a structure the same as the former one at current market prices. No deductions will be made for depreciation or salvageable materials. - Compensation for other structures/fixed assets will be at full replacement cost and will be in cash. Tenants of state or organization s houses will be: (i) entitled to rent or buy a new apartment of the area at least equal to their affected ones; or (ii) provided an assistance equal 60% of replacement cost of the affected land and houses. Any investments such as structures, trees, crops etc. made on the land by the DPs will be compensated at their full replacement cost. The tenants who are leasing a private house for living purposes will be provided with transportation allowance for moving their assets. They will also be assisted in identifying alternative accommodation. For poor or vulnerable DPs who have no other residential land in the same as their affected commune, the project will provide either a residential plot of minimum size at a common resettlement site, or an individual resettlement site, with title to the land (plot of 40 m2 in urban area and 100m2 in rural area); or on request of the DP, through informed choice, an assistance amount corresponding 60% of the land replacement cost for them to rearrange relocation by themselves. The calculation of rates will be based on the actual affected area and not the useable area. The calculation of rates will be based on the actual affected area and not the useable area. 4. Crops and Trees, Owners regardless of tenure For annual and perennial standing crops or trees, DPs will be given notice several months in advance regarding evacuation. Power Engineering Consulting Joint Stock Company 3 75

76 Type of Loss/ Impacts aquaculture products status Application Entitlements Implementation Arrangements aquaculture products regardless of the legal status of the land, compensation in cash will be paid to the affected persons, who cultivate the land, at full replacement cost in local markets to ensure the compensation is sufficient to replace the lost standing crops, trees or aquaculture products. 6. Public structures Loss of, or damage to assets Either in (i) cash compensation to cover the cost of restoring the facilities or (ii) in kind compensation based on the negotiation between District Compensation Board/ Land Fund Development Center and owners of assets. 7. Communalowned assets, collective assets Loss of,, or damage to assets of village, ward, commune, district, provincial government unit. 8. Graves Have to move the graves or tombs Either (i) cash compensation to cover the cost of restoring the facilities or (ii) in kind compensation based on the negotiation between DCB/ CLDF and owners of assets. - All costs of excavation, relocation and reburial will be reimbursed in cash to the affected family. - Graves to be exhumed and relocated in culturally sensitive and appropriate ways. Crops grown after issuance of the deadline will not be compensated. For public structures, the displacement will be carried out by the owners prior to the start of works. For the communal owned assets directly affecting lives and production activities of the community, restoration must be done prior to the start of works. 9. Loss of Income/ Livelihood due to loss of productive land Impacts due to permanent loss of 20% or more of their total productive land or where <20% land affected but the remaining land is rendered unviable. (Legal, legalizable land users and DPs with lease agreement over the affected land) - Allowance for Loss of Livelihood: Affected person will be compensated with one-time payment at cash equivalent to 30 kg of rice/person/month at local market price, including: (a) DPs losing 20-70% of their agricultural landholding (or 10-70% for the poor and vulnerable groups) will be provided with the amount equivalent to 30 kg of rice/person/month for 6 months if they do not have to relocate and 12 months in case of relocation. In some special cases, in extremely difficult areas, the compensation may be provided for a maximum of 24 months; (b) DPs losing more than 70% of their agricultural landholding will be assisted for 12 months if they do not have to relocate and 24 months in case of relocation. In some special cases, in extremely difficult areas, the compensation may be provided upto a maximum of 36 The amount will be given in tranches every 6 months to coincide with the cropping season while affected households are taking part in the income restoration program in order to restore their pre-project income/livelihood. Power Engineering Consulting Joint Stock Company 3 76

77 Type of Loss/ Impacts 10. Loss of Income/ Livelihood due to relocation of business Application Entitlements Implementation Arrangements Marginal impacts Owner of the affected business and employees months;.(c) Households affected by loss of less than 20% of land, where the remaining land is rendered unviable for continued use, will be assisted with the above support plus any additional support as determined, for a period of 12 months. In case of land-for-land compensation, DPs will be assisted with seedlings, agricultural-forestry extension programs, husbandry etc. Support for job changing: Every DP affected by loss of productive land, irrespective of the degree of impact, will be provided with additional assistance equivalent to 2-5 times the compensation amount. Support for vocational training and job creation: DPs will be exempted from exemption from tuition fees for the training courses for those of working age (not applicable for those who enroll for a vocational training outside the province). After finishing training courses, they will be given priorities to be recruited in local manufacturers/businesses. For DPs losing income and/or business/productive assets as a result of land acquisition, the mechanism for compensating will be: The registered non-farm producer/business DPs, who have income-generating and/or business/productive assets affected, will be given cash business assistance for the loss of business income, equivalent to 50% of the annual average for the last 3 years net income. (This amount is equivalent to 100% of monthly net income for 6 months). The non-registered business or non-farm producer DPs, whose operations are recognized by local authority and who have income and/or business/productive assets affected, will be given assistance in cash for the income losses for three Power Engineering Consulting Joint Stock Company 3 77

78 Type of Loss/ Impacts Application Entitlements Implementation Arrangements months at the minimum If the business has to be relocated, then, a priority to provide a replacement business site accessible to customers, or, compensation in cash for the affected area at a replacement cost, plus transportation allowance to remove movable attached assets. If there is no land available, then the business/nonfarm producer DPs will be entitled for rehabilitation measures such as job training, credit access to help restore the income sources Relocating shop owners regardless of tenure status. If the business has to be relocated, the project will provide alternative site with local advantage and physical attributes similar to the land lost with easy access to customers base, satisfactory to the DP, OR compensation in cash for the affected land at replacement cost, plus transportation allowance for movable attached assets. DPs will be given priority for business relocation along highway, communal roads and along canals near the bridges or footbridges in order to maximize their benefit from business opportunities. At the time of compensation, allowances will be adjusted to account for inflation. 11. Allowances /Assistance Targeted to Vulnerable Households Loss of land and non-land assets Affected vulnerable groups regardless of severity of impacts. The vulnerable groups were defined as in Terms of Terminology Specific assistance to vulnerable groups would be as follows: -Social Policy: (i) Relocating Households that include heroic mothers, war veterans, wounded or dead soldiers families will be provided with support as regulated by the PPCs but not less than VND 10 mil per household: (ii) Poor Relocated Households or Poor Households where 20% or more of their productive land is affected or where <20% land is affected but the remaining land is rendered unviable: 3-5 mil/hh (to be certified by local authority). - Other vulnerable groups affected by the Project, whether they have to relocate or not, (female headed households, households with disabled persons, elderly without any source of support, ethnic minority households) will get the same support given to poor households in accordance with the provincial policy but not less than VND 3 mil per household. - Allowance for households as per Government regulation (social policy households, heroic mothers, wounded, dead soldiers). If the household eligible to more than one additional support allowance for the vulnerable people, only one package with the highest value will be applied. - These households are entitled to take part in Income Restoration Program 12. Other Loss of land and non-land Incentive Bonus: A bonus of maximum 5 million VND Power Engineering Consulting Joint Stock Company 3 78

79 Type of Loss/ Impacts Allowances/ Assistances assets Application Entitlements Implementation Arrangements will be awarded to DPs who dismantle their houses and vacate their premises in accordance with the resettlement schedule. Repair Allowance: If house/structure is partially affected and the remaining structure is viable for continued use, the project will ensure that these will be restored or repaired at no cost for the community and to the community s satisfaction. The relocating households with children who are going to schools will be supported with 1-year tuition as regulated by the Ministry of Education Based on the actual situation of the locality, the PPC Chairman issues other allowances to ensure accommodation and livelihood restoration for DPs. Special cases have to be submitted to the Prime Minister for approval. 13. Temporary impacts Temporary loss of land and assets. Compensation for all affected assets/investments made on the land, including trees, crops etc., at full replacement cost; Cash compensation for land temporarily acquired in the form of rent which is at least equivalent to the net income that would have been derived from the affected property during the period of disruption; Restoration of the land within 3 months after use: The contractor is expected to return the land in its original condition within 3 months of the termination of the civil works. If the quality of land is radically changed when returned to DPs, requiring DPs to change in the types of land use; then DPs should be compensated for all envisaged cost of losses. 14. Any other impacts that may be identified during implementation Individuals, organizations in the project area Entitlements to compensation and other assistance would be provided in accordance with the compensation policy. Secondary impacts on production and business or DPs isolated from access to resources temporarily have to be compensated and supported in accordance with RP. In case of impacts on livelihoods of DPs, the contractors, construction units have to agree with the households on payment for disruption of business. Power Engineering Consulting Joint Stock Company 3 79

80 ANNEX 3 SITE AGREEMENT Power Engineering Consulting Joint Stock Company 3 80

81 ANNEX 4 MINUTES AND PICTURES OF MEETINGS ON PUBLIC CONSULTATION Photo of socio-economic survey House in ROW of the connection line Photo of meeting at Thanh Phuoc commune Photo of meeting at Thanh Phuoc commune Photo of meeting at Thai Hoa township Photo of meeting at Thai Hoa township Power Engineering Consulting Joint Stock Company 3 81

SUB-PROJECT: OVERHEAD LINE BAY EXTENSION AT 500kV QUANG NINH SUBSTATION AND 500kV HIEP HOA SUBSTATION

SUB-PROJECT: OVERHEAD LINE BAY EXTENSION AT 500kV QUANG NINH SUBSTATION AND 500kV HIEP HOA SUBSTATION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION CENTRAL VIETNAM POWER PROJECT MANAGEMENT BOARD RESETTLEMENT PLAN (RP) SUB-PROJECT:

More information

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Ho Chi Minh City)

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Ho Chi Minh City) Social Monitoring Report 3 rd Monitoring Report January 2015 VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Ho Chi Minh City) Prepared by the Central

More information

VIETNAM ELECTRICITY TRUNG SON HYDROPOWER MANAGEMENT BOARD RP857 V4. Vietnam: Trung Son Hydropower Project Transmission Line Component

VIETNAM ELECTRICITY TRUNG SON HYDROPOWER MANAGEMENT BOARD RP857 V4. Vietnam: Trung Son Hydropower Project Transmission Line Component Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY TRUNG SON HYDROPOWER MANAGEMENT BOARD RP857 V4 Vietnam: Transmission

More information

RESETTLEMENT POLICY FRAMEWORK

RESETTLEMENT POLICY FRAMEWORK Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized HAI PHONG DEPARTMENT OF TRANSPORT RP1035 V. 3 PROJECT MANAGEMENT UNIT OF REGIONAL TRANSPORT

More information

SUB-PROJECT. BINH SON 110kV SUBSTATION AND TEE-OFF RESETTLEMENT PLAN

SUB-PROJECT. BINH SON 110kV SUBSTATION AND TEE-OFF RESETTLEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ELECTRICITY VIETNAM SOUTHERN POWER CORPORATION ---------------------------------------------------

More information

RESETTLEMENT POLICY FRAMEWORK AND PROCEDURAL GUIDELINES GAUNGXI ROADS DEVELOPMENT II PROJECT

RESETTLEMENT POLICY FRAMEWORK AND PROCEDURAL GUIDELINES GAUNGXI ROADS DEVELOPMENT II PROJECT Village Roads Component on the GAUNGXI ROADS DEVELOPMENT II PROJECT in THE PEOPLE S REPUBLIC OF CHINA (PRC) Guangxi Comnications Department Nanning, PRC This report was prepared by the Borrower and is

More information

RESETTLEMENT ACTION PLAN

RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM HO CHI MINH CITY PEOPLE S COMMITTEE INVESTMENT MANAGEMENT

More information

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Lines

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Lines Social Monitoring Report Quarter Report April June 2015 VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Lines Prepared by the Southern Vietnam Power Projects

More information

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT, AND REHABILITATION OF DISPLACED PERSONS

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT, AND REHABILITATION OF DISPLACED PERSONS Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RP275 Socialist Republic of Vietnam Ministry of Transport and National Traffic Safety

More information

Socialist Republic of Vietnam POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF DISPLACED PERSONS

Socialist Republic of Vietnam POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF DISPLACED PERSONS Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Socialist Republic of Vietnam POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION

More information

RP1 85 November The Resettlement Policy Framework (RPF) Report on the GEF Hai Basin Project. (Final Version)

RP1 85 November The Resettlement Policy Framework (RPF) Report on the GEF Hai Basin Project. (Final Version) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PIP annex 9 - C of GEF Hai Basin Integrated Water and Environment Management Project

More information

RESETTLEMENT POLICY FRAMEWORK (RPF)

RESETTLEMENT POLICY FRAMEWORK (RPF) SOCIALIST REPUBLIC OF VIET NAM MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT ============================================= MEKONG DELTA INTEGRATED CLIMATE RESILIENCE AND SUSTAINABLE LIVELIHOODS PROJECT

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Resettlement Due Diligence Report Project Number: 46391-001 March 2017 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation for the Asian

More information

Subproject: Nhat Trai pumping station in Bac Ninh province

Subproject: Nhat Trai pumping station in Bac Ninh province External Resettlement Monitoring Report Semi annual Report Mission 3 Octocber, 2013 VIE: STRENGTHENING WATER MANAGEMENT AND IRRIGATION SYSTEMS REHABILITATION PROJECT Subproject: Nhat Trai pumping station

More information

DA NANG QUANG NGAI EXPRESSWAY PROJECT

DA NANG QUANG NGAI EXPRESSWAY PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Ministry of Transport Vietnam Expressway Corporation DA NANG QUANG NGAI EXPRESSWAY PROJECT

More information

REPUBLIC OF MACEDONIA

REPUBLIC OF MACEDONIA Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized REPUBLIC OF MACEDONIA Municipal Services Improvement Project (MSIP) LAND ACQUISITION

More information

LIVESTOCK WASTE MANAGEMENT IN EAST ASIA

LIVESTOCK WASTE MANAGEMENT IN EAST ASIA Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized LIVESTOCK WASTE MANAGEMENT IN EAST ASIA Project preparation under the PDF-B grant RP337

More information

DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN

DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN DUE DILIGENCE REPORT AND CORRECTIVE ACTION PLAN Project Number: 42039-035 August 2012 Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission Investment Program PLEIKU-MY PHUOC-CAU

More information

Viet Nam: Secondary Cities Development Project - Buon Ma Thuot Subproject

Viet Nam: Secondary Cities Development Project - Buon Ma Thuot Subproject Resettlement Monitoring Report Semi-Annual Report January 2017 Viet Nam: Secondary Cities Development Project - Buon Ma Thuot Subproject Prepared by Nguyen Van Trung, External Resettlement Monitoring Consultant,

More information

DECREE GENERAL PROVISIONS

DECREE GENERAL PROVISIONS THE GOVERNMENT ------- SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom Happiness --------------- No: 44/2014/ND-CP Hanoi, May 15, 2014 DECREE REGULATIONS ON LAND PRICES Pursuant to Law on Government

More information

RURAL DISTRIBUTION PROJECT

RURAL DISTRIBUTION PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ELECTRICITY OF VlET NAM POWER COMPANY 3 VOL 33 RURAL DISTRIBUTION PROJECT COMPONENT PROJECT

More information

VIE: Yen Vien-Lao Cai Railway Upgrading Project

VIE: Yen Vien-Lao Cai Railway Upgrading Project Social Monitoring Report Semi-Annual Report June 2014 VIE: Yen Vien-Lao Cai Railway Upgrading Project External Monitoring Report on RP Implementation Lao Cai Province Prepared by Railway Projects Management

More information

Resettlement Policy framework for the Albania s Improvement of the Management and Conditions of the Secondary and Local Roads Project

Resettlement Policy framework for the Albania s Improvement of the Management and Conditions of the Secondary and Local Roads Project Resettlement Policy framework for the Albania s Improvement of the Management and Conditions of the Secondary and Local Roads Project I. Introduction The overall length of the road network in Albania totals

More information

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF PROJECT AFFECTED PERSONS. November 2000

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF PROJECT AFFECTED PERSONS. November 2000 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized LAO PDR: AGRICULTURAL DEVELOPMENT PROGRAM RP-59 POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT

More information

(DRAFT) LIVESTOCK WASTE MANAGEMENT IN EAST ASIA PROJECT POLICY FRAMEWORK FOR RESETTLEMENT OF PROJECT DISPLACED PERSON IN THAILAND

(DRAFT) LIVESTOCK WASTE MANAGEMENT IN EAST ASIA PROJECT POLICY FRAMEWORK FOR RESETTLEMENT OF PROJECT DISPLACED PERSON IN THAILAND (DRAFT) Public Disclosure Authorized RP337 v2 LIVESTOCK WASTE MANAGEMENT IN EAST ASIA PROJECT POLICY FRAMEWORK FOR RESETTLEMENT OF PROJECT DISPLACED PERSON IN THAILAND Public Disclosure Authorized Public

More information

RP607. Summary of Land Acquisition & Resettlement Policy Framework JAMAICA: JM Hurricane Dean ERL Project. A. Introduction. B. Means of Obtaining Land

RP607. Summary of Land Acquisition & Resettlement Policy Framework JAMAICA: JM Hurricane Dean ERL Project. A. Introduction. B. Means of Obtaining Land Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Summary of Land Acquisition Policy Framework JAMAICA: JM Hurricane Dean ERL Project RP607

More information

LAND SUBLEASE CONTRACT FOR SETTING UP THE FACTORY IN GIANG DIEN INDUSTRIAL ZONE No.:... /HDTD

LAND SUBLEASE CONTRACT FOR SETTING UP THE FACTORY IN GIANG DIEN INDUSTRIAL ZONE No.:... /HDTD LAND SUBLEASE CONTRACT FOR SETTING UP THE FACTORY IN GIANG DIEN INDUSTRIAL ZONE No.:... /HDTD - Pursuant to Land Law No. 13/2003/QH11 dated 26 th November, 2003 passed by the National Assembly of the Socialist

More information

Viet Nam: Central Region Small and Medium Towns Development Project Khanh Hoa Province

Viet Nam: Central Region Small and Medium Towns Development Project Khanh Hoa Province Resettlement Planning Document Resettlement Plan Document Stage: Draft for Consultation Project Number: 30286 June 2006 Viet Nam: Central Region Small and Medium Towns Development Project Khanh Hoa Province

More information

Vietnam Land Administration - the Past, Recent and for the Future

Vietnam Land Administration - the Past, Recent and for the Future Mr. Ton Gia Huyen, Former Director General of General Department of Land Administration and Mrs. Tran Thi Minh Ha, Director of International Relation Department, Ministry of Natural Resources and Environment,

More information

Resettlement Plan. Feasibility Study Vinh Long Province. Rural Distribution Project. Volume 2. Final Version. E~~crarcrr~ OF VIETNAM VOL.

Resettlement Plan. Feasibility Study Vinh Long Province. Rural Distribution Project. Volume 2. Final Version. E~~crarcrr~ OF VIETNAM VOL. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized E~~crarcrr~ OF VIETNAM POWER COMPANY 2 Rural Distribution Project Feasibility Study VOL.

More information

THE GOVERNMENT. THE SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness. No. 84/2007/NĐ-CP. Hanoi, May 25, 2007

THE GOVERNMENT. THE SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness. No. 84/2007/NĐ-CP. Hanoi, May 25, 2007 THE GOVERNMENT THE SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness No. 84/2007/NĐ-CP Hanoi, May 25, 2007 DECREE On supplementary regulations for issuance of Certificate of land use right,

More information

Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project

Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project Resettlement Plan July 215 Viet Nam: Central Region Rural Water Supply and Sanitation Sector Project WATER SUPPLY AND SANITATION OF TIEN LOC COMMUNE HAU LOC DISTRICT, THANH HOA PROVINCE Prepared by National

More information

LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK (LARPF)

LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK (LARPF) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PT PLN (Persero) INDONESIA POWER SECOND TRANSMISSION DEVELOPMENT PROJECT (IPTD-2) RP1232

More information

Republic of Turkey Additional Financing to Second Renewable Energy and Energy Efficiency Project Resettlement Policy Framework For TSKB and TKB

Republic of Turkey Additional Financing to Second Renewable Energy and Energy Efficiency Project Resettlement Policy Framework For TSKB and TKB Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Republic of Turkey Additional Financing to Second Renewable Energy and Energy Efficiency

More information

REPORT ON PROJECT STATUS AND DEVELOPMENT PROGRESS IN Respectfully submitted to: THE ANNUAL GENERAL MEETING OF SHAREHOLDERS

REPORT ON PROJECT STATUS AND DEVELOPMENT PROGRESS IN Respectfully submitted to: THE ANNUAL GENERAL MEETING OF SHAREHOLDERS No. 11 VINGROUP JOINT STOCK COMPANY ----------- ---------- THE SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness ----------- ---------- Hanoi, 02 April 2015 REPORT ON PROJECT STATUS AND

More information

DRAFT EXECUTIVE SUMMARY

DRAFT EXECUTIVE SUMMARY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DRAFT EXECUTIVE SUMMARY IPUH - BANTAL (LINK 015.1) KABUPATEN MUKO-MUKO YEAR 2010 EXECUTIVE

More information

RENEWABLE ENERGY INTEGRATION PROJECT

RENEWABLE ENERGY INTEGRATION PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DRAFT TURKISH ELECTRICITY TRANSMISSION COMPANY TEIAS RP1530 RENEWABLE ENERGY INTEGRATION

More information

VOLUME 3 RESETTLEMENT PLAN PHU THO PROVINCE VIETNAM ADDITIONAL FINANCING TO RURAL ENERGY 2 PROJECT VOL. 4 ELECTRICITY OF VIETNAM POWER COMPANY NO1

VOLUME 3 RESETTLEMENT PLAN PHU THO PROVINCE VIETNAM ADDITIONAL FINANCING TO RURAL ENERGY 2 PROJECT VOL. 4 ELECTRICITY OF VIETNAM POWER COMPANY NO1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ELECTRICITY OF VIETNAM POWER COMPANY NO1 POWER CONSTRUCTION CONSULTING CENTER NO1 VOL.

More information

Kazakhstan: Proposed Moinak Electricity Transmission Project Land Acquisition Policy Framework

Kazakhstan: Proposed Moinak Electricity Transmission Project Land Acquisition Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Kazakhstan: Proposed Moinak Electricity Transmission Project Land Acquisition Policy

More information

MINISTRY OF HEALTH CAN THO PROVINCIAL HEALTH DEPARTMENT CAN THO PROVINCE. Resettlement Action Plan (RAP) DRAFT JANUARY 2002 CAN THO JANUARY 2002

MINISTRY OF HEALTH CAN THO PROVINCIAL HEALTH DEPARTMENT CAN THO PROVINCE. Resettlement Action Plan (RAP) DRAFT JANUARY 2002 CAN THO JANUARY 2002 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF HEALTH CAN THO PROVINCIAL HEALTH DEPARTMENT VETNAM: REGIONAL BLOOD TRANSFUSION

More information

Tan Hung Investment Joint Stock Co.,

Tan Hung Investment Joint Stock Co., Tan Hung Investment Joint Stock Co., www.tanhungco.com www.hungdiennewtown.com Dale E. Washington Le Thi Giau Brief Introduction! Organization name: Tan Hung Investment Joint Stock Co.,! Head office: 11

More information

SFG kv İzmir Substation Abbreviated Resettlement Action Plan (ARAP) Turkish Electricity Transmission Company. Public Disclosure Authorized

SFG kv İzmir Substation Abbreviated Resettlement Action Plan (ARAP) Turkish Electricity Transmission Company. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Turkish Electricity Transmission Company 380 kv İzmir Substation Abbreviated Resettlement

More information

SOCIALIST REPUBLIC OF VIET NAM ELECTRICITY OF VIET NAM POWER ENGINEERING CONSULTING COMPANY I. Project: Project: Project: 51.

SOCIALIST REPUBLIC OF VIET NAM ELECTRICITY OF VIET NAM POWER ENGINEERING CONSULTING COMPANY I. Project: Project: Project: 51. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PECC I RP82 V. 7 SOCIALIST REPUBLIC OF VIET NAM ELECTRICITY OF VIET NAM POWER ENGINEERING

More information

VIET NAM: CENTRAL MEKONG DELTA REGION CONNECTIVITY PROJECT DUE DILIGENCE REPORT FOR USE OF ADB FUNDS FOR LAND ACQUISITION AND RESETTLEMENT

VIET NAM: CENTRAL MEKONG DELTA REGION CONNECTIVITY PROJECT DUE DILIGENCE REPORT FOR USE OF ADB FUNDS FOR LAND ACQUISITION AND RESETTLEMENT VIET NAM: CENTRAL MEKONG DELTA REGION CONNECTIVITY PROJECT DUE DILIGENCE REPORT FOR USE OF ADB FUNDS FOR LAND ACQUISITION AND RESETTLEMENT February 2013 A. Introduction 1. Under the ADB Policy on Cost

More information

Replacement of 110kV Noyemberyan and Lalvar Overhead Transmission Lines. Abbreviated Resettlement Action Plan

Replacement of 110kV Noyemberyan and Lalvar Overhead Transmission Lines. Abbreviated Resettlement Action Plan Replacement of 110kV Noyemberyan and Lalvar Overhead Transmission Lines Abbreviated Resettlement Action Plan Part 1: Alaverdi, Mets Ayrum, Chochkan and Ayrum communities Contract: Procurement of Plant,

More information

SUMMARY LAND ACQUISITION PLAN. Supplementary Appendix to the. Report and Recommendation of the President to the Board of Directors.

SUMMARY LAND ACQUISITION PLAN. Supplementary Appendix to the. Report and Recommendation of the President to the Board of Directors. SUMMARY LAND ACQUISITION PLAN Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the RURAL ROADS SECTOR I PROJECT in INDIA Ministry of Rural Development

More information

RP606 RURAL POWER DISTRIBUTION PROJECT VIETNAM ELECTRICITY RD FOR QUANG NGAI PROVINCE. Volume 4 COMPENSATION AND RESETTLEMENT PLAN. POWER COMPANY No.

RP606 RURAL POWER DISTRIBUTION PROJECT VIETNAM ELECTRICITY RD FOR QUANG NGAI PROVINCE. Volume 4 COMPENSATION AND RESETTLEMENT PLAN. POWER COMPANY No. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY POWER COMPANY No.3 RURAL POWER DISTRIBUTION PROJECT RD FOR QUANG

More information

RP1599 TRANSMISSION GRID STRENGTHENING PROJECT CONSTRUCTION OF AKHALTSIKHE-BATUMI 220KV POWER TRANSMISSION LINE RESETTLEMENT POLICY FRAMEWORK

RP1599 TRANSMISSION GRID STRENGTHENING PROJECT CONSTRUCTION OF AKHALTSIKHE-BATUMI 220KV POWER TRANSMISSION LINE RESETTLEMENT POLICY FRAMEWORK Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TRANSMISSION GRID STRENGTHENING PROJECT CONSTRUCTION OF AKHALTSIKHE-BATUMI 220KV POWER

More information

Summary of Land Acquisition, Resettlement and Rehabilitation Policy for Infrastructure Development Project 2015

Summary of Land Acquisition, Resettlement and Rehabilitation Policy for Infrastructure Development Project 2015 Summary of Land Acquisition, Resettlement and Rehabilitation Policy for Infrastructure Development Project 2015 Vision Contribute to overall development of the nation and its citizens by creating conducive

More information

Involuntary Resettlement Due Diligence Report. ARM: Water Supply and Sanitation Sector Project Additional Financing

Involuntary Resettlement Due Diligence Report. ARM: Water Supply and Sanitation Sector Project Additional Financing Involuntary Resettlement Due Diligence Report Loan 2860 (SF) July 2015 ARM: Water Supply and Sanitation Sector Project Additional Financing Prepared by the Armenian Water and Sewerage Closed Joint Stock

More information

DECREE GENERAL PROVISIONS DETAILED REGULATIONS ON COMPENSATION, SUPPORT, AND RESETTLEMENT UPON LAND EXPROPRIATION BY THE STATE

DECREE GENERAL PROVISIONS DETAILED REGULATIONS ON COMPENSATION, SUPPORT, AND RESETTLEMENT UPON LAND EXPROPRIATION BY THE STATE THE GOVERNMENT -------- SOCIALIST REPUBLIC OF VIETNAM Independence Freedom - Happiness ---------------- No.: 47/2014/NĐ-CP Hanoi, May 15, 2014 DECREE REGULATIONS ON COMPENSATION, SUPPORT, AND RESETTLEMENT

More information

RESETTLEMENT POLICY FRAMEWORK FOR KENYA POWER PROJECTS

RESETTLEMENT POLICY FRAMEWORK FOR KENYA POWER PROJECTS RESETTLEMENT POLICY FRAMEWORK FOR KENYA POWER PROJECTS REVISED SEPTEMBER - 2012 i EXECUTIVE SUMMARY The Kenya power and Lighting Company Ltd (KPLC) falls under the Ministry of Energy (MoE). KPLC, which

More information

COAL MINE METHANE DEVELOPMENT PROJECT (SHANXI PROVINCE) RESETTLEMENT PLAN. CMM and CBM Production for Power Generation

COAL MINE METHANE DEVELOPMENT PROJECT (SHANXI PROVINCE) RESETTLEMENT PLAN. CMM and CBM Production for Power Generation COAL MINE METHANE DEVELOPMENT PROJECT (SHANXI PROVINCE) RESETTLEMENT PLAN CMM and CBM Production for Power Generation Shanxi Jincheng Coal Mining Group Co., Ltd. September 2004 THIS IS NOT AN ADB BOARD

More information

Land Acquisition and Resettlement Policy Framework

Land Acquisition and Resettlement Policy Framework Myanmar Agriculture Development Support Project Land Acquisition and Resettlement Policy Framework Ministry of Agriculture and Irrigation The Union Government of Myanmar Draft for Public Consultation 1

More information

RESETTLEMENT POLICY FRAMEWORK

RESETTLEMENT POLICY FRAMEWORK Ministry of Agriculture and Environmental Protection Directorate for Water Management 11070 Belgrade, Blvd. Umetnosti 2a ELEKTROPRIVREDA SRBIJE FLOODS EMERGENCY AND RECOVERY PROJECT (FERP) RESETTLEMENT

More information

Resettlement and Ethnic Minority Development Plan

Resettlement and Ethnic Minority Development Plan Resettlement and Ethnic Minority Development Plan November 2015 VIE:The Second Northern Greater Mekong Subregion Transport Network Improvement Project NH217 Improvement, Thanh Hoa Province Ba Thuoc Section

More information

Social Screening and Impact Assessment for Sub Projects. B. Justification of project design and alternative analysis:

Social Screening and Impact Assessment for Sub Projects. B. Justification of project design and alternative analysis: Code No: 1.9 Social Screening and Impact Assessment for Sub Projects A. Sub Project Description: Proposed Activity Walkability and Parking Improvements Lotus Road Implementing Agency: Colombo Municipal

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 03/03/2010 INTEGRATED SAFEGUARDS DATASHEET

More information

Dhaka Water Supply and Sanitation Project Resettlement Policy Framework

Dhaka Water Supply and Sanitation Project Resettlement Policy Framework 1. BACKGROUND Dhaka Water Supply and Sanitation Project Resettlement Policy Framework The Dhaka Water and Sewerage Authority (DWASA) currently supplies water to about 70% of the population of the Dhaka

More information

MARKETILED SMALLHOLDER

MARKETILED SMALLHOLDER Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized GOVERNMENT OF THE REPUBLIC OF MOZAMBIQUE MINISTRY OF PLANNING AND DEVELOPMENT RP428 MARKETILED

More information

CIRCULAR On strategic environmental assessment, environmental impact assessment, and environmental protection plans (*)

CIRCULAR On strategic environmental assessment, environmental impact assessment, and environmental protection plans (*) Issue nos 09-10/June 2015 OFFICIAL GAZETTE 17 THE MINISTRY OF NATURAL RESOURCES AND ENVIRONMENT THE SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness No. 27/2015/TT-BTNMT Hanoi, May 29,

More information

World Bank Loan. Hohhot-Zhangjiakou Rapid Railway. Resettlement Policy Framework

World Bank Loan. Hohhot-Zhangjiakou Rapid Railway. Resettlement Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized World Bank Loan Hohhot-Zhangjiakou Rapid Railway Resettlement Policy Framework The Foreign

More information

Resettlement Planning Document

Resettlement Planning Document Resettlement Planning Document June 2012 Pakistan: Sindh Cities Improvement Investment Program (SCIP) Prepared by North Sindh Urban Services Corporation Limited for the Asian Development Bank. PFR-2 Annex-11

More information

B. Justification of project design and alternative analysis:

B. Justification of project design and alternative analysis: Social Screening and Impact Assessment for Sub Projects Code No: 3 A. Sub Project Description: Proposed Activity Town Hall Square Development Implementing Agency: Colombo Municipal Council (CMC) Sub project

More information

KYRGYZ REPUBLIC COMMUNITY DEVELOPMENT AND INVESTMENT AGENCY THIRD RURAL WATER SUPPLY AND SANITATION PROJECT

KYRGYZ REPUBLIC COMMUNITY DEVELOPMENT AND INVESTMENT AGENCY THIRD RURAL WATER SUPPLY AND SANITATION PROJECT SFG1940 REV KYRGYZ REPUBLIC COMMUNITY DEVELOPMENT AND INVESTMENT AGENCY THIRD RURAL WATER SUPPLY AND SANITATION PROJECT RESETTLEMENT POLICY FRAMEWORK JUNE 2016 Public Disclosure Authorized Public Disclosure

More information

Dhaka Water Supply and Sanitation Project

Dhaka Water Supply and Sanitation Project Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VOL. 1 Dhaka Water Supply and Sanitation Project Resettlement Policy Framework Dhaka

More information

RESSETTLEMENT POLICY FRAMEWORK

RESSETTLEMENT POLICY FRAMEWORK Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Department of Water Resources and Land Improvement of the Kyrgyz Republic Project Implementation

More information

PRC: Xinjiang Urban Transport and Environmental Improvement Project

PRC: Xinjiang Urban Transport and Environmental Improvement Project Resettlement Plan April 2013 PRC: Xinjiang Urban Transport and Environmental Improvement Project Prepared by Xinjiang Project Management Office, Hami Construction Bureau for the Asian Development Bank.

More information

LAND ACQUISITION AND RESETTLEMENT DUE DILIGENCE REPORT. ARMENIA: WATER SUPPLY AND SANITATION SECTOR PROJECT. Phase II

LAND ACQUISITION AND RESETTLEMENT DUE DILIGENCE REPORT. ARMENIA: WATER SUPPLY AND SANITATION SECTOR PROJECT. Phase II LAND ACQUISITION AND RESETTLEMENT DUE DILIGENCE REPORT SUBPROJECT 1, ARMAVIR ARMENIA: WATER SUPPLY AND SANITATION SECTOR PROJECT. Phase II Project Number: L2860-ICB-1-01 Prepared by the Project Management

More information

Greater Beirut Water Supply Project Additional Finance Addendum to the Resettlement Action Plan

Greater Beirut Water Supply Project Additional Finance Addendum to the Resettlement Action Plan Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Greater Beirut Water Supply Project Additional Finance Addendum to the Resettlement Action

More information

SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS

SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS MINISTRY OF EDUCATION GOVERNMENT OF NEPAL August 2011 2 A. Introduction 1.

More information

REPORT ON PROJECT IMPLEMENTATION IN 2011

REPORT ON PROJECT IMPLEMENTATION IN 2011 VINCOM JOINT STOCK COMPANY (VINCOM JSC) ----------- ---------- SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness ----------- ---------- Hanoi, April 06 2012 REPORT ON PROJECT IMPLEMENTATION

More information

Mini-Thesis Siam University (International Master of Business Administration), Bangkok, Thailand 2015 CHAPTER IV

Mini-Thesis Siam University (International Master of Business Administration), Bangkok, Thailand 2015 CHAPTER IV CHAPTER IV 4. Land Issues: 4.1 Land Ownership: In Vietnam, land cannot be owned either by individuals or by entities, whether they are Vietnamese or foreign. The Constitution provides that land is owned

More information

a. RIGHTS OF WAY: Utility will own, operate and maintain extension facilities only: ISSUED BY Date Filed: July 2, 1996

a. RIGHTS OF WAY: Utility will own, operate and maintain extension facilities only: ISSUED BY Date Filed: July 2, 1996 SOUTHERN CALIFORNIA WATER COMPANY ORIGINAL Cal. P.U.C. Sheet No. 1005-E Page 1 APPLICABILITY: This rule is applicable to extension of electric Distribution Lines 1 of Utility s standard voltages (less

More information

Cibuk 1 Wind Farm Land Acquisition Plan Vetroelektrane Balkana d.o.o. October 2014

Cibuk 1 Wind Farm Land Acquisition Plan Vetroelektrane Balkana d.o.o. October 2014 Vetroelektrane Balkana d.o.o. October 2014 Table of contents Chapter Pages 1. Introduction 3 2. Project Land Acquisition 3 2.1. Land previously acquired 3 2.2. Land in the process of acquisition 4 3. Legal

More information

PAPUA NEW GUINEA ROAD MAINTENANCE AND REHABILITATION PROJECT (RMRP) II

PAPUA NEW GUINEA ROAD MAINTENANCE AND REHABILITATION PROJECT (RMRP) II Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PAPUA NEW GUINEA ROAD MAINTENANCE AND REHABILITATION PROJECT (RMRP) II Land Acquisition

More information

LAND ACQUISITION FRAMEWORK

LAND ACQUISITION FRAMEWORK LAND ACQUISITION FRAMEWORK (This framework was prepared in accordance to the ADB requirements for preparing Resettlement Framework as described in the ADB Safeguards Policy Statement, 2009) Project Number:

More information

ISLAMIC REPUBLIC OF AFGHANISTAN. Ministry of Rural Rehabilitation and Development (MRRD) And. Independent Directorate of Local Governance (IDLG)

ISLAMIC REPUBLIC OF AFGHANISTAN. Ministry of Rural Rehabilitation and Development (MRRD) And. Independent Directorate of Local Governance (IDLG) Public Disclosure Authorized SFG2396 Public Disclosure Authorized Public Disclosure Authorized ISLAMIC REPUBLIC OF AFGHANISTAN Ministry of Rural Rehabilitation and Development (MRRD) And Independent Directorate

More information

Cambodia Health Equity and Quality Improvement Project (H-EQIP) (P157291) Resettlement Policy Framework (RPF) (DRAFT)

Cambodia Health Equity and Quality Improvement Project (H-EQIP) (P157291) Resettlement Policy Framework (RPF) (DRAFT) Cambodia Health Equity and Quality Improvement Project (H-EQIP) (P157291) Resettlement Policy Framework (RPF) (DRAFT) Date: December 2, 2015 Contents 1. Introduction... 1 2. Project Description... 2 Project

More information

Draft Land Acquisition and Resettlement Framework. Cambodia: National Solar Park Project

Draft Land Acquisition and Resettlement Framework. Cambodia: National Solar Park Project National Solar Park Project (RRP CAM 51182) Draft Land Acquisition and Resettlement Framework September 2018 Cambodia: National Solar Park Project Prepared by the Electricité Du Cambodge for the Asian

More information

RESETTLEMENT POLICY FRAMEWORK (RPF)

RESETTLEMENT POLICY FRAMEWORK (RPF) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized JANUARY 2013 Republic of Mozambique Mozambique Climate Resilience: Transforming Hydro-Meteorological

More information

Resettlement Policy Framework for the Turkey Geothermal Development Project

Resettlement Policy Framework for the Turkey Geothermal Development Project SFG1378 V3 Public Disclosure Authorized 2016 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Resettlement Policy Framework for the Turkey Geothermal Development Project

More information

PAPUA NEW GUINEA. ROAD MAINTENANCE AND REHABILITATION PROJECT (RMRP) II Additional Financing

PAPUA NEW GUINEA. ROAD MAINTENANCE AND REHABILITATION PROJECT (RMRP) II Additional Financing Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PAPUA NEW GUINEA ROAD MAINTENANCE AND REHABILITATION PROJECT (RMRP) II Additional Financing

More information

I U B Reddy The World Bank New Delhi, India

I U B Reddy The World Bank New Delhi, India IAIA15 India s New Land Acquisition Act Right To Fair Compensation and Transparency in Land Acquisition and Rehabilitation and Resettlement Act, 2013 I U B Reddy The World Bank New Delhi, India Challenging

More information

Resettlement Policy Framework

Resettlement Policy Framework Republic of Turkey Second Renewable Energy and Energy Efficiency Project Resettlement Policy Framework Background 1. The Second Renewable Energy and Energy Efficiency Project will fund private sector investments

More information

Upgrading and Construction of Chumateleti-Khevi Section of the E-60 Highway

Upgrading and Construction of Chumateleti-Khevi Section of the E-60 Highway mail33 Ministry of Regional Development and Infrastructure of Georgia Roads Department of Georgia Resettlement Policy Framework EAST-WEST HIGHWAY CORRIDOR IMPROVEMENT PROJECT AF Upgrading and Construction

More information

Resettlement Policy Framework for the Turkey Geothermal Development Project

Resettlement Policy Framework for the Turkey Geothermal Development Project 2016 Resettlement Policy Framework for the Turkey Geothermal Development Project COMPONENT 2 FINANCIAL INTERMEDIARIES (TSKB) FINAL 1 Contents 1. Project Description &Background...3 2. Principles & Objectives...4

More information

COMPONENT 2 - TSKB DRAFT

COMPONENT 2 - TSKB DRAFT 2015 Resettlement Policy Framework for the Turkey Geothermal Development Project COMPONENT 2 - TSKB DRAFT Contents 1. Project Description & Background... 2 2. Principles & Objectives... 3 3. Process for

More information

Resettlement Action Plan (RAP)

Resettlement Action Plan (RAP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Resettlement Action Plan (RAP) FOR THE 33 kv SUB TRANSMISSION LINE IN THE WESTERN AREA

More information

TONGA: Nuku alofa Urban Development Sector Project. Core Subproject 1 (Water Supply)

TONGA: Nuku alofa Urban Development Sector Project. Core Subproject 1 (Water Supply) Nuku'alofa Urban Development Sector Project (RRP TON 42394-22) Resettlement Plan TONGA: Nuku alofa Urban Development Sector Project Core Subproject 1 (Water Supply) Prepared by Planning and Urban Management

More information

TAN VIET TIN (TVT) CONSTRUCTION CO., LTD. PROJECTS PRESENTATION

TAN VIET TIN (TVT) CONSTRUCTION CO., LTD. PROJECTS PRESENTATION TAN VIET TIN (TVT) CONSTRUCTION CO., LTD. PROJECTS PRESENTATION GENERAL INFORMATION of TVT Const. Co., Ltd: Established and licensed on 19 February 2001 with Registration No. 0302227857, TVT now is in

More information

Land Acquisition/Resettlement Framework. Proposed Loan and Administration of Grant Cook Islands: Renewable Energy Sector Project

Land Acquisition/Resettlement Framework. Proposed Loan and Administration of Grant Cook Islands: Renewable Energy Sector Project Land Acquisition/Resettlement Framework Project Number: 46453 March 2014 Proposed Loan and Administration of Grant Cook Islands: Renewable Energy Sector Project Prepared by the Ministry of Finance and

More information

Social Due Diligence Report

Social Due Diligence Report Social Due Diligence Report Can Giuoc District Province of Long An September 2013 VIE: GMS Ben Luc - Long Thanh Expressway Project Prepared by Vietnam Expressway Corporation for the Asian Development Bank.

More information

Rule No. 15. Distribution Line Extensions Page 1 of 14

Rule No. 15. Distribution Line Extensions Page 1 of 14 GOLDEN STATE WATER COMPANY (U 913-E) Revised Cal. P.U.C. Sheet No. 2103-E SAN DIMAS, CALIFORNIA 91773-9016 Canceling Revised Cal. P.U.C. Sheet No. 1005-E Page 1 of 14 APPLICABILITY: This rule is applicable

More information

JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK

JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK I. Introduction The Jamaica Social Investment Fund (JSIF) was established in 1996 under the Government of Jamaica s National

More information

Government of the Kingdom of Swaziland MINISTRY OF HOUSING AND URBAN DEVELOPMENT MINISTRY OF TINKHUNDLA ADMINISTRATION AND DEVELOPMENT

Government of the Kingdom of Swaziland MINISTRY OF HOUSING AND URBAN DEVELOPMENT MINISTRY OF TINKHUNDLA ADMINISTRATION AND DEVELOPMENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Government of the Kingdom of Swaziland MINISTRY OF HOUSING AND URBAN DEVELOPMENT MINISTRY

More information

Land Acquisition and Resettlement Framework. Date: May 2016 Status: Update. FIJI: Transport Infrastructure Investment Sector Project

Land Acquisition and Resettlement Framework. Date: May 2016 Status: Update. FIJI: Transport Infrastructure Investment Sector Project Land Acquisition and Resettlement Framework Date: May 2016 Status: Update FIJI: Transport Infrastructure Investment Sector Project CURRENCY EQUIVALENTS (as of August 2014) Fiji Dollar (FJD) FJD 1.00 =

More information

Draft Land Acquisition and Resettlement Plan (LARP) TAJ: CAREC Corridors 2, 5 and 6 (Dushanbe-Kurgonteppa) Road Project

Draft Land Acquisition and Resettlement Plan (LARP) TAJ: CAREC Corridors 2, 5 and 6 (Dushanbe-Kurgonteppa) Road Project Draft Land Acquisition and Resettlement Plan (LARP) Project Number: 49042-004 August 2016 TAJ: CAREC Corridors 2, 5 and 6 (Dushanbe-Kurgonteppa) Road Project Prepared by the Ministry of Transport. This

More information

Mongolia: Western Regional Road Corridor Investment Program

Mongolia: Western Regional Road Corridor Investment Program Western Regional Road Corridor Investment Program (RRP MON 41193) Resettlement Framework September 2011 Mongolia: Western Regional Road Corridor Investment Program Prepared by the Ministry of Roads, Transportation,

More information

nhatrangrenting.com SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness Page 1 of 9

nhatrangrenting.com SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness Page 1 of 9 BRANCH OF CONSTRUCTION PRIVATE ENTERPRISE NO. 1 DIEN BIEN PROVINCE MUONG THANH KHANH HOA HOTEL No:. / HDMBCH-MTKH SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness APARTMENT SALE AND PURCHASE

More information