GOVERNMENT OF KARNATAKA PUBLIC WORKS DEPARTMENT KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT - II

Size: px
Start display at page:

Download "GOVERNMENT OF KARNATAKA PUBLIC WORKS DEPARTMENT KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT - II"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized GOVERNMENT OF KARNATAKA PUBLIC WORKS DEPARTMENT KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT - II RESETTLEMENT IMPLEMENTATION PLAN WAP 4 (Managuli Talikota - Tadasa) RP946 v5 June 2012

2 Table of Contents ABBREVIATIONS... iv EXECUTIVE SUMMARY...1 I. INTRODUCTION...3 Objectives of RIP... 4 Main activities of RIP... 4 Minimization of Impacts and Corridor of Impact... 4 II. LAND ACQUISITION AND RESETTLEMENT IMPACTS...6 Land Acquisition Status... 6 Guidance Value... 6 Negotiation Committee... 6 Method of Price Negotiation... 7 Records to be submitted by the Land Owners... 7 Failure of KHA and Appellate Committee... 8 Conclusion of negotiation... 8 Valuation of Assets on land under LA... 8 Valuation of Crops... 8 Valuation of other structures/assets... 8 Site Requirement for and impacts... 8 Loss of Community Assets... 8 III. BASELINE CENSUS SURVEYS AND CONSULTATIONS...10 Characteristics of displaced households Major and Minor Impacts Vulnerable groups Consultations IV. IMPLEMENTATION MECHANISMS...14 Institutional Arrangements i

3 Extending R& R Assistance to PAPs Implementation support by NGOs IR Activities Monitoring and Evaluation support for RAP Grievance Redressal mechanism Resettlement Colonies and Vendor Markets Protection of RoW Impacts on Municipal Towns Data Base Management Co ordination between R&R and Civil works Monitoring and R&R Activities Additional Impacts Budget Disclosure Annexure 1: Guidance Value of land as on May Annexure 2: PAF DETAILS 10 A...25 Annexure 3: PAF DETAILS 10 B...29 Annexure 4: Community Asset Details...36 LIST OF TABLES Table 1-1: Summary Tables on Impacts... 3 Table 2-2: Summary Table on Community Assets... 9 Table 3-1: Baseline Socio Economic information - for Major impacts Table 3-2: Distribution of PAFs by Major and Minor Impacts for WAP 4 (10 A&B) Table 3-3: Consultation Summary Table 4-1: R& R Assistance Table 4-2: Time line for Key LA and R & R Activities... Error! Bookmark not defined. Table 4-3: Time line for LA and R & R Activities... Error! Bookmark not defined. ii

4 Table 4-4: Monitoring Indicators for Physical Progress Table 4-5: Budget Table 4-6: Guidance Value of land Table 4-7: PAF Structure details of link 10A (Managuli - Talikota) Table 4-8: PAF Structure details of link 10B (Talikota - Devapur) Table 4-9: Community Asset Details of link 10A (Managuli - Talikota) Table 4-10: Community Asset Details of link 10B (Talikota - Devapur) LIST OF FIGURES Figure 1-1: Distribution of PAFs for WAP Figure 1-2: Distribution of PAFs for link 10B iii

5 ABBREVIATIONS AC ADSW CAO CPO CPR COI DC DPR EWS EPC GOI GOK GRC ID IPDP IR KHA KSHIP LAA LAO LAP NGO PAF PAG PAP PIU PGB PWD PU PGB RTC R & R RAP ROW SIA SDO SDRC SWI SC SR ST Assistant Commissioner Assistant Director Social Welfare Chief Administrative Officer Chief Project Officer Common Property Resources Corridor of Impact Deputy Commissioner Detail Project Report Economically Weaker Section Engineering Procurement Contract Government of India Government of Karnataka Grievance Redressal Cell Identity Card Indigenous People Development Plan Income Restoration Karnataka Highways Act Karnataka State Highways Improvement Project Land Acquisition Act Land Acquisition Officer Land Acquisition Plan Non-Governmental Organization Project Affected Family Project Affected Group Project Affected Person Project Implementation Unit Project Governing Body Public Works Department Pre University Project Governing Body Record of Rights Resettlement and Rehabilitation Resettlement Action Plan Right of Way Social Impact Assessment Social Development Officer Social Development Resettlement Cell Social Welfare Inspector Scheduled Caste Schedule of Rates Scheduled Tribes iv

6 SHG SIA ToR UR ZP Self Help Group Social Impact Assessment Terms of Reference Upgradation Zilla Panchayat v

7 EXECUTIVE SUMMARY The Karnataka State Highways Improvement Project (KSHIP) II, covers a length of kms. The roads have been categorized into two types of contracts EPC and Annuity. It consists of kms of EPC roads consisting of 5 packages and kms of roads under annuity contract consisting of 4 packages. Contract package WAP 4, is an Annuity package which covers kms consisting of 2 links, passing through the districts of Bijapur and Gulbarga. This Resettlement Implementation Plan covers the implementation requirements for Package WAP 4. In this package about 4 acres 18 guntas land has to be acquired, of this 3 acre 39 guntas is dry land, there are no wet land, 08 guntas is plantation and 0.11 guntas is kharab land. As a result of land acquisition and related impacts, 36 PAFs will lose part of their land; and another 226 PAFs lose their house hold/commercial/ assets /livelihood are getting affected. In addition, 106 community assets will also be affected. Out of these impacts, 183 PAFs are in the major impact category losing their houses/shop and livelihood and 79 PAFs in the minor impact category who loses only part of their land or assets and the remaining land and asset is sufficient to continue their shelter and livelihoods. A baseline survey was conducted amongst affected people who indicate that a large majority of them are Hindus which dominate with percent followed by Muslims at percent. Distribution of PAPs by occupation indicates that percent are in agriculture; agricultural labourers account for percent; commerce and trade supports percent. In this package percent of population has income less than Rs.26, percent of the population falls within the age group of 18-60, which happens to be the working age group. In this package illiterate population accounts for percent; those with secondary education account for percent and professionals account for 0.35 percent. Average land holding size is acres. A look at the ownership of household assets indicate percent own televisions; 9.16 percent own 2/4 wheelers while only 6.22 percent own refrigerators. Public consultations were held at two important locations along this corridor in November, 2008 and 110 persons participated in these consultations. The consultations focused on mainly in explaining the entitlements under the R&R policy and measures taken to minimize the impacts and receive the suggestions from the participants. The consultations have helped in not only in disseminating the policy provisions to deal with land acquisition related impacts, but also assisted in gathering suggestions for mitigation of adverse impacts, improvement in designs and facilitating inputs for the resettlement plan preparation and implementation During the consultations people asked for equal widening from the center line; it was explained that this will done as per wherever it is technically feasible, taking into consideration the likely impacts. People wanted to know about what the project would provide in terms of entitlements, which was explained to them. It was explained that what the livelihood options are likely to be made available from the project such as income generation grant. On the issue of safety, it was explained that safety was a part of the design and all precautions will be taken such as signages, barriers etc. Safety concerns have been addressed by building foot paths in built up area, providing foot path barricades, school/village signages, rumble strips and road humps. People also asked for relocation of community assets, it was explained that community assets if affected will be replaced and relocated by the project authorities. 1

8 The GOK has adopted the Resettlement and Rehabilitation (R&R) Policy for KSHIP- II consistent with the NRRP, 2007 and the World Bank policy on involuntary resettlement to address the adverse impacts arising out of this project. Land Acquisition will be done through the Karnataka Highways Act Land acquisition under this Act will help the PAPs to receive the market price/replacement cost of land as compensation through negotiation. Negotiation Committee has been to negotiate the price of land with the landlord. The minimum negotiated price will be twice the current guidance value for Bijapur and Gulbarga district. Key issue related to resettlement and land acquisition identified as of now is the site requirement. Based on the joint verification report of the NGO, 38 sites will be required for non- titleholders. The titleholder verification is under progress. Some of the entitlements include payment of compensation through negotiation according to the Karnataka Highways Act, 1964; additional compensation for those becoming marginal farmers; grant for replacement of cattle shed; alternative house or developed plot +construction cost for those losing house; additional 25% compensation for partially affected structures towards reconstruction; support for purchase of income generating assets; Rental allowance for affected tenants; support for non-titleholders to provide alternate house or developed plot + construction cost for those losing residential structures; support for providing alternate shop or income generating asset to those who lose commercial structures; employees losing livelihood will be given a onetime payment; vulnerable groups including physically challenged and those above 60 years will be assisted to get Government pension, if they are eligible or given a lump sum amount as assistance; and all community assets will be replaced and reconstructed. This RIP will be implemented by Karnataka PWD-PIU Social Development Resettlement Cell with support from the NGO - BIRDS (Bijapur Integrated Rural Development Society). The SDRC is responsible for monitoring the implementation of all resettlement and rehabilitation activities, including land acquisition The Special Deputy Commissioner, Land Acquisition, will be responsible for land acquisition activities while the Chief Administrative Officer will be responsible for all Resettlement and Rehabilitation works. A Grievance Redressal Cell with 3 members is constituted with Deputy Commissioner of the District as the Chairman. An independent agency viz., Samaj Vikas has been hired for Monitoring and Evaluation support. The SDRC, PIU will facilitate land acquisition and compensation, relocation and resettlement, distribution of assistance for the PAPs. WAP 4 will be implemented by KSHIP Division, Belgaum. The SDO and SWIs appointed for the Belgaum division will take care of R&R activities of this package. The civil works for this package is likely to commence in December The R&R and land acquisition is targeted to be completed by August Implementation activities include land acquisition process, relocation and rehabilitation and monitoring. The budget estimated for land acquisition and R&R activities for this package is Rs.3.33 crores which forms a part of the overall budget approved by the GoK. All cash allowances to be paid to the PAPs is adjusted for inflation for and those who receive the assistance beyond April, 2013 will further be adjusted by 10% as needed. This RIP will be disclosed through public consultations, Government of Karnataka/PWD Website. In addition, copies will be kept in: (i) State Government Library at Bangalore; (ii) - District library of Bijapur and Gulbarga districts; and (iii) in the Panchayat offices along the project roads. 2

9 I. INTRODUCTION 1. The Karnataka State Highways Improvement Project (KSHIP) II Phase-I covers a length kms. In this connection a detailed Resettlement Action plan has been prepared in consultation with the affected persons, PIU and other stakeholders. This document includes, amongst other things, legal frame work and Resettlement Policy Provisions, Land acquisition and compensation payment, Social impact assessment and base line Socio-Economic characteristic and the implementation arrangement. The Government approved the Resettlement Action plan vide its order dated 28 th July This has been published in the PWD web sites in the month of August This Resettlement Implementation Plan outlines the steps for resettlement and rehabilitation of PAFs/PAPs losing their land and structures and relocation of community assets for WAP Contract package WAP 4 covers kms consisting of 2 links. The details about the package are given in Table 1. In the annexure the lists of those loosing structures are provided which are enumerated in and verified by NGOs in Details of those loosing land are given in the notifications issued u/s 15 of the KHA. The list of vulnerable people will be subsequently prepared and assistance extended as needed. Any additional people moved into the ROW after the cut-off data and are not served notices subsequently will be identified through additional verification by 31 st July The question of extending assistance to them will be examined on case to case basis. In case of those who are mobile type of shop will not be provided any assistance since, the keep on changing on regular basis and they can easily find another alternative place to continue their petty business. Table 1-1: Package Details Link Description Length Districts Taluks Cutoff date 10A Managuli - Basavana Bijapur Basavana Bagewadi, Bagewadi - Talikota Muddebihal 10B Talikota - Hunasagi Gulbarga, Shorapur Devapur 3. WAP 4 falls within the Northern Karnataka Plateau, with mixed land use. 4. The entire package is regarded as a single milestone. Link 10 A is from chainage 0+00 to and link 10B is from 0.00 to In this package 4 acres 22 ½ guntas land has to be acquired, of this 4 acre 9 ½ guntas is dry land, there are no wet land, 8 guntas is plantation and 5 guntas is kharab land; there are 226 PAFs whose house hold/commercial structures/ assets/ livelihood is getting affected. There are 106 of community assets getting affected. In this Package there are 36 PAFs losing land. The PAPs listed in this RIP is as recorded during the cut-off date and further verified by the NGOs. 6. Key issue related to resettlement and land acquisition identified as of now is the site requirement. Based on the joint verification report of the NGO 38 sites will be required for non- titleholders. The titleholder verification is under progress. 3

10 Objectives of RIP 7. The objective of this RIP is to provide a package specific guideline for implementation for R&R activities. The implementation plan identifies the persons affected, the type of entitlements to be provided for specific losses, what are the steps that will be adopted in getting compensation, details of members of the Negotiation Committee and the GRC members in the package, time table and steps to be taken by the PIU for protecting right ROW. Overall it provides how the RAP will be implemented in this particular package. Main activities of RIP 8. The main activities to be carried out in finalising the RIP includes, Joint verification, distribution of ID cards, identification for sites for relocation, identification of income generating options, identification of vulnerable people who are getting any assistance from the State Government, identification of resettlement centers and vendor markets, negotiations for land acquisition, payment of compensation, relocation and shifting of community assets. The members of the GRC and Negotiation committees have to be identified and informed, as mentioned in the RIP. The RIP after finalization will be disclosed. Minimization of Impacts and Corridor of Impact 9.. There are 8 cross section options adopted in this package to minimize impacts, the COI width varies from 11 m to 26m. In Basavana Bagewadi town specific cross sections have been designed ( UR4A and UR4B). Besides this, safety concerns have been addressed by building foot paths in built up area, providing foot path barricades, school/village signages, rumble strips and road humps have also been provided. The different cross sections used are: 1. UR1A Rural Cross section with paved shoulders varying from m 2. UR1B Rural Cross section without paved shoulders varying from m 3. UR1C Rural Cross section with paved shoulder to maximum width of 20 mt. 4. UR2 Rural Cross section through village width varying from 11m to 22 m. 5. UR3 Urban Cross Section in built up area with covered drain with a maximum width of 22 m 6. UR4 Urban Dual lane Cross section in built up area with covered drain with a maximum width of 24 m. 7. UR4A Urban Dual Lane Cross- Section in built up area with covered drain in link 10 A from chainage to at Basavana Bagewadi 8. UR4B Urban Dual Lane Cross- Section in built up area in link 10 A from chainage to at Basavana Bagewadi 4

11 Table 1-2: Summary Tables on Impacts Link 10 A 10 B Description TOTAL LA Pvt ( in acres) 2Ac 23 guntas 1Ac 34 ¼ guntas 4 Ac 22 ½ guntas Land Transfer ( in acres) Major Impact Minor Impact Community Assets 2 guntas gunta guntas

12 II. LAND ACQUISITION AND RESETTLEMENT IMPACTS 10. This chapter provides an overview of the extent of land acquisition and the process of land price negotiations and details of documents to be submitted. It also provides the impacts of the project on community assets. 11. In this package 4 acres 22 ½ guntas land has to be acquired, of this 4 acre 9 ½ guntas is dry land, there are no wet land, 8 guntas is plantation and 5 guntas is kharab land In this package, total land required is 4 acres 17 ½ guntas. 5 guntas of government land has to be transferred. The details of the PAFs losing land is given in Notification issued under section 15 of the KHA 1964 in connection with land acquisition. There are 10 PAFs who are losing 5 guntas and more of agricultural land as per preliminary notification. Land Acquisition Status 1. The Notifications under section 15 under the KHA for WAP 4 (links 10 A and 10 B) has been published in September 2010 vide GO No: PWD 107 EAP 2010, dated for 10A; and vide GO No: PWD 137 EAP 2011, dated for 10B. The last date for filing of claims along with relevant documents for 10 A was and for 10B it was Guidance Value 12. The Guidance Value of land for different categories of land, for the villages along the project road is given in Annexure 1. This guidance value will be referred to by the Negotiation Committee. 13. The rates will be revised annually by 10% on the 1st of April every year, in case Government has not revised it. The guidance value varies from a minimum of Rs. 32,000 per acre in Kalladevanahalli village to Rs 1,00,000 per acre in Basavana Bagewadi village. Negotiation Committee 14. The Replacement Cost of land for consent award will be determined by the Negotiation Committee. In this package the Negotiation Committee has been constituted vide GO No. PWD 215 EAP 2007 dated This Committee consists the following members: 1. Assistant Commissioner of the concerned Sub Division : Chairman 2. Assistant Commissioner of KSHIP : Member Secretary 3. Executive Engineer KSHIP Division, : Member 4. Zilla Panchayat Member of the concerned jurisdiction : Member. 15. For Link 10 A Assistant Commissioner Bijapur will be the Chairman. The Assistant Commissioner of KSHIP, Belgaum will be Member Secretary; Executive Engineer Belgaum Division will be Member. Zilla Panchyat members will be nominated by 30 th June,

13 For Link 10B Assistant Commissioner, Yadgir will be Chairman. AC (LAQ) KSHIP will be Member Secretary and Executive Engineer, Belgaum will be Member. Zilla Panchyat members will be nominated by 30 th June Method of Price Negotiation 1. The concerned Land Acquisition officer who is the member secretary of the Negotiation Committee will call for a meeting; 2. Dates for price negotiation will be given village wise. Negotiation will be conducted village wise calling all the land losers together for negotiation. This is to ensure transparency. 3. The PIU will provide information on the guidance value of the land to land losers before negotiations. 4. The minimum negotiated price will be twice the current guidance value for Raichur and Gulbarga district. 5. The Negotiation Committee will negotiate the price with the landlord; 6. Based on the decision of the Negotiation Committee the Special Land Acquisition Officer will initiate action to collect documents after obtaining the approval of competent authority in the PIU. 7. Compensation will be given within 30 days of receiving all the necessary documents by the Special LA officer. In case of delay, 9% interest will be given to the beneficiary upto a period of one year and after which, it will be increased to15%. (This is as per the provisions of the LA Act). 8. On approval of the award by the Special DC or PD, the Special Land Acquisition Officer will make the payments accordingly. 9. Possession of Land will be taken vide Section 19, which will be only after the payment of compensation. Records to be submitted by the Land Owners 16. As soon as Notification u/s 19 is issued, the NGO shall collect the following documents in respect of lands to be acquired, before inviting for negotiations: 1. Original copy of RTC for current year; 2. Original or attested copy of mutation in respect of land and Khatha Certificate in respect of site / building; 3. Encumbrance Certificate for 13 years; 4. No Tenancy Certificate and Certificate regarding 79A, 79B and 66; 5. Bank Account details; 6. Land holding / small / marginal farmers Certificate whenever necessary; and 7. G. Tree. After offering of compensation, the NGO shall collect the remaining documents such as 1. Attested copy of Sale Deed/Partition Deed/Saguvali Chit/Regrant Order etc., to prove title of land; 2. Indemnity Bond; 3. Agreement and Affidavit and submit them to the Assistant Commissioner for processing for compensation. Any fees incurred by the NGO in obtaining the documents shall be reimbursed by the Executive Engineer of the Division. 7

14 Failure of KHA and Appellate Committee 17. Even after the minimum negotiation price as per the RAP is offered and the land owner does not agree for it, then the negotiation will be treated as failed and award will be passed as per the general LA Act. The price offered and the price demanded by the land owner in such cases will be recorded in the proceedings. The provisions of the LA amendment bill will be followed when they come into force.. Valuation of Assets on land under LA 18. The valuation of structures and other assets will be carried out by Government approved valuators appointed by the Executive Engineer in consultation with PIU. Valuation will be done on the basis of current PWD Schedule of Rates, without depreciation only for those who agree for consent award. Based on the valuation another 30% will be given as top up. Crops / Trees will be valued by the Agriculture / Horticulture / Forest department. Valuation of Crops 19. Crop loss will be compensated based on the valuation done by the Agriculture/Horticulture Department. Valuation of other structures/assets 20. The valuation of structures and other assets will be carried out as mentioned above. However, this will be verified and approved by the concerned Executive Engineer. Site Requirement for and impacts 21. Actual requirement of sites in each package, has been indicated in the Joint Verification report of NGO. In this package 38 sites are required for non titleholders. Verification for titleholders is under progress. As for as possible, Government land will be identified for formation of sites and allotted to the eligible PAFs/PAPs. Where Government land is not available then the PIU, KSHIP shall examine alternatives such as - cash in lieu of sites or purchase of private land - on case to case basis, based on local factors. Loss of Community Assets 22. In the contract package WAP 4, 106 community Assets getting affected. 8

15 Sl. No. Type of Community Asset Table 2-1: Summary Table on Community Assets 1. Temple/Shrines Aralikatte Bus Shelters Hand s MWS/Water supply tanks 4 6. Borewells Others 20 Total All community assets on Government land will be shifted by PIU. All assets on private land will be shifted with assistance of NGO. There are two community assets belonging to private trust and another two CPRs on private land. In case these assets are affected, compensation has to be paid according to the entitlement matrix. 24. For Temple/shrine, Aralikatte, new site has to be identified by NGO in coordination with SDO/SWI at the Divisional level. This site should be a Grama thana land or land given as donation. For land that is donated the concerned Engineer has to take a site consent letter from the donor of the site in prescribed format which will be prepared by NGO. The format will have Donor name and address, Site details(survey nos, place, boundary) with measurement,; the signatures of at least 3 persons from the village is necessary on the letter for evidence. The donor has to also sign on the consent letter. The letter will be submitted to the Executive Engineer of the division. The EE will then have to construct the new community structure/temple/shrine/ Aralikatte etc. After the construction of the new structure the SDO/SWI and NGO will jointly convince the concerned village people to demolish the existing structure, and shift the activities to the new place. 25. Bus shelters, Hand pump, MWS tanks, Bore wells and other community assets will be relocated and reconstructed. The KSHIP divisional staff will be taking necessary action with assistance of SDO/SWI. The chainage wise community assets details are given in Annexure 4. No 9

16 III. BASELINE CENSUS SURVEYS AND CONSULTATIONS Characteristics of displaced households 26. This chapter outlines the characteristics of displaced households. As a part of the project, a census survey of Project Affected Families / Persons (PAFs and PAPs) was carried out in the month of October The findings of the census survey provided the magnitude of social impacts on the PAFs and PAPs. In this chapter, baseline socio-economic analysis has been done separately for the major impacted families. 27. Among religious groups, Hindus dominate with percent followed by Muslims at percent. Distribution of PAPs by occupation indicates that percent are in agriculture; agricultural labourers account for percent; commerce and trade supports percent. In this package percent of population has income less than Rs.26, percent of the population falls within the age group of 18-60, which happens to be the working age group. In this package illiterate population accounts for 33.76; those with secondary education account for percent and professionals account for 0.35 percent. Average land holding size is acres. A look at the ownership of household assets indicate percent own televisions; 9.16 percent own 2/4 wheelers while only 6.22 percent own refrigerators. Some of the baseline parameters identified for those with major impacts are given in the table below. The details of the PAPs losing structures are given in Annexure 2&3. Table 3-1: Baseline Socio Economic information - for Major impacts 1. Losing total house Average area sq.m 3. % of houses electrified % of houses having water supply Nil 5. Average earning Rs. 28, % of earners 30.17% 7. % of PAPs earning less than Rs.26,000* 13.56% 8. Average land holding (out of 36 PAFs) Acres 9. % of Farmers having less than 2.20 acres of holding (out 11% of 36 PAFs) 10. % of PAPs in agriculture 1.69% 11. % of PAPs working as agriculture labour 6.10% 12. % of PAPs in the service sector 0.17% 13. % of PAPs in Commerce and Trade 24.24% 14. Loss of commercial structures Type of commercial structure 1 Pucca 0.00% 2. Semi pucca 9.09% 3. Kutcha 90.91% 16. Average area of commercial structure 7.27 sqm 17. Type of shops affected (majority) 1. Pan/cigarette 25.14% 2. Tea shop/hotel % 10

17 3. Barber % 18. Average monthly turnover of shops 1. Rs.13, Ownership of Household assets 1. Television % 2. Telephone 18.58% 4. 2/4 wheeler % Note : * Rs.26,000 has been taken as the cut off for BPL Major and Minor Impacts 28. The list of major and minor impacts for this package is given below. Sl. No. Table 3-2: Distribution of PAFs by Major and Minor Impacts for WAP 4 (10 A&B) Extent of Loss Owner Tenant Major Impact 1 Losing Total House Losing Total Com. Struc Losing Total House and Com. Struc Tenants Losing Total Livelihood Marginal Farmers Total Major Impact Minor Impact 1 Losing only Part of House Losing Part of Com. Struc Losing Part of House and Com. Struc Partial Plot Total Boundary Wall Partial Boundary Wall Cattle shed Non Marginal Farmers Others (Toilet, Steps etc.) Total Minor Impact Total Major & Minor Impacts

18 Figure 1-1: Distribution of PAFs for WAP4 Figure 1-2: Distribution of PAFs by Major Impact for Package WAP4 12

19 Vulnerable groups 29. Based on the Census survey there are 103 PAPs who come within the purview of vulnerable group. The categories include 34 widows; 61 persons above the age of 60 and 8 persons with disabilities. However this is only an enlistment of all persons coming under the vulnerable category. Only after verification by the NGO it will be confirmed whether these people are vulnerable. If so it will be verified further whether are getting pension/ or other assistance from the government. If the person is already receiving pension / assistance, then this offer will not be extended. Only after such verification will the person be entitled to assistance under this category. Consultations 30. Two consultations were carried out in this package. The outcome of the consultation are summarized below Date: ; Place: : No. of Participants: 25, covering 6 villages. Table 3-3: Consultation Summary Section Details Issued Raised Response of project Authority 1 10A Alternative site for relocation of BPL squatters will be provided as per policy People wanted to widen the road equally from the centerline. They wanted know what compensation will be paid to title holder and non title holders Those losing house wanted to know what alternative would be provided by the project. Most of the people asked for alternative house/site. The people asked for safety measures in hospital and school zones. Asked for relocation of community assets and public utilities. s asked for alternative livelihood option and for commercial sites. The people wanted equal widening of road. This would be done if it is technically feasible. Assistance for squatters will be according to the Project Policy. II 13B Date: ; Place: Hunasagi ; No. of Participants: 85, covering 10 villages. The people asked for equal widening of the road from the existing centerline. This will save a number of structures from getting affected by road widening. Those losing houses wanted to know what alternatives would be provided by the project. There are some important community assets, such as the near Temple and aralikatte are getting affected. The people asked for the relocation of the same. The people wanted to know about the The people wanted equal widening of road. This would be done if it is technically feasible. Community assets being affected by the project will be replaced by the project, on gram thana land provided by the panchayat. The project will pay compensation for agricultural land according to KHA. Structure compensation will be according to the current PWD SR. Assistance for squatters will be according to the Project Policy. compensation to be given by the project. 13

20 Institutional Arrangements IV. IMPLEMENTATION MECHANISMS 31. This chapter outlines the implementation mechanism specifically for this package, including the tasks of the NGO and the GRC. It also outlines the assistance to be paid to affected persons and provides the tasks to be completed before the start of civil works. 32. The SDRC, PIU will facilitate land acquisition and compensation, relocation and resettlement, distribution of assistance to the PAPs. The SDRC is responsible for monitoring the implementation of all resettlement and rehabilitation activities, including land acquisition. WAP 4 will be implemented by KHSIP Division, Belgaum. The SDO and SWIs appointed for the Belgaum division will take care of R&R activities of this package. The SDRC will be supported by the NGO for implementation of RAP. Extending R& R Assistance to PAPs 33. R&R assistance will be disbursed according to the R&R Policy. The NGO will verify the PAPs and ensure that they get the assistance in accordance with their entitlements. The entitlements given here are accurate as far as possible; however, because only preliminary notification for land losers has been issued at this stage, the exact details about entitlements need to be updated at the time of paying R&R assistance. The cash allowances are updated for and will be further adjusted as needed for and beyond. The exact number of disbursements made for each year will be computed after all assistance is given. The annually revised amounts are mentioned in the Implementation Manual. Table 4-1: R& R Assistance Entitlement Category of loss Entitlement Category 1a 36 PAF losing land Negotiation as per Karnataka State Highway Act, 1964; Amount equivalent to current stamp duty and registration charges on compensation amount; **Additional 25% compensation in case remaining land is severed; Crop/tree damage compensation as assessed by concerned Departments; *In case land owners becomes landless or marginal families, the following additional entitlements will be offered: (a) subsistence allowance of Rs.36,300 for land less and marginal; and, (b) assistance for creating Income generation asset valued upto Rs. 90,750 for those becoming marginal farmers and landless only; Additional amount of Rs.24,200 1 will be restricted to those who loose narrow stretch of land as additional compensation in lieu of 1 Narrow stretch of land is defined as persons losing upto 5 guntas of land. ** This will be verified after Section

21 Entitlement Category Ib IIIa IIIb Category of loss 1owner losing total residential structure 27 s losing residential structure 146 losing commercial structures 3 losing residential cum commercial structure Entitlement all other benefits. Additional amount of Rs 24,200 to those who lose more than a narrow stretch and are not eligible for any other additional benefits. *For those becoming landless and all marginal farmers training assistance will be provided for income generating vocational training and skill upgradation options as per affected persons choice ; Employment opportunity for affected persons as per his skills and availability of suitable work in road construction work. Compensation at current PWD scheduled rates without depreciation and 30% solatium Alternative houses in resettlement colony or developed plot 2 and construction cost of Rs. 60,000 linked to construction progress. Shifting assistance of Rs. 12,100 Subsistence allowance of Rs. 36,300 House in resettlement colony or developed plot and construction cost of Rs. 60,000 linked to construction progress. Subsistence allowance of Rs.18,150; Shifting Allowance of Rs Alternative shop of 100 sq.ft or assistance for income generation asset valuated upto Rs. 36,300; Subsistence allowance of Rs.18150; Shifting Allowance of Rs House in resettlement colony or developed plot and construction cost of Rs. 60,000 linked to construction progress OR. Alternative shop of 100 sq.ft or assistance for income generation asset valuated upto Rs. 36,300 Subsistence allowance of Rs Shifting Allowance of Rs.6050 IIIc 38 encroachers Replacement cost of affected structure calculated at current PWD scheduled rates without depreciation Va 103 Vulnerable Assistance to include in government pension schemes if not included, if eligible as per Government criteria (OR) Lump-sum amount of Rs. 25,000 Implementation support by NGOs 34. The work of the NGO will include consultations and counseling of PAPs, encouraging PAPs for productive utilization of compensation and rehabilitation grants, facilitating PAP access to income generating assets, increasing the social acceptability, ensuring effectiveness of training programs organized for PAPs electing participation in self employment schemes etc. *These entitlements will be applicable only when the farmers submit the landholding/ marginal farmer document, and if found applicable. 2 Developed plot will be restricted to those who do not have any homestead land. 15

22 35. The NGO will work as a link between the PIU - SDR Cell and the affected community. For this section the NGO is: BIRDS (Bijapur Integrated Rural Development Society). The division office of this NGO is located in Dharwad. They will educate the PAPs on the need to implement the Project, on aspects relating to LA and R&R measures and ensure proper utilization of various compensations extended to the PAPs under the R&R entitlement package. The tasks of the NGO will be to facilitate the resettlement process. The responsibilities of the NGOs include 1. Identification, verification and updating of PAP Census, includes verification of properties of PAPs and estimation of their type and level of losses; 2. Educate PAPs on their rights, entitlements, and obligations under the RAP; Assist the PAPs to identify suitable alternate land for resettlement purposes; 3. Preparation and Distribution of Entitlement cum Identity Card. All eligible project affected families will be issued Identity Cards, giving details of the type of losses and type of entitlements. 4. Ensure that PAPs receive their full entitlements; Where options are available, the NGO will provide advice to PAPs on benefits of each option; Ensure proper utilization by the PAPs of various compensations available under the R&R package; Assist the PAPs in getting benefits from various government development programs; 5. Rehabilitation of Affected Families and restoration of Income and Livelihood. The NGO will help the communities derive maximum benefits out of the project without losing their livelihoods and the least impact on socio-cultural aspects of their lives. 6. Assist PAPs on grievance redressal through the established system; and 7. Will relocate PAPs. Assist PIU in making arrangements for the smooth relocation of the PAPs; No Physical relocation from agriculture land, residential units, commercial establishments or other immovable properties will begin before alternate arrangements are made. 8. Any other responsibility that may be assigned by the PIU for the welfare of the affected communities. 36. In order to carry out the above tasks, NGO staff will be stationed in the site office at Basavana Bagewadi. Besides contacting the PAPs on an individual basis to regularly update the baseline information, group meetings and village-level meetings will be conducted by the support agency on a regular basis. The frequencies of such meetings will depend on the requirements of the PAPs but should occur at least once a month. The support agency will have to encourage participation of individual APs in such meeting by discussing their problems regarding LA, R&R and other aspects relating to their socio-economic lives. Such participation will make it easier to find a solution acceptable to all involved. IR Activities 37. There are two types of IR activities, i.e. short term and long term. Income generating activities will have to be identified for 146 commercial squatters and 3squatter losing residential cum commercial 16

23 structure. Process of identifying income generating options for commercial squatters is under progress. 38. Short Term IR activities: Short-term IR activities mean restoring APs income during periods immediately before and after relocation. For this, the NGO shall ensure that: compensation and R&R assistance as provided in the entitlement matrix such as subsistence allowance and shifting allowance are provided to the PAPs. Other works of the NGO include facilitating employment to the PAPs in the project construction activities, depending on their skill and other allied activities. 39. Long Term IR Activities: This includes provision of shops for those losing their total livelihood to re-establish their commercial activities. It also includes providing of a shop plot in a commercial block or purchase of income generating assets upto Rs.36,300 in case of commercial squatters. 40. The steps to be followed for income restoration include: Step 1: Identification of Target Groups NGOs need to identify the affected persons; Step 2: Identification of IR Activities - Prepare a list of possible and feasible income restoration options. While identifying IR options, the following factors shall also be considered: (i) Education level of APs; (ii) Skill possession;(iii)likely economic activities in the post displacement period; (iii) Extent of land left; (iii) Suitability of economic activity to supplement the income; (iv)market potential and marketing facilities. Based on socio-economic characteristics and options preferred by APs, the NGO may have to re-assign trades to PAPs. Options include (i) petty trade (iii) skill related schemes and loans for pumps, bore wells, bullock carts etc to increase productivity. The NGO will assist PAPs in identifying appropriate alternative economic rehabilitation schemes through counseling and consultation. Step 3: Training: Option for training for skill enhancement for those losing their livelihood has been provided in the Entitlement Matrix for owners losing commercial structure and employees losing their livelihood. Step 4: Identification of Trainers / Training Institutes: Based on trades selected, NGO shall have to identify master trainer and/or training institute for different trades / activities who can provide on the job training. Step 5: Training Arrangement: NGO shall make different groups of PAPs as per trades selected and make all the arrangements such as fixing the venue etc. Step 6: Monitoring of APs: After training the NGO shall monitor the PAPs in order to take mid-term correction measures, if required. Monitoring and Evaluation support for RAP 41. An external monitoring and evaluation agency, Samaj Vikas, has been appointed to concurrently monitor and evaluate R&R activities on periodical basis with NGOs. The role of such an agency will facilitate process of R&R and thus provide support in the proper implementation of rehabilitation programmes. And the M&E Consultant will ensure and certify that the stretch is free from all encumbrances related R&R measures, at every stage prior to issue of bids, prior to signing concession agreement, prior to appointed date and prior to hand over of the second milestone stretches to the developer. The end evaluation will be carried out through independent consultants not associated with the implementation to verify as to how the R&R activities are realized and the 17

24 changes in the living conditions of the PAPs which will be compared with the baseline data on key impact indicators related to income, occupation, assets, housing conditions, landownership pattern, etc. Grievance Redressal mechanism 42. The project will establish a Grievance Redressal process with district-level committees. The following persons constitute the District Level Grievance Redressal Cell : 1. Deputy Commissioner of the District Chairman 2. Academician (to be selected by the DC) Member 3. Representative from PAPs (to be selected by the DC) Member 4. Divisional EE Convener The members of the GRC to be selected by the DC and representatives from the PAPs are under progress and will be completed by 30 th June, The main functions of the GRC will be: a. to provide support to PAPs on problems arising out of eligibility for RAP-provided entitlements and assistance provided; b. to record the grievances of the PAPs, and categorize, prioritize and solve them within one month; c. to inform PIU of serious cases within one week; and d. to report to the aggrieved parties about the developments regarding their grievance and decisions of the PIU, within one month. 44. The Grievance Committees will meet regularly during implementation of the RAP, at least once a month. The committees will suggest corrective measures at the field level itself and fix responsibilities for implementation of its decisions. However the NGOs will form the first level of intervention in resolving PAP related grievances and attempt to motivate the PAP to facilitate implementation of the R&R program. Details regarding registering complaints, response times, communication modes, and mechanisms for appeal or approaching civil courts if other provisions fail are: 1. At the first level intervention the NGO will attempt to resolve the grievance; 2. Next the CAO will attempt to address land related grievance and the ADSW will address the nonland related grievances; 3. The third step will be to approach the Grievance Redressal Committee; 4. Next the PAP can approach the Regional Commissioner who is the Appellate Authority. 5. If all the above fails, the PAPs can approach the court. It is the responsibility of the SDRC/NGO to inform the affected person s decisions of the GRC to make it effective. 18

25 Resettlement Colonies and Vendor Markets 45. In this package there is no requirement for resettlement colony, as more than 20 families are not losing their residential structure in this stretch. Protection of RoW 46. Section 5 of the KHA mentions the Highway Authority will exercise power and discharge duties in accordance with provisions of the KHA for restriction of ribbon development along the highways and for prevention and removal of encroachments. The Highway Authority under Section 7 has power to fix boundary of building and control lines of highways. Section 21 mentions prevention of unauthorized occupation of highway. Thus the onus of protecting the COI/RoW lies with the Project Authority. Once the COI/Row has been identified and frozen, the COI/RoW has to be clearly marked with boundary stones. 47. Any new encroachment into the area will be monitored by the concerned KSHIP Division; The Divisional Engineers shall visit the project roads periodically, at least once in three months, in order to ensure that no new encroachments take place and submit quarterly reports in this regard. Any additional encroachments noticed through periodical visits will be issued notices immediately and their shifting will be done immediately to avoid implications R&R assistance to those additional movers. To avoid future encroachments, it is proposed to construct drains at the edge of ROW and ROW stones will also be laid. 48. The NGOs shall take photographs of the affected structures at the time of joint verification and also after their shifting / demolition of the affected portion and prepare documentation of structures. 49. Those Non-titleholders already identified by the project will be issued Identity Cards by the PIU. All new encroachers / squatters not present during the time of survey, will have to be verified by the NGO/PIU. All squatter and encroachers have to be shifted from out of the COI and RoW. Those who remain in the Row will not be eligible to entitlements Impacts on Municipal Towns 50. Verification for non- titleholders has already been completed on this package. All the persons identified at the time of survey and verified by the NGOs at the time of Joint Verification but subsequently shifted by the Municipalities will be extended assistance as per the RAP. 51. KSHIP shall address all the Municipalities in the Project Roads informing them of the Rehabilitation and Resettlement Policy of the Government under KSHIP-II and the details of persons identified as Project Affected Persons in their jurisdiction. If the Municipality wants to shift any of them for their development works, they may do so after providing them assistance as per the R&R Policy of the Government or inform the details of such persons to KSHIP for extending assistance under the project. 19

26 52. In this package the project road passes through the Municipality areas of Basavana Bagewadi. The Municipality will be addressed informing them of the Rehabilitation and Resettlement policy of Government under KSHIP-II project and the details of the persons identified as Project Affected Persons in their respective jurisdiction. In case the Municipalities / Corporation desire to shift any of the Project Affected Person on account of development work, they may do so after providing assistance to them as per the R&R Policy of Government or inform the details of such displaced persons to KSHIP for extending assistance to them under the project Data Base Management 53. The database generated will be used for tracking progress of this package by PIU. The data in the HQ will be updated based on the information sent by the division office. PIU will be responsible for tracking payments, generation of ID cards etc through the Data Base Management Consultants. The socio-economic data for all PAPs are recorded in the data base and will be used for monitoring and impact evolution and other purposes. Compensation and R&R assistance payment: 54. All the compensation and R&R assistance will be directly credited to the individual Bank A/cs. The deduction of income tax is not applicable for receipt of compensation. The NGOs will assist in opening of the Bank A/cs and the details of payments will be recorded in the individual Identification Cards and Pass Books. In case where the house/shop plots are allotted, the titles to those will be provided in the joint name of wife and husband. Co ordination between R&R and Civil works 55. The resettlement program will be co-coordinated with the timing of civil works. The Civil works for this package is expected to start in June R&R and land acquisition is estimated to be completed by August Under the Annuity Packages all land has to be handed over at one stage. This will be after issue of Notification under Section 19 of KHA. The timeline for key activities is given below. 56. The implementation of RIP will be performed in coordination with the procurement process and civil works. The key milestone in the process includes: issue of bids, signing of concession agreement, appointed date and handing over of second milestone stretches within three months of appointed date. The various land acquisition and resettlement implementation actions to be completed prior to those milestones which are listed below with respective target dates. The completion of these actions will be certified through certification and confirmation by the M&E Consultant. I Table 4-2: Time line for Key LA and R & R Activities Tasks Target Date Prior to Event Land Acquisition Land Acquisition Plans Section 15 Notification (first Issue of bids notification) 20

GOVERNMENT OF KARNATAKA PUBLIC WORKS DEPARTMENT Karnataka State Highways Improvement Project - II

GOVERNMENT OF KARNATAKA PUBLIC WORKS DEPARTMENT Karnataka State Highways Improvement Project - II Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized GOVERNMENT OF KARNATAKA PUBLIC WORKS DEPARTMENT Karnataka State Highways Improvement

More information

ENTITLEMENT MATRIX. Gujarat State Highway Project - II. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

ENTITLEMENT MATRIX. Gujarat State Highway Project - II. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ROADS AND BUILDINGS DEPARTMENT GOVERNMENT OF GUJARAT Gujarat State Highway Project -

More information

SUMMARY LAND ACQUISITION PLAN. Supplementary Appendix to the. Report and Recommendation of the President to the Board of Directors.

SUMMARY LAND ACQUISITION PLAN. Supplementary Appendix to the. Report and Recommendation of the President to the Board of Directors. SUMMARY LAND ACQUISITION PLAN Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the RURAL ROADS SECTOR I PROJECT in INDIA Ministry of Rural Development

More information

NATIONAL GANGA RIVER BASIN AUTHORITY

NATIONAL GANGA RIVER BASIN AUTHORITY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL GANGA RIVER BASIN AUTHORITY (Ministry of Environment and Forests, Government

More information

Andhra Pradesh Rural Roads Connectivity Project The Asian Infrastructure Investment Bank assisted

Andhra Pradesh Rural Roads Connectivity Project The Asian Infrastructure Investment Bank assisted GOVERNMENT OF ANDHRA PRADESH PANCHAYAT RAJ ENGINEERING DEPARTEMNT The (RPF) July 2018 Samaj Vikas Development Support Organisation Table of Contents List of Acronyms... 3 Glossary of Resettlement & Rehabilitation

More information

SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS

SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS MINISTRY OF EDUCATION GOVERNMENT OF NEPAL August 2011 2 A. Introduction 1.

More information

Involuntary Resettlement Assessment and Measures. IND: Karnataka State Highway Improvement Project

Involuntary Resettlement Assessment and Measures. IND: Karnataka State Highway Improvement Project Involuntary Resettlement Assessment and Measures Resettlement Plan for AEP 3: 57 A, B and C (Gubbi Pura Beeragonahalli (NH-48) Kowdley Mandya) Document Stage: Draft for Consultation Project Number: 42513

More information

Summary of Land Acquisition, Resettlement and Rehabilitation Policy for Infrastructure Development Project 2015

Summary of Land Acquisition, Resettlement and Rehabilitation Policy for Infrastructure Development Project 2015 Summary of Land Acquisition, Resettlement and Rehabilitation Policy for Infrastructure Development Project 2015 Vision Contribute to overall development of the nation and its citizens by creating conducive

More information

RP607. Summary of Land Acquisition & Resettlement Policy Framework JAMAICA: JM Hurricane Dean ERL Project. A. Introduction. B. Means of Obtaining Land

RP607. Summary of Land Acquisition & Resettlement Policy Framework JAMAICA: JM Hurricane Dean ERL Project. A. Introduction. B. Means of Obtaining Land Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Summary of Land Acquisition Policy Framework JAMAICA: JM Hurricane Dean ERL Project RP607

More information

RP55 RESETTLEMENT ACTION PLAN (RAP) BYPASSES OF RAICHUR AND BIJAPUR TOWNS TABLE OF CONTENTS

RP55 RESETTLEMENT ACTION PLAN (RAP) BYPASSES OF RAICHUR AND BIJAPUR TOWNS TABLE OF CONTENTS Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Kamataka State Highways RP55 Volume 5 TABLE OF CONTENTS RESETTLEMENT ACTION PLAN (RAP)

More information

LAND ACQUISITION FRAMEWORK

LAND ACQUISITION FRAMEWORK LAND ACQUISITION FRAMEWORK (This framework was prepared in accordance to the ADB requirements for preparing Resettlement Framework as described in the ADB Safeguards Policy Statement, 2009) Project Number:

More information

RESETTLEMENT POLICY FRAMEWORK AND PROCEDURAL GUIDELINES GAUNGXI ROADS DEVELOPMENT II PROJECT

RESETTLEMENT POLICY FRAMEWORK AND PROCEDURAL GUIDELINES GAUNGXI ROADS DEVELOPMENT II PROJECT Village Roads Component on the GAUNGXI ROADS DEVELOPMENT II PROJECT in THE PEOPLE S REPUBLIC OF CHINA (PRC) Guangxi Comnications Department Nanning, PRC This report was prepared by the Borrower and is

More information

The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013

The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 CAME INTO FORCE ON 1.1.2014 (VIDE GOI GAZETTE NOTIFICATION DT. 19.12.2013) DR. R. K. SRIVASTAVA

More information

Republic of Turkey Additional Financing to Second Renewable Energy and Energy Efficiency Project Resettlement Policy Framework For TSKB and TKB

Republic of Turkey Additional Financing to Second Renewable Energy and Energy Efficiency Project Resettlement Policy Framework For TSKB and TKB Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Republic of Turkey Additional Financing to Second Renewable Energy and Energy Efficiency

More information

RP1 85 November The Resettlement Policy Framework (RPF) Report on the GEF Hai Basin Project. (Final Version)

RP1 85 November The Resettlement Policy Framework (RPF) Report on the GEF Hai Basin Project. (Final Version) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PIP annex 9 - C of GEF Hai Basin Integrated Water and Environment Management Project

More information

Practice Followed by APIIC in Land Acquisition & Industrial Area Management

Practice Followed by APIIC in Land Acquisition & Industrial Area Management Practice Followed by APIIC in Land Acquisition & Industrial Area Management Acquisition, Allotment and Disposal of Land for Industrial Purpose Gives highest priority to creation of quality infrastructure

More information

I U B Reddy The World Bank New Delhi, India

I U B Reddy The World Bank New Delhi, India IAIA15 India s New Land Acquisition Act Right To Fair Compensation and Transparency in Land Acquisition and Rehabilitation and Resettlement Act, 2013 I U B Reddy The World Bank New Delhi, India Challenging

More information

KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT RESETTLEMENT AND REHABILITATION POLICY DRAFT PRINCIPLES AND POLICY FRAME WORK NOVEMBER 2009

KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT RESETTLEMENT AND REHABILITATION POLICY DRAFT PRINCIPLES AND POLICY FRAME WORK NOVEMBER 2009 KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT RESETTLEMENT AND REHABILITATION POLICY DRAFT PRINCIPLES AND POLICY FRAME WORK NOVEMBER 2009 PROJECT DIRECTOR PROJECT IMPLEMENTATION UNIT KARNATAKA STATE HIGHWAYS

More information

PROJECT REPORT PROCESS & PROCEDURE OF LAND ACQUISITION UNDER RFCTLARR ACT, Submitted By Babita Mishra Addl. Tahasildar, 16 TH Batch

PROJECT REPORT PROCESS & PROCEDURE OF LAND ACQUISITION UNDER RFCTLARR ACT, Submitted By Babita Mishra Addl. Tahasildar, 16 TH Batch PROJECT REPORT PROCESS & PROCEDURE OF LAND ACQUISITION UNDER RFCTLARR ACT, 2013 Submitted By Babita Mishra Addl. Tahasildar, 16 TH Batch The Right to Fair Compensation and Transparency in Acquisition Rehabilitation

More information

FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATIONS OR WILLING BUYER/WILLING SELLER PROCESSES

FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATIONS OR WILLING BUYER/WILLING SELLER PROCESSES Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SCHOOL SECTOR REFORM PROGRAM (SSRP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY

More information

Resettlement Policy framework for the Albania s Improvement of the Management and Conditions of the Secondary and Local Roads Project

Resettlement Policy framework for the Albania s Improvement of the Management and Conditions of the Secondary and Local Roads Project Resettlement Policy framework for the Albania s Improvement of the Management and Conditions of the Secondary and Local Roads Project I. Introduction The overall length of the road network in Albania totals

More information

SOCIAL ASSESSMENT OF BANGALORE METRO RAIL PROJECT LINE R6

SOCIAL ASSESSMENT OF BANGALORE METRO RAIL PROJECT LINE R6 SOCIAL ASSESSMENT OF BANGALORE METRO RAIL PROJECT LINE R6 1. Socio Economic Profile of the Project Area 1.1 General Profile Bangalore officially known as Bengaluru, is the capital of the Indian state of

More information

Dhaka Water Supply and Sanitation Project

Dhaka Water Supply and Sanitation Project Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VOL. 1 Dhaka Water Supply and Sanitation Project Resettlement Policy Framework Dhaka

More information

REHABILITATION AND RESETTLEMENT PLAN

REHABILITATION AND RESETTLEMENT PLAN REHABILITATION AND RESETTLEMENT PLAN INTRODUCTION This chapter contains the resettlement plan for the potential social impact anticipated due to the proposed project. In this regard, a compatible Rehabilitation

More information

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF PROJECT AFFECTED PERSONS. November 2000

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF PROJECT AFFECTED PERSONS. November 2000 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized LAO PDR: AGRICULTURAL DEVELOPMENT PROGRAM RP-59 POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT

More information

Resettlement Policy Revised Vol. 3 METRO MANILA URBAN TRANSPORT INTEGRATED PROJECT POLICY FRAMEWORK FOR

Resettlement Policy Revised Vol. 3 METRO MANILA URBAN TRANSPORT INTEGRATED PROJECT POLICY FRAMEWORK FOR Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RP47 Resettlement Policy Revised Vol. 3 METRO MANILA URBAN TRANSPORT INTEGRATED PROJECT

More information

The Bill is called the Land Acquisition, Rehabilitation and Resettlement Act, 2011

The Bill is called the Land Acquisition, Rehabilitation and Resettlement Act, 2011 The Land Acquisition, Rehabilitation and Resettlement Bill, 2011 was introduced in Lok Sabha on September 7, 2011. On December 17, 2012, during the winter session of Parliament, the government circulated

More information

Dhaka Water Supply and Sanitation Project Resettlement Policy Framework

Dhaka Water Supply and Sanitation Project Resettlement Policy Framework 1. BACKGROUND Dhaka Water Supply and Sanitation Project Resettlement Policy Framework The Dhaka Water and Sewerage Authority (DWASA) currently supplies water to about 70% of the population of the Dhaka

More information

Presentation on RFCTLARR Act, March 22, 2018

Presentation on RFCTLARR Act, March 22, 2018 Presentation on RFCTLARR Act, 2013 March 22, 2018 Hukum Singh Meena IAS, Joint Secretary Department of Land Resources Ministry of Rural Development Government of India The Right to Fair Compensation and

More information

Minerals and Mining (Compensation And Resettlement) Regulations, 2012 (L.I. 2175)

Minerals and Mining (Compensation And Resettlement) Regulations, 2012 (L.I. 2175) Minerals and Mining (Compensation And Resettlement) Regulations, 2012 (L.I. 2175) ARRANGEMENT OF REGULATIONS Regulations 1. Claims for compensation 2. Assessment of compensation 3. Compensation principles

More information

Government of Andhra Pradesh Rural Water Supply and Sanitation Department

Government of Andhra Pradesh Rural Water Supply and Sanitation Department Government of Andhra Pradesh Rural Water Supply and Sanitation Department Andhra Pradesh Rural Water Supply and Sanitation Project Under The World Bank Assistance Social Assessment, Tribal Development

More information

Legislative Brief The Land Acquisition, Rehabilitation and Resettlement Bill, 2011

Legislative Brief The Land Acquisition, Rehabilitation and Resettlement Bill, 2011 Legislative Brief The Land Acquisition, Rehabilitation and Resettlement Bill, 2011 The Land Acquisition, Rehabilitation and Resettlement Bill, 2011 was introduced in the Lok Sabha by the Minister for Rural

More information

DRAFT EXECUTIVE SUMMARY

DRAFT EXECUTIVE SUMMARY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DRAFT EXECUTIVE SUMMARY IPUH - BANTAL (LINK 015.1) KABUPATEN MUKO-MUKO YEAR 2010 EXECUTIVE

More information

Socialist Republic of Vietnam POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF DISPLACED PERSONS

Socialist Republic of Vietnam POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF DISPLACED PERSONS Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Socialist Republic of Vietnam POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION

More information

B. Justification of project design and alternative analysis:

B. Justification of project design and alternative analysis: Social Screening and Impact Assessment for Sub Projects Code No: 3 A. Sub Project Description: Proposed Activity Town Hall Square Development Implementing Agency: Colombo Municipal Council (CMC) Sub project

More information

Social Screening and Impact Assessment for Sub Projects. B. Justification of project design and alternative analysis:

Social Screening and Impact Assessment for Sub Projects. B. Justification of project design and alternative analysis: Code No: 1.9 Social Screening and Impact Assessment for Sub Projects A. Sub Project Description: Proposed Activity Walkability and Parking Improvements Lotus Road Implementing Agency: Colombo Municipal

More information

REPUBLIC OF MACEDONIA

REPUBLIC OF MACEDONIA Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized REPUBLIC OF MACEDONIA Municipal Services Improvement Project (MSIP) LAND ACQUISITION

More information

LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK (LARPF)

LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK (LARPF) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PT PLN (Persero) INDONESIA POWER SECOND TRANSMISSION DEVELOPMENT PROJECT (IPTD-2) RP1232

More information

LIVESTOCK WASTE MANAGEMENT IN EAST ASIA

LIVESTOCK WASTE MANAGEMENT IN EAST ASIA Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized LIVESTOCK WASTE MANAGEMENT IN EAST ASIA Project preparation under the PDF-B grant RP337

More information

Resettlement, Relief, Rehabilitation and Compensation Policy. May, Barowalias House, Khallini, Shimla ( HP)

Resettlement, Relief, Rehabilitation and Compensation Policy. May, Barowalias House, Khallini, Shimla ( HP) Resettlement, Relief, Rehabilitation and Compensation Policy May, 2011 Barowalias House, Khallini, Shimla-171 002 ( HP) 2 Index Part/Chapter No. Heading Page No. Introduction Introduction 4 Part-I Preamble,

More information

REPORT 2014/050 INTERNAL AUDIT DIVISION. Audit of United Nations Human Settlements Programme operations in Sri Lanka

REPORT 2014/050 INTERNAL AUDIT DIVISION. Audit of United Nations Human Settlements Programme operations in Sri Lanka INTERNAL AUDIT DIVISION REPORT 2014/050 Audit of United Nations Human Settlements Programme operations in Sri Lanka Overall results relating to the effective and efficient implementation of the UN-Habitat

More information

Expropriation. Recommended Policy Wordings (full): Lao National Land Policy. Context. Policy. Standard of Public Purpose

Expropriation. Recommended Policy Wordings (full): Lao National Land Policy. Context. Policy. Standard of Public Purpose Expropriation Context Following from the goal of the National Land Policy, to promote and ensure a secure land tenure system that is transparent, effective, non-discriminative, equitable and just ; it

More information

NO.632/ (29)2004

NO.632/ (29)2004 (English Translation) (Hindi Version is the Authorized Version) NO.632/1-13-11-20(29)2004 From To, K.K.Sinha, Principal Secretary, Govt. of Uttar Pradesh. 1. All Principal Secretaries/Secretaries, Govt.

More information

Government of Uttar Pradesh. Workshop for Housing for All Date - 09/08/2016. State Urban Development Agency

Government of Uttar Pradesh. Workshop for Housing for All Date - 09/08/2016. State Urban Development Agency Government of Uttar Pradesh Workshop for Housing for All Date - 09/08/2016 State Urban Development Agency Overview of Scheme Housing shortage estimated at 2 Cr, out of these 2 Cr, 30 Lakh shortage is in

More information

India: Madhya Pradesh Irrigation Efficiency Improvement Project. Subproject: Pipeline Distribution System for 500 Hectares of Command Area

India: Madhya Pradesh Irrigation Efficiency Improvement Project. Subproject: Pipeline Distribution System for 500 Hectares of Command Area Madhya Pradesh Irrigation Efficiency Improvement Project (RRP IND 45371) Resettlement Plan/Land Acquisition Plan (This document is prepared in accordance to the ADB Resettlement Plan Requirement as described

More information

JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK

JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK I. Introduction The Jamaica Social Investment Fund (JSIF) was established in 1996 under the Government of Jamaica s National

More information

VOLUNTARY LAND DONATION FRAMEWORK

VOLUNTARY LAND DONATION FRAMEWORK Community-Managed Irrigated Agriculture Sector Project Additional Financing (RRP NEP 33209) A. The Project and Context 1. Project Description VOLUNTARY LAND DONATION FRAMEWORK 1. The proposed Community

More information

RESETTLEMENT POLICY FRAMEWORK (RPF)

RESETTLEMENT POLICY FRAMEWORK (RPF) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized JANUARY 2013 Republic of Mozambique Mozambique Climate Resilience: Transforming Hydro-Meteorological

More information

LAND ACQUISITION FOR RAILWAY INFRASTRUCTURE PROJECTS

LAND ACQUISITION FOR RAILWAY INFRASTRUCTURE PROJECTS LAND ACQUISITION FOR RAILWAY INFRASTRUCTURE PROJECTS Manish Gandhi, Nishant Doshi Manuscript History Number: IJIRAE/RS/Vol.05/Issue02/FBAE10084 DOI: 10.26562/IJIRAE.2018.FBAE10084 Received: 13, February

More information

Due Diligence Report on Social Safeguards. IND: Rural Connectivity Investment Program Projects I and II

Due Diligence Report on Social Safeguards. IND: Rural Connectivity Investment Program Projects I and II Due Diligence Report on Social Safeguards December 2015 IND: Rural Connectivity Investment Program Projects I and II Rural Road Network Management Unit in Midnapur, West Bengal Prepared by Ministry of

More information

Kazakhstan: Proposed Moinak Electricity Transmission Project Land Acquisition Policy Framework

Kazakhstan: Proposed Moinak Electricity Transmission Project Land Acquisition Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Kazakhstan: Proposed Moinak Electricity Transmission Project Land Acquisition Policy

More information

GOVERNMENT OF BIHAR DEPARTMENT OF REVENUE AND LAND REFORMS NOTIFICATION. No-1401/र ०

GOVERNMENT OF BIHAR DEPARTMENT OF REVENUE AND LAND REFORMS NOTIFICATION. No-1401/र ० GOVERNMENT OF BIHAR DEPARTMENT OF REVENUE AND LAND REFORMS NOTIFICATION No-1401/र ० Dated-27/10/2014 Whereas certain draft rules, namely the Bihar Right to Fair Compensation and Transparency in Land Acquisition,

More information

ERRA S RURAL LANDLESS PROGRAMME (PHASE - II FOR VIRTUALLY LANDLESS PEOPLE)

ERRA S RURAL LANDLESS PROGRAMME (PHASE - II FOR VIRTUALLY LANDLESS PEOPLE) ERRA S RURAL LANDLESS PROGRAMME (PHASE - II FOR VIRTUALLY LANDLESS PEOPLE) Introduction Earthquake Reconstruction & Rehabilitation Authority s Policy for virtually landless people is an extension of the

More information

THE UNITED REPUBLIC OF TANZANIA PRESIDENT S OFFICE REGIONAL ADMINISTRATION AND LOCAL GOVERNMENT (PO-RALG) Tanzania Strategic Cities Project (TSCP)

THE UNITED REPUBLIC OF TANZANIA PRESIDENT S OFFICE REGIONAL ADMINISTRATION AND LOCAL GOVERNMENT (PO-RALG) Tanzania Strategic Cities Project (TSCP) THE UNITED REPUBLIC OF TANZANIA PRESIDENT S OFFICE REGIONAL ADMINISTRATION AND LOCAL GOVERNMENT (PO-RALG) Tanzania Strategic Cities Project (TSCP) Resettlement Action Plan Update Report for the ARUSHA

More information

Greater Beirut Water Supply Project Additional Finance Addendum to the Resettlement Action Plan

Greater Beirut Water Supply Project Additional Finance Addendum to the Resettlement Action Plan Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Greater Beirut Water Supply Project Additional Finance Addendum to the Resettlement Action

More information

Rehabilitation & Resettlement (R&R) Policy (June-2010)

Rehabilitation & Resettlement (R&R) Policy (June-2010) Rehabilitation & Resettlement (R&R) Policy (June-2010) NTPC Limited New Delhi INDIA CONTENTS Sl. No. DESCRIPTION PAGE No. 1. List of Abbreviations 1-2 2. Definitions 3-5 Part-I: Policy Guidelines for

More information

Resettlement Policy Framework

Resettlement Policy Framework Republic of Turkey Second Renewable Energy and Energy Efficiency Project Resettlement Policy Framework Background 1. The Second Renewable Energy and Energy Efficiency Project will fund private sector investments

More information

Residential Rehabilitation Program Frequently Asked Questions

Residential Rehabilitation Program Frequently Asked Questions Residential Rehabilitation Program Frequently Asked Questions Q. What is the Residential Rehabilitation Program? The Housing Rehabilitation Program is provides financial assistance to City of West Palm

More information

Resettlement Planning Document

Resettlement Planning Document Resettlement Planning Document June 2012 Pakistan: Sindh Cities Improvement Investment Program (SCIP) Prepared by North Sindh Urban Services Corporation Limited for the Asian Development Bank. PFR-2 Annex-11

More information

THE RIGHT TO FAIR COMPENSATION AND TRANSPARENCY IN LAND ACQUISITION, REHABILITATION AND RESETTLEMENT ACT, 2013 AN OVERVIEW

THE RIGHT TO FAIR COMPENSATION AND TRANSPARENCY IN LAND ACQUISITION, REHABILITATION AND RESETTLEMENT ACT, 2013 AN OVERVIEW THE RIGHT TO FAIR COMPENSATION AND TRANSPARENCY IN LAND ACQUISITION, REHABILITATION AND RESETTLEMENT ACT, 2013 AN OVERVIEW Ministry of Rural Development Government of India September 8 th, 2013 1 Agenda

More information

Decree on State Land Lease or Concession

Decree on State Land Lease or Concession Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity ~~~~~~~~~~~~~ Prime Minister s Office No. 135/PM VCC, Date 25/05/2009 Decree on State Land Lease or Concession - Pursuant

More information

GOVERNMENT OF JAMMU & KASHMIR Chief Minister s Monitoring Cell

GOVERNMENT OF JAMMU & KASHMIR Chief Minister s Monitoring Cell 1 GOVERNMENT OF JAMMU & KASHMIR Chief Minister s Monitoring Cell Physical verification report of the project namely WIDENING OF ROAD FROM QAMARWARI CHOWK TO PARIMPORA BYE-PASS JUNCTION AS FOUR LANE District

More information

RIGHT OF WAY LIFE CYCLE

RIGHT OF WAY LIFE CYCLE EXPEDITING THE RIGHT OF WAY PROCESS RIGHT OF WAY LIFE CYCLE Right of Way planning begins during the Feasibility Phase of a project. Determining the magnitude of the Right of Way Phase allows the LDOTD

More information

(DRAFT) LIVESTOCK WASTE MANAGEMENT IN EAST ASIA PROJECT POLICY FRAMEWORK FOR RESETTLEMENT OF PROJECT DISPLACED PERSON IN THAILAND

(DRAFT) LIVESTOCK WASTE MANAGEMENT IN EAST ASIA PROJECT POLICY FRAMEWORK FOR RESETTLEMENT OF PROJECT DISPLACED PERSON IN THAILAND (DRAFT) Public Disclosure Authorized RP337 v2 LIVESTOCK WASTE MANAGEMENT IN EAST ASIA PROJECT POLICY FRAMEWORK FOR RESETTLEMENT OF PROJECT DISPLACED PERSON IN THAILAND Public Disclosure Authorized Public

More information

Presented by: K.Vidyadhar AMD MEPMA

Presented by: K.Vidyadhar AMD MEPMA Status of RAY in Andhra Pradesh: Issues and Challenges Presented by: K.Vidyadhar AMD MEPMA SLUM PROFILE OF ANDHRA PRADESH No. of ULBs - 173 Total Urban Population (2001 census) - 208.08 Lakhs Urban Population

More information

Summary: Resettlement Action Plan for the Thwake Multi- Purpose Dam-Kenya

Summary: Resettlement Action Plan for the Thwake Multi- Purpose Dam-Kenya Summary: Resettlement Action Plan for the Thwake Multi- Purpose Dam-Kenya 1. Introduction and Background The proposed Thwake water supply and sanitation Dam is a project conceived and intended to be constructed

More information

Scheme of Service. for. Housing Officers

Scheme of Service. for. Housing Officers REPUBLIC OF KENYA Scheme of Service for Housing Officers APPROVED BY THE PUBLIC SERVICE COMMISSION AND ISSUED BY THE PERMANENT SECRETARY MINISTRY OF STATE FOR PUBLIC SERVICE OFFICE OF THE PRIME MINISTER

More information

Resettlement Policy Framework for Power Transmission and Distribution Projects

Resettlement Policy Framework for Power Transmission and Distribution Projects Resettlement Policy Framework for Power Transmission and Distribution Projects Andhra Pradesh May, 2016 Page 1 Table of Contents ACRONYMS AND ABBREVIATIONS 4 DEFINITIONS 5 EXECUTIVE SUMMARY 8 1. INTRODUCTION

More information

Prepared by Nepal Electricity Authority and Tanahu Hydropower Limited of the Government of Nepal

Prepared by Nepal Electricity Authority and Tanahu Hydropower Limited of the Government of Nepal Tanahu Hydropower Project (RRP NEP 43281) Resettlement Framework October 2012 NEP: TANAHU HYDROPOWER PROJECT Prepared by Nepal Electricity Authority and Tanahu Hydropower Limited of the Government of Nepal

More information

ABBREVIATED RESETTLMENT PLAN LEZHA MUNICIPALITY

ABBREVIATED RESETTLMENT PLAN LEZHA MUNICIPALITY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Background ABBREVIATED RESETTLMENT PLAN LEZHA MUNICIPALITY Abbreviated Resettlement

More information

Chapter RELOCATION SERVICES AND PAYMENTS FOR RESIDENTIAL TENANT HOUSEHOLDS

Chapter RELOCATION SERVICES AND PAYMENTS FOR RESIDENTIAL TENANT HOUSEHOLDS Effective December 15, 2011, City Council has authorized that Chapter 13.84 of the Berkeley Municipal Code be rescinded and reenacted to read as follows: Chapter 13.84 RELOCATION SERVICES AND PAYMENTS

More information

Tamil Nadu Slum Clearance Board was established in September and has been implementing various Housing, Slum Development and

Tamil Nadu Slum Clearance Board was established in September and has been implementing various Housing, Slum Development and HOUSING AND URBAN DEVELOPMENT DEPARTMENT DEMAND NO. 26 POLICY NOTE 2015-2016 2. TAMIL NADU SLUM CLEARANCE BOARD Tamil Nadu Slum Clearance Board was established in September 1970 and has been implementing

More information

Uniform Relocation/ Section 104(D)/ Environmental Review

Uniform Relocation/ Section 104(D)/ Environmental Review Uniform Relocation/ Section 104(D)/ Environmental Review CONTENTS Applicability... 1 Acquisition of Real Property... 2 Value of Land... 2 Market Value... 2 Voluntary Sale Disclosure... 2 Involuntary Sale...

More information

PAPUA NEW GUINEA ROAD MAINTENANCE AND REHABILITATION PROJECT (RMRP) II

PAPUA NEW GUINEA ROAD MAINTENANCE AND REHABILITATION PROJECT (RMRP) II Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PAPUA NEW GUINEA ROAD MAINTENANCE AND REHABILITATION PROJECT (RMRP) II Land Acquisition

More information

SAMPLE 1 INDUCEMENT AND INDEMNITY AGREEMENT LETTER

SAMPLE 1 INDUCEMENT AND INDEMNITY AGREEMENT LETTER SAMPLE 1 INDUCEMENT AND INDEMNITY AGREEMENT LETTER (Date) Ohio Housing Finance Agency 57 E. Main Street Columbus, OH 43215-5135 RE: (Project Name) Colleagues: We have this day filed with the Ohio Housing

More information

INDEX. of subrecipients, VIII -2 records, VI-1, 4, 13. OMB Circular A-122, VIII- 3 certification: I-28

INDEX. of subrecipients, VIII -2 records, VI-1, 4, 13. OMB Circular A-122, VIII- 3 certification: I-28 INDEX A B Barney Frank Amendment, IV-7 accounts beneficiary characteristics (form), VI-1, 2, 19 escrow, II-2,4,7-11, 16,20 bidder s instructions, I-12 interest-bearing, II-7, 0 compliance notion, I-12

More information

Resettlement Policy Framework

Resettlement Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Ministry of Regional Development and Infrastructure of Georgia Roads Department of Georgia

More information

Chittagong Water Supply Improvement and Sanitation Project. Resettlement Policy Framework

Chittagong Water Supply Improvement and Sanitation Project. Resettlement Policy Framework Chittagong Water Supply Improvement and Sanitation Project Resettlement Policy Framework Chittagong Water Supply & Sanitation Authority Government of Bangladesh February 2010 Table of Contents 1. BACKGROUND

More information

Social Safeguards Due Diligence Report

Social Safeguards Due Diligence Report Social Safeguards Due Diligence Report June 2018 IND: Bihar State Highways III Project Establishment of Bihar Road Research Institute Prepared by Bihar State Roads Development Corporation Limited, Government

More information

BIOMASS-BASED DISTRICT HEATING PROJECT

BIOMASS-BASED DISTRICT HEATING PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Biomass-Based District Heating Project BIOMASS-BASED DISTRICT HEATING PROJECT Construction

More information

Chief Administrator Haryana Urban Development Authority C-3, HUDA Complex, Sector-6, Panchkula , Haryana, www. huda.org.

Chief Administrator Haryana Urban Development Authority C-3, HUDA Complex, Sector-6, Panchkula , Haryana, www. huda.org. Chief Administrator Haryana Urban Development Authority C-3, HUDA Complex, Sector-6, Panchkula-134109, Haryana, www. huda.org.in email : huda@hry.nic.in Helpline (Toll free): 1800 180 3030 It really is

More information

Consulted With Individual/Body Date Head of Finance Financial

Consulted With Individual/Body Date Head of Finance Financial Equipment Disposal Policy Developed in response to: Policy Register No: 12037 Status: Public Internal Audit Report for Fixed Assets Contributes to CQC Regulation 17 Consulted With Individual/Body Date

More information

Mammoth Lakes Town Council Agenda Action Sheet. Council Meeting Date: August 17, 2016 Date Prepared: August 8, 2016

Mammoth Lakes Town Council Agenda Action Sheet. Council Meeting Date: August 17, 2016 Date Prepared: August 8, 2016 Agenda Item# FileNo. Mammoth Lakes Town Council Agenda Action Sheet Council Meeting Date: August 17, 2016 Date Prepared: August 8, 2016 Prepared by: Title: Agenda: Ruth Traxier, Associate Planner Consider

More information

UNIT 7 THE LAND ACQUISITION ACT (LAA), 1894: AWARD AND COMPENSATION

UNIT 7 THE LAND ACQUISITION ACT (LAA), 1894: AWARD AND COMPENSATION UNIT 7 THE LAND ACQUISITION ACT (LAA), 1894: AWARD AND COMPENSATION Structure 7.0 Objectives 7.1 Introduction 7.2 Award by the Collector 7.3 Consequences of taking Possession Section 16 of the Act 7.3.1

More information

Mandatory Requirement for Certification Bodies in Assessing Free, Prior and Informed Consent (FPIC) in New Planting Procedures

Mandatory Requirement for Certification Bodies in Assessing Free, Prior and Informed Consent (FPIC) in New Planting Procedures Mandatory Requirement for Certification Bodies in Assessing Free, Prior and Informed Consent (FPIC) in New Planting Procedures February 2018 Document Name: Mandatory Requirement for Certification Bodies

More information

SENIOR CITIZEN RESIDENCES SCHEME CHEERFUL COURT / JOLLY PLACE NGAU TAU KOK TSEUNG KWAN O. Application Form

SENIOR CITIZEN RESIDENCES SCHEME CHEERFUL COURT / JOLLY PLACE NGAU TAU KOK TSEUNG KWAN O. Application Form SENIOR CITIZEN RESIDENCES SCHEME CHEERFUL COURT / JOLLY PLACE NGAU TAU KOK TSEUNG KWAN O Application Form The completed application form must be mailed to Hong Kong Housing Society, General Post Office

More information

PAK: National Trade Corridor Highway Investment Program (NTCHIP)

PAK: National Trade Corridor Highway Investment Program (NTCHIP) Land Acquisition and Resettlement (E-35, Hassanabdal Havelian Expressway) September 2015 PAK: National Trade Corridor Highway Investment Program (NTCHIP) Prepared by National Highways Authority for the

More information

STATE OF OHIO FINANCIAL REPORTING APPROACH GASB 34 IMPLEMENTATION ISSUES TRANSPORTATION INFRASTRUCTURE

STATE OF OHIO FINANCIAL REPORTING APPROACH GASB 34 IMPLEMENTATION ISSUES TRANSPORTATION INFRASTRUCTURE TRANSPORTATION INFRASTRUCTURE GASB 34 Reporting Requirements (Paragraphs 19 through 26) Paragraph 19 includes infrastructure assets in the definition of capital assets. Infrastructure assets are defined

More information

Guidelines For Creating a TBRA Administrative Plan

Guidelines For Creating a TBRA Administrative Plan NOTE: Do not submit this document as your administrative plan. Also, do not submit KHC s Housing Choice Voucher Administrative Plan. You must create your own by using the document below as your guide.

More information

SHORT TERM TENDER NOTIFICATION CALL - 2 (Through e- Procurement only) No: KBJNL/MLI Dn-1/PB/Tender/ SCP-TSP / / 45 Date:

SHORT TERM TENDER NOTIFICATION CALL - 2 (Through e- Procurement only) No: KBJNL/MLI Dn-1/PB/Tender/ SCP-TSP / / 45 Date: 1 KRISHNA BHAGYA JALA NIGAM LIMITED (A Government of Karnataka Undertaking) Office of the Executive Engineer, KBJNL MLI Division No.1, Mattihal-586210, B.Bagewadi taluk, Bijapur District, Karnataka SHORT

More information

Acquisition & Relocation CDBG/HOME Guidebook

Acquisition & Relocation CDBG/HOME Guidebook Acquisition & Relocation CDBG/HOME Guidebook Section H 2 ANTI-DISPLACEMENT & RELOCATION ASSISTANCE PLAN Introduction Applicants for federal funds must comply with the Uniform Relocation Assistance and

More information

NOTICE INVITING TENDER FOR PURCHASE OF PLOT AT GERUGAMBAKKAM, KANCHEEPURAM DISTRICT

NOTICE INVITING TENDER FOR PURCHASE OF PLOT AT GERUGAMBAKKAM, KANCHEEPURAM DISTRICT NOTICE INVITING TENDER FOR PURCHASE OF PLOT AT GERUGAMBAKKAM, KANCHEEPURAM DISTRICT Bank of Baroda invites proposal / offers in two bid system from owners having clear and marketable title, also no objection

More information

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT, AND REHABILITATION OF DISPLACED PERSONS

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT, AND REHABILITATION OF DISPLACED PERSONS Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RP275 Socialist Republic of Vietnam Ministry of Transport and National Traffic Safety

More information

YUROK INDIAN HOUSING AUTHORITY

YUROK INDIAN HOUSING AUTHORITY The Yurok Indian Housing Authority (YIHA), a Tribal Designated Housing Entity, wishes to establish effective, fair and consistent policies and procedures for Federally Recognized Native American who are

More information

2018 Requirements Manual An In-Depth Look at Changes to the Requirements

2018 Requirements Manual An In-Depth Look at Changes to the Requirements 2018 Requirements Manual An In-Depth Look at Changes to the Requirements Executive Summary The Requirements Manual helps land trusts understand how the Land Trust Accreditation Commission verifies that

More information

Resettlement Plan. BHU: SASEC Road Connectivity Project. Phuentsholing Bypass Road. March 2014

Resettlement Plan. BHU: SASEC Road Connectivity Project. Phuentsholing Bypass Road. March 2014 Resettlement Plan March 2014 BHU: SASEC Road Connectivity Project Phuentsholing Bypass Road Prepared by the Phuentsholing Thromde for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 12 March 2014)

More information

National Workshop on Sectoral Perspectives & Initiatives: Creating an Enabling Framework for Stimulating Investments in Manufacturing

National Workshop on Sectoral Perspectives & Initiatives: Creating an Enabling Framework for Stimulating Investments in Manufacturing Setting up a business 1 Publish a comprehensive checklist for all requirements for NOCs, licences, registrations, environment clearances and land and building related approvals and certificates. 2 Prescribe

More information

KEMENTERIAN PEKERJAAN UMUM DIREKTORAT JENDERAL BINA MARGA Jalan Pattimura No 20, Kebayoran Baru, Jakarta Selatan 12110

KEMENTERIAN PEKERJAAN UMUM DIREKTORAT JENDERAL BINA MARGA Jalan Pattimura No 20, Kebayoran Baru, Jakarta Selatan 12110 KEMENTERIAN PEKERJAAN UMUM DIREKTORAT JENDERAL BINA MARGA Jalan Pattimura No 20, Kebayoran Baru, Jakarta Selatan 12110 LARP IMPLEMENTATION REPORT For Regional Roads Development Project West Kalimantan

More information

Registering Property

Registering Property Registering Property Delhi 1. Description of Reform: For procedure 3 Conduct charges search at the Registrar of Companies, Doing Business 2018 records that the buyer must conduct a search in office of

More information

India: Mundra Ultra Mega Power Project

India: Mundra Ultra Mega Power Project Resettlement Planning Document Short Resettlement Plan Document Stage: Final Project Number: 41946 September 2008 India: Mundra Ultra Mega Power Project Prepared by Coastal Gujarat Power Limited (CGPL)

More information