FINAL REPORT SOCIAL IMPACT ASSESSMENT (SIA) & RESETTLEMENT ACTION PLAN (RAP) FOR BRT CORRIDOR IN NAYA RAIPUR CHHATTISGARH

Size: px
Start display at page:

Download "FINAL REPORT SOCIAL IMPACT ASSESSMENT (SIA) & RESETTLEMENT ACTION PLAN (RAP) FOR BRT CORRIDOR IN NAYA RAIPUR CHHATTISGARH"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized FINAL REPORT SOCIAL IMPACT ASSESSMENT (SIA) & RESETTLEMENT ACTION PLAN (RAP) FOR BRT CORRIDOR IN NAYA RAIPUR CHHATTISGARH NAYA RAIPUR DEVELOPMENT AUTHORITY RAIPUR CHHATTISGARH, INDIA December, 2012

2 Executive Summary 1. NayaRaipurNewTownship: Naya Raipur is being developed in Greenfield area as a CapitalCity for the State of Chhattisgarh at a distance of about 17 km in the south-east of the present day capital city Raipur. (NRDA) has been constituted by Government of Chhattisgarh for the planning and development of the New City. The planning area of Naya Raipur comprises three planning layers and covers a total area of sq km. However, the Layer I of the planning area, where major development activities including the of BRTS would take place, is spread over in area of sq km which is surrounded by green belt of sq km. Layer II is the peripheral area under development control jurisdiction and Layer III is Airport zone. Naya Raipur is being developed for a population of 5.6 lacs by the year 2031, in three phases. The first phase development for a target population of 1.50 lacs including that of the existing villages is in progress. 2. Land Procurement for Township (Non Bank Project):Out of the total land required for the development of planning layer I, 29% is Government land and 71% is Privateland. The Government land has been transferred to the NRDA. In accordance with Rehabilitation and Resettlement Plan of Naya Raipur, NRDA started purchasing private land in the year 2006 by mutual agreement with the land owners NRDA has purchased haPrivatelandthrough mutual consent and has paid Rs million to the private parties as cost of land for development of buildings, roads, other facilities till July The private negotiation process had series of public consultation meetings with land owners and after obtaining their consent on replacement value of land the land procurement process was completed. Thus of the total private land (6365 ha), ha land has been purchased by mutual agreement, 1387 ha (of 82 title holders)which could not be purchaseddespite best effort, is under different stages of land acquisition process under the LAA NRDA R&R Policy and Implementation: NRDA has prepared a special rehabilitation plan under section 69 of ChhattisgarhTown and Country Planning Act 1973 read together with Section 56, for land procurementwith mutual consent and agreement to ensure a reasonable compensation package to project affected persons. The rehabilitation plan was approved by GO No /32/2005 Raipur dated It emphasizes that the agricultural land required for the development shall be purchased from the farmers on mutual consent instead of acquiring the land under the Land Acquisition Act, as far as possible. The compensation package for the land and assets over it has been decided after a series of consultations at different level, with the project affected persons, public representatives and other stake holders. A hassle - free system is in place for registration i

3 of the sale deed of agriculture land and payment of compensation. In addition to cash compensation for land the PAPs are entitled to special rehabilitation benefits such as land for horticulture/ floriculture or utility shops or residential plot, free of cost as a special benefit for livelihood restoration to the project affected persons. Families of any village which need to be relocated on account of development works of the NRDA are provided new houses in a residential colony developed by NRDA within 0.5 km distance from their existing houses. Special benefits are also provided to the project affected landless labourers.a systematic and exhaustive implementation process was followed to allothouse or plot to the project affected persons who have been resettled. As a first step their household information was collected through a census and socio economic survey. A biometric card jointly with husband and wife was done with photography of both. Since 2007, NRDA has taken up resettlement and rehabilitation as per the policy framed. Till July 2012 NRDA provided 2250 houses to PAPs in Naya Raipur with a total cost of Rs million. In addition, it created a housing colony of 71 displaced persons in Naigaon with total cost of Rs.5.56 million. All the resettlement colonies are provided with infrastructure like water, electricity drainage etc. The social amenities like school community centers etc. are provided in all the resettlement colonies. In order to restore livelihood, NRDA arranged training in different trade and vocations for income restoration and livelihood loss after conducting a thorough training need assessment. Since 2007 till date 1104 project impacted personsreceived training in different trades like Mushroom production, flower art, Masonry, electrician, driving, computer etc. The total expenditure in conducting training was Rs.7.81 million till July BRTS - SUTP (World Bank Assisted Project): NRDA prepared a DPR for development of BRTS and submitted it for inclusion in the Sustainable Urban Transport Programme initiated by Government of India. The BRTS proposed by NRDA shall facilitate connectivity between Raipur and Naya Raipur. Based on the DPR it has been selected as a DemonstrationCity under GEF - UNDP - World Bank assisted Sustainable Urban Transport Programme (SUTP) of Ministry of Urban Development, Government of India. A funding plan of Rs million has been approved. 5. SUTP of Naya Raipur:NRDA along with the Government of Chhattisgarh signed the Participation Agreement with the MoUD GoI, on 10th February 2009 for implementation of component - 2 of GEF - Sustainable Urban Transport Program in Naya Raipur. The Loan Agreement, Project Agreement and Global Environment Facility Grant Agreement were signed on 5th February Naya Raipur Sustainable Urban Project bears Loan no IN and GEF grant no A funding plan of INR million has been approved based on the DPR submitted by NRDA. Under the project NRDA was required to develop 7 km of road links from its own funds which have since been completed. The GEF-WB/SUTP Component of BRT Naya Raipur project includes: (1) Development of- Cycle Tracks & Pedestrian Walkways (36 km app). (2) Bus stops /Shelters. (3) Bus ii

4 Depot. (4) 2 Bus Terminals(5) Traffic Safety system for non motorized vehicles.6.control & information centre including off board ITS. 6. SIA&RAP: To address and mitigate any adverse impacts on people and assets on account of the Project (BRTS under the guidelines of Environmental and Social Management Framework (ESMF) of SUTP NRDA carried out Social Impact Assessment of Naya Raipur and prepare a Resettlement Action Plan for the BRT component. The RAP is based on the general findings of the census/socioeconomic surveys, field visits, and meetings with various project-affected persons in the project area. 7. BRTS Roads, Impact and Land Procurement: There are two corridors selected for BRTS line services (i) Corridor I having total length of 24.7 km, out of which 9.4 km is within Raipur city where the RoW availability is mts, road section 2.4 km is a section of National Highway with RoW of 60 mts. NRDA constructed 12.9 mts as a part of City Development, a part (road no. 13 length 3 km) has been constructed to complete the corridor. (ii) Corridor III has a length of 17.8 km Three road sections (Road no. 11 (0.5 km, Road no. 12 A (2.7 km) and Road no. 10 (0.3 km) have been constructed to complete the corridor. The land acquisitions for the roads were completed in Thus no strip acquisition or any additional land acquisition for the purpose of the BRTS project is required. For the purpose of preparation of RAP an attempt has been made to estimate the land acquisition and compensation details. For the purpose of BRTS project ha, and 3.95ha land was procured through private negotiation and LA Act respectively. For the construction of Bus depot 5.18 ha land was procured through negotiated purchase. The government land transferred to NRDA was ha. The NRDA paid Rs million as compensation payment through negotiated purchase. 8. Land Acquisition and Details of PAPs:There are 122 title holder PAPs. The corridor wise distribution of PAPs shows that ha of land was purchased through negotiation/mutual consent from 102 PAPs and Rs million were paid to them in For the purpose of development of bus depot at Naya Raipur 5.18 ha of land was purchased by NRDA ata total cost of Rs.6.96 million from 15 PAPs. For corridor number III 1.48 ha of land was procured through mutual agreement and Rs.1.73 million was paid as compensation to 5 PAPs. 9. Relocation Measures for NTH PAPs: Relocation of 12 squatter families has already been done and resettled in close proximity in relocation colony. The houses that have been allotted to them give them legal titles to the homestead plot and house. The size of the plot is large enough for them to accommodate their house according to their iii

5 needsand also in addition to construct structures for service units, shops, etc. The road has been constructed for resettlement colony by NRDA from State Government grant as provided in the funding plan. The employable members of all the affected families are engaged in meaningful employment. The new houses are located near their old homes about 200 metres away. It is less than ten minutes walk to the main road. The PAPs have been provided with a concrete house consisting of a 1500 sq. ft house plot with a 400 sq ft built up area. The house consists of two rooms, kitchen and sanitation. A well for drinking water is located less than 100 metres from dwelling unit for water supply. A borewell is in the process of being installed from which water will be provided to individual houses. All the houses were given electricity connection. Kaccha roads are available and these have to tarred or cemented. 10. Utilization of Compensation: Nearly 46 percent of the households from original land holding households reported having purchased land from compensation amount received. The lands purchased are at a distance ranging from 20 kilometres to 70 kilometres away and have been leased out. Other expenses included expenses on marriage, consumption and medical treatment. Other major purchases included a van and tractor which are rented. An AF also reported that the money had been invested in a fixed deposit. 11. Consultation: Public consultation on the Planning, Design, Implementation, Environmental and Social Aspects of BRTS Project in Naya Raipur was held in two stages first with the elected representatives of the residents of the Project area on 3rd February 2009 and subsequently with the general invitees on 20th February Advertisements were published in local Hindi and English News paper inviting interested stakeholders for the consultation. The dates, Time and venues of the meetings were specified in the advertisement. The salient details of the background of the Programme, the agencies which would be funding the SUTP, the Project period etc were also given. The Draft DPR and the advertisement were posted in NRDAs website The consultation with the elected representatives of the residents of the project area was held in the auditorium of State Institute of Rural Development, Nimora between pm, on3rd February The venue is located in close proximity of the project area. A list of representatives who participated in the consultants Pvt Limited, Mumbai along with Shri Jitendra, urban Planner and Shri Prashant Agle, socio economic expert participated in the meeting. The consultation with the Government Officers of different Departments, Municipal Corporation, practicing Architects and Engineers was held on 20th February 2009 in the office of NRDA. Public consultations and disclosure of the SUTP project is continuous process through seminar, workshops etc. iv

6 12. Grievance Redress Mechanisms: Naya Raipur R & R Plan sets out constitutions of a grievance redress mechanism. As laid down in the said plan, for settlement of grievances a Committee under the Chairmanship of the Chief Executive Officer of NRDA is constituted. The committeealso includes representative of PAPs. There is direct interaction between NRDA officials and the Project Affected Persons to resolve any grievance or complaint. The Grievance Redress Committee is in place and meetings are held from time to time. NRDA has a separatesection for land procurement headed by General Manager (Lands). A dedicated officer of the rank of Manager is responsible for Resettlement and Rehabilitation matters. Any Appeal from the decision of the committee can be made to the Principal Secretary/Secretary Housing and Environment Department, Government of Chhattisgarh, whose decision would be final and binding on all parties. 13. Monitoring: RAP implementation is being monitored internally. Broadly, monitoring involves but not limited to daily planning, implementation, feedback and trouble shooting, individual PAPs file maintenance and reporting of progress. Internal monitoring for RAP implementation is a continuous process. It will be carried out during the entire project period. Regular monitoring of resettlement progress will identify potential difficulties and problem areas. It will include documenting actual achievements against targets fixed and identifying reasons for shortfalls, if any.the external monitoring shall be done by the Project Management Consultant appointed by the National Project Manager, Project Management Unit for the project term. 14. Institutional Mechanism: The Government of Chhattisgarh, Housing and Environment Department constituted a "Special Area" named as "Capital Area" and also a Special Area Development Authority named as "Capital Area Development Authority" in the year 2002, under the provisions of the C.G. Town & Country Planning Act, 1973 (23 of 1973) for the planning, development of the proposed Capital area. Subsequently the Capital Area Development Authority was renamed as (NRDA). It has also been decided that NRDA shall be responsible for the management and urban governance of Naya Raipur till a sustainable population is in place and an Urban Local Body is constituted. is a body corporate with perpetual succession and common seal and has power to acquire, hold develop, manage and dispose property, both movable and immovable and to contract and sue and be sued by its name. Its functions include preparation and implementation of development plan. 15. Budget: The cost of Resettlement is charged to the budget of Naya Raipur Development Authority under the head of Land Procurement and Rehabilitation. v

7 Contents CHAPTER 1 INTRODUCTION DEVELOPMENT PLAN OF NAYA RAIPUR AND LAND ACQUISITION REHABILITATION POLICY BRTS PROJECT - SUTP SCOPE OF SIA AND RAP METHODOLOGY OF SIA AND RAP Socio-economic Profile and Baseline Stakeholder Consultations RAP... 4 CHAPTER 2 NAYA RAIPUR CITY SOCIO-ECONOMIC PROFILE LOCATION NAYA RAIPUR PLANNING AREA SOCIO-ECONOMIC PROFILE AND IMPACT Affected Villages Working Population RESETTLEMENT PLAN AND R&R POLICY FOR NAYA RAIPUR R&R package Land Price Fixation Committee and process Adopted Disbursement of Compensation and Assistance Key Feature of National Policy, Naya Raipur R&R Policy LAND ACQUISITION IMPACT & PAYMENT OF COMPENSATION CENSUS AND BIOMETRIC SURVEY AND ISSUE OF IDENTITY CARD RESETTLEMENT AND REHABILITATION LIVELIHOOD AND INCOME RESTORATION CONVERGENCE WITH GOVERNMENT PROGRAMME FOR ECONOMICALLY WEAKER SECTION HOUSING ENVIRONMENTAL CLARENCE CHAPTER 3 SUTP - BRTS PROJECT INTRODUCTION GEF- UNDP/SUTP- BRT PROJECT NAYA RAIPUR BRTS INFRASTRUCTURE Bus Depot Night Parking Facilities Stops in BRT Corridor Pick-Up Points in Raipur Bus Shelters in Naya Raipur CHAPTER 4 BRTS - LAND ACQUISITON, SOCIO-ECONOMIC IMPACT AND RESETTLEMENT ACTION PLAN BRTS ROADS, IMPACT AND LAND ACQUISITION LAND ACQUISITION AND DETAILS OF TH PAPS OTHER IMPACT AND MITIGATION MEASURES SOCIO ECONOMIC PROFILE OF PAPS General Profile Literacy level Occupational Structure and employment RELOCATION OF HOUSES UTILIZATION OF COMPENSATION GRIEVANCE REDRESS MECHANISMS

8 4.8 MONITORING INSTITUTIONAL MECHANISM BUDGET CHAPTER 5 CONSULTATIONS AND PARTICIPATION BACK GROUND C.G T&CP ACT, PREPARATION OF CITY DEVELOPMENT PLAN CONSULTATION OF ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) FOR GEF/SUTP CONSULTATION AND DISCLOSURE List of Tables Table 2.1. Area Profile of sub-district of Raipur district, Chhattisgarh state... 7 Table 2.2. Population Data... 8 Table 2.3. Projected Occupational Structure For Naya Raipur Table 2.4. Land Acquisition and payment of Compensation (Till July 2012) Table 2.5. EWS Housing Table 3.1. BRT/SUTP Table 3.2. Route Length and Ownership Table 4.1. BRTS Roads ROW details and land Acquisition Table 4.2. land Acquired and details of TH PAPs Table 4.3. Impact and Mitigation Measures Table 4.4. Re-habitation of project Affected Persons List of Figures Figure 2-1. Raipur and Naya Raipur... 6 Figure 2-2. Planning layer of Naya Raipur... 7 Figure 3-1. BRTS Corridors (I and III) Under SUTP Figure 3-2. Proposed Site for Bus Terminal at Existing Government Secretariat Figure 3-3. Location of Bus Shelters in Naya Raipur Figure 5-1. Publication of Draft Development Plan of Naya Raipur Figure 2-1. Raipur and Naya Raipur... 6 Figure 2-2. Planning layer of Naya Raipur... 7 Figure 3-1. BRTS Corridors (I and III) Under SUTP Figure 3-2. Proposed Site for Bus Terminal at Existing Government Secretariat Figure 3-3. Location of Bus Shelters in Naya Raipur Figure 5-1. Publication of Draft Development Plan of Naya Raipur

9 Chapter 1 Introduction Back Ground 1. Naya Raipur is being developed in Greenfield area as a CapitalCity for the State of Chhattisgarh at a distance of about 17 km in the south-east of the present day capital city Raipur. (NRDA) has been constituted by Government of Chhattisgarh for the planning and development of the New City. The planning area of Naya Raipur comprises three planning layers having a total area of sq km covering 41 villages. However, the Layer I of the planning are, where major development activities would take place, is spread over in area of ha (80.13 sq km and green belt of sq km). Layer II is the peripheral area under development control jurisdiction and Layer III is Airport zone. Naya Raipur is being developed for a population of 5.6 lacs by the year 2031, in three phases. The first phase development for a target population of 1.50 lacs including that of the existing villages is in progress. The planning areas of Raipur and Naya Raipur are not contiguous but are separated by rural areas, and farm land. 1.1 Development Plan of Naya Raipur and Land Acquisition 2. The Draft Development Plan for the development of Naya Raipur was prepared under the provision of the CG Town & Country Planning Act, 1973 by NRDA after due consultations at every stage with wide spectrum of stakeholders. Suggestions and objections were invited after exhibiting the detailed maps, including the maps for proposed landuse, road network, transportation plan etc. in the Town Hall, Raipur, which is at central location. The objections were heard by a Public Committee which compiled its recommendations after due consideration of every suggestion and objection for consideration of the State Government. Subsequently the development plan was approved and notified by the State Government on in the official Gazette of Chhattisgarh. As per the Naya Raipur Development Plan 2031,the NRDA Planning Area consists of three layers: 1. Planning Layer I (NayaRaipurCity including green belt area) sq km ( ha) 2. Planning Layer II (Peripheral rural Zone) sq km ( ha) 3. Planning Layer III (Airport Zone) sq km ( ha) Currently NRRDA is developing the PlanningLayerI.The total area under Planning Layer I is ha. The land area is located in the revenue land of 27 villages. However, the settlement of 13 villages are located in the planninglayer I. 3. The city of Naya Raipur is being developed as a capital city with all State level and regional level Government offices, Housing, Central Business District, Educational and Health care 1

10 facilities and all other social and recreational facilities. Out of the total land required for the development of planning layer I, 29% is Government land and 71% is Privateland.The Government land has been transferred to the NRDA. In accordance with Rehabilitation and Resettlement Plan of Naya Raipur, NRDA started purchasing private land in the year 2006 by mutual agreement with the land owners NRDA has purchased ha Privateland through mutual consent and has paid Rs million to the private parties as cost of land for development of buildings, roads, other facilities till July The private negotiation process had series of public consultation meetings with land owners and after obtaining their consent on replacement value of land the land procurement process was completed. Thus of the total private land (6365 ha), ha land has been purchased by mutual agreement, 1387 ha (of 82 title holders) which could not be purchased despite best effort, is under different stages of land acquisition process under the LAA Rehabilitation Policy 4. NRDA has prepared a Rehabilitation scheme based on the Rehabilitation Policy of the Government of Chhattisgarh. It emphasizes that the agricultural land required for the development shall be purchased from the farmers on mutual consent instead of acquiring the land under the Land Acquisition Act, as far as possible. The compensation package for the land and assets over it, has been decided after a series of consultations at different level, with the project affected persons, public representatives and other stake holders. A hassle - free system is in place for registration of the sale deed of agriculture land and payment of compensation. The detailed rehabilitation policy for Naya Raipur is discussed in subsequent section. 1.3 BRTS Project - SUTP World Bank Assisted Project 5. NRDA prepared a DPR for development of BRTS and submitted it for inclusion in the Sustainable Urban Transport Programme initiated by Government of India. The BRTS proposed by NRDA shall facilitate connectivity between Raipur and Naya Raipur. Based on the DPR it has been selected as a DemonstrationCity under GEF - UNDP - World Bank assisted Sustainable Urban Transport Programme (SUTP) of Ministry of Urban Development, Government of India. A funding plan of Rs million has been approved. 6. NRDA along with the Government of Chhattisgarh signed the Participation Agreement with the MoUD GoI, on 10th February 2009 for implementation of component - 2 of GEF - Sustainable Urban Transport Program in Naya Raipur. The Loan Agreement, Project Agreement and Global Environment Facility Grant Agreement were signed on 5th February Naya Raipur Sustainable Urban Project bears Loan no IN and GEF grant no A funding plan of INR million has been approved based on the DPR submitted by NRDA. 2

11 1.4 Scope of SIA and RAP 7. To address and mitigate any adverse impacts on people and assests on account of the Project (BRTS), the Government of India, and SUTP/ESMF (based on the World Bank Policies) require the implementing agency, NRDA to carry out Social Impact Assessment of Naya Raipur and prepare a Resettlement Action Plan for the BRT component. 8. For preparation of Social Impact Assessment (SIA) & Resettlement Action Plan (RAP),the scope of the work is given below: (i) To conduct social impact assessment and mitigation measures among the project impacted persons for proposed BRTS and prepare a Resettlement Action Plan for project affected population. (ii) (iii) To conduct public consultations in general and also to conduct general public consultations for awareness of the SUTP project To conduct social assessment among various stakeholders particularly among the potential BRTS users to maximize social utility of the BRTS. 1.5 Methodology of SIA and RAP 9. The approach underlying the assessment of social impacts and developing appropriate mitigation strategies is based on the principles of local participation and consultations with stakeholders etc. The broad methodology and methodological tools adapted for the preparation of the SIA are detailed below. This section deals with the approach and methodology followed for the collection and analysis of data for social impact assessment Socio-economic Profile and Baseline 10. A socio-economic profile for the project areas has been prepared based on the information collected from secondary and primary sources and provides an overview, levels of socioeconomic development etc. of the Naya Raipur where the project will be implemented. A Resettlement Action Plan has also been prepared for the project, based on 100 percent Census/ socio-economic baseline survey of affected persons due to BRTS Stakeholder Consultations 11. The identification of stakeholders and social impacts involves systematic consultation with project beneficiaries, project affected people, women, vulnerable and poor members of the community, and other stakeholders who may have an influence over the project. To identify social impacts and concerns, consultations were undertaken with primary stakeholders: beneficiaries, poor and vulnerable groups, people who may potentially be impacted adversely by the project, and the implementing agency. Consultations were also carried out with secondary stakeholders: local community based organizations (CBOs) and community representatives as well as government departments etc. 3

12 1.5.3 RAP 12. The RAP is based on the general findings of the census/socioeconomic surveys, field visits, and meetings with various project-affected persons in the project area. 13. The RAP identifies: type and extent of loss of assets, including land and houses; type and extent of loss of livelihood or income opportunities; collective losses, such as common property resources and social infrastructure; entitlement matrix and provisions for relocation assistance; and Institutional framework for the implementation of the plan. 4

13 Chapter 2 NayaRaipurCItySocio-economic Profile 2.1 Location 14. The new state of Chhattisgarh was formed on 1st November 2000 by carving out the region of Chhattisgarh from the state of Madhya Pradesh. It is situated in the heart of India. It shares its borders with six States of the country namely; Uttar Pradesh, Jharkhand, Orissa Madhya Pradesh, Maharashtra and Andhra. At the time of formation of the State, the largest city Raipur was named capital of Chhattisgarh. Raipur is located near the centre of large fertile plains of Chhattisgarh region. With already burdened civic infrastructure, Raipur was illequipped to function as the administrative capital of the rapidly growing state. With a view to decongest the city and to provide adequate space for State level administrative office buildings and housing and also to cater to the infrastructural needs of industry and trade in the region, it was decided to develop a satellite town in a radius of 50 km, keeping Raipur as the centre. 15. The site for the New City Naya Raipur was selected at a distance of 17 km in the South- East of Raipur. The site is wedged between National Highway No. 6 (NH 6) on north and National Highway No. 43 (NH 43) on south and extends between kilometers 257/5 (West) and kilometers 253/3 (East) of NH 6 and kilometers 17 and kilometers 22/4 of NH 43.Naya Raipur gets its connectivity from NH6 in North through an interchange and access-controlled road (Road No. 1). The approach from NH-43 in south to Naya Raipur is provided by at grade intersections. NH-6 is being widened to 4 lanes with median and service roads. The road junctions have been re-engineered and the number of crossing has been reduced, traffic signals are being provided. The work is in advance stage of progress. Widening of NH-43, from 2 lanes to 4 lanes is also under consideration by NHAI.The region enjoys very good railway connectivity. The railway line runs almost parallel to the National Highway No.6. The Mumbai-Howrah railway line passes through Raipur. Other railway line Raipur to Visakhapatnam broad gauge line passes through northern part of Naya Raipur and has potential to provide railway connectivity to Naya Raipur. Raipur Airport is situated in the middle of Raipur and Naya Raipur, in the village of Mana, and is popularly known as ManaAirport. The ManaAirport is about 13 km away from the city of Raipur towards the South East and is about 5 kms from the city of Naya Raipur to wards west. It handles domestic flights. 5

14 Figure 2-1. Raipur and Naya Raipur 2.2 Naya Raipur Planning Area 16. The Naya Raipur Planning area is spread over sqkm and covers 41 villages. It has been divided into three Planning layers namely, Layer-I, Layer-II and Layer-III. 17. The land details of the planning layers are as follows: 1. Planning Layer I (NayaRaipurCity including green belt area) sq km ( ha) 2. Planning Layer II (Peripheral rural Zone) sq km ( ha) 3. Planning Layer III (Airport Zone) sq km ( ha) Planning Layer I NayaRaipurCity including green belt area 18. Planning Layer I consists of the Naya Raipur City inclusive of the 500 m green belt around the Naya Raipur city covering an area of sq km ( ha). Hence, the total area under Planning Layer I is ha. 19. Naya Raipur, once developed would be taking State Level administrative functions from the Raipur city and special intensive activity in the new city would also attract population from other parts of Chhattisgarh and also from other states of India. The population of Naya Raipur is planned as 3,65,000 in 2021 to 560,000 in Naya Raipur is to be developed in three phases by The phase 1 development of Naya Raipur includes the implementation of land use and infrastructure development activities including BRTS under SUTP project in Planning layer 1. 6

15 Figure 2-2. Planning layer of Naya Raipur 2.3 Socio-Economic Profile and Impact 21. The planning area of Naya Raipur covers 41 villages in planning layer I, II and III, located in three sub districts namely Raipur, Arang and Abhanpur of district Raipur. The area profile of sub districts in which the villages are located is given below. Table 2.1. Area Profile of sub-district of Raipur district, Chhattisgarh state Particulars Raipur Sub District Arang Sub District Abahnpur Sub District Number of Households 193,156 42,827 34,658 Population-Total 1,014, , ,431 Population-Rural Population-Urban Population(0-6Years) 161,308 45,838 37,514 Sex Ratio Sex Ratio(0-6 Year)

16 Particulars Raipur Sub District Arang Sub District Abahnpur Sub District SC Population 136,297 57,805 35,048 Proportion of SC (%) ST Population 42,691 8,366 10,940 Proportion of ST (%) Literacy Rate (%) Work Participation Rate (%) % of Main Workers % of Marginal Worker % of non Workers Proportion of Cultivator (CL) (%) Proportion of Agricultural Labourers (AL) (%) Proportion of Household Industry Workers (HHI) (%) Proportion of Other Workers (OW) (%) (Source: Census of India 2001) Affected Villages 22. As mentioned earlier,naya Raipur city is being developed in planning layer I which is spread over a total area of sq. km. There are 13 village settlements (Abadi) within this area. The population distributions of all the 13 affected villages are given below. It can be seen from the following Table 2.2that the Naya Raipur town development will impact upon S.No populations as per 2001 census report. Of the total impacted population 51 percent and 49 percent are male and female respectively. The average household size of impacted population is Of the total impacted population nearly 32 percent and 4 percent are Schedule Caste and Schedule Tribe respectively. Village Name Sub- District Table 2.2. Population Data Total Population Male Female SC Population ST Population No of Households 1 Uparwara Arang Chicha Arang Kayabandha Arang Jhanj Arang Rakhi-1 (Rakhi) Arang Nawagaon-1 (Nawagaon) Khapri-2 (Khapri) Arang Arang Tuta Abhanpur Sendh Arang Kotara Bhantha Arang Nawagaon Parsatti Chhatouna (Chhatouna) Arang Arang Riko Arang Total

17 % to total (100) (51.06) (48.94) (31.71) (4.26) (Source: Census of India 2001) Working Population 23. As per census of India 2001, the Work Participation Rate (WPR) is more than 46 percent in Abhanpur rural and more than 42 percent for Raipur rural. The percentage of main workers for Raipur rural is 33.4 and for Abhnapur rural it is 33.4 which is more than for the urban areas. The marginal workers comprise less than 13 percent for Abhanpur rural and 12 percent for Raipur rural. There is a large gap between the percentage of male and female main workers and is observed more for urban areas than rural. While for Abhanpur female main workers are almost 38 percent, in Raipur rural the percentage is less than 30. The percentage of agriculture labour is high for both urban and rural. In Raipur rural the category of other workers is higher at 45.4 percent. 24. It is generally observed that work participation ratio for proposed new towns is higher as compared to existing old towns. With this in view, for the Naya Raipur capital city a work participation ratio adopted for 2031 is 40 percent. With this work participation rate the total employment of the Naya Raipur works out to 222,950. The occupational Structure of Naya Raipur has been projected as shown in the table below. Table 2.3. Projected Occupational Structure For Naya Raipur-2031 Sector Percentage Primary sector Cultivation, Livestock, etc. Negligible Mining & Quarrying Negligible Secondary Sector Tertiary Sector Manufacturing in Household Industries & non household industries Construction 8 Trade & Commerce 28 Transport & Communication 7 Other Services Total Source : Naya Raipur Development Plan Resettlement Plan and R&R Policy for Naya Raipur R&R package 9

18 25. A Rehabilitation and Resettlement Plan for families affected by Naya Raipur has been prepared to compensate and resettle and rehabilitate the affected people. Some key features of the policy are mentioned below. (i) (ii) (iii) (iv) It was decided by the State Government that the land required for the development shall be purchased from the farmers on mutual consent instead of acquiring the land under the Land Acquisition Act, as far as possible. A special rehabilitation plan under section 69 of ChhattisgarhTown and Country Planning Act 1973 read together with Section 56, for land acquisition with mutual consent and agreement was prepared to ensure a reasonable compensation package to project affected persons in NRDA area. The rehabilitation plan was approved by GO No /32/2005 Raipur dated As per the provisions of the plan, those persons who agree to give their land under a mutual consent and an agreement with NRDA are eligible to benefit from this special rehabilitation scheme. Those persons who do not agree to sell their land to under this scheme shall be entitled only to benefits under the normal provisions of the Land Acquisition Act As per the provisions of the Rehabilitation scheme those persons, who agree to give their lands under a mutual consent and agreement with, are entitled to special rehabilitation benefits such as land for horticulture/ floriculture or utility shops or residential plot, free of cost as a special benefit for livelihood restoration to the project affected persons. Families of any village which need to be relocated on account of development works of the NRDA are provided new houses in a residential colony developed by NRDA within 0.5 km distance from their existing houses. Special benefits are also provided to the project affected landless labourers. The compensation package for the land and assets over it has been decided after a series of consultations at different level, with the project affected persons, public representatives and other stake holders Land Price Fixation Committee and process Adopted (v) The State Government vide GO No. 384/1247/AaParya/2006 Raipur dated constituted a committee comprising of the Secretary, Government of Chhattisgarh, Relief and Rehabilitation Department and Collector, Raipur, Chief Executive Officer, NRDA and Two elected Representatives of the project area(project affected persons) as members to determine the rates of land to be procured on mutual consent for the development of the project. (vi) The State Government reconstituted the committee vide GO No. 1104/1274/32/ 2006 Raipur dated under the Chairmanship of the Principal Secretary, Government of Chhattisgarh, Housing and Environment Department and Collector, Raipur, Chief Executive Officer, NRDA and Two elected Representatives of the project area as members to determine the rates of land to be procured on mutual consent for the development of the project. 10

19 (vii) (viii) (ix) The CEO, NRDA in the meeting of the committee, held on presented the analysis of the Guideline rates ( ) fixed by the Collector and Chairman District valuation committee, for the villages under the core area (27 villages) and villages out side it. It was proposed by the CEO that based on the highest rates fixed in the Guideline and adding 30% over and above it as an incentive, the rates of purchase of un irrigated land may be fixed as Rs 7.00 lac per ha. and 10% additional rate may be given for irrigated land. It was further proposed that the rate would be applicable uniformly in all villages within the project area irrespective location and type of land. However the elected representative members of the committee did not agree with the proposal and proposed that the matter be referred to the Government for decision. The matter of determination of rate of land procurement was placed before the Empowered Committee in its 5th meeting held on The committee decided that the rate of land would be Rs 7.00 lac per ha. for un-irrigated land and 15% additional rate would be given for irrigated land. A delegation of villagers of project affected village Rakhi, Khapari and other villages represented against the decision and requested the Chief Minister to intervene. Hon'ble Chief Minister held a meeting on with the villagers and heard their grievances. The following decision regarding the rate for land procurement were taken (Government of Chhattisgarh, Housing and Environment Department Memo No. 1936/22/32/2004 Raipur dated ) Head Non irrigated land Irrigated Land Basic Rate Rs 7.50 Lac per ha. 15 % over and above Rs 7.50 Lac per ha. Ex gratia compensation in case of sale due to mutual consent Special Ex gratia compensation in case the project affected person does not opt for alternative plot as per his eligibility. Rs 1.00 Lac per ha. Rs 2.75 Lac per ha. Rs 1.00 Lac per ha Rs 2.75 Lac per ha. (x) It is noteworthy that the basic rates as shown above vary from 1.5 times to 8 times more than the guideline rates prevailing at that time and that the rates were applicable to all project affected villages irrespective of the type of land. (xi) Additional compensation over and above the rates shown in the above para have been sanctioned as shown in the table below. Period during which compensation paid Additional compensation package as Percent over and above the summation of basic rate, Ex gratia compensation, Special Ex gratia compensation 2006 to % to % to % 11

20 to % (xii) The rates have been revised with effect from as given below- Head Non irrigated land Irrigated Land Basic Rate Rs Lac per ha. Rs Lac per ha. and ` 1.25 additional compensation Ex gratia compensation in case of Rs 1.75 Lac per ha. Rs 1.75 Lac per ha sale due to mutual consent Special Ex gratia compensation in case the project affected person does not opt for alternative plot as per his eligibility. Rs 5.00 Lac per ha. Rs 5.00 Lac per ha. (xiii) (xiv) In addition to the above, stamp duty is exempted for sale of the land and also the project affected persons are also exempted from paying Stamp duty if they purchase any property within three years from the date of registration of the sale deed of the project land. A committee under the Chairmanship of District Collector having Executive Engineer (PWD), Two elected representatives of the Project area nominated by Collector and representative of NRDA was constituted to determine the market rates of assets on the land. The principle adopted for determining the value of buildings is based on the market rate/basic Schedule of Rate and the depreciated value of building.in case of dislocations, the affected person is allotted a housing unit free of cost and transportation is provided by NRDA Disbursement of Compensation and Assistance 26. A hassle - free system is in place for registration of the sale deed of land and payment of compensation. Special camps are organised, every week on a given day and the compensation is paid across the counter immediately after the registration, by account payee cheques Key Feature of National Policy, Naya Raipur R&R Policy 27. The key features of the National R & R Policy and the Naya Raipur R & R Policy are compared in the table below. Key Features National R & R Policy 2007 Naya Raipur R & R Policy Eligibility "affected family" means: (i) a family whose primary place of residence or other property or source of livelihood is adversely affected by the acquisition of land for a project or involuntary displacement for any other reason; or (ii) any tenure holder, tenant, lessee or owner of other property, who on Project affected person: The definition of project affected persons is: (A) whose private agricultural land is being acquired for the project. (B) private agricultural lands in such village where more than 50 percent of the total lands are being, the landless agricultural laborers. 12

21 Key Features National R & R Policy 2007 Naya Raipur R & R Policy Compensation account of acquisition of land (including plot in the abadi or other property) in the affected area or otherwise, has been involuntarily displaced from such land or other property; or - (iii) any agricultural or non-agricultural labourer, landless person (not having homestead land, agricultural land, or either homestead or agricultural land), rural artisan, small trader or selfemployed person; who has been residing or engaged in any trade, business, occupation or vocation continuously for a period of not less than three years preceding the date of declaration of the affected area, and who has been deprived of earning his livelihood or alienated wholly or substantially from the main source of his trade, business, occupation or vocation because of the acquisition of land in the affected area or being involuntarily displaced for any other reason; In case of a project involving land acquisition on behalf of a requiring body: (a) The compensation award shall be declared well in time before displacement of the affected families. Full payment of compensation as well as adequate progress in resettlement shall be ensured in advance of the actual displacement of the affected families. 48 THEGAZETTE OF INDIA: EXTRAORDINARY [PARTI-SEC. 1] (b) The compensation award shall take. into account the market value of the property being acquired, including the location-wise minimum price per unit area fixed (or to be fixed) by the respective State Government or UT Administration. (c) Conversion to the intended category of use of the land being acquired (for example, from agricultural to non-agricultural) shall be taken into account in advance of the acquisition, and the compensation award shall be determined as per the intended land use category. (d) The applicable conversion charges (C) Land held through Kotwar service, whose lands are being acquired under the project. (D) persons whose residential units are being acquired under the project. Provided such individuals should be compulsorily residents of village on the cut off date. (NRDA) has prepared a Rehabilitation Scheme based on the Rehabilitation Policy of the Government of Chhattisgarh, wherein it is emphasized in the Rehabilitation Planthat agricultural land for development will be purchased from farmers by mutual consent and that the Land Acquisition Act will not be used as far as possible. The rates worked out for compensation and some key features of the policy are: Land Rs Lakhs per hectare for irrigated land Rs Lakhs per hectare for unirrigated land. 13

22 Key Features National R & R Policy 2007 Naya Raipur R & R Policy House Plot Amenities Resettlement Sites in for the change in the land use category shall be paid by the requiring body, and no reduction shall be made in the compensation award on this account. Any affected family owning house and whose house has been acquired or lost, may be allotted free of cost house site to the extent of actual loss of area of the acquired house but not more than two hundred and fifty square metre of land in rural areas, or one hundred and fifty square metre of land in urban areas, as the case may be, for each nuclear family. Each affected below poverty line family which is without homestead land and which has been residing in the affected area continuously for a period of not less than three years preceding the date of declaration of the affected area and which has been involuntarily displaced from such area, shall be entitled to a house of minimum one hundred square metre carpet area in rural areas, or fifty square metre carpet area in urban areas (which may be offered, where applicable, in a multistoried building complex), as the case may be, in the resettlement area: Provided that any such affected family. which opts not to take the house offered, shall get a suitable one-time financial assistance for l10use construction, and the amount shall not be less than what is given under any programme of house construction by the Government of India. Such facilities and amenities shall, inter alia, include roads, public transport, drainage, sanitation, safe drinking water, drinking water for cattle, community ponds, grazing land, land for fodder, plantation (social forestry or agro forestry), Fair Price shops, panchayat ghars, Cooperative Societies, Post Offices, seed-cumfertilizer storage, irrigation, electricity, health centres, child" and mother supplemental nutritional services, children's playground, community centres, schools, institutional arrangements for training, places of worship, land for traditional tribal institutions, burial/cremation grounds, Families, which need to be relocated, would be provided new houses in a residential colony developed by NRDA within 0.5 km distance from their existing homes. Special benefits are also provided to the project affected landless labourers. Homestead plots of 1500 sq. Ft with a 400 built up house is also provided. Irrigated horticulture plots for cultivating greens, vegetables, fruits and flowers will be provided. The size of plot will be as per the category of loss of land holding ranging from 3600 to 9000 sq. ft. For some categories of PAPs shops with an area of 100 to 150 Sq ft and some vacant land will be provided. Besides the shops some gumtiyans viz. temporary shops will be provided to some categories of PAPs. The rehabilitated colony developed by NRDA would have a school building, an Anganwadi and a common facility centre. If any temple or any other place of worship in the existing abadi area also comes under the development programme of NRDA, funds would be provided to the village for creating a new place of worship in the new colony. 14

23 Key Features National R & R Policy 2007 Naya Raipur R & R Policy and security arrangements. Provision of drinking water, electricity, schools, dispensaries, and access to the resettlement sites, amongst others, be included in the resettlement plan approved by the appropriate Government. Comprehensive infrastructural facilities and amenities notified by the appropriate Government shall be provided in the resettlement area (s). 2.5 Land Acquisition Impact & payment of Compensation 28. For the development of Naya Raipur Planning layer I land located in 27 villages are being procured. Out of the total land required for the development of planning layer I, 29% is Government land and 71% is Privateland. The Government land has been transferred to the NRDA. In accordance with Rehabilitation and Resettlement Plan of Naya Raipur, NRDA started purchasing private land in the year 2006 by mutual agreement with the land owners NRDA has purchased ha Privateland through mutual consent and has paid Rs million to the private parties as cost of land for development of buildings, roads, other facilities till July The private negotiation process had series of public consultation meetings with land owners and after obtaining their consent on replacement value of land the land procurement process was completed. Thus of the total private land (6365 ha), ha land has been purchased by mutual agreement, 1387 ha (of 82 title holders) which could not be purchased despite best effort, is under different stages of land acquisition process under the LAA Table 2.4. Land Procurement (Till October 2012) Sl. No. Land Details Land Procured (in ha) 1. Privateland Purchased through Private negotiation (6222) 2. Government land Transferred to 2756 NRDA 3. Privateland through Compulsory land Acquisition through LA Act (82) Total land procured Source: Tabulate from NRDA LA file July 2012 Note: Figures in parenthesis are number of title holders. 2.6 Census and Biometric Survey and Issue of Identity card 29. Each project affected person those who have to receive house or accommodation in resettlement colony covered through a exhaustive implementation process. As a first step their household information was collected through a census and socio economic survey. A 15

24 biometric card jointly with husband and wife was done with photography of both. A sample biometric card is place below. 2.7 Resettlement and Rehabilitation 30. Since 2007, NRDA has taken up resettlement and rehabilitation as per the policy framed. 31. Till October 2012, NRDA constructed 313houses in Naya Rakhi with a total cost of Rs million. In addition, it created a housing colony of 14 displaced persons in Naigaon with total cost of Rs.5.56 million. All the resettlement colonies are provided with infrastructure like water, electricity drainage etc. The social amenities like school community centers etc. are provided in all the resettlement colonies. A rehabilitation colony developed by NRDA 16

25 2.8 Livelihood and Income restoration 32. In order to restore livelihood, NRDA arranged training in different trade and vocations for income restoration and livelihood loss after conducting a through training need assessment. Since 2007 till date 1104 project impacted personreceived training in different trades like Mushroom production,masonary,electrician,driving,computer etc. The total expenditure in conducting training was Rs.7.81 million till July I Income Restoration and livelihood training organized by NRDA 2.9 Convergence with Government Programme for Economically weaker Section Housing 33. In February 2009, a detail estimate for 888 EWS House to be funded by GoI under JNNURM was proposed. The central committee approved the same. Accordingly out of the total project out of Rs million 80% i.e. Rs Million will be given by Govt. of Chhattisgarh. In March 2010, the approval in 12th meeting at Board of Director of NRDA was given Rs million under the project. The houses are being constructed for the economically weaker section families in 13 villages within Naya Raipur as detail below: S. No. Village No. (Which Houses to be Constructed for Poor Families) Table 2.5. EWS Housing Sector/Zone No Allotted Area by planning section (in hectare) 1 Uparwara 32/ Tuta 23/ Chatouna 01/ Khandwa Riko 06/ NavaGaon 02/ NavaGaon(Khapri) 28/ Chincha 07/ Sendh No. of Houses 17

26 10 Khapri 32/ KotraBhata 17/ KayaBandh 26/ Jhanjh 25/ Total These houses were constructed within 13 months. Khasra Number of 888 House are following : Group A B C D Village Name (Whom House to be Constructed for Poor Family) Uperwara and Khandva (288) and Khapri(24) NavaGaon(khapri) 72, Jhanj(24), Tuta(120) KayaBandha(24), KotraBhata(24), Chicha and Sendh(96) Riko(72), Navagaon(72), Chatoona(72) Place of Construction (Unit No) Khasra Number Area (in Hectare) Upervara(288) 1527, Khapri 43, NavaGaon Khapri(72) Jhanj(24) Tuta(120) KayaBandha(24), KotraBhata(24), Chicha(96) Riko(72), Navagaon(72), Chatoona(72) 408/1 408/32 408/ Villages 11 Villages Environmental Clarence 34. Naya Raipur Development project comes under serial no: 8(b) Townships and Area Development Project of EIA Notification, 2006 issued by GoI, Ministry of Environment and Forest on September 14, In this notification, projects are categorized as A category and B category based on the type of industry/development, pollution load and size of the project. The A category projects are appraised at the Central level whereas the category B projects are appraised at the State level. The State Level Environment Impact Assessment authority, Chhattisgarh had given environment clearance for the city development vide its order no 303/SEIAA-CG/EC/T & AD/R4P/1/08 Raipur dated

27 Chapter 3 SUTP - BRTS Project 3.1 Introduction 35. It is important to note that all the land required for /BRTS was acquired much before the SUTP/BRTS project was launched. NRDA commenced land procurement in the year The accurate estimation on stages of acquisition/procurement is not documented by NRDA. Based on the above situation this RAP has been prepared. 3.2 GEF- UNDP/SUTP- BRT Project Naya Raipur 36. NRDA along with the Government of Chhattisgarh signed the Participation Agreement with the MoUD GoI, on 10th February 2009 for implementation of component - 2 of GEF - Sustainable Urban Transport Program in Naya Raipur. The Loan Agreement, Project Agreement and Global Environment Facility Grant Agreement were signed on 5th February Naya Raipur Sustainable Urban Project bears Loan no IN and GEF grant no A funding plan of Rs million has been approved based on the DPR submitted by NRDA. 37. The GEF-WB/SUTP Component of BRT Naya Raipur project summarized as below. GEF 1. Part grant for TA for Transit Oriented Development 2.Monitoring and Evaluation World Bank Development of - 1.Cycle Tracks & Pedestrian Walkways (36 km app) 2. Bus stops/shelters 3. Bus Depot 4. 2 Bus Terminals 5.Traffic Safety system for non motorized vehicles 6.Control & information centre including off board ITS 38. The funding plan of BRTS proposals and financial stakeholders are detailed in below table. Table 3.1. BRT/SUTP 19

28 Components PROJECT Total cost NURM Eligible Total cost Total GOI State 80% Grant for TAs from MOUD GEF Implem enting Agency GAP World Bank Implementation of BRTS ( For Phase 1) Development of new roads identified in Naya Raipur (approximately 7 km) Development of Cycle Tracks and Pedestrian walkways (approximately 36 km) Development of Bus Stops / Bus Shelters Development of 2Bus Terminal (Interface point) in Raipur Development of Bus Depot in Naya Raipur (1) Traffic safety system for nonmotorised vehicles Control & Information Centre (Including Off Board ITS) Rolling Stock & On -Board ITS streamline BRT buses mini buses operating as feeder service to the main BRT buses within Naya Raipur GPS/PIS System Ticketing System Monitoring & Evaluation TA for Transit Oriented Development Training for CapacityBuilding TOTAL BASE COST Contingencies (10% of Total Base Cost ) Price Escalation (5% of Total Base Cost ) Project Preparation (Includes 3packages; 1 to be sourced through GEF) Project Implementation&M&E Expenses TOTAL in Million Rs TOTAL in Million USD The administrative functions of the State Secretariat has been shifted from Raipur to Naya Raipur in November 2012 whereas the BRT facilities will be completed in early 2014, therefore the Raipur Naya Raipur public transport service shall have two phases:- 20

29 40. Phase I: Interim Service: The objective would be to provide bus services for government employees, service personnel residing in Raipur and visitors needing travel to state secretariat at Naya Raipur. NRDA has entered into Memorandum of Understanding with Raipur Nagar Nigam Transport Limited for providing Interim Bus Service which is functionalfrom 7 th November Phase II: BRT Service: It is proposed to commence full BRT bus service from January 2014, by the time the BRT infrastructures shall be in place. 42. BRTS Corridor III will be developed under SUTP. The Corridor III is selected keeping in view the future demand within Naya Raipur. Development of the residential zones in Naya Raipur will raise the demand in near future. This route serves the North-South the mobility covering the major points in Naya Raipur. 43. The second BRTS corridor i.e. Corridor II, would be subsequently developed, however, till such time the corridor is developed as BRT corridor, NRDA would run simple city bus service that would cater to NRDA employees residing in that area. This Corridor is beyond the scope of SUTP. Figure 3-1. BRTS Corridors (I and III) Under SUTP 44. The Route Length, Ownership of Road Section within the Route and the road sections which have been constructed as a project component under SUTP Naya Raipur by NRDA through State Government grant are described below: 21

30 Table 3.2. Route Length and Ownership Road Developed Route Length Ownership Length under SUTP (NRDA Funding) Corridor I : Length 25 km Origin: Railway Station Via: Old Secretariat, Telibandha, Seri Khedi interchange Destination: Capitol Complex Corridor III : Length 17.8 km Within Naya Raipur Two Sections of Road in this corridor having Aggregate Length 7km. have been taken under the project. The roads have since been constructed by NRDA. Raipur Municipal 9.4 Corporation NHAI 2.4 NRDA km NRDA 17.8km 0.5 km 2.7 km 0.3 km 3.3 BRTS Infrastructure 45. The sites for the BRT facilities like depot, transfer Station, night parking facilities have been analyzed by rating them on parameter (a) accessibility by majority of users (b) land availability (c) land procurement cost, number and cost of involuntary settlement. The sites emerging as most suitable one for the respective components based on the aforesaid parameters were selected. Selections of site for pick up points have been guided by availability of adequate space and accessibility to passengers Bus Depot 46. Bus Depot is proposed to be developed at Naya Raipur in area of sq m. The land is owned by NRDA. It is a land having gentle slope. Sufficient land is available for future expansion. The depot shall have servicing and maintenance-workshop facilities, fuelling and night parking facilities and control centre of Intelligent Transport System.The site including its surrounding is free from any settlement therefore is no resettlement issue involved. The site plan is given below: 22

31 3.3.2 Night Parking Facilities 47. The parking space, in front of gate no. 4 of the existing SecretariatBuilding in Raipur, shall be used for night parking of buses of Corridor I. It is a GovernmentLand and being used for parking of four wheel and two wheel motor vehicles. There is no land acquisition and displacement Stops in BRT Corridor 48. Bus Stops act as the entry and exit points to the system. As they are the single most important passenger interface; supporting a strong identity for the system, it is essential for these facilities to be aesthetically attractive convenient, comfortable, safe and easily accessible for all age groups of people. 49. The buses would operate in median side dedicated "bus only" lanes in Naya Raipur and in mixed traffic beyond Naya Raipur. The Bus Stops in mixed traffic are planned on the kerb side, one in each direction, at a given location. The left side of bus shall have steps to facilitate boarding and alighting at these pick up points. The bus stops in Naya Raipur are planned to be located on the medians and are termed as "Bus Shelter". The right side of the bus shall not have any step and would be used for level boarding and alighting through the high level median Bus Shelters by way of docking Pick-Up Points in Raipur 50. Two Pickup terminals have been identified in Raipur presented below. 23

32 At Railway Station Raipur 51. One-way flow through the Railway Station terminal, buses moving in one entrance and out the other, with suitable traffic engineering improvements made to facilitate entrances and exits from the surrounding streets has been considered. Walk access to the Railway Station terminal could be facilitated by extending the foot-over bridge crossing the mainline railway tracks to the vicinity of the bus terminal platform. Protected street crossings protected by signals should be provided from/to the areas surrounding the Railway Station. Sufficient space needs to be provided at the Railway Station terminal to accommodate buses on layover/schedule recovery for both local Raipur and BRT Lite services. 52. Alternative concept plans have been submitted to the Divisional Railway Manager (Raipur) for finalizing the location of the terminal. The railways officers suggested another location for the proposed terminal. The concepts plans are being prepared by the Consultant appointed for the designs by NRDA under the project. It is a railway land and any permanent dislocation is not involved. At Existing Government Secretariat 53. The parking space, in front of gate no. 4 of the existing SecretariatBuilding in Raipur, shall be used as a terminal and also for night parking of buses of Corridor I. Figure 3-2. Proposed Site for Bus Terminal at Existing Government Secretariat : 54. The land is owned by the State Government. Permanent dislocation of any settlement is not involved Bus Shelters in Naya Raipur 55. Bus shelters in Naya Raipur are proposed at median. Three types of shelters based on the width of the median shall be developed. In the first phase ten shelters at different locations shall be proposed. The locations are shown in the map given below. The land is owned by NRDA. No resettlement is involved

33 Figure 3-3. Location of Bus Shelters in Naya Raipur 25

34 Chapter 4 BRTS - Land Acquisition, Socio-Economic Impact and Resettlement Action Plan 4.1 BRTS Roads, Impact and Land Acquisition 57. It can be seen from following table that of the total length of 41.8 Kms BRTS routes 17.5 kms BRTS facilities will be accommodated in existing road where the RoW availability is mts. It was mentioned earlier, the land procurement for Naya Raipur capital city took place from 2006 onwards. The bulk acquisition took place since then, as a result there was no strip acquisition or any additional land acquisition for the purpose of the BRTS projects. The land procurementfor the roads were mostly completed in The road infrastructure including BRTS infrastructure has been planned within the acquired land. Due to the purpose of preparation of RAP an attempt has been made to estimate the land acquisition and compensation details. For the purpose of BRTS project ha, and 3.95ha land was procured through private negotiation and LA Act respectively. For the construction of Bus depot 5.18 ha land was procured through negotiated purchase.the government land transferred to NRDA was ha. The NRDA paid Rs million as compensation payment through negotiated purchase. SUTP Project Road Section Table 4.1. BRTS Roads ROW details and land Acquisition Existi Proposed Land Compensa Land Compens ng RoW Purchased tion Procured ation RoW through paid(inr through paid(inr Million) LAAct(Ha) Million) Mutual Agreement (Ha) Length of the Road(in Kms) Govt.Land Transferre d to NRDA(Ha) Remark Raipur Railway to 22 to 60 m No land Acquisition-4 lane road is available.the facilities Station to 60 m and infrastructure will be accommodated in Serikhedi existing/proposed Row. Interchange Interchange to m 100 m No land Acquisition-4 lane road is available. The facilities Junction of Road and infrastructure will be accommodated in 3 and 4 in Naya existing/proposed Row. Raipur Road no m 100 m No Land Acquisition, the facility and infrastructure will be accommodated in the existing RoW. Road no m 60 m Development under SUTP and there is no Land acquisition and Project affected people (PAPs) Central Axis m 200 m No Land Acquisition, the facility and infrastructure will be accommodated in the existing RoW. From road no No Land Acquisition, the facility and infrastructure will be towards capitol accommodated in the existing RoW. complex Corridor no I LA and Procure ment complet ed in Road no m 100 m No Land Acquisition, the facility and infrastructure will be accommodated in the existing RoW. Road no m 60 m No Land Acquisition, the facility and infrastructure will be accommodated in the existing RoW. Road no. 12 A m 60 m Developed under the SUTP and no land acquisition and 26

35 having 14 PAPs Road no m 60 m Corridor no III LA and Procure ment complet ed in Bus Depot LA and Procure ment complet ed in Total Land Acquisition and Details of PAPs 58. It can be seen from the following table that there are 122 title holder PAPs. The corridor wise distribution of PAPs shows that ha of land was purchased through negotiation/mutual consent from 102 TH PAPs and Rs million were apid to them in For the purpose of bus depot at Naya Raipur 5.18 ha of land was purchased by NRDA with a total cost of Rs.6.96 million from 15 TH PAPs. For corridor number III 1.48 ha of land was procured through mutual agreement and Rs.1.73 million was paid as compensation to 5 TH PAPs. SUTP Project Road Section Length of the Road(in Kms) Table 4.2. land Acquired and details of PAPs Compens Land Compens No of ation ation PAPs paid(inr paid(inr titleholde Million) Million) r Land Purchased through Mutual Agreement (Ha) Procured through LAAct(Ha ) Corridor no I Advance paid. Award awaited GovtLan d Transferr ed to NRDA(Ha ) Remark Details of TH wise land acquired has been placed in Annexure-1 Corridor no III Details of TH wise land acquired has been place in Annexure-2 Bus Depot Details of TH wise land acquired has been placed in Annexure-3 Total Other Impact and Mitigation Measures 59. The advent of a BRTS would enhance the development of Naya Raipur. However, the project has the following impacts and issues - Specific areas, which are covered during the study, are given below in Table No

36 Table 4.3. Impact and Mitigation Measures Location Additional Roads in Naya Raipur Access to ponds and grazing ground in Naya Raipur Proposed Terminal near old secretariat in Raipur Transfer Terminal on NH-6 Proposed Pickup point at Raipur Railway Station ADVERSE IMPACTS AND MITIGTAIVE MEASURES -There are 12 PAPs who lost the house due to construction of road no 12. The Relocation of 12 houses has been done. The affected families have been complemented and rehabilitated -Road no 13 required tree cutting. The trees were cut after obtaining Permission for 478 tree cutting has been granted by the competent authority. Tree plantation has been done to mitigate the impact on the village community. Accesses to ponds have been secured in the village development plan. Presently grazing grounds are available in the area where no construction activity has commenced. Subsequently when the area gets urbanized, a separate area would be earmarked for animals in the layer II of Naya Raipur. Permanent dislocation of any house/shop is not there as it is government land The land has not been transferred as yet finalized. Social impact shall be assessed separately once the land is transferred. This is railway land. Permanent dislocation of any house/shop is not anticipated. 4.4 Socio Economic Profile of PAPs General Profile 60. All the families barring one belong to the Satnami caste which is a category of the schedule caste. The average size of household is about 7 and the sex ratio for 15 families is About 87.5 percent of the households have a BPL card. 81 percent of the households owned agricultural land a few years ago which was sold to NRDA. They sold their lands in at the prevalent rates of Rs lakh per hectare of land and Rs 1.00 lakh per hectare for irrigated land with an additional amount which has been paid separately. Subsequently extra payment of 5 percent was declared which has been paid to the affected persons. At the time of preparation of the SIA Report an additional 30 percent compensation was to be paid to the AFs as per revisions and policy provisions for the houses which has since been paid. Joint families are common. The practice of child marriages was prevalent in the community and area. Children were married before they reach puberty. Till the age of 15 or 16 the girl continues to reside in her maternal home. There is also a preference for male children due to which families tend to be fairly large. Dowry is prevalent although it was not articulated as a few AFs reported taking significant loans for the purpose of marriage in the family Literacy level 61. The literacy level is upto higher secondary with 1-2 exceptions who have done graduation. All the family members are not literate. Among the adults the illiterates especially those aged 25 and above comprised of 50 percent, those who had completed primary were percent. 62. Family members who had completed secondary constituted percent. Family members who had completed upto tenth standard comprised of percent and graduates and post 28

37 graduates were just 2.27 percent each.among those still continuing their education a large proportion percent were in primary, percent in secondary, 9.76 percent in higher secondary and upto tenth standard and just 2.44 percent in post graduation Occupational Structure and employment 63. Before relocation it was observed that 1-2 household members were engaged in some sort of regular employment while the rest are either operating petty shops (vegetable, tea stalls, dhabbas, grocery store) in their residential premises or on the temporary structures along the proposed roads. The earnings were sufficient for their needs. Only one youth was technically trained and he was working on part time basis percent of the family members were working as labour (agriculture and non agriculture). 10 percent of the family members were engaged as contractors and 10 percent were engaged in skilled labour. 5 percent each of the family members were involved in services and pandal decorators. 4.5 Relocation of Houses 65. Relocation of 12 families has already been done and resettled in close proximity. The road has been constructed by NRDA from State Government grant as provided in the funding plan. The employable members of all the affected families are engaged in meaningful employment. Among the displaced houses, only one house was pucca and the others were either Kaccha or semi pucca. The houses had a maximum area of 15X20 m with 2-5 rooms in each house. All the houses had separate space for cooking. Sanitation facilities were very poor with open water outlets and absence of toilets. The source of potable water for all the households was through a public hand pump which is located at a distance of 500 metres from the houses. Only one fourth of the households had a legal metered power connection. Most of the others had taken it illegally from the main power line. 66. The new houses are located near their old homes about 200 metres away. It is less than ten minutes walk to the man road. The APs have been provided with a pacca house consisting of a 1500 sq. ft house plot with a 400 sq ft built up area. The house consists of two rooms, kitchen and sanitation. 29

38 67. All these were squatters with no legal titles to the homestead land. In the relocation site, the houses that have been allotted to them give them legal titles to the homestead plot and house. The size of the plot is large enough for them to enlarge their house according to their needs or in addition construct structures for service units, shops, etc. 68. A well for drinking water is located less than 100 metres from dwelling unit for water supply. A borewell is in the process of being installed from which water will be provided to individual houses. All the houses were given electricity connection. Kaccha roads are available and these have to tarred or cemented. S/ N Table 4.4. Re-habitation of project Affected Persons Navagaon PH No-71/16 R1 Circle-Mandir Hasoud Tahsil-Arang, Distt-Raipur Name & Father's Name Affected Residential Compensation Unit, Size Type and Paid 1 Shri Radhe Lal S/O- Shri Visharami Satnami 2 Shri Nathelu S/O- Shri Visharami Satnami 3 Shri Champeshwar S/o- Shri Jhumka Satnami 4 Shri Jhumka S/o- Budhu Ram Satnami 5 Shri Punau Satnami S/o- Shri Tijau Satnami Kachha Makan- 152 S/pt. Verandha- 202 S/pt. Total 345 S/pt. Kachha Makan- 152 S/pt. Verandha- 202 S/pt. Total 345 S/pt. 27,686 8,306 Total 35,992 27,686 8,306 Total 35,992 Kachha Makan- 950 S/pt. 92,510 27,753 Total 1,20,263 Kachha Makan- 732 S/pt. 52,796 15,839 Total 68,635 Kachha Makan- 198 S/pt. Verandha- 55 S/pt Total 253 S/pt. 27,115 8,134 Total 35,249 Allotted House No. N/16 N/15,16 N/14 N/13 N/12 6 Shri Panchu S/o- Shri Shyam Lal Satnami Pakka Makan- 680 S/pt. Kachha Makan S/pt. Total 1698 S/pt. 1,44,000 1,21,500 Total 2,65,500 N/1, 2 7 Shri Etwari S/o- Shri Bartiya Satnami 8 Shri Kusharam S/o- Shri Gayaram Satnami 9 Shri Nathu Ram S/o- Shri Dauwa 10 Shri Ramprashad S/o- Shri Baniya 11 Shri Ramcharan S/o- Shri Dev Singh Kachha Makan- 520 S/pt. 1,43,000 N/11 Pakka Makan- 551 S/pt. 1,51,525 N/4 Kachha Makan- 442 S/pt 55,250 N/5 Kachha Makan- 500 S/pt 62,500 N/28 Kachha Makan- 384 S/pt 1,05,600 N/3 12 Shri Eshwar S/o - Shri Bhondu Satnami Kachha Makan- 388 S/pt. Verandha- 58 S/pt. Total 446 S/pt. 50,994 15,298 Total 66,292 N/28 13 Shri Niranjan S/o- Shri Bhondu Satnami Kachha Makan- 388 S/pt. Verandha- 58 S/pt. Total 446 S/pt. 50,994 15,298 Total 66,292 N/28 14 Shri Hemlal Kachha Makan- 388 S/pt. 50,994 N/28, 30

39 S/ N Name & Father's Name Affected Residential Unit, Size Type and S/o- Shri Bhondu Satnami Verandha- 58 S/pt. Total 446 S/pt. Compensation Paid 15,298 Total 66,292 Allotted House No. 4.6 Utilization of Compensation percent of the households from original land holding households reported having purchased land from compensation amount received. The lands purchased are at a distance ranging from 20 kilometres to 70 kilometres away and have been leased out. Other expenses included expenses on marriage, consumption and medical treatment. Other major purchases included a van and tractor which are rented. An AF also reported that the money had been invested in a fixed deposit. 4.7 Grievance Redress Mechanisms 70. Naya Raipur R & R Plan sets out constitutions of a grievance redress mechanism. As laid down in the said plan, for settlement of grievances a Committee under the Chairmanship of the Chief Executive Officer of NRDA is constituted. The committee has the following members:- (i) Designated Rehabilitation Officer of NRDA (ii) Tehasildar of the affected areas. (iii) Janpad President of the area (iv) Sarpanchs of project affected Panchayats. 71. Any Appeal from the decision of the committee can be made to the Principal Secretary/Secretary Housing and Environment Department, Government of Chhattisgarh, whose decision would be final and binding on all parties. 72. There is direct interaction between NRDA officials and the Project Affected Persons to resolve any grievances or complaints. The Grievance Redress Committee is in place and meetings are held from time to time. NRDA has a Section for land procurement headed by General Manager (Lands). A dedicated officer of the rank of Manager is responsible for Resettlement and Rehabilitation matters. 4.8 Monitoring 73. RAP implementation is being monitored internally. Broadly, monitoring involves but not limited to daily planning, implementation, feedback and trouble shooting, individual PAPs file maintenance and reporting of progress. Internal monitoring for RAP implementation is a continuous process. It will be carried out during the entire project period. Regular monitoring of resettlement progress will identify potential difficulties and problem areas. It will include documenting actual achievements against targets fixed and identifying reasons for shortfalls, if any.the external monitoring shall be done by the Project Management Consultant appointed by the National Project Manager, Project Management Unit for the project term. 31

40 4.9 Institutional Mechanism 74. The Government of Chhattisgarh, Housing and Environment Department constituted a "Special Area" named as "Capital Area" and also a Special Area Development Authority named as "Capital Area Development Authority" in the year 2002, under the provisions of the C.G. Town & Country Planning Act, 1973 (23 of 1973) for the planning, development of the proposed Capital area. Subsequently the Capital Area Development Authority was renamed as (NRDA). It has also been decided that NRDA shall be responsible for the management and urban governance of Naya Raipur till a sustainable population is in place and an Urban Local Body is constituted. Naya Raipur Development Authority is a body corporate with perpetual succession and common seal and has power to acquire, hold develop, manage and dispose property, both movable and immovable and to contract and sue and be sued by its name. Its functions include preparation and implementation of development plan Budget 75. The cost of Resettlement is charged to the budget of under the head of Land Procurement and Rehabilitation. 32

41 Chapter 5 Consultations and participation 5.1 Back Ground 76. The ethos around which Naya Raipur Development Plan is built is the notion of participatory planning so as to ensure acceptance of the proposed development by different cross-section of stakeholders. The planning process has been consultative one, with stakeholders representing a wide spectrum of interests taking part in the discussions and dialogue leading to the formulation of a vision and development objectives, identification of priority sectors and projects. 77. The Planning Process for preparing the Development Plan for Naya Raipur has followed the participatory process. Exhaustive consultations were carried out with key stakeholders, both institutional and individual. These stakeholders included public representations, villagers, community leaders, social workers, officials, experts and other concerned people. 5.2 C.G T&CP Act, The C.G. Town and Country Planning Act, 1973 (the Act, 1973) under section 15 requires that prior to the preparation of the draft Development Plan, existing land use maps have to be prepared by carrying out the survey and the same have to be published has to be together with public notice of the preparation of the map and of place or where the copies may be inspected, inviting objections and suggestions in writing from any person with respect thereto within thirty days from the date of publication of such notice. 79. A workshop was held on 14 September 2005 to discuss and to incorporate the suggestions on the concept of the Naya Raipur and how the city was perceived. Some of the core issues which emerged during interaction with stakeholders include rehabilitation of the existing settlements, housing, urban design, transportation, environmental issues, etc. 80. The Act, 1973 mandates to publish the Draft Development Plan prepared together with a notice of the preparation of the draft development plan and the place or places where the copies any be inspected, inviting objections and suggestions in writing from any person with respect thereto within thirty days from the date of publication of such notice. Such notice shall specify in specify in regard to the draft development plan the following particulars, namely : (i) the existing land use maps (ii) a narrative report, supported by maps and charts, explaining the provisions of the draft development plan (iii) the phasing of implementation of the draft development plan as suggested by the Director (iv) the provisions for enforcing the draft development plan and stating the manner in which permission to development may be obtained (v) an approximate of the cost of land acquisition for public purposes and the cost of works involved in the implementation of the plan. 33

42 Figure 5-1. Publication of Draft Development Plan of Naya Raipur 81. The Act, 1973 requires that after expiry of the notice period, the objections and the suggestions have to be considered and after giving reasonable opportunity to all persons affected thereby of being heard, make such modifications in the draft development plan as he may consider necessary, and submit not later than six months after the publication the draft development plan, the plan as so modified, to the State Government for approval, together with all connected documents, plans, maps and charts.the Development Plan is approved under section 19 of the Act, 1973 by the State Government 5.3 Preparation of City Development Plan 82. Naya Raipur has been included in JnNURM with the mission city of Raipur in December As per the requirement of JnNURM a city development plan was prepared by NRDA through participatory planning. A technical consultant Consulting Engineering Service (India) Private Limited was engaged by NRDA for preparation of the CDP. The CDP, along with other priority included BRT project. Stakeholder consultations were conducted in 29 and 30 May 2008 with the various Government Departments and local villagers. 5.4 Consultation of Environment and Social Management Framework (ESMF) For GEF/SUTP 83. Public consultation on the Planning, Design, Implementation, Environmental and Social Aspects of BRTS Project in Naya Raipur was held in two stages first with the elected representatives of the residents of the Project area on 3rd February 2009 and subsequently with the general invitees on 20th February Advertisements were published in local Hindi and English News paper inviting interested stakeholders for the consultation. The dates, Time and venues of the meetings were specified in the advertisement. The salient 34

43 details of the background of the Programme, the agencies which would be funding the SUTP, the Project period etc were also given. The Draft DPR and the advertisement were posted in NRDAs website The consultation with the elected representatives of the residents of the project area was held in the auditorium of State Institute of Rural Development, Nimora between pm, on3rd February The venue is located in close proximity of the project area. A list of representatives who participated in the consultants Pvt Limited, Mumbai along with Shri Jitendra, urban Planner and Shri Prashant Agle, socio economic expert participated in the meeting. The consultation with the Government Officers of different Departments, Municipal Corporation, practicing Architects and Engineers was held on 20th February 2009 in the office of NRDA. 85. The views and concerns expressed by the stakeholders during the consultation are summarized below No financial burden should come on any stake holder for implementation of this Project. In this proposed project, maximum employment should be made available to local educated and non-educated person as per their qualifications. Proper rehabilitation should be provided if any hutment is affected. The timings and routes should be decided taking into consideration of the requirements of the villagers also. Bus stops should be so made that old people, women and children can use them safely and comfortably. Project should provide best opportunities to local people for operation of their own buses. 86. The copies of the advertisement, attendance sheet and the minutes of consultations are attached at Annexure Consultation and Disclosure 87. Public consultations and disclosure of the SUTP project is continuous process through seminar, workshops etc. Some photographs of such consultations are presented below. The formal and informal consultations are also become continuous process. To keep more transparency in planning and for further active involvement of PAPs and other stakeholders, the project information will be disseminated through disclosure of resettlement planning 35

44 documents. The NRDA will keep the displaced people informed about the impacts, the compensation and assistances proposed for them and facilitate addressing any grievances. Once the RAP is approved by the competent authority, will be disclosed NRDA web site and a copy will be provided to the affected people. Annexure 36

45 Annexure 1:Village Vise Information Regarding Corridor1(Road No. 13) constructed under Naya Raipur areas. Sr. Name of Land Owner No. Land Purchased through Mutual Agreement Village : Kayabandha Khasara No. Area Compensation Date of Compensation 1 Dayalu S/o Bharat /29/ Ghasiya S/o Jaysawal /3/ Magtin W/o Itwari /9/ Radheshyam S/o Kondu Urf Ramadhar /13/ Tejpal S/o Ballal Singh /5/ Girish Kumar S/o V.K. Nayar /8/ Ashok Kumar S/o Ramayan /12/ Rajkumari Singh W/o Harendra Kumar /12/ Rajkumari Singh W/o Harendra Kumar /12/ Geeta Choudhary S/o Ashok Choudhary /12/ Kunjbai W/o Hiralal 42/ /20/ Vidhya S/o Indarman /7/ Gopalkrishna S/o Ramsay /14/ Gopalkrishna S/o Ramsay /14/ Gopalkrishna S/o Ramsay /14/ Rajendra S/o Ramayan Choudhary 598/ /12/ Shekh Moh. Najeem S/o Shekh Moh. Kusheem /26/ Ashwani Kumar S/o Bhangi Prasad and /3/2008 others 19 Gajanan S/o Fasu Ji Funde /24/ Shekh Moh. Najeem S/o Shekh Moh. Kusheem /27/ Chamelibai S/o Ramdas and others /20/ Tajindar S/o Amarjeet /20/ Netram S/o Dukhit Pal /19/ Magteen W/o Itwari /6/ Anil Kumar S/o Radheshyam /14/ Anil Kumar S/o Radheshyam /14/ Anilkumar S/o Radheshyam /14/ Anilkumar S/o Radheshyam /14/ Anilkumar S/o Radheshyam /14/ Anilkumar S/o Radheshyam /14/ Anilkumar S/o Radheshyam /14/ Anilkumar S/o Radheshyam /14/ Urmila W/o Mohan /1/ Urmila W/o Mohan /1/ Indra Kaish W/o Nageshwar /20/2012 Total ,095,

46 Village : Chicha 36 Mugilal S/o Budharu /2/ Pawan S/o Prithram /4/ Bashilal /27/ Bodhi S/o Kewal /13/ Brijkumar S/o Prithram /16/ Brijkumar S/o Prithram /16/ Ashraf S/o Agmed and others /11/ Sarita W/o Swadhar /10/2011 Total ,050, Village : Baroda 44 Shiv Prasad S/o Sukhram /20/ Surjeet W/o Harmindar /9/ Jashmir Kaur /2/ Rohit Kumar S/o Nanku /23/2012 Total ,465, Grand Total ,611, Sr. Name of Land Owner No. Land Procured through LA Act Village : Kayabandha Khasara No. Area Compensation 1 Radheshyam S/o Ramsay Yuvraj S/o Yashwant Dube Anil Kumar S/o Radheshyam Yuvraj S/o Yashwant Dube Radheshyam S/o Ramsay Manish S/o K.K. Sharma Radhesyam S/o Ramsay Shyam Lal S/o Dhanshing Dhimar Total Date of Compensation Village Vise Information Regarding Road No. 12 constructed under Naya Raipur areas. Sr. Name of Land Owner No. Land Purchased through Mutual Agreement Village : Khapari Khasara No. Area Compensation Date of Compensation 1 Krishna Kumar S/o Mannulal /14/ Harishankar S/o Tetaku /14/ Ramesh S/o Preetdas /4/ Balulal S/o Itwari /28/ Babulal S/o Itwari /8/ Satish Chandra S/o Radhakant /2/ Kaliram S/o Ramadheen Part of 2/ /30/

47 8 Manglu S/o Sukhram /30/ Harichand So/ Bali and Othres 22/ /30/ Bali S/o Ramadhin 22/ /30/ Nandkumar S/o Ramadhin 22/ /30/ Shatruhan S/o Ramnath Part of 2/ /8/ Shatruhan S/o Ramnath 22/ /8/ Ramadhin S/o Hardeo /19/2012 Total ,098, Village : Navagaon Kalabai W/o Kishun /25/ Gokul S/o Dekhu /6/ Chandan S/o Bodhi and others /7/ Ishwar S/o Bhodu and others /16/ Suresh S/o Ratiram 391/ /28/ Sukhchand S/o Gangadas /17/ Santosh S/o Kishun /25/ Kalabai W/o Kishun 418/ /25/ Khedu S/o Bihari /4/ Kruiparam S/o Ramlal /11/ Shantibai W/o Khorbahara /30/ Kriparam and others /6/ Ratnu S/o Namdas /13/ Baratu S/o Namdas /13/ Ratnu S/o Namdas /13/ Uttan S/o Budharu /16/ N.B. Danesh S/o Laladas /23/ Uderam S/o Sudarshan /30/ Kushkumar S/o Rampyare /15/ Rampyare S/o Madhukar /15/ Kushkumar S/o Rampyare /15/ Punni Bai W/o Budharu /14/ Deomari W/o Jherka /20/ Nagesh S/o Parsram and others 417/ /22/ Narendra S/o Prabhulal and others 417/ /22/ Bhagat S/o Jhagaru /25/2010 Total ,226, Village : Jhanjh 41 Tijau S/o Khedu Pal /29/ Tijau S/o Khedu Pal /29/ Dilipkumar S/o paliram /6/ Jhuniya W/o Premlal /28/ Daulal S/oKhedu pal /11/ Bela W/o S.D. Diwan /6/ NanhuS/o Ramadhar and others /6/2008 Total ,

48 Grand Total ,997,

49 Annexure 2 Village Vise Information Regarding Corridor III(Road No. 12-A) constructed under Naya Raipur areas. Sr. Name of Land Owner No. Land Purchased through Mutual Agreement Village : Navagaon 71 Khasara No. Area Compensation Date of Compensation 1 Premshankar S/o Bhagela and Others /17/ Santram S/o Anhanram 614/ /17/ Anju W/o Kamlesh 549/ /12/ Achal Kumar/Basaki S/o Amarnath and others 549/ /22/ Premnarayan S/o Prabhulal 549/ /22/2008 Total ,731, Grand Total ,731,

50 Annexure 3 Village Vise Information Regarding Bus Depot constructed under Naya Raipur areas. Sr. Name of Land Owner No. Land Purchased through Mutual Agreement Village : Riko Khasara No. Area Compensation Date of Compensation 1 Jhagan Lal S/o Pyarelal Part of /7/ /1 2 Derhin S/o Bodhan Part of /16/ Derhin S/o Bodhan Part of /16/ Ramesh kumar S/o Lakshme Dayal Part of /9/2008 and others 178/2 5 Ramesh kumar S/o Lakshme Dayal and others Part of /9/ Ramesh kumar S/o Lakshme Dayal and others 7 Ramesh kumar S/o Lakshme Dayal and others 8 Ramesh kumar S/o Lakshme Dayal and others Part of /9/2008 Part of /9/2008 Part of 205/ /9/ Prashant Kumar So/ Ramesh Kumar Part of /9/ Prashant Kumar So/ Ramesh Kumar Part of /9/ /1 11 Prashant Kumar So/ Ramesh Kumar Part of /9/ Prashant Kumar So/ Ramesh Kumar Part of /9/ /2 13 Bharat Lal S/o Manrakhan Part of /8/ Bharat Lal S/o Manrakhan Part of /8/ Jayprakash S/o Sriram and others Part of /9/ /2 Total ,963,

51 Annexure 4, Government of Chhattisgarh 43

52

53

54

55

56

57

58

59

60

61

ENTITLEMENT MATRIX. Gujarat State Highway Project - II. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

ENTITLEMENT MATRIX. Gujarat State Highway Project - II. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ROADS AND BUILDINGS DEPARTMENT GOVERNMENT OF GUJARAT Gujarat State Highway Project -

More information

SUMMARY LAND ACQUISITION PLAN. Supplementary Appendix to the. Report and Recommendation of the President to the Board of Directors.

SUMMARY LAND ACQUISITION PLAN. Supplementary Appendix to the. Report and Recommendation of the President to the Board of Directors. SUMMARY LAND ACQUISITION PLAN Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the RURAL ROADS SECTOR I PROJECT in INDIA Ministry of Rural Development

More information

Presentation on RFCTLARR Act, March 22, 2018

Presentation on RFCTLARR Act, March 22, 2018 Presentation on RFCTLARR Act, 2013 March 22, 2018 Hukum Singh Meena IAS, Joint Secretary Department of Land Resources Ministry of Rural Development Government of India The Right to Fair Compensation and

More information

Summary of Land Acquisition, Resettlement and Rehabilitation Policy for Infrastructure Development Project 2015

Summary of Land Acquisition, Resettlement and Rehabilitation Policy for Infrastructure Development Project 2015 Summary of Land Acquisition, Resettlement and Rehabilitation Policy for Infrastructure Development Project 2015 Vision Contribute to overall development of the nation and its citizens by creating conducive

More information

The Bill is called the Land Acquisition, Rehabilitation and Resettlement Act, 2011

The Bill is called the Land Acquisition, Rehabilitation and Resettlement Act, 2011 The Land Acquisition, Rehabilitation and Resettlement Bill, 2011 was introduced in Lok Sabha on September 7, 2011. On December 17, 2012, during the winter session of Parliament, the government circulated

More information

NO.632/ (29)2004

NO.632/ (29)2004 (English Translation) (Hindi Version is the Authorized Version) NO.632/1-13-11-20(29)2004 From To, K.K.Sinha, Principal Secretary, Govt. of Uttar Pradesh. 1. All Principal Secretaries/Secretaries, Govt.

More information

Legislative Brief The Land Acquisition, Rehabilitation and Resettlement Bill, 2011

Legislative Brief The Land Acquisition, Rehabilitation and Resettlement Bill, 2011 Legislative Brief The Land Acquisition, Rehabilitation and Resettlement Bill, 2011 The Land Acquisition, Rehabilitation and Resettlement Bill, 2011 was introduced in the Lok Sabha by the Minister for Rural

More information

Practice Followed by APIIC in Land Acquisition & Industrial Area Management

Practice Followed by APIIC in Land Acquisition & Industrial Area Management Practice Followed by APIIC in Land Acquisition & Industrial Area Management Acquisition, Allotment and Disposal of Land for Industrial Purpose Gives highest priority to creation of quality infrastructure

More information

Minerals and Mining (Compensation And Resettlement) Regulations, 2012 (L.I. 2175)

Minerals and Mining (Compensation And Resettlement) Regulations, 2012 (L.I. 2175) Minerals and Mining (Compensation And Resettlement) Regulations, 2012 (L.I. 2175) ARRANGEMENT OF REGULATIONS Regulations 1. Claims for compensation 2. Assessment of compensation 3. Compensation principles

More information

RESETTLEMENT POLICY FRAMEWORK AND PROCEDURAL GUIDELINES GAUNGXI ROADS DEVELOPMENT II PROJECT

RESETTLEMENT POLICY FRAMEWORK AND PROCEDURAL GUIDELINES GAUNGXI ROADS DEVELOPMENT II PROJECT Village Roads Component on the GAUNGXI ROADS DEVELOPMENT II PROJECT in THE PEOPLE S REPUBLIC OF CHINA (PRC) Guangxi Comnications Department Nanning, PRC This report was prepared by the Borrower and is

More information

SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS

SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS MINISTRY OF EDUCATION GOVERNMENT OF NEPAL August 2011 2 A. Introduction 1.

More information

The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013

The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 CAME INTO FORCE ON 1.1.2014 (VIDE GOI GAZETTE NOTIFICATION DT. 19.12.2013) DR. R. K. SRIVASTAVA

More information

RP1 85 November The Resettlement Policy Framework (RPF) Report on the GEF Hai Basin Project. (Final Version)

RP1 85 November The Resettlement Policy Framework (RPF) Report on the GEF Hai Basin Project. (Final Version) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PIP annex 9 - C of GEF Hai Basin Integrated Water and Environment Management Project

More information

SOCIAL ASSESSMENT OF BANGALORE METRO RAIL PROJECT LINE R6

SOCIAL ASSESSMENT OF BANGALORE METRO RAIL PROJECT LINE R6 SOCIAL ASSESSMENT OF BANGALORE METRO RAIL PROJECT LINE R6 1. Socio Economic Profile of the Project Area 1.1 General Profile Bangalore officially known as Bengaluru, is the capital of the Indian state of

More information

I U B Reddy The World Bank New Delhi, India

I U B Reddy The World Bank New Delhi, India IAIA15 India s New Land Acquisition Act Right To Fair Compensation and Transparency in Land Acquisition and Rehabilitation and Resettlement Act, 2013 I U B Reddy The World Bank New Delhi, India Challenging

More information

LAND REFORM IN MALAWI

LAND REFORM IN MALAWI LAND REFORM IN MALAWI Presented at the Annual Meeting for FIG Commission 7 In Pretoria, South Africa, Held From 4 th 8 th November, 2002 by Daniel O. C. Gondwe 1.0 BACKGROUND Malawi is a landlocked country

More information

National Land Use Policy

National Land Use Policy Government of the Republic of the Union of Myanmar National Land Use Policy (6 th Draft) 2015, May CONTENT Sr. Content Page 1. Introduction 1-2 2. Part-I Objectives and Basic Principles Chapter-I Objectives

More information

Government of Uttar Pradesh. Workshop for Housing for All Date - 09/08/2016. State Urban Development Agency

Government of Uttar Pradesh. Workshop for Housing for All Date - 09/08/2016. State Urban Development Agency Government of Uttar Pradesh Workshop for Housing for All Date - 09/08/2016 State Urban Development Agency Overview of Scheme Housing shortage estimated at 2 Cr, out of these 2 Cr, 30 Lakh shortage is in

More information

RP607. Summary of Land Acquisition & Resettlement Policy Framework JAMAICA: JM Hurricane Dean ERL Project. A. Introduction. B. Means of Obtaining Land

RP607. Summary of Land Acquisition & Resettlement Policy Framework JAMAICA: JM Hurricane Dean ERL Project. A. Introduction. B. Means of Obtaining Land Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Summary of Land Acquisition Policy Framework JAMAICA: JM Hurricane Dean ERL Project RP607

More information

PROJECT REPORT PROCESS & PROCEDURE OF LAND ACQUISITION UNDER RFCTLARR ACT, Submitted By Babita Mishra Addl. Tahasildar, 16 TH Batch

PROJECT REPORT PROCESS & PROCEDURE OF LAND ACQUISITION UNDER RFCTLARR ACT, Submitted By Babita Mishra Addl. Tahasildar, 16 TH Batch PROJECT REPORT PROCESS & PROCEDURE OF LAND ACQUISITION UNDER RFCTLARR ACT, 2013 Submitted By Babita Mishra Addl. Tahasildar, 16 TH Batch The Right to Fair Compensation and Transparency in Acquisition Rehabilitation

More information

Andhra Pradesh Rural Roads Connectivity Project The Asian Infrastructure Investment Bank assisted

Andhra Pradesh Rural Roads Connectivity Project The Asian Infrastructure Investment Bank assisted GOVERNMENT OF ANDHRA PRADESH PANCHAYAT RAJ ENGINEERING DEPARTEMNT The (RPF) July 2018 Samaj Vikas Development Support Organisation Table of Contents List of Acronyms... 3 Glossary of Resettlement & Rehabilitation

More information

NATIONAL GANGA RIVER BASIN AUTHORITY

NATIONAL GANGA RIVER BASIN AUTHORITY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL GANGA RIVER BASIN AUTHORITY (Ministry of Environment and Forests, Government

More information

DRAFT EXECUTIVE SUMMARY

DRAFT EXECUTIVE SUMMARY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DRAFT EXECUTIVE SUMMARY IPUH - BANTAL (LINK 015.1) KABUPATEN MUKO-MUKO YEAR 2010 EXECUTIVE

More information

Socialist Republic of Vietnam POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF DISPLACED PERSONS

Socialist Republic of Vietnam POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF DISPLACED PERSONS Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Socialist Republic of Vietnam POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION

More information

Resettlement Policy framework for the Albania s Improvement of the Management and Conditions of the Secondary and Local Roads Project

Resettlement Policy framework for the Albania s Improvement of the Management and Conditions of the Secondary and Local Roads Project Resettlement Policy framework for the Albania s Improvement of the Management and Conditions of the Secondary and Local Roads Project I. Introduction The overall length of the road network in Albania totals

More information

LAND ACQUISITION FOR RAILWAY INFRASTRUCTURE PROJECTS

LAND ACQUISITION FOR RAILWAY INFRASTRUCTURE PROJECTS LAND ACQUISITION FOR RAILWAY INFRASTRUCTURE PROJECTS Manish Gandhi, Nishant Doshi Manuscript History Number: IJIRAE/RS/Vol.05/Issue02/FBAE10084 DOI: 10.26562/IJIRAE.2018.FBAE10084 Received: 13, February

More information

Resettlement Planning Document

Resettlement Planning Document Resettlement Planning Document June 2012 Pakistan: Sindh Cities Improvement Investment Program (SCIP) Prepared by North Sindh Urban Services Corporation Limited for the Asian Development Bank. PFR-2 Annex-11

More information

INSTRUCTIONS TO PRIVATE DEVELOPERS

INSTRUCTIONS TO PRIVATE DEVELOPERS INSTRUCTIONS TO PRIVATE DEVELOPERS Government of Andhra Pradesh has established the A.P.Township and Infrastructure Development Corporation Limited(APTIDCO) to develop sustainable Townships and also creating

More information

REPUBLIC OF MACEDONIA

REPUBLIC OF MACEDONIA Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized REPUBLIC OF MACEDONIA Municipal Services Improvement Project (MSIP) LAND ACQUISITION

More information

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF PROJECT AFFECTED PERSONS. November 2000

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF PROJECT AFFECTED PERSONS. November 2000 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized LAO PDR: AGRICULTURAL DEVELOPMENT PROGRAM RP-59 POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT

More information

Due Diligence Report on Social Safeguards. IND: Rural Connectivity Investment Program Projects I and II

Due Diligence Report on Social Safeguards. IND: Rural Connectivity Investment Program Projects I and II Due Diligence Report on Social Safeguards December 2015 IND: Rural Connectivity Investment Program Projects I and II Rural Road Network Management Unit in Midnapur, West Bengal Prepared by Ministry of

More information

Expropriation. Recommended Policy Wordings (full): Lao National Land Policy. Context. Policy. Standard of Public Purpose

Expropriation. Recommended Policy Wordings (full): Lao National Land Policy. Context. Policy. Standard of Public Purpose Expropriation Context Following from the goal of the National Land Policy, to promote and ensure a secure land tenure system that is transparent, effective, non-discriminative, equitable and just ; it

More information

Model Regulations for Grant of Transferable Development Rights

Model Regulations for Grant of Transferable Development Rights Model Regulations for Grant of Transferable Development Rights In exercise of the powers conferred by sub-section-(2) (i) of section-56 of the Uttar Pradesh Urban Planning and Development Act, 1973...

More information

Republic of Turkey Additional Financing to Second Renewable Energy and Energy Efficiency Project Resettlement Policy Framework For TSKB and TKB

Republic of Turkey Additional Financing to Second Renewable Energy and Energy Efficiency Project Resettlement Policy Framework For TSKB and TKB Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Republic of Turkey Additional Financing to Second Renewable Energy and Energy Efficiency

More information

TIMOR-LESTE EXPROPRIATIONS LEGAL FRAMEWORK APPROVED

TIMOR-LESTE EXPROPRIATIONS LEGAL FRAMEWORK APPROVED TIMOR-LESTE EXPROPRIATIONS LEGAL FRAMEWORK APPROVED INTRODUCTION After approximately 8 years of discussions, the Timor-Leste Parliament recently approved the Country s Expropriations Law (the Law ) by

More information

6. The Screening Committee will meet every fortnight and consider all the cases received.

6. The Screening Committee will meet every fortnight and consider all the cases received. Guidelines of Mega Projects A) GENERAL PROCEDURE (MEGA PROJECTS) 1. Application for approval of mega project will be received in the office of the concerned nodal agency i.e. the Punjab Urban Development

More information

DRAFT PROTOCOL/GUIDELINES FOR VOLUNTARY VILLAGE RELOCATION IN NOTIFIED CORE/CRITICAL TIGER HABITATS OF TIGER RESERVES

DRAFT PROTOCOL/GUIDELINES FOR VOLUNTARY VILLAGE RELOCATION IN NOTIFIED CORE/CRITICAL TIGER HABITATS OF TIGER RESERVES DRAFT PROTOCOL/GUIDELINES FOR VOLUNTARY VILLAGE RELOCATION IN NOTIFIED CORE/CRITICAL TIGER HABITATS OF TIGER RESERVES PREAMBLE: The Wildlife (Protection) Act, 1972 has been amended in 2006, and a separate

More information

India: Madhya Pradesh Irrigation Efficiency Improvement Project. Subproject: Pipeline Distribution System for 500 Hectares of Command Area

India: Madhya Pradesh Irrigation Efficiency Improvement Project. Subproject: Pipeline Distribution System for 500 Hectares of Command Area Madhya Pradesh Irrigation Efficiency Improvement Project (RRP IND 45371) Resettlement Plan/Land Acquisition Plan (This document is prepared in accordance to the ADB Resettlement Plan Requirement as described

More information

THE RIGHT TO FAIR COMPENSATION AND TRANSPARENCY IN LAND ACQUISITION, REHABILITATION AND RESETTLEMENT ACT, 2013 AN OVERVIEW

THE RIGHT TO FAIR COMPENSATION AND TRANSPARENCY IN LAND ACQUISITION, REHABILITATION AND RESETTLEMENT ACT, 2013 AN OVERVIEW THE RIGHT TO FAIR COMPENSATION AND TRANSPARENCY IN LAND ACQUISITION, REHABILITATION AND RESETTLEMENT ACT, 2013 AN OVERVIEW Ministry of Rural Development Government of India September 8 th, 2013 1 Agenda

More information

How Swaziland Is Upgrading Its Slums

How Swaziland Is Upgrading Its Slums Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized How Swaziland Is Upgrading Its Slums CIVIS chose to profile this example from Swaziland

More information

Land Acquisition Rehabilitation and Resettlement Act, 2013

Land Acquisition Rehabilitation and Resettlement Act, 2013 Land Acquisition Rehabilitation and Resettlement Act, 2013 Gopal K Agarwal Member National Executive BJP Land Acquisition Issue Committee 1 History of LARR, 2013 The Primary Land Acquisition Act was the

More information

RESETTLEMENT POLICY FRAMEWORK (RPF)

RESETTLEMENT POLICY FRAMEWORK (RPF) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized JANUARY 2013 Republic of Mozambique Mozambique Climate Resilience: Transforming Hydro-Meteorological

More information

Ministry of Housing & Urban Poverty Alleviation. Ministry of Housing & Urban Poverty Alleviation Government of India. JnNURM & RAY

Ministry of Housing & Urban Poverty Alleviation. Ministry of Housing & Urban Poverty Alleviation Government of India. JnNURM & RAY Government of India JnNURM & RAY Faridabad, 16 th March 2012 1 MoHUPA: Key Functions & Programmes Formulation of Housing Policy and Programs Matters related to Human Settlements & Urban Development including

More information

LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK (LARPF)

LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK (LARPF) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PT PLN (Persero) INDONESIA POWER SECOND TRANSMISSION DEVELOPMENT PROJECT (IPTD-2) RP1232

More information

Dhaka Water Supply and Sanitation Project Resettlement Policy Framework

Dhaka Water Supply and Sanitation Project Resettlement Policy Framework 1. BACKGROUND Dhaka Water Supply and Sanitation Project Resettlement Policy Framework The Dhaka Water and Sewerage Authority (DWASA) currently supplies water to about 70% of the population of the Dhaka

More information

FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATIONS OR WILLING BUYER/WILLING SELLER PROCESSES

FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATIONS OR WILLING BUYER/WILLING SELLER PROCESSES Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SCHOOL SECTOR REFORM PROGRAM (SSRP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY

More information

Dhaka Water Supply and Sanitation Project

Dhaka Water Supply and Sanitation Project Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VOL. 1 Dhaka Water Supply and Sanitation Project Resettlement Policy Framework Dhaka

More information

S L U M R E H A B I L I T A T I O N A U T H O R I T Y M U M B A I M A H A R A S H T R A I N D I A M A R C H 2 1 ST

S L U M R E H A B I L I T A T I O N A U T H O R I T Y M U M B A I M A H A R A S H T R A I N D I A M A R C H 2 1 ST S L U M R E H A B I L I T A T I O N A U T H O R I T Y M U M B A I M A H A R A S H T R A I N D I A M A R C H 2 1 ST 2 0 1 8 BACKGROUND Since beginning of 20th century slums existed in Mumbai e.g. Dharavi,

More information

DELHI DEVELOPMENT AUTHORITY NOTIFICATION

DELHI DEVELOPMENT AUTHORITY NOTIFICATION DELHI DEVELOPMENT AUTHORITY NOTIFICATION S. O.... - In exercise of the powers conferred by sub-section (1) of Section 57 of the Delhi Development Act, 1957, the Delhi Development Authority, with the previous

More information

The Odisha Land Reforms Act, 1960 Odisha Act 16 of 1960 & The Odisha Land Reforms (General) Rules, 1965

The Odisha Land Reforms Act, 1960 Odisha Act 16 of 1960 & The Odisha Land Reforms (General) Rules, 1965 The Odisha Land Reforms Act, 1960 Odisha Act 16 of 1960 & The Odisha Land Reforms (General) Rules, 1965 1 Partition among co-sharer raiyats (Section 19) 1) Partition of a holding among co-sharers shall

More information

RHLF WORKSHOP The National Housing Code

RHLF WORKSHOP The National Housing Code RHLF WORKSHOP The National Housing Code Outline 1. Statutory requirements 2. Background- why a new Code 3. The structure of the new Code 4. National Housing Programmes 5. National Housing Programmes under

More information

LAND ACQUISITION FRAMEWORK

LAND ACQUISITION FRAMEWORK LAND ACQUISITION FRAMEWORK (This framework was prepared in accordance to the ADB requirements for preparing Resettlement Framework as described in the ADB Safeguards Policy Statement, 2009) Project Number:

More information

Tamil Nadu Slum Clearance Board was established in September and has been implementing various Housing, Slum Development and

Tamil Nadu Slum Clearance Board was established in September and has been implementing various Housing, Slum Development and HOUSING AND URBAN DEVELOPMENT DEPARTMENT DEMAND NO. 26 POLICY NOTE 2015-2016 2. TAMIL NADU SLUM CLEARANCE BOARD Tamil Nadu Slum Clearance Board was established in September 1970 and has been implementing

More information

DELHI DEVELOPMENT AUTHORITY OFFICE OF PR.COMMISSIONER(H,LD&CWG)

DELHI DEVELOPMENT AUTHORITY OFFICE OF PR.COMMISSIONER(H,LD&CWG) 1 DELHI DEVELOPMENT AUTHORITY OFFICE OF PR.COMMISSIONER(H,LD&CWG) Sub: Draft Slum Rehabilitation Policy based on Mumbai s Slum Rehabilitation Policy One of the major challenges that face DDA is to handle

More information

South African Council for Town and Regional Planners

South African Council for Town and Regional Planners TARIFF OF FEES South African Council for Town and Regional Planners PLEASE NOTE : THE TARIFF OF FEES WAS APPROVED BY THE COUNCIL CHAPTER 10 : TARIFF OF FEES 10.1 INTRODUCTION 10.1.1 General This tariff

More information

Kazakhstan: Proposed Moinak Electricity Transmission Project Land Acquisition Policy Framework

Kazakhstan: Proposed Moinak Electricity Transmission Project Land Acquisition Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Kazakhstan: Proposed Moinak Electricity Transmission Project Land Acquisition Policy

More information

Resettlement Compensation Framework Railway Corridor VIII - Eastern section

Resettlement Compensation Framework Railway Corridor VIII - Eastern section Republic of Macedonia February 2012 Resettlement Compensation Framework Railway Corridor VIII - Eastern section Contract No: C21196/EBSF-2010-07-101 Macedonian Railways: Feasibility Study for Corridor

More information

SUTP Peering Event

SUTP Peering Event GEF-UNDP-WB Assisted Sustainable Urban Transport Project (SUTP) INDIA SUTP Peering Event 11.11.11 Pimpri Chinchwad Municipal Corporation (PCMC) Structure of the Presentation BRTS Projects at PCMC Implementation

More information

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT, AND REHABILITATION OF DISPLACED PERSONS

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT, AND REHABILITATION OF DISPLACED PERSONS Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RP275 Socialist Republic of Vietnam Ministry of Transport and National Traffic Safety

More information

Koridori Srbije Corridor X Highway Project Land Acquisition and Resettlement Framework LARF

Koridori Srbije Corridor X Highway Project Land Acquisition and Resettlement Framework LARF Land Acquisition and Resettlement Framework LARF Issue 1 June 2018 PREPARED BY Contents List of Abbreviations 2 Glossary 3 1 Introduction 7 1.1 Principles and Objectives 12 2 Gaps Between RS Legislation

More information

Comparative Analysis of Afghanistan s Legal Framework and Involuntary Resettlement Safeguards in the ADB Safeguard Policy Statement

Comparative Analysis of Afghanistan s Legal Framework and Involuntary Resettlement Safeguards in the ADB Safeguard Policy Statement Comparative Analysis of Afghanistan s Legal Framework and Involuntary Resettlement Safeguards in the ADB Safeguard Involuntary Resettlement Safeguards Objectives: To avoid resettlement wherever possible;

More information

INSIDE RFCTLARR ACT, 2013

INSIDE RFCTLARR ACT, 2013 INSIDE RFCTLARR ACT, 2013 STATEWISE ANALYSIS OF STATE LAND ACQUISITION RULES, NOTIFICATIONS, DRAFT LAND ACQUISITION RULES, & NEW STATE LAND ACQUISITION BILLS AMIT KUMAR NATIONAL ALLIANCE OF PEOPLE S MOVEMENTS

More information

Summary: Resettlement Action Plan for the Thwake Multi- Purpose Dam-Kenya

Summary: Resettlement Action Plan for the Thwake Multi- Purpose Dam-Kenya Summary: Resettlement Action Plan for the Thwake Multi- Purpose Dam-Kenya 1. Introduction and Background The proposed Thwake water supply and sanitation Dam is a project conceived and intended to be constructed

More information

JNNURM Experience Sharing Workshop II Learning from Cities

JNNURM Experience Sharing Workshop II Learning from Cities JNNURM Experience Sharing Workshop II Learning from Cities Session 3 : Smart Cities 18 th September 2013 Venue: India International Centre, New Delhi (Organized by NIUA and the Ministry of Urban Development

More information

Briefing Paper: Allotment Law in Scotland Introduction Allotments (Scotland) Act of 1892

Briefing Paper: Allotment Law in Scotland Introduction Allotments (Scotland) Act of 1892 Disclaimer: The contents of this paper is the best understanding of the current state of Scottish law relating to allotments by a lay person who is a member of the SAGS committee. It is not intended to

More information

Decree on State Land Lease or Concession

Decree on State Land Lease or Concession Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity ~~~~~~~~~~~~~ Prime Minister s Office No. 135/PM VCC, Date 25/05/2009 Decree on State Land Lease or Concession - Pursuant

More information

Resettlement, Relief, Rehabilitation and Compensation Policy. May, Barowalias House, Khallini, Shimla ( HP)

Resettlement, Relief, Rehabilitation and Compensation Policy. May, Barowalias House, Khallini, Shimla ( HP) Resettlement, Relief, Rehabilitation and Compensation Policy May, 2011 Barowalias House, Khallini, Shimla-171 002 ( HP) 2 Index Part/Chapter No. Heading Page No. Introduction Introduction 4 Part-I Preamble,

More information

Scheme of Service. for. Housing Officers

Scheme of Service. for. Housing Officers REPUBLIC OF KENYA Scheme of Service for Housing Officers APPROVED BY THE PUBLIC SERVICE COMMISSION AND ISSUED BY THE PERMANENT SECRETARY MINISTRY OF STATE FOR PUBLIC SERVICE OFFICE OF THE PRIME MINISTER

More information

Presented by: K.Vidyadhar AMD MEPMA

Presented by: K.Vidyadhar AMD MEPMA Status of RAY in Andhra Pradesh: Issues and Challenges Presented by: K.Vidyadhar AMD MEPMA SLUM PROFILE OF ANDHRA PRADESH No. of ULBs - 173 Total Urban Population (2001 census) - 208.08 Lakhs Urban Population

More information

UNIT 7 THE LAND ACQUISITION ACT (LAA), 1894: AWARD AND COMPENSATION

UNIT 7 THE LAND ACQUISITION ACT (LAA), 1894: AWARD AND COMPENSATION UNIT 7 THE LAND ACQUISITION ACT (LAA), 1894: AWARD AND COMPENSATION Structure 7.0 Objectives 7.1 Introduction 7.2 Award by the Collector 7.3 Consequences of taking Possession Section 16 of the Act 7.3.1

More information

MADE EASY WEST BENGAL CO-OPERATIVE SOCIETIES LAW

MADE EASY WEST BENGAL CO-OPERATIVE SOCIETIES LAW MADE EASY WEST BENGAL CO-OPERATIVE SOCIETIES LAW 1. What Act and Rules are applicable in this law? The West Bengal Co-operative Societies (Amendment) Act, 2011 as well as Rules, 2011 are applicable relating

More information

Government of Gujarat Industries and Mines Department Resolution No. MIS/102014/430906/CH Sachivala ya, Gandhiagar.

Government of Gujarat Industries and Mines Department Resolution No. MIS/102014/430906/CH Sachivala ya, Gandhiagar. Scheme of assistance to MSEs For Shed and Plot developed By Private Developer Read: {1) Government of Gujarat Industries and Mines Department Resolution No. MIS/102014/430906/CH Sachivala ya, Gandhiagar.

More information

2011 Farmland Bill. The Union Government of the Republic of the Union of Myanmar Farmland Law

2011 Farmland Bill. The Union Government of the Republic of the Union of Myanmar Farmland Law 2011 Farmland Bill Note: This 2011 Farmland Bill was approved by the second regular session of the first Pyithu Hluttaw on 20 September, 2011 and passed in line with Pyithu Hluttaw Rules 159(d). The Union

More information

MASTER PLAN PROVISIONS (1st, 2nd & 3rd MASTER PLANS)

MASTER PLAN PROVISIONS (1st, 2nd & 3rd MASTER PLANS) Policy On FARM HOUSES in Delhi PLANNING MUST 6 1 MASTER PLAN PROVISIONS (1st, 2nd & 3rd MASTER PLANS) 1.1 PERMISSIBILITY As per MPD-2021, the new farm houses shall not be permitted in proposed urban extension.

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EUROPE AND CENTRAL ASIA Tajikistan Agriculture and Rural Development Global Practice IBRD/IDA Specific Investment Loan FY 2005 Seq No: 27 ARCHIVED on 01-Jun-2015 ISR19129 Implementing

More information

SLUMS IN DELHI ISSUES AND POLICY PERSPECTIVES

SLUMS IN DELHI ISSUES AND POLICY PERSPECTIVES SLUMS IN DELHI ISSUES AND POLICY PERSPECTIVES SEMINAR ON URBAN GOVERNANCE IN THE CONTEXT OF JAWAHARLAL NEHRU NATIONAL URBAN RENEWAL MISSION (JNNURM) 24th-25th November 2006, New Delhi DELHI DEVELOPMENT

More information

COUNTY GOVERNMENT OF LAMU Department of Land, Physical Planning, Infrastructure & Urban Development

COUNTY GOVERNMENT OF LAMU Department of Land, Physical Planning, Infrastructure & Urban Development 1 COUNTY GOVERNMENT OF LAMU Department of Land, Physical Planning, Infrastructure & Urban Development TERMS OF REFERENCE FOR OUTSOURCING OF CONSULTANCY SERVICES FOR SURVEY & REGULARIZATION OF KATSAIKAIKAIRU

More information

IND: National Grid Improvement Project

IND: National Grid Improvement Project Resettlement Plan (Draft) May 2011 IND: National Grid Improvement Project Prepared by Power Grid Corporation of India Ltd. for the Asian Development Bank. 1 POWERGRID CORPORATION OF INDIA LTD. (A Government

More information

SUCCESS STORY VOLUNTARY VILLAGE RELOCATION (MELGHAT TIGER RESERVE) LEGAL PROVISIONS FOR VOLUNTARY VILLAGE RELOCATION

SUCCESS STORY VOLUNTARY VILLAGE RELOCATION (MELGHAT TIGER RESERVE) LEGAL PROVISIONS FOR VOLUNTARY VILLAGE RELOCATION SUCCESS STORY VOLUNTARY VILLAGE RELOCATION (MELGHAT TIGER RESERVE) Melghat Tiger Reserve has been awarded prize under best practices for Voluntary Village Relocation 2014-15 in January 2015. The Tiger

More information

REPORT 2014/050 INTERNAL AUDIT DIVISION. Audit of United Nations Human Settlements Programme operations in Sri Lanka

REPORT 2014/050 INTERNAL AUDIT DIVISION. Audit of United Nations Human Settlements Programme operations in Sri Lanka INTERNAL AUDIT DIVISION REPORT 2014/050 Audit of United Nations Human Settlements Programme operations in Sri Lanka Overall results relating to the effective and efficient implementation of the UN-Habitat

More information

Public Inspection for the Kuala Lumpur-Singapore High Speed Rail Frequently Asked Questions (FAQ)

Public Inspection for the Kuala Lumpur-Singapore High Speed Rail Frequently Asked Questions (FAQ) Public Inspection for the Kuala Lumpur-Singapore High Speed Rail Frequently Asked Questions (FAQ) Public Inspection 1. What is the purpose of Public Inspection? The Public Inspection is a mandatory process

More information

OFFICIAL DOCUMENTS. Financing Agreement. Public Disclosure Authorized CREDIT NUMBER 6306-MD. Public Disclosure Authorized

OFFICIAL DOCUMENTS. Financing Agreement. Public Disclosure Authorized CREDIT NUMBER 6306-MD. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized OFFICIAL DOCUMENTS Financing Agreement (Land Registration and Property Valuation Project) CREDIT NUMBER 6306-MD Public Disclosure Authorized between

More information

REHABILITATION AND RESETTLEMENT PLAN

REHABILITATION AND RESETTLEMENT PLAN REHABILITATION AND RESETTLEMENT PLAN INTRODUCTION This chapter contains the resettlement plan for the potential social impact anticipated due to the proposed project. In this regard, a compatible Rehabilitation

More information

Serbia Corridor X Highway Project E-75 and E-80. Resettlement Policy Framework. Final Version June 4, 2009

Serbia Corridor X Highway Project E-75 and E-80. Resettlement Policy Framework. Final Version June 4, 2009 Public Disclosure Authorized Serbia Corridor X Highway Project E-75 and E-80 Resettlement Policy Framework RP789 rev Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

More information

INDEX. of subrecipients, VIII -2 records, VI-1, 4, 13. OMB Circular A-122, VIII- 3 certification: I-28

INDEX. of subrecipients, VIII -2 records, VI-1, 4, 13. OMB Circular A-122, VIII- 3 certification: I-28 INDEX A B Barney Frank Amendment, IV-7 accounts beneficiary characteristics (form), VI-1, 2, 19 escrow, II-2,4,7-11, 16,20 bidder s instructions, I-12 interest-bearing, II-7, 0 compliance notion, I-12

More information

R E Q U E S T F O R P R O P O S A L S

R E Q U E S T F O R P R O P O S A L S P.O. Box 3209, Houghton, 2041 Block A, Riviera Office Park, 6-10 Riviera Road, Riviera R E Q U E S T F O R P R O P O S A L S M A R K E T S U R V E Y T O I N F O R M R E S I D E N T I A L H O U S I N G

More information

In light of this objective, Global Witness is providing feedback on key sections of the 6 th draft of the national land policy:

In light of this objective, Global Witness is providing feedback on key sections of the 6 th draft of the national land policy: Summary Global Witness submission on the 6 th draft of Myanmar s draft national land policy June 2015 After a welcome extension to public participation on the 5 th draft of the national land policy, in

More information

B. Justification of project design and alternative analysis:

B. Justification of project design and alternative analysis: Social Screening and Impact Assessment for Sub Projects Code No: 3 A. Sub Project Description: Proposed Activity Town Hall Square Development Implementing Agency: Colombo Municipal Council (CMC) Sub project

More information

Social Screening and Impact Assessment for Sub Projects. B. Justification of project design and alternative analysis:

Social Screening and Impact Assessment for Sub Projects. B. Justification of project design and alternative analysis: Code No: 1.9 Social Screening and Impact Assessment for Sub Projects A. Sub Project Description: Proposed Activity Walkability and Parking Improvements Lotus Road Implementing Agency: Colombo Municipal

More information

Standard Information / Document Request List. Application for the Authority s Consent to the Merger of MPF Schemes

Standard Information / Document Request List. Application for the Authority s Consent to the Merger of MPF Schemes The applicant should note that a person who in any document given to the Authority makes a statement that the person knows to be false or misleading in a material respect, or recklessly makes a statement

More information

Chittagong Water Supply Improvement and Sanitation Project. Resettlement Policy Framework

Chittagong Water Supply Improvement and Sanitation Project. Resettlement Policy Framework Chittagong Water Supply Improvement and Sanitation Project Resettlement Policy Framework Chittagong Water Supply & Sanitation Authority Government of Bangladesh February 2010 Table of Contents 1. BACKGROUND

More information

THE UNITED REPUBLIC OF TANZANIA PRESIDENT S OFFICE REGIONAL ADMINISTRATION AND LOCAL GOVERNMENT (PO-RALG) Tanzania Strategic Cities Project (TSCP)

THE UNITED REPUBLIC OF TANZANIA PRESIDENT S OFFICE REGIONAL ADMINISTRATION AND LOCAL GOVERNMENT (PO-RALG) Tanzania Strategic Cities Project (TSCP) THE UNITED REPUBLIC OF TANZANIA PRESIDENT S OFFICE REGIONAL ADMINISTRATION AND LOCAL GOVERNMENT (PO-RALG) Tanzania Strategic Cities Project (TSCP) Resettlement Action Plan Update Report for the ARUSHA

More information

EXHIBIT LIST No Exhibit Name Page 1 P7 Compensation Presentation.pdf (P7) 2-47

EXHIBIT LIST No Exhibit Name Page 1 P7 Compensation Presentation.pdf (P7) 2-47 Reference No: HOC/10001 Petitioner: Phase 2a Teach-ins Published to Collaboration Area: Friday 23-Mar-2018 EXHIBIT LIST Page 1 of 47 No Exhibit Name Page 1 P7 Compensation Presentation.pdf (P7) 2-47 HOC/10001/0001

More information

Resettlement Policy Framework

Resettlement Policy Framework Republic of Turkey Second Renewable Energy and Energy Efficiency Project Resettlement Policy Framework Background 1. The Second Renewable Energy and Energy Efficiency Project will fund private sector investments

More information

REVIEW OF LAND MANAGEMENT PRACTICES IN URBAN GROWTH PERSPECTIVE

REVIEW OF LAND MANAGEMENT PRACTICES IN URBAN GROWTH PERSPECTIVE REVIEW OF LAND MANAGEMENT PRACTICES IN URBAN GROWTH PERSPECTIVE Akash N. Shah 1, Sejal S. Bhagat 2 P.G. Student, M.E. Town & Country Planning, SCET, Surat, Gujarat 1 Assistant Professor, Faculty of Civil

More information

UNOFFICIAL COPY OF HOUSE BILL 1272 A BILL ENTITLED

UNOFFICIAL COPY OF HOUSE BILL 1272 A BILL ENTITLED UNOFFICIAL COPY OF HOUSE BILL 1272 M4 6lr0525 By: Delegates Smigiel, Kelley, Rosenberg, and Sossi Introduced and read first time: February 10, 2006 Assigned to: Environmental Matters 1 AN ACT concerning

More information

UNRA Connecting Uganda! LA - DRBD 1

UNRA Connecting Uganda! LA - DRBD 1 UNRA Connecting Uganda! LA - DRBD 1 Presentation on Challenges Affecting Land Acquisition for Infrastructure Projects in Uganda 9 th December 2016 Presented by: Norah Njangali, Head Land Acquisition William

More information

LAND ACQUISITION BILL: THEN AND NOW

LAND ACQUISITION BILL: THEN AND NOW June 17, 2015 Land Acquisition Bill Background LAND ACQUISITION BILL: THEN AND NOW After independence, the Indian government adopted the Land Acquisition Act of 1894 (LAA 1894). However, an argument against

More information

INDIAN OVERSEAS BANK SMALL AND MEDIUM ENTERPRISES SME-6 APPLICATION FORM FOR CREDIT FACILITIES OVER Rs.10 lacs & UPTO Rs.50 lacs

INDIAN OVERSEAS BANK SMALL AND MEDIUM ENTERPRISES SME-6 APPLICATION FORM FOR CREDIT FACILITIES OVER Rs.10 lacs & UPTO Rs.50 lacs INDIAN OVERSEAS BANK SMALL AND MEDIUM ENTERPRISES APPLICATION FORM FOR CREDIT FACILITIES OVER Rs.10 lacs & UPTO Rs.50 lacs 1.1. Name of the Unit (In Block letters) 1.2. Constitution PROPRIETARY / PARTNERSHIP

More information

Indonesia: Neighborhood Upgrading and Shelter Project Phase 2

Indonesia: Neighborhood Upgrading and Shelter Project Phase 2 Resettlement Plan March 2018 Indonesia: Neighborhood Upgrading and Shelter Project Phase 2 Prepared by the City of Kendari and Directorate General of Human Settlements, Ministry of Public Works and Housing

More information