Staff Report for Committee of the Whole Meeting

Size: px
Start display at page:

Download "Staff Report for Committee of the Whole Meeting"

Transcription

1 Agenda Item 4 Staff Report for Committee of the Whole Meeting Department: Division: Environment and Infrastructure Services Asset Management Services Division Subject: Third Party Placement of Cell Towers/Antennas on Town- Owned Land and Buildings Purpose: Third party cellular providers have approached the Town of Richmond Hill requesting the placement of their equipment on Town-owned land and buildings. This report provides information and options on proceeding and outlines a potential approach to dealing with such requests. Recommendation(s): a) That the Town s Public Consultation Protocol for Radiocommunication and Broadcasting Antenna Systems be revised to specifically allow for applications by third party cellular providers to request the placement of cellular equipment on Town-owned land and/or buildings; b) That the fees for the placement of cell towers/antennas on Town-owned property as set out in staff report SREIS be approved and be included as part of the Town s Tariff of Fees by-law and reviewed on an annual basis; c) That the attached Cell Towers/Antennas on Town-Owned Property Policy (Appendix B) and Procedure (Appendix C) which sets out the application and review process for third party requests be approved; d) That the authority to review and approve applications involving Town-owned property so they may proceed through the public consultation process as set out in the Town s protocol be delegated to the Commissioner of Environment and Infrastructure Services or his or her designate and that this delegation include the authority to: 1. Establish site-specific licensing terms; and 2. Authorize the entry and execution by the Mayor and Clerk of licensing agreements for cellular equipment on Town property once approved by Industry Canada. 31

2 Page 2 Contact Person: Steve Fick, Director of Design and Construction, Extension, 3501 Pat Caron, Director of Asset Management Services, Extension 2403 David Dexter, Acting Commissioner of Corporate and Financial Services / Treasurer, Extension 3656 Andreea Adari, Assistant Town Solicitor, Extension 3820 Tricia Myatt, Manager of Policy and Intergovernmental Affairs, Extension 5463 Submitted by: "Signed version on file in the Office of the Clerk" Italo Brutto Commissioner of Environment and Infrastructure Services Approved by: "Signed version on file in the Office of the Clerk" Neil Garbe Chief Administrative Officer 32

3 Page 3 Background: The Town is being approached by third party cellular service providers with requests to locate cell towers/antennas on Town-owned property. At present, the Town does not have an explicit policy on this matter and therefore there is no direction on how requests by third party providers should be processed. However any applications of this nature would be required to follow the Town s Public Consultation Protocol for Radiocommunication and Broadcasting Antenna Systems. The purpose of this report is to provide information on the use of municipal buildings and lands by third parties for cell towers/antennas and to present options and recommendations for proceeding with third party requests. Current Third Party Arrangements The Town currently has one building with third party antennas located on it. Bell Cellular entered into an agreement in 1990, with the former owners of 225 East Beaver Creek Road (Captain Developments Ltd.), to house antennas on the roof of the building along with a 500 square foot equipment room in the basement. This lease was assigned to the Town when it became the owner of 225 East Beaver Creek and has been renewed up to November 30, Other Wireless Antennas on Town Property In order to allow for effective communications for Town operations, the Town has 4 wireless antennas located at the following Town facilities: Bayview Hill Community Centre communicates to Operations Elgin West Community Centre communicates to Operations Richmond Green communicates to Operations Operations Centre. In addition, Fire Services has an antenna on the roof of an apartment building at Yonge and Crosby (39/41 Crosby Avenue) for its purposes. There are also paging frequency towers on Fire Station 8-1 (Major Mackenzie) and micro links to Fire Station 8-1as part of the Region s Police/Fire communications link for our dispatch centre. Radiocommunications and Broadcasting Federal Jurisdiction The regulation of radiocommunications and broadcasting, including the location of cell towers/antennas is solely within federal jurisdiction. Only the Federal Ministry of Industry has authority under the Radio-Communication Act, to issue radio authorizations (i.e. what companies may offer these services), to approve each site on which antenna systems are to be installed and to approve the erection of all masts, towers and other antenna-supporting structures. 33

4 Page 4 The role of municipal governments is limited to assisting with the public consultation process and providing comment on a potential application for cell towers/antennas from a land use planning perspective. On February 5, 2014, Industry Canada changed its policy regarding public consultation requirements. The policy now requires consultation with communities for all commercial tower installations regardless of height. Council, at its March 24, 2014 meeting directed staff to report back to Council with updates to the Town s protocol that reflect these changes. Staff report SRPRS presented revisions to the Town s protocol to address the revised Industry Canada policy and other administrative/process refinements. These updates were approved by Council on June 21, Richmond Hill s Application Process In order to be effective participants in this process, Richmond Hill has a Public Consultation Protocol for Radiocommunication and Broadcasting Antenna Systems. It sets out the required public consultation process that must be followed by third party providers considering locating a cell tower/antenna in Richmond Hill. More specifically, the objectives of the Town s protocol are to: designate contacts within the Town for receiving, reviewing and providing comments to proponents constructing antenna systems; establish clear and concise proposal submission and public consultation requirements; encourage the location of new antenna systems in a manner that respects the natural features, landscapes and significant sight-lines in the Town; encourage the location of new antenna systems at desirable distances from residential and institutional uses whenever technically possible and feasible; encourage the location of new antenna systems in a manner that provides for a high level of service whenever possible and in keeping with the objectives of the Town s protocol; encourage proponents to explore alternatives such as co-location wherever possible and appropriate; and provide a forum that will inform the public as to the intentions of radiocommunication and broadcasting service providers in their community. The Town s current protocol is silent on the issue of locating communication towers/antennas on Town-owned land and buildings. However, any application, including those where a third party provider wishes to place cell towers/antennas on Town-owned land or buildings would be required to follow this established protocol. Applications under this protocol are submitted to the Planning and Regulatory Services Department for review. Applicants must participate in a pre-meeting with Town staff prior to making a submission to obtain a full understanding of the requirements of the application process. Applicants must submit a completed form which includes specific 34

5 Page 5 detail regarding the location and nature of the cell tower/antenna(s) being proposed. They must complete all public consultation required under the protocol prior to the application being considered by Council. All required fees must also be paid. Richmond Hill s application fee for cellular communications facilities is $1, as set out in the 2016 Tariff of Fees By-law. The Town reviews applications it receives against our Official Plan, Zoning By-law provisions and general land use planning matters that are applicable to the subject lands. This can include: How the antenna system s physical dimensions, including the antenna, mast and tower compare to the local surroundings; The location of the proposed antenna system on the property and its proximity to neighbouring residents; The likelihood of an area being a community-sensitive location due to a unique land use planning issue; and Whether the Transport Canada markings and lighting requirements present a unique land use planning conflict. It should be noted that the Ontario Building Code, which the Town supports through the building permit process, is not intended to regulate communications towers or antennas. However, a building permit is required: For the material alteration to a building that occurs when an antenna system is to be located on the roof of an existing building; For the construction of or material alteration to buildings associated with an antenna system; and/or For the design and construction of a ground-based antenna system structure e.g. the foundation for a structure. Any required building permit fees would be in addition to the cell tower/antenna application fees. Approach to Having Communication Towers/Antennas on Municipal Property in Other Municipalities The location of cell towers/antennas is often a controversial issue when brought before municipal Councils. The public is concerned about a range of issues including health impacts related to these facilities, environmental concerns and the impact on property values. As a result, many municipalities have adopted protocols to address the public consultation required for proponents who wish to locate these facilities in their municipalities. At the same time, municipalities are making it clear that they do not have any jurisdiction over the location of these facilities on private property as it is within federal jurisdiction. 35

6 Page 6 Public consultation under a municipal protocol may not address issues which are federally regulated such as health concerns, however, a municipality may seek clarification as to how the proponent is addressing these issues, such as how they are meeting Health Canada s public radio frequency exposure guidelines, known as Safety Code 6. Most municipalities have followed Industry Canada s Guide to Assist Land-use Authorities in Developing Antenna Siting Protocols. They have also been guided by FCM s Antenna System Siting Protocol Template. The main aspect municipalities vary in their protocols is in the area of people required to receive notice when a proposal for a cell tower/antenna is being considered. Municipalities also set out the specific nature of the notice required including appropriate wording, size of signage etc. In addition, some municipalities include in their protocols the issue of locating cell towers/antennas on municipal property or buildings. The following chart provides an overview of municipalities that have protocols and whether or not they address the issue of locating cell towers/antennas on municipal land or buildings. Table 1 Benchmarking Information on Municipal Protocols If you require an alternative format for the following table please call one of the contact persons listed in this staff report. Municipality Have General Public Consultation Protocol Application Fee Protocol Speaks to Possible Location on Municipal Property Have Standard Leasing Agreement for locating on Municipal Property (Lease Fees if known) Currently have Cell Towers / Antennas on Municipal Property (approximate number) Richmond Hill Yes $1,683 No No* Yes (6)** Aurora Yes $7,820 Yes No No+ Barrie Yes $3,020 Yes Yes Yes (1) Hamilton Yes $1,130 Yes Yes Yes (10) ($15,000 to $35,000 per year) King Township Yes $810.50# No No No Markham Yes $12,870 Yes Yes Yes (1) ($18,000 per year) Mississauga Yes $4,280 to $5,350 Yes Yes ($18,000 per year) Yes (2) 36

7 Page 7 Municipality Have General Public Consultation Protocol Application Fee Protocol Speaks to Possible Location on Municipal Property Have Standard Leasing Agreement for locating on Municipal Property (Lease Fees if known) Currently have Cell Towers / Antennas on Municipal Property (approximate number) Oakville Yes $5,332 Yes No No Vaughan Yes $7,820 Yes Yes Yes (1) ($15,000 to $25,000 per year) Ottawa Yes $2,832 No Yes Yes (30) ($18,000 to $27,000 per year) York Region Yes $2,200 Yes Yes Yes (36) $840 to $13,100 per year) * Richmond Hill has a lease agreement with Bell Cellular for the telecommunications equipment located at 225 East Beaver Creek Road. ** Number includes both equipment for Town use as well as third party equipment at East Beaver Creek Road. + The Town of Aurora has recently entered into an agreement with Bell for the installation of small cell technology. #Applicant may have to go through a site plan approval process. If it is considered simple the fee is $ More information on how other municipalities regulate cell towers on municipal property may be found in Appendix A to staff report SREIS Proposed Options for Third Party Requests to Place Equipment on Town-Owned Property: There are three options proposed for dealing with the issue of third party cell towers/antennas on Town property and facilities: Option 1 Use existing protocol for all applicants including third party applicants for towers/antennas on Town-owned land and buildings; 37

8 Page 8 Option 2 - Update existing protocol to explicitly allow third parties to apply to the Town to place on Town land or buildings; Option 3 - Update existing protocol to explicitly indicate the Town will not consider third party requests to place cell towers/antennas on Town-owned land or buildings. The following sets out the pros and cons of each of these options for consideration. Option 1. Use existing protocol for all applicants including third party applicants for towers/antennas on Town-owned land and buildings. Pros: Existing protocol is clear and understood by third party applicants. The process for third party applicants requesting to place equipment on Townowned land and buildings would be the same as all other cell tower/antenna applicants. Allows for the opportunity for potential revenues from third party telecommunications providers locating equipment on Town-owned land and buildings. Cons: By not explicitly stating cell towers/antennas may be considered on Town-owned land and buildings, revenues related to leasing this space to third parties may not be realized. Some members of the public may oppose the locating of telecommunications towers/antennas on Town-owned land and buildings as they have concerns related to the impact on people s health with respect to exposure to these structures. There is no formal Council policy on the acceptance/approval of third party requests to place equipment on Town-owned lands. Option 2. Update Richmond Hill s existing Public Consultation Protocol for Radiocommunication and Broadcasting Antenna Systems to explicitly allow proponents to apply to the Town to place telecommunications towers/antennas on Town-owned land or buildings. Pros: Having an explicit statement provides clarity for the telecommunications industry, the public and staff. Allowing third party providers with the possibility of placing telecommunications towers/antennas on Town land and buildings provides flexibility and increases the overall siting options available. Allowing third party providers to place equipment on Town-owned land or buildings may result in additional revenues. 38

9 Page 9 Cons: Having a policy that allows telecommunications towers/antennas on Town-owned land or buildings may make it difficult to refuse such a request. Some members of the public may oppose the locating of telecommunications towers/antennas on Town-owned land and buildings as they have concerns related to the impact on people s health with respect to exposure to these structures. People who oppose the locating of telecommunications towers/antennas in townowned parks and open spaces would not support this approach. Option 3. Update Richmond Hill s existing Public Consultation Protocol for Radiocommunication and Broadcasting Antenna Systems to explicitly state that the Town will not consider applications from proponents to place telecommunication towers/antennas on Town-owned land or buildings. Pros: Having a policy provides clarity for the telecommunications industry, the public and staff. People who oppose the locating of telecommunications towers/antennas on townowned land and buildings will support this approach. Cons: Revenues related to leasing space to third parties for telecommunications towers/antennas on Town-owned land and buildings will not be realized. Limiting the number of telecommunications towers/antennas located in the Town may impact service levels for members of the public in receiving cell service. Limits flexibility and may eliminate potential sites that would have limited opposition. Proposed Approach It is proposed that the Town proceed with Option 2. Update the existing protocol explicitly allowing proponents to make an application to the Town to place telecommunications towers/antennas on Town-owned land and buildings. The existing protocol allows any third party to submit an application to the Town for locating cell towers/antennas on lands not owned by the applicant. Explicitly stating that this could include Town-owned property and facilities provides clarity to potential proponents. It also results in a consistent process for all applicants. The location of cell towers/antennas continues to be a controversial issue with the public. However, the demand for cellular services for both personal and professional purposes continues to expand. In order to allow for the greatest range of options for locating cellular towers/antennas, it is proposed that Richmond Hill consider 39

10 Page 10 applications from third party providers to locate their equipment on Town-owned land and buildings. Richmond Hill currently has five Town sites with telecommunications equipment for its own purposes and one third party site. As noted on Table 1, seven of the ten municipalities benchmarked have indicated they allow such installations to ensure adequate services for their residents. Installation of this equipment on municipal property serves as a new revenue source and an opportunity to use these third party towers and antennas to house required municipal equipment. Cell Towers/Antennas on Town Owned Property Policy and Procedure In order to implement this approach, in addition to amending the Town s Public Consultation Protocol for Radiocommunication and Broadcasting Antenna Systems as noted above, it is proposed that a Cell Towers/Antennas on Town-Owned Property Policy and a Cell Towers/Antennas on Town-Owned Property Procedure be put in place to specifically address issues with respect to these applications. Both the Policy and Procedure are attached for consideration as Appendices B and C respectively, to this report. The Policy sets out the principles for reviewing these types of applications, which are consistent with our current Protocol. It also sets out at a high level, the process applications related to Town-owned property will follow to determine whether the proposed location is appropriate for the community. The Procedure sets out this process in more detail. Specifically, the Commissioner of Environment and Infrastructure Services and EIS staff will be the lead in reviewing these applications, circulating them to the appropriate comment agencies and determining whether the proposed location is suitable. If the Commissioner of Environment and Infrastructure Services determines the site is not suitable the application will not proceed. If it is considered suitable, the application will then proceed to staff in Planning and Regulatory Services, as do all other cell tower applications, for public consultation and a report back to Council for final review and approval. In order to allow the Commissioner of Environment and Infrastructure Services to process these applications, it is recommended that Council delegate authority to the Commissioner or his designate to accept and sign-off on these applications as the land owner in those instances where the Commissioner feels the location being proposed would be suitable. This does not bind Council in any way, but allows the application to proceed following the Town s protocol, so all applications are reviewed in the same manner. Council will review the application as well as the public feedback when the report on the proposed application is brought forward for consideration and decision. Telecommunications Structure Licence Agreement In those instances where the Town agrees to the placement of cell tower/antennas on Town-owned property, the third party will be required to enter into a 40

11 Page 11 Telecommunications Structure Licence Agreement which sets out all terms and conditions with respect to the licence. More specifically, the agreement would set out the term of the licence, renewal requirements, insurance that needs to be in place, colocation conditions as well as a site access protocol to define when, how and who may access Town-owned property with respect this equipment. It will also set out the fee schedule for the term of the agreement including annual increases and penalties for non-payment. It is intended that the Commissioner of Environment and Infrastructure Services or his or her designate would determine the final terms of any agreement to allow for site-specific provisions. Fees for Placement of Cell Towers/Antennas on Town-owned Property Staff recommend that the application fee for requests related to Town-owned land be the same as any other application as the overall process to be followed is the same. That fee is currently set in the 2016 Tariff of Fees By-law at $ A re-application fee of $ will be charged for any application that has been dormant for 1 year or for owner initiated modifications or revisions to an application that was previously circulated for review and comment. After reviewing the licence fees charged in a range of municipalities and based on the current fee charged to the existing third party equipment located on the main Municipal Offices at East Beaver Creek, the following fees are proposed to be included in the Tariff of Fees by-law and reviewed on an annual basis: Each cell tower structure location be charged a site fee of $25,000; and An additional charge of $1,000 per antenna on the site. In instances where the third party provider has allowed others to place their equipment on their site, with Town approval as set out in the Licensing Agreement, the co-location fees would be: 30% of the site fee (or $7500 at the current rate); and An additional charge of $1,000 per antenna. It would be up to the third party provider who has the agreement with the Town to collect and submit all fees, including those of any co-locator, on annual basis at the start of each year. All fees, site, antenna and co-location, would be increased on an annual basis by 3% per year. This is the same rate of increase currently charged to the Town s agreement for the equipment located at East Beaver Creek. Penalties for late payments would be 1.25% per month on the principal amount, the same rate charged for other late payments at the Town. 41

12 Page 12 Financial/Staffing/Other Implications: There are no direct financial implications to this report. If the Town agrees to allow third party equipment on Town-owned facilities and property there is a possibility of additional revenues to the Town through additional application fees and licensing revenues. Existing staff resources would review any additional applications that may be received if this approach is approved. The volume of applications and time required to complete the review would be monitored to determine if there were any staffing implications or a need to amend the application and licensing fees. Relationship to the Strategic Plan: Considering whether or not to allow third party providers to place telecommunications towers/antennas on Town-owned facilities and property is in keeping with Strategic Plan goal four, wise management of resources. Council and staff are responsible for meeting the needs of our community and reviewing this issue provides an opportunity to determine if moving in this direction is appropriate. Conclusion: The Town of Richmond Hill currently has a protocol in place for processing applications for the placement of telecommunications towers/antennas within the municipality. The purpose of this protocol is to set out a process for reviewing these applications including required public notice. The Town also reviews these applications to determine if there are any specific land use planning issues. It is proposed that this protocol be revised to explicitly allow third party providers to request to place telecommunications towers/antennas on Town-owned property and facilities. The process for reviewing these applications related to Town-owned property would be set out in the Cell Towers/Antennas on Town-owned Property Policy and Procedure and mirrors the process required for all other cell tower/antenna applications. To protect the Town s interests, any specific conditions would be set out in the Telecommunications Structure License Agreement. The location of cell towers/antennas continues to be a controversial issue with the public, however, the demand for cellular services for both personal and professional purposes continues to expand. The consideration of third party providers placing equipment on Town-owned property would allow for the greatest range of options for locating cellular towers/antennas in Richmond Hill. Installation of this equipment on municipal property serves to capitalize on a new revenue source and an opportunity to use these third party towers and antennas to house required municipal equipment. 42

13 Page 13 Attachments: Appendix A to SREIS Municipal Benchmarking Other Municipal Approaches to the Issue of Cell Towers on Municipal Property Appendix B to SREIS Cell Towers/Antennas on Town-Owned Property Policy Appendix C to SREIS Cell Towers/Antennas on Town-Owned Property Procedure The following attached documents may include scanned images of appendices, maps and photographs. If you require an alternative format please call one of the contact persons listed in this staff report. 43

14 Page 14 Appendix A to SREIS Municipal Benchmarking Other Municipal Approaches to the Issue of Cell Towers on Municipal Property Town of Aurora The Town of Aurora s Telecommunication Tower/Antenna Facilities Protocol explicitly allows for the consideration of Town-owned property for communications towers/antennas. It states, In selecting a site for a new tower, the following shall be considered: o The availability of Town-owned land to accommodate the proposal. o Property and/or infrastructure owned by the Town that meets the proponent s network objectives, subject to standard industry financial compensation arrangements The Town charges an application/commenting fee of $ per application. As of October 2016, the Town of Aurora does not have any telecommunications facilities on Town-owned property. In September 2016 the Town entered into an agreement with Bell to install small cell technology in the community. This will improve mobile data coverage in certain areas of the Town without the need for a traditional cellular tower. The small cell agreement with Bell is a pilot project. Staff anticipate two installations on Town property: at the Town Hall and Joint Operations Centre. City of Barrie The City of Barrie s Protocol for Consideration of Telecommunication Facilities Applications speaks to the issue of siting such facilities on City-owned lands. It states, Any request to install a facility on lands owned by the City shall be made to the City, in accordance with City policy. A formal application for approval shall be required in accordance with Section 4.0 of this protocol. The City charges a fee of $3, for any application to be considered under this protocol. The City does currently have one third party provider tower on City-owned lands. It includes communications equipment of the City along with that of the third party provider. The third party provider pays rent to use the lands and the City pays maintenance fees for its equipment on the tower. 44

15 Page 15 City of Hamilton The City of Hamilton s Telecommunication Tower and Antenna Protocol speaks to requests to install communications facilities on City-owned lands as follows: Any request to install a telecommunication facility on City-owned lands shall be reviewed in accordance with the Procedure for the Installation of Broadcasting Facilities on City of Hamilton Properties. This procedure requires any such request to be submitted to the Corporate Buildings and Real Estate Division of the Community Services Department for consideration. The proposal is provided to the ward Councillor for information and to the host department (the department under whose jurisdiction, the site falls), for review. The host department undertakes a technical review of the proposal and may require adjustments to the submission or the meeting of certain conditions in order to grant approval. Conditions could include the requirement for space on the structure for City communications equipment that may be required in the future, annual inspections and the requirement for a proponent to provide a survey of the subject location if it is to be a free standing structure. If it is determined that the site is acceptable, a licence agreement will be entered into between the proponent and the City including all required fees and conditions. This includes the proponent being responsible for all operating costs, utilities and property taxes in addition to the rent for the site. An administration fee of $1, is charged per application. When the application is on City property and an agreement to place the equipment on the City s property has been reached, a one-time administrative fee of $ is charged. The City s protocol states the one-time administrative fee plus the annual fees will be credited to the host department. It should be noted that CityHousing Hamilton also has licenses/leases for cell towers on their properties. King Township At present, King Township has a telecommunications protocol but does not have a policy for the siting of telecommunications towers/antennas on Township property or buildings. As a result they do not have a standard agreement. Applications under the protocol may have to go through a site plan approval process. The fees for a simple site plan approval are $ King Township has been approached by Rogers Communications Inc. to determine if the Township would be willing to host a tower at the Trisan Centre located at 25 Dillane Drive in Schomberg. A report to King Council on August 26, 2013 (PRC ) recommended that Council approve in principle this site. In addition, it indicated that Rogers will be undertaking soil and fill testing of the site as well as undertaking the required land use consultation process identified in the Township s Telecommunications 45

16 Page 16 Protocol. The report goes on to state that this site would improve service to this part of King and could result in annual revenues to the Township of between $18,000 to $20,000 for a twenty year period. As of October 2016, the Trisan Centre tower was not yet installed. City of Markham The City of Markham s Policy for Establishing Telecommunication Facilities includes specific provisions for proponents wishing to have a site on City-owned property. The policy states, Telecommunication facility proposals on City-owned lands/facilities will require an internal municipal review and endorsement by the Development Services Committee. In addition, lease agreements will be required to be executed as a final step in the approval process, to the satisfaction of the Chief Administrative Officer and City Solicitor. Where Public Consultation is not required, as per this policy, the City shall apply its best efforts to finalize the site plan application review process as soon as possible. Discussions with staff have indicated that they have leased space to a third party provider for a cell tower/antenna on one City facility, the Fire Hall on Birchmount Road. The lease rate is approximately $18, per year and the carrier paid a one-time signing fee of $5, Discussions to date to increase the rental rates to approximately $30,000 per site per year have been unsuccessful. A review of City documents indicates that applications for cell towers/antennas are handled under the site plan application process and have a fee of $12, per application. City of Mississauga The City of Mississauga s Telecommunication Tower/Antenna Facilities Protocol includes specific provisions for proponents wishing to have a site on City-owned property. It reads as follows, Any request to install a tower facility on lands owned by the City shall be made to the Director (Director, Development and Design Division, Planning and Building Department) (or designate). Proponents must still submit a formal request to the Land Use Authority in accordance with Section 8 of this protocol and follow the public consultation process in accordance with Section 9 of this protocol, unless the proposal meets the exclusion criteria under Section 4 of this protocol. Notwithstanding the public consultation requirements outlined in Section 9 of this protocol, the Director (or designate) may identify the need to amend the content of the public notification requirements accordingly. Discussions with staff have indicated that the City has established an internal working group to review third party requests. It is comprised of staff from impacted departments depending on the proposed location. Once staff has reviewed the submission, it is 46

17 Page 17 provided to the ward councilor for review and if there is no objection, public consultation is held. If there continues to be agreement in proceeding, the City s Realty Services group prepares a licensing agreement. Application fees for processing applications under the City s protocol were recently increased. For applications where a public information session is required, the fee is $5, If no public information session is required the fee is $4, Telecommunication tower/antenna facilities that are excluded from the requirement to submit a tower application must still apply for a notice of exclusion at a cost of $ per notice. The average annual rent per tower is $18, For companies co-locating on an existing tower, there are charges of $5, per year. Additionally, the telecommunications provider gives a one-time contribution that is used to improve the area where the tower is being located (e.g. a play structure in a nearby park). Staff indicated that there are currently two towers/antennas located on City property. One is in a right of way and one is on the Hershey Centre. Town of Oakville The Town of Oakville s Interim Radiocommunications Facilities Protocol includes the following provision with respect to locating communications towers/antennas on Townowned properties. Any request to install a radiocommunications facility on lands owned by the Town shall be made to the Manager of Realty Services, in accordance with Town policy and subject to Council approval. At present, the Town of Oakville has not been approached to have a third party cell tower/antenna on Town property. Discussions with staff indicated that Oakville s requirement that cell towers/antennas be 200 metres away from development would likely prevent any equipment being placed in Town property or buildings. If the Town did receive a request for the placement of a tower/antenna on Town property it would be reviewed by Council. If an agreement was reached, the Town would develop a standard lease agreement to address any issues. The application fee under the Town of Oakville protocol is $5, per application. City of Ottawa The City of Ottawa has a Municipal Concurrence and Public Consultation Process for Antenna Systems Policy that addresses land use issues with respect to residential as well as other types of antennas and towers. It sets out the public consultation requirements and process for submitting an application related to these antennas and towers. The policy is silent on the issue of siting towers/antennas on City-owned property. City staff has indicated that the policy was written this way as the issue of who 47

18 Page 18 owns the land should not be a factor in assessing potential land use impacts. The City charges a $2, application fee for review under this policy. There are currently approximately 30 sites with third party cell towers/antennas on Cityowned property. In many instances, City equipment is also housed on these structures. Rates charged range from $18, to $27, per year depending on the nature of the site and location. For companies co-locating on an existing tower, there are charges of $10, per year. In each instance a legal agreement is entered into with the third party. These can relate to a license of occupancy for roof top antennas, land leases or licenses of occupancy for fiber use. City of Vaughan The City of Vaughan s 2003 Protocol for Establishing Telecommunication Tower/Antenna Facilities has been under review by the City s Telecommunication Facility Siting Protocol Task Force since late In October 2016, a revised Telecommunication Facility Siting Protocol was approved by Vaughan Council. Vaughan currently has one lease agreement for a telecommunication facility on Cityowned land, and one sub-lease agreement for a facility on Infrastructure Ontario land. The City of Vaughan charges a base site plan application fee of $7, for telecommunication tower applications. The annual lease fees range from $15, to $25, Region of York The Region of York s Communications Installations on Regional Property Policy specifically deals with requests to install communications equipment on Regional property and facilities. This policy sets out a specific process to be followed by third parties interested in installing equipment. The Region also has a standard licence agreement which must be entered into and details all conditions including expenses covered by the third party, insurance requirements, security requirements etc. The Region has created Master Agreements with carrier companies that capture a series of locations in order to streamline administration. According to York Region staff as of September 30, 2016, the Region has 6 Master Agreements with 6 different carriers, covering 36 telecommunication equipment installations (note: several sites are co-locations thus containing more than one piece of telecommunications equipment). The specific providers and locations of the sites are not publicly available. In 2016, the Region anticipates approximately $760, in license revenues. The Policy requires that the annual license fees are subject to a 5% annual increase while application fees are at a fixed rate of $2, The Region s License Fees for 2016 are as set out in the chart below: 48

19 Page 19 Fee Description 2015 Fee Annual License Fee per telecommunications site $13, Annual License Fee per antenna $ Application Fee for new installations, and for modifications to existing installations $ It should be noted that Housing York Inc. enters into its own agreements and received revenues from communications towers/antennas on their facilities. These are in addition to the license agreements the Region currently has as noted above. 49

20 Page 20 Appendix B to SREIS Cell Towers/Antennas on Town- Owned Property Policy Policy Policy Name: Cell Towers/Antennas on Town-Owned Property Policy Policy Owner: Commissioner of Environment and Infrastructure Services Approved by: Council Effective Date: Draft February 21, 2017 Date of Last Revision: New Policy Review Date: Every 2 years Policy Status: New Policy Purpose: To set out Richmond Hill s policy for the review of applications by third parties to place cell towers/antennas on Town-owned property. This Policy is to be followed in advance of any application proceeding through the Town s Public Consultation Protocol for Radio-Communication and Broadcasting Antenna Systems. Policy Principles: In determining whether or not cell towers/antennas should be placed on Town-owned property the following principles should be considered: the location should respect the natural features, landscapes and significant sightlines in the Town; the location should be at desirable distances from residential and institutional uses whenever technically possible and feasible; the location should result in a high level of service for Richmond Hill; the location should allow for the ability to co-locate with other providers wherever possible; the location should not impact the provision of Town of Richmond Hill services in any way; the public consultation process set out in the Town of Richmond Hill s Public Consultation Protocol for Radio-Communication and Broadcasting Antenna Systems must be followed upon completion of a review of an application under this Policy to ensure the views of the public on a proposed application are known and considered. If it is determined that the Town property proposed to locate cell towers/antennas by a third party is not appropriate, the Town shall not allow the property to be used for this purpose. 50

21 Page 21 Definitions: For the purposes of this policy the following 13 definitions have been provided: Antennas: antennas, means device used to transmit or receive telecommunications signals. Cell Towers: cell towers, means all equipment including cell towers and related infrastructure required to provide cellular service. Commissioner: Commissioner, means the Commissioner of Environment and Infrastructure Services or his/her successor or his/her designate. Council: Council, means the Council of the Town of Richmond Hill. Designated Municipal Contact: Designated Municipal Contact, means the Commissioner of Planning and Regulatory Services or his/her successor or his/her designate, who is responsible for receiving, reviewing and processing submissions for cell towers/antennas under the Town of Richmond Hill s Public Consultation Protocol for Radio-Communication and Broadcasting Antenna Systems. Licensing Agreement: licensing agreement, means an agreement entered into between a third party provider and the Town once the application has been approved by the CRTC. The licensing agreement sets out the obligations of the third party provider including any fees, terms and conditions as determined by the Town for the placement of cell towers/antennas on Town-owned property. Municipality: municipality, means the Town of Richmond Hill. Policy: Policy, means the Cell Towers/Antennas on Town-owned Property Policy. 51

22 Page 22 Procedure: Procedure, means the Cell Towers/Antennas on Town-owned Property Procedure. Proponent: Proponent, means any third party provider or other proponent applying to place cell towers/antennas on Town-owned property. Protocol: Protocol, means the Town of Richmond Hill s Public Consultation Protocol for Radio- Communication and Broadcasting Antenna Systems. Third Party Provider: third party provider, means any cellular service provider or other proponent requesting cell towers/antennas be placed on town-owned property. Town-Owned Property: Town-owned property, means any land or facilities owned by the municipality. Scope: This Policy applies to all applications by third party providers interested in locating cell towers/antennas on Town-owned property. Policy The Town of Richmond Hill may receive requests from third party providers to place cell towers/antennas on Town-owned property. These applications will be reviewed to ensure the needs of the Town, community and cellular service providers are considered. More specifically, any third party wishing to place cell towers/antennas on Town-owned property must complete a Richmond Hill Radio-Communication and Broadcasting Antenna Systems Public Application Form and attend a pre-consultation meeting with the Planning and Regulatory Services Department to ensure all required materials have been provided. Planning and Regulatory Services staff will then provide the application to the Commissioner of Environment and Infrastructure Services who will review the application to determine: if the proposed location is in keeping with the Policy Principles identified in this Policy; 52

23 Page 23 what impact the proposed location would have on the Town s ability to provide services today and in the future; what conditions and terms may be required if the Town were agreeable to locating cell tower/antenna equipment on Town property that would be included in a draft licensing agreement; and ensuring any application, once reviewed by the Commissioner, proceeds through the Town s Public Consultation Protocol for Radio-Communication and Broadcasting Antenna Systems before any agreement is completed. As part of this process, the Commissioner will consult with all relevant Departments at the Town and any other related agencies to obtain feedback on a request. Full details on the process to be followed are set out in the Cell Towers/Antennas on Town-Owned Property Procedure. In addition, the Commissioner will provide the third party provider with a standard licensing agreement which the third party will be required to enter into with the Town if it is agreed that the location proposed is suitable. The licensing agreement will set out the responsibilities of the third party and all required fees and conditions. It should be noted that all building permits, other approvals, costs and liabilities related to the location of such equipment on Town-owned property are the responsibility of the third party. If after completing the review, the Commissioner feels that the proposed location of third party cell towers/antennas on a specific town-owned property is supportable, and the third party agrees with the terms set out in the licensing agreement, the Commissioner will sign the third party s application as the land owner under the Town s Radio- Communication and Broadcasting Antenna Systems Public Consultation Application Form so it may be submitted to the Designated Municipal Contact for review under the Protocol. Sign-off by the Commissioner does not bind the Council in any way, it allows the application to proceed through the public consultation process. If after completing the public consultation required under the Town s Radio- Communication and Broadcasting Antenna Systems Public Consultation Protocol, Council has no objections, the CRTC will be notified of the Town s position. Once the Town is notified that the CRTC has approved the application, the licensing agreement will be finalized and signed off by all appropriate parties. The Commissioner is responsible for the review and potential renewal of any licensing agreements. Construction of any cell tower/antenna system must be completed within three years of the completion of the public consultation undertaken with respect to the application. If construction is not complete at that time, the third party is required to reapply to the Town for further consideration of the request. It is recognized that the final decision for the approval of locating cell towers/antennas rests with Industry Canada under the Radio-Communication Act. 53

24 Page 24 Roles and Responsibilities: Commissioner of Environment and Infrastructure Services Receive and review all requests for the placement of third party cell towers/antennas on Town-owned property. Consult with all relevant Town Departments and other agencies in the review of third party requests for the placement of cell towers/antennas on Town-owned property. Development and maintenance of licensing agreements entered into by the Town and third parties for the location of third party cell towers/antennas on Town-owned property. Maintain and update this Policy. Town Departments Review and provide comments on the placement of cell towers/antennas on Townowned property as requested by the Commissioner. Review and provide feedback on the Cell Towers/Antennas on Town-owned Property Policy and Procedure as required. Planning and Regulatory Services Undertake a pre-consultation meeting with a proponent and where the application relates to Town-owned property, direct the application to the Commissioner of Environment and Infrastructure for review as set out in the Cell Towers/Antennas on Town-owned Property Procedure. Process applications signed by the Commissioner of Environment and Infrastructure Services through the public consultation process of the Town s Protocol. ELT Review and approve the Cell Towers/Antennas on Town-owned Property Policy and Procedure. Ensure appropriate staff are aware of the Policy and Procedure and support its application. Legal Services Provide support to the Commissioner in the development and maintenance of any licensing agreements related to this Policy. Council Review and approve the Cell Towers/Antennas on Town-owned Property Policy. 54

25 Page 25 Consider any cell tower/antenna applications brought before Council under the Town s Public Consultation Protocol for Radio-Communication and Broadcasting Antenna Systems and submit comments to the CRTC. Related Documents: Town of Richmond Hill Public Consultation Protocol for Radio-Communication and Broadcasting Antenna Systems Town of Richmond Hill Radio-Communication and Broadcasting Antenna Systems Public Consultation Application Form Cell Towers/Antennas on Town-owned Property Procedure 55

Staff Report for Council Public Meeting

Staff Report for Council Public Meeting Agenda Item 3.1 a Staff Report for Council Public Meeting Date of Meeting: October 25, 2017 Report Number: SRPRS.17.161 Department: Division: Subject: Planning and Regulatory Services Development Planning

More information

Staff Report for Committee of the Whole Meeting

Staff Report for Committee of the Whole Meeting Agenda Item 5 Staff Report for Committee of the Whole Meeting Department: Division: Planning and Regulatory Services Development Planning Subject: Request for Comments Site Plan Application - Whitehorn

More information

Telecommunications Development Permit Application Package

Telecommunications Development Permit Application Package Telecommunications Development Permit Application Package POLICY POL#308 Title: Policy Guidelines to Evaluate Commercial Communications Facilities Legal References: Radio Communication Act Municipal Government

More information

Staff Report for Committee of the Whole Meeting

Staff Report for Committee of the Whole Meeting Agenda Item 8 Staff Report for Committee of the Whole Meeting Department: Division: Planning and Regulatory Services Development Planning Subject: Request for Approval - Draft Plan of Condominium The Oak

More information

Council Public Meeting

Council Public Meeting Agenda 3.1 a Council Public Meeting Department: Division: Subject: Planning and Regulatory Services Development Planning Request for Comments Zoning By-law Amendment and Draft Plan of Subdivision Applications

More information

Staff Report for Council Public Meeting

Staff Report for Council Public Meeting Agenda Item 3.3 Staff Report for Council Public Meeting Date of Meeting: September 27, 2017 Report Number: SRPRS.17.134 Department: Division: Subject: Planning and Regulatory Services Development Planning

More information

Staff Report for Council Public Meeting

Staff Report for Council Public Meeting Agenda Item 3.3 a Staff Report for Council Public Meeting Date of Meeting: February 7, 2018 Report Number: SRPRS.18.022 Department: Division: Subject: Planning and Regulatory Services Development Planning

More information

Staff Report for Council Public Meeting

Staff Report for Council Public Meeting Agenda Item 3.1 a Staff Report for Council Public Meeting Date of Meeting: April 5, 2017 Report Number: SRPRS.17.043 Department: Division: Subject: Planning and Regulatory Services Development Planning

More information

Staff Report for Council Public Meeting

Staff Report for Council Public Meeting Agenda Item 3.3 a Staff Report for Council Public Meeting Date of Meeting: April 11, 2018 Report Number: SRPRS.18.087 Department: Division: Subject: Planning and Regulatory Services Development Planning

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF DECEMBER 11, 2012

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF DECEMBER 11, 2012 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF DECEMBER 11, 2012 Item 1, Report No. 51, of the Committee of the Whole (Working Session), which was adopted without amendment by the Council of the

More information

PLACEMENT OF SECURITY HUTS ON CITY OWNED LAND

PLACEMENT OF SECURITY HUTS ON CITY OWNED LAND PLACEMENT OF SECURITY HUTS ON CITY OWNED LAND Policy No: 17957 Approved by Council 29 May 2014 C 39/05/14 Contents 1. Definitions 2. Problem Statement 3. Desired Outcomes 4. Strategic Intent 5. Role Players

More information

Staff Report for Council Public Meeting

Staff Report for Council Public Meeting Agenda Item 3.2 a Staff Report for Council Public Meeting Department: Division: Planning and Regulatory Services Development Planning Subject: Request for Comments Draft Plan of Subdivision - Elm Carrville

More information

18 Sale and Other Disposition of Regional Lands Policy

18 Sale and Other Disposition of Regional Lands Policy Clause 18 in Report No. 7 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on April 19, 2018. 18 Sale and Other Disposition

More information

Agenda The District of Sooke Committee of the Whole Meeting Monday, June 19, 7:00 PM Council Chamber 2225 Otter Point Road Sooke, BC

Agenda The District of Sooke Committee of the Whole Meeting Monday, June 19, 7:00 PM Council Chamber 2225 Otter Point Road Sooke, BC Agenda The District of Sooke Committee of the Whole Meeting Monday, June 19, 2017 @ 7:00 PM Council Chamber 2225 Otter Point Road Sooke, BC Please note: The Open Portion of this meeting may be webcast

More information

5. Responsibilities. City Council

5. Responsibilities. City Council Policy Name: Disposition of Real Property Administrator: Manager of Real Estate & Land Development Approval Date: August 12, 2014 Effective Date: August 12, 2014 Next Review Date: August 2019 Approval

More information

REPORT Peel Living. ~ecember 16,2010 REPORT TITLE: TWIN PINES REVIEW FROM: Mwarigha MS., General Manager, Peel Living RECOIMIMENDATION

REPORT Peel Living. ~ecember 16,2010 REPORT TITLE: TWIN PINES REVIEW FROM: Mwarigha MS., General Manager, Peel Living RECOIMIMENDATION REPORT Peel Living DATE: ~ecember 16,2010 REPORT TITLE: FROM: Mwarigha MS., General Manager, Peel Living RECOIMIMENDATION That staff review the request by the Cedar Grove Residents' Community Corporation

More information

CITY OF HAMILTON. PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Economic Development Division

CITY OF HAMILTON. PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Economic Development Division CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Economic Development Division TO: Mayor and Members General Issues Committee WARD(S) AFFECTED: WARD 11 COMMITTEE DATE: May 2, 2012 SUBJECT/REPORT

More information

4. Disclosures of Pecuniary Interest and General Nature Thereof. 5.1 Council Public Meeting C#20-16 held June 8, 2016

4. Disclosures of Pecuniary Interest and General Nature Thereof. 5.1 Council Public Meeting C#20-16 held June 8, 2016 RICHMOND HILL () t'l 0 0 0 0 ' ' 0 (J INCORPORATE D 187 3 0 COUNCIL MEETING C#24-16 Monday, 7:30p.m. RichmondHill.ca Chambers Richmond Hill Town Hall 225 East Beaver Creek Road Richmond Hill, Ontario His

More information

Audit of City Lease Administration

Audit of City Lease Administration July 22, 2009 Audit of City Lease Administration Sam M. McCall, Ph.D., CPA, CGFM, CIA, CGAP City Auditor HIGHLIGHTS Highlights of City Auditor Report #0917, a report to the City Commission and City management

More information

2 REVISED NOBLETON COMMUNITY DEVELOPMENT CHARGE OPTIONS AND PREPAID DEVELOPMENT CHARGE CREDIT AGREEMENT PRINCIPLES TOWNSHIP OF KING

2 REVISED NOBLETON COMMUNITY DEVELOPMENT CHARGE OPTIONS AND PREPAID DEVELOPMENT CHARGE CREDIT AGREEMENT PRINCIPLES TOWNSHIP OF KING 2 REVISED NOBLETON COMMUNITY DEVELOPMENT CHARGE OPTIONS AND PREPAID DEVELOPMENT CHARGE CREDIT AGREEMENT PRINCIPLES TOWNSHIP OF KING The Finance and Administration Committee recommends the adoption of the

More information

PROTOCOL FOR ESTABLISHING TELECOMMUNICATION FACILITIES

PROTOCOL FOR ESTABLISHING TELECOMMUNICATION FACILITIES Town of Mono Procedure ESTABLISHING TELECOMMUNICATION FACILITIES PLANNING DEPARTMENT Approved by Council: December 20, 2002 by Resolution #9-23-2002 PROTOCOL FOR ESTABLISHING TELECOMMUNICATION FACILITIES

More information

PLANNING PRIMER: SESSION 2 MARCH 2013

PLANNING PRIMER: SESSION 2 MARCH 2013 PLANNING PRIMER: SESSION 2 MARCH 2013 DEVELOPMENT APPLICATIONS Agenda 6 Most Common Applications Pre-consultation + Submission Notification + Review Break Time Issue Resolution + Report Writing The Decision

More information

Request for Approval Proposed Expansion to the Puccini Drive Neighbourhood Residential Infill Study Town File D (SRPRS.17.

Request for Approval Proposed Expansion to the Puccini Drive Neighbourhood Residential Infill Study Town File D (SRPRS.17. Staff Report for Committee of the Whole Meeting Department: Division: Subject: Planning and Regulatory Services Development Planning Request for Approval Proposed Expansion to the Puccini Drive Neighbourhood

More information

Parkland Encroachment Policy and Procedures (All Wards)

Parkland Encroachment Policy and Procedures (All Wards) Parkland Encroachment Policy and Procedures (All Wards) The Economic Development and Parks Committee recommends the adoption of the report (June 26, 2000) from the Commissioner of Economic Development,

More information

TOWN OF AURORA SUBDIVISION AND/OR CONDOMINIUM APPLICATION GUIDE

TOWN OF AURORA SUBDIVISION AND/OR CONDOMINIUM APPLICATION GUIDE PLANNING & DEVELOPMENT SERVICES Phone: 905-727-3123 ext. 4226 Fax 905-726-4736 Email: planning@aurora.ca Town of Aurora 100 John West Way Box 1000, Aurora, ON L4G 6J1 www.aurora.ca February, 2014 TABLE

More information

REPORT TITLE: AFFORDABLE HOUSING PROGRAM EXTENSION (2009): VILLA POLONIA AND CHANGES TO ROYAL CANADIAN LEGION PROJECT

REPORT TITLE: AFFORDABLE HOUSING PROGRAM EXTENSION (2009): VILLA POLONIA AND CHANGES TO ROYAL CANADIAN LEGION PROJECT C Region d Ped Wonkiq fon you REPORT General Committee DATE: May 12,2010 REPORT TITLE: AFFORDABLE HOUSING PROGRAM EXTENSION (2009): VILLA POLONIA AND CHANGES TO ROYAL CANADIAN LEGION PROJECT FROM: Janet

More information

Cannabis Retail Rezoning Policy

Cannabis Retail Rezoning Policy Cannabis Retail Rezoning Policy September 2018 1.0 PURPOSE 1.1 This purpose of this policy is to provide transparency, clarity and flexibility in the City of New Westminster s consideration of rezoning

More information

City of Kitchener & Region of Waterloo. Brownfields Financial Incentive Program: Joint Tax Increment Grant (TIG) Application Package

City of Kitchener & Region of Waterloo. Brownfields Financial Incentive Program: Joint Tax Increment Grant (TIG) Application Package City of & Region of Waterloo : (TIG) Application Package April 2016 1 Table of Contents A. Guidelines for Applicants... 3 A1. Eligibility Criteria... 3 A2. Terms of Financial Assistance... 4 A3. Eligible

More information

SUBJECT: Character Area Studies and Site Plan Approval for Low Density Residential Areas. Community and Corporate Services Committee

SUBJECT: Character Area Studies and Site Plan Approval for Low Density Residential Areas. Community and Corporate Services Committee Page 1 of Report PB-70-16 SUBJECT: Character Area Studies and Site Plan Approval for Low Density Residential Areas TO: FROM: Community and Corporate Services Committee Planning and Building Department

More information

ADOPTION OF 2018/19 FEES AND CHARGES FOR REGULATORY SERVICES

ADOPTION OF 2018/19 FEES AND CHARGES FOR REGULATORY SERVICES RS-18-498 Mayor and Councillors COUNCIL 31 MAY 2018 Meeting Status: Public Purpose of Report: For Decision ADOPTION OF 2018/19 FEES AND CHARGES FOR REGULATORY SERVICES PURPOSE OF REPORT 1 This report proposes

More information

Committee of Adjustment Agenda

Committee of Adjustment Agenda Committee of Adjustment Agenda Hearing Date: May 25, 2017 Time: 7:00 p.m. Location: 225 East Beaver Creek Road, 1 st Floor (Council Chambers) Call to Order Disclosure of Pecuniary Interest Requests for

More information

CITY OF VAUGHAN POLICY AND PROCEDURES FOR DEALING WITH CONTAMINATED OR POTENTIALLY CONTAMINATED SITES

CITY OF VAUGHAN POLICY AND PROCEDURES FOR DEALING WITH CONTAMINATED OR POTENTIALLY CONTAMINATED SITES CITY OF VAUGHAN POLICY AND PROCEDURES FOR DEALING WITH CONTAMINATED OR POTENTIALLY CONTAMINATED SITES MAY 2001 This Report should be read in conjunction with the City of Vaughan BACKGROUND REPORT ON POLICY

More information

CITY CLERK. (City Council on April 14, 15 and 16, 2003, adopted this Clause, without amendment.)

CITY CLERK. (City Council on April 14, 15 and 16, 2003, adopted this Clause, without amendment.) CITY CLERK Clause embodied in Report No. 3 of the, as adopted by the Council of the City of Toronto at its meeting held on April 14, 15 and 16, 2003. 16 Final Report Combined Application TF CMB 2002 0004

More information

Applicant: ONTARIO INC. JOE NUOSCI. MARK MCCONVILLE Humphries Planning Group Inc.

Applicant: ONTARIO INC. JOE NUOSCI. MARK MCCONVILLE Humphries Planning Group Inc. File: A043/15 Item # 20 Ward #1 Applicant: 2109179 ONTARIO INC. JOE NUOSCI Address: Agent: 3501 King-Vaughan Road, Woodbridge MARK MCCONVILLE Humphries Planning Group Inc. Adjournment Status: Notes: Comments/Conditions:

More information

INTERROGATORIES OF THE CORPORATION THE COUNTY OF MIDDLESEX

INTERROGATORIES OF THE CORPORATION THE COUNTY OF MIDDLESEX EB-2013-0040 EB-2013-0041 ONTARIO ENERGY BOARD THE MATTER OF the Ontario Energy Board Act 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Bornish Wind, LP, Kerwood Wind, Inc.

More information

TOWNSHIP OF LANARK HIGHLANDS POLICY FOR THE STOPPING UP, CLOSURE AND SALE OF ROADS POLICY STATEMENT

TOWNSHIP OF LANARK HIGHLANDS POLICY FOR THE STOPPING UP, CLOSURE AND SALE OF ROADS POLICY STATEMENT TOWNSHIP OF LANARK HIGHLANDS POLICY FOR THE STOPPING UP, CLOSURE AND SALE OF ROADS Approval Date: POLICY STATEMENT The Municipal Act provides that the Council of a municipality may pass by-laws for stopping

More information

A Guide to the Municipal Planning Process in Saskatchewan

A Guide to the Municipal Planning Process in Saskatchewan A Guide to the Municipal Planning Process in Saskatchewan A look at the municipal development permit and the subdivision approval process in Saskatchewan May 2008 Prepared By: Community Planning Branch

More information

Final Audit Follow-Up

Final Audit Follow-Up Final Audit Follow-Up As of September 30, 2010 Sam M. McCall, Ph.D., CPA, CGFM, CIA, CGAP City Auditor Audit of City Lease Administration (Report #0917, Issued July 22, 2009) Report #1107 February 3, 2011

More information

CITY CLERK. Consolidated Clause in Policy and Finance Committee Report 7, which was considered by City Council on July 19, 20, 21 and 26, 2005.

CITY CLERK. Consolidated Clause in Policy and Finance Committee Report 7, which was considered by City Council on July 19, 20, 21 and 26, 2005. CITY CLERK Consolidated Clause in Report 7, which was considered by City Council on July 19, 20, 21 and 26, 2005. 3 Regent Park Revitalization - Financial Strategy (Ward 28) City Council on July 19, 20,

More information

TRCA Administrative Fee Schedule for ENVIRONMENTAL ASSESSMENT and INFRASTRUCTURE PERMITTING SERVICES IMPLEMENTATION GUIDELINES May 2014

TRCA Administrative Fee Schedule for ENVIRONMENTAL ASSESSMENT and INFRASTRUCTURE PERMITTING SERVICES IMPLEMENTATION GUIDELINES May 2014 IMPLEMENTATION GUIDELINES Introduction TRCA s Fee Schedule for Environmental Assessment and Permitting Services was adopted by Resolution #A237/13 of the Authority Board on January 31, 2014. The Fee Schedule

More information

Audit Follow-Up. Audit of City Lease Administration (Report #0917, Issued July 22, 2009) Report #1019 June 16, As of March 31, 2010.

Audit Follow-Up. Audit of City Lease Administration (Report #0917, Issued July 22, 2009) Report #1019 June 16, As of March 31, 2010. Audit Follow-Up As of March 31, 2010 Sam M. McCall, Ph.D., CPA, CGFM, CIA, CGAP City Auditor Audit of City Lease Administration (Report #0917, Issued July 22, 2009) Report #1019 June 16, 2010 Summary Sixteen

More information

Standard for the acquisition of land under the Public Works Act 1981 LINZS15005

Standard for the acquisition of land under the Public Works Act 1981 LINZS15005 Standard for the acquisition of land under the Public Works Act 1981 LINZS15005 Version date: 20 February 2014 Table of contents Terms and definitions... 5 Foreword... 6 Introduction... 6 Purpose... 6

More information

Our Focus: Your Future A HERITAGE PROPERTY TAX RELIEF PROGRAM FOR THE TOWN OF FORT ERIE

Our Focus: Your Future A HERITAGE PROPERTY TAX RELIEF PROGRAM FOR THE TOWN OF FORT ERIE Town of Fort Erie Our Focus: Your Future Corporate Services Prepared for Council-in-Committee Report No. CS-24-07 Agenda Date September 17,2007 File No. 230517 Subject A HERITAGE PROPERTY TAX RELIEF PROGRAM

More information

CITY CLERK. Provincial Policy for Secondary Uses in Hydro Corridors

CITY CLERK. Provincial Policy for Secondary Uses in Hydro Corridors CITY CLERK Clause embodied in Report No. 3 of the, as adopted by the Council of the City of Toronto at its meeting held on April 14, 15 and 16, 2003. 4 Provincial Policy for Secondary Uses in Hydro Corridors

More information

PART 2.7 DEPARTMENT OF GOVERNMENT SERVICES REAL ESTATE REGULATION

PART 2.7 DEPARTMENT OF GOVERNMENT SERVICES REAL ESTATE REGULATION PART 2.7 DEPARTMENT OF GOVERNMENT SERVICES REAL ESTATE REGULATION Executive Summary The Financial Services Regulation Division (the Division) within the Consumer and Commercial Affairs Branch of the Department

More information

CITY CLERK. (City Council at its Special Meeting held on July 30, 31 and August 1, 2002, adopted this Clause, without amendment.)

CITY CLERK. (City Council at its Special Meeting held on July 30, 31 and August 1, 2002, adopted this Clause, without amendment.) CITY CLERK Clause embodied in Report No. 7 of the, as adopted by the Council of the City of Toronto at its Special Meeting held on July 30, 31 and August 1, 2002. 19 Affordable and Transitional Housing

More information

Corporate Report. 2. That the Interim Control By-law prohibit within the Low Density Residential Suburban Neighbourhood (R1) zone, the following:

Corporate Report. 2. That the Interim Control By-law prohibit within the Low Density Residential Suburban Neighbourhood (R1) zone, the following: Corporate Report Report from Planning and Building Services, Planning Services Date of Report: November 23,2016 Date of Meeting: December 5, 2016 Report Number: PBS-330-2016 File: 60.35.2.1 Subject: Interim

More information

Assets, Regeneration & Growth Committee 17 March Development of new affordable homes by Barnet Homes Registered Provider ( Opendoor Homes )

Assets, Regeneration & Growth Committee 17 March Development of new affordable homes by Barnet Homes Registered Provider ( Opendoor Homes ) Assets, Regeneration & Growth Committee 17 March 2016 Title Report of Wards Status Urgent Key Enclosures Officer Contact Details Development of new affordable homes by Barnet Homes Registered Provider

More information

Zoning Richmond Road Zonage - 971, chemin Richmond. Recommendations. (File: OZP1999/004) Ward/Quartier OT1 % Britannia%Richmond Action/Exécution

Zoning Richmond Road Zonage - 971, chemin Richmond. Recommendations. (File: OZP1999/004) Ward/Quartier OT1 % Britannia%Richmond Action/Exécution July 8, 1999 Department of Urban Planning and Public Works Planning and Economic Development Committee / Comité de l urbanisme et de l expansion économique City Council / Conseil municipal Zoning - 971

More information

TOWN OF PARRY SOUND NOTICE POLICY

TOWN OF PARRY SOUND NOTICE POLICY rtuiuuon lull. -&L/a TOWN OF PARRY SOUND NOTICE POLICY I. Purpose The Municipal Act, 2001, as amended, Section 238(2.1) requires that the procedural by-law provide for public Notice of meetings. The Municipal

More information

THE CORPORATION OF THE MUNICIPALITY OF HIGHLANDS EAST BY-LAW

THE CORPORATION OF THE MUNICIPALITY OF HIGHLANDS EAST BY-LAW THE CORPORATION OF THE MUNICIPALITY OF HIGHLANDS EAST BY-LAW 2007-53 BEING A BY-LAW TO ESTABLISH A TOWNSHIP POLICY ON THE USE OF UNOPENED ROAD ALLOWANCES WHEREAS, Section 44 of the Municipal Act, 2001,

More information

CITY OF HAMILTON. PUBLIC WORKS DEPARTMENT Operation and Waste Management Division

CITY OF HAMILTON. PUBLIC WORKS DEPARTMENT Operation and Waste Management Division CITY OF HAMILTON PUBLIC WORKS DEPARTMENT Operation and Waste Management Division TO: Chair and Members Public Works Committee WARD(S) AFFECTED: CITY WIDE COMMITTEE DATE: April 4, 2011 SUBJECT/REPORT NO:

More information

Proponent s Guide to the NCC s Federal Land Use, Design and Transaction Approvals Process

Proponent s Guide to the NCC s Federal Land Use, Design and Transaction Approvals Process Proponent s Guide to the NCC s Federal Land Use, Design and Transaction Approvals Process September 2018 Table of Contents 1. INTRODUCTION 3 2. WHAT IS THE NATIONAL CAPITAL REGION? 4 3. WHEN IS APPROVAL

More information

2019 Development Charges By-law Update Project Plan

2019 Development Charges By-law Update Project Plan Staff Report for Committee of the Whole Meeting Department: Division: Subject: Corporate and Financial Services Financial Services 2019 Development Charges By-law Update Project Plan Purpose: This report

More information

Mutual Exchanges Policy

Mutual Exchanges Policy Mutual Exchanges Policy December 2017 Website 1 1.0 Introduction 1.1 CHS Group is committed to offering mobility opportunities to its tenants who wish to move. Mutual exchanges provide them with an opportunity

More information

Community Planning Permits Technical Report

Community Planning Permits Technical Report April 2017 Community Planning Permits Technical Report Town of Ajax Consultant Team Gladki Planning Associates This page left intentionally blank Contents 1. Introduction 1 1.1 Why is the Town Looking

More information

1.3. The Policy is based on the City of London governing principles:

1.3. The Policy is based on the City of London governing principles: Real Property Acquisition Policy Policy Name: Real Property Acquisition Policy Legislative History: Enacted September 19, 2017 (By-law No. CPOL.-188-440); Amended July 24, 2018 (By-law No. CPOL.-188(a)-447)

More information

LAND USE AND ZONING OVERVIEW

LAND USE AND ZONING OVERVIEW OVERVIEW OF PLANNING POLICIES LAND USE AND ZONING OVERVIEW The Minneapolis Plan for Sustainable Growth and Other Adopted Plans Community Planning and Economic Development Development Services Division

More information

4700 Highway 7, Woodbridge. ROSEMARIE HUMPHRIES Humphries Planning Group Inc.

4700 Highway 7, Woodbridge. ROSEMARIE HUMPHRIES Humphries Planning Group Inc. File: B035/13 Item # 6 Ward #2 Applicant: VISTA PARC LIMITED Address: Agent: 4700 Highway 7, Woodbridge ROSEMARIE HUMPHRIES Humphries Planning Group Inc. Adjournment Status: Notes: NO PLANNING COMMENTS

More information

The Corporation of the Township of Otonabee-South Monaghan. Public Meeting - Section 34 Zoning By-law Amendment. Monday, January 8, 6:00pm

The Corporation of the Township of Otonabee-South Monaghan. Public Meeting - Section 34 Zoning By-law Amendment. Monday, January 8, 6:00pm The Corporation of the Township of Otonabee-South Monaghan Public Meeting - Section 34 Zoning By-law Amendment Monday, January 8, 2018 @ 6:00pm Council Chambers, Municipal Office - Keene Page 1. CALL TO

More information

261 Queens Quay East Application to remove the Holding Symbol from the Zoning By-law Final Report

261 Queens Quay East Application to remove the Holding Symbol from the Zoning By-law Final Report STAFF REPORT ACTION REQUIRED 261 Queens Quay East Application to remove the Holding Symbol from the Zoning By-law Final Report Date: May 25, 2017 To: From: Wards: Reference Number: Toronto and East York

More information

Committee of the Whole Meeting CW# Monday, February 6, :30 p.m. Minutes. RichmondHill.ca

Committee of the Whole Meeting CW# Monday, February 6, :30 p.m. Minutes. RichmondHill.ca Committee of the Whole Meeting Monday, 4:30 p.m. RichmondHill.ca Council Chambers Richmond Hill Town Hall 225 East Beaver Creek Road Richmond Hill, Ontario Chair Karen Cilevitz Ward 5 Councillor Minutes

More information

70 Melbourne Ave Application to amend the (former) City of Toronto Zoning By-law Parkdale Pilot Project Final Report

70 Melbourne Ave Application to amend the (former) City of Toronto Zoning By-law Parkdale Pilot Project Final Report STAFF REPORT ACTION REQUIRED 70 Melbourne Ave Application to amend the (former) City of Toronto Zoning By-law 438-86 Parkdale Pilot Project Final Report Date: March 27, 2009 To: From: Wards: Reference

More information

Council Policy. Council policy title: Lease and Licence Policy 2018

Council Policy. Council policy title: Lease and Licence Policy 2018 Council Policy Council policy title: Lease and Licence Policy 2018 Council policy owner: Adopted by: 1. Policy intent Council is the custodian of land and building assets that support a wide range of community

More information

MODEL WIRELESS TELECOMMUNICATIONS ORDINANCE for Siting of "Small Cell" Telecommunication Infrastructure in Public Rights-Of-Way

MODEL WIRELESS TELECOMMUNICATIONS ORDINANCE for Siting of Small Cell Telecommunication Infrastructure in Public Rights-Of-Way MODEL WIRELESS TELECOMMUNICATIONS ORDINANCE for Siting of "Small Cell" Telecommunication Infrastructure in Public Rights-Of-Way This document is intended for use by towns and villages that have existing

More information

Results of the Request for Proposals to Develop and Operate Affordable Rental Housing at 200 Madison Avenue

Results of the Request for Proposals to Develop and Operate Affordable Rental Housing at 200 Madison Avenue AH3.4 STAFF REPORT ACTION REQUIRED Results of the Request for Proposals to Develop and Operate Affordable Rental Housing at 200 Madison Avenue Date: August 19, 2015 To: From: Wards: Reference Number: Affordable

More information

EX28.8 REPORT FOR ACTION. Community Space Tenancy Policy SUMMARY

EX28.8 REPORT FOR ACTION. Community Space Tenancy Policy SUMMARY EX28.8 REPORT FOR ACTION Community Space Tenancy Policy Date: October 6, 2017 To: Executive Committee From: Deputy City Manager, Internal Corporate Services, and Executive Director, Social Development,

More information

Number Same. This document provides procedural direction to implement Policy PL Onshore Windpower Development on Crown Land.

Number Same. This document provides procedural direction to implement Policy PL Onshore Windpower Development on Crown Land. Ministry of Natural Resources Subject ONSHORE WINDPOWER DEVELOPMENT ON CROWN LAND NON-COMPETITIVE APPLICATION Procedure PL 4.10.04 Compiled by Renewable Energy Program Replaces Directive Title Same Number

More information

Consolidated as of May 14, 2012

Consolidated as of May 14, 2012 THE CORPORATION OF THE CITY OF WHITE ROCK BYLAW NO. 1869 A Bylaw to amend the provisions of City of White Rock Planning Procedures Bylaw, 2009, No. 1869. DISCLAIMER: THIS BYLAW IS CONSOLIDATED FOR CONVENIENCE

More information

Provincial Announcements on Social Housing Devolution

Provincial Announcements on Social Housing Devolution Provincial Announcements on Social Housing Devolution (City Council at its regular meeting held on October 3, 4 and 5, 2000, and its Special Meetings held on October 6, 2000, October 10 and 11, 2000, and

More information

DISTRICT ADMINISTRATIVE RULE

DISTRICT ADMINISTRATIVE RULE DISTRICT ADMINISTRATIVE RULE FEAE-R Construction on District Property Funded by Others 7/25/16 GSBA Reference: FEAE (Community Involvement in Project Planning) RATIONALE/OBJECTIVE: The Cobb County School

More information

ADMINISTRATIVE GUIDANCE

ADMINISTRATIVE GUIDANCE 11 ADMINISTRATIVE GUIDANCE ON CONTAMINATED SITES Effective date: April 1, 2013 Version 1.1 May 2013 Expectations and Requirements for Contaminant Migration Introduction This guidance focusses on the ministry

More information

OWNERS, BUSINESSES AND TENANTS PARTICIPATION AND RE-ENTRY RULES

OWNERS, BUSINESSES AND TENANTS PARTICIPATION AND RE-ENTRY RULES OWNERS, BUSINESSES AND TENANTS PARTICIPATION AND RE-ENTRY RULES Prepared For The CALIMESA REDEVELOPMENT PROJECT NO. 2 THE CALIMESA REDEVELOPMENT AGENCY July 2010 OWNERS, BUSINESSES AND TENANTS PARTICIPATION

More information

Subject. Date: 2016/10/25. Originator s file: CD.06.AFF. Chair and Members of Planning and Development Committee

Subject. Date: 2016/10/25. Originator s file: CD.06.AFF. Chair and Members of Planning and Development Committee Date: 2016/10/25 Originator s file: To: Chair and Members of Planning and Development Committee CD.06.AFF From: Edward R. Sajecki, Commissioner of Planning and Building Meeting date: 2016/11/14 Subject

More information

Below Market Rate Program Administrator. Request for Proposals

Below Market Rate Program Administrator. Request for Proposals Below Market Rate Program Administrator Request for Proposals Housing and Community Development 7351 Rosanna Street Gilroy, CA 95020 Page 1 Introduction and Important Dates The City of Gilroy is seeking

More information

4. INTRODUCTION AND OVERVIEW PUBLIC MEETINGS

4. INTRODUCTION AND OVERVIEW PUBLIC MEETINGS TOWNSHIP OF CRAMAHE PUBLIC MEETING DATE: MARCH 8, 2016 TIME: PLACE: 6:45 PM COUNCIL CHAMBERS Page 1. CALL TO ORDER at 6:45 pm 2. RECORDING EQUIPMENT Members of the Public are to advise the Clerk of the

More information

Understanding the Consent Application Process

Understanding the Consent Application Process Understanding the Consent Application Process Your Step-By-Step Guide for Consent-Granting Authorities 1 2 3 4 5 6 7 8 9 10 11 Section 53 of the Planning Act ontario.ca/municipallearning Understanding

More information

PART ONE - GENERAL INFORMATION

PART ONE - GENERAL INFORMATION Corrected Date: Page 7 Date of Submittal Changed to Coincide with Submittal Date on Page 5 PART ONE - GENERAL INFORMATION A. INTRODUCTION B. Background Miami Shores Village is soliciting responses to this

More information

GM26.17 REPORT FOR ACTION

GM26.17 REPORT FOR ACTION GM26.17 REPORT FOR ACTION Transfer of 9 Madison Avenue Date: March 21, 2018 To: Government Management Committee From: Director, Real Estate Services Wards: Ward 20, Trinity Spadina SUMMARY This report

More information

Sale of 2 Bloor Street West, North-West Corner of Bloor Street and Yonge Street (Ward 23 - Midtown)

Sale of 2 Bloor Street West, North-West Corner of Bloor Street and Yonge Street (Ward 23 - Midtown) Sale of 2 Bloor Street West, North-West Corner of Bloor Street and Yonge Street (Ward 23 - Midtown) (City Council at its regular meeting held on October 3, 4 and 5, 2000, and its Special Meetings held

More information

T-MOBILE DAVID WILKINS MESSINA & HARRIS, INC.

T-MOBILE DAVID WILKINS MESSINA & HARRIS, INC. APPLICATION NUMBER 5368 A REQUEST FOR HEIGHT, SETBACK, AND BUFFER SEPARATION VARIANCES TO ALLOW THE CONSTRUCTION OF A 70 MONOPOLE TELECOMMUNICATIONS TOWER, SETBACK 6.89 FROM A LEASE PARCEL LINE, AND 6.89

More information

DEVELOPMENT APPLICATION PRE-CONSULTATION FORM

DEVELOPMENT APPLICATION PRE-CONSULTATION FORM DEVELOPMENT APPLICATION PRE-CONSULTATION FORM Meeting Date: Property Owner: Site Address: Applicant & Address Site Area: APPLICATION TYPE (check applicable applications): Local Official Plan Amendment

More information

IMPACT OF INFILL PROGRAM ON NEIGHBOURHOODS TASK FORCE AGENDA WEDNESDAY, MAY 30, :00 p.m. CHARLIE WARD ROOM, BRANTFORD CITY HALL

IMPACT OF INFILL PROGRAM ON NEIGHBOURHOODS TASK FORCE AGENDA WEDNESDAY, MAY 30, :00 p.m. CHARLIE WARD ROOM, BRANTFORD CITY HALL IMPACT OF INFILL PROGRAM ON NEIGHBOURHOODS TASK FORCE AGENDA WEDNESDAY, MAY 30, 2018 3:00 p.m. CHARLIE WARD ROOM, BRANTFORD CITY HALL ROLL CALL 1. DECLARATIONS OF CONFLICTS OF INTEREST 2. ITEMS FOR CONSIDERATION

More information

A Class Environmental Assessment for Provincial Parks and Conservation Reserves. Phase III: Submission to Ministry of the Environment

A Class Environmental Assessment for Provincial Parks and Conservation Reserves. Phase III: Submission to Ministry of the Environment A Class Environmental Assessment for Provincial Parks and Conservation Reserves Phase III: Submission to Ministry of the Environment II CLASS EA FOR PROVINCIAL PARKS AND CONSERVATION RESERVES 2001, Queen

More information

Cell Towers on Campus IS IT RIGHT FOR YOUR DISTRICT?

Cell Towers on Campus IS IT RIGHT FOR YOUR DISTRICT? Cell Towers on Campus IS IT RIGHT FOR YOUR DISTRICT? Overview Pasco County Case Study Self-management of towers Hillsborough County Case Study Management company management of towers Stake-holder engagement

More information

Planning Advisory Committee Meeting Agenda

Planning Advisory Committee Meeting Agenda Planning Advisory Committee Meeting Agenda April 24, 2018 3:00 p.m. City Board Room Pages 1. Call to Order 2. Election of Chair and Vice Chair 3. Disclosure of Pecuniary Interest 4. Reports and Communications

More information

At its 4 October 2002 meeting the Regulatory and Consents Committee resolved:

At its 4 October 2002 meeting the Regulatory and Consents Committee resolved: 1. PERIODIC DETENTION CENTRES IN THE BUSINESS 1 ZONE Officer responsible Author Environmental Services Manager Sean Elvines, DDI 941-8295 The purpose of this report is to provide an overview of the estimated

More information

THE CORPORATION OF THE TOWNSHIPSHIP OF McNAB/BRAESIDE BY-LAW NO

THE CORPORATION OF THE TOWNSHIPSHIP OF McNAB/BRAESIDE BY-LAW NO THE CORPORATION OF THE TOWNSHIPSHIP OF McNAB/BRAESIDE BY-LAW NO. 2013-50 A by-law to repeal by-law No. 98-47 and to establish a policy and procedures, including the giving of notice, governing the sale

More information

Community Occupancy Guidelines

Community Occupancy Guidelines Community Occupancy Guidelines Auckland Council July 2012 Find out more: phone 09 301 0101 or visit www.aucklandcouncil.govt.nz Contents Introduction 4 Scope 5 In scope 5 Out of scope 5 Criteria 6 Eligibility

More information

5.0 Permit Applications

5.0 Permit Applications 5.0 Permit Applications A primary objective of the Toronto and Region Conservation Authority () is to prevent the loss of life and property due to flooding and erosion. Accordingly, administers a natural

More information

Subject Mississauga Housing Strategy: Rental Housing Protection By-law File: CD.06.AFF

Subject Mississauga Housing Strategy: Rental Housing Protection By-law File: CD.06.AFF Date: 2018/05/04 To: Chair and Members of Planning and Development Committee From: Andrew Whittemore, Commissioner Planning and Building Department Originator s files: CD.06. AFF Meeting date: 2018/05/28

More information

Report of Commissioning Director, Environment. Urgent No Key No Enclosures Appendix 1 Example of licence conditions. Summary

Report of Commissioning Director, Environment. Urgent No Key No Enclosures Appendix 1 Example of licence conditions. Summary Environment Committee 24 September 2015 Title Damage to the Public Highway Caused by Development Activities Report of Commissioning Director, Environment Wards All Status Public Urgent No Key No Enclosures

More information

Edward R. Sajecki Commissioner of Planning and Building

Edward R. Sajecki Commissioner of Planning and Building Corporate Report Clerk s Files Originator s Files H-OZ 08/002 W2 DATE: November 11, 2008 TO: FROM: SUBJECT: Chair and Members of Planning and Development Committee Meeting Date: December 1, 2008 Edward

More information

Townhouse and Low-Rise Apartment Guidelines Project. Planning and Growth Management Committee. Chief Planner and Executive Director, City Planning

Townhouse and Low-Rise Apartment Guidelines Project. Planning and Growth Management Committee. Chief Planner and Executive Director, City Planning PG8.12 STAFF REPORT ACTION REQUIRED Townhouse and Low-Rise Apartment Guidelines Project Date: October 20, 2015 To: From: Wards: Reference Number: Planning and Growth Management Committee Chief Planner

More information

Request for Decision STAFF REPORT. Recommendation. Applicant: Location: Application: Proposal: Presented To: Planning Committee

Request for Decision STAFF REPORT. Recommendation. Applicant: Location: Application: Proposal: Presented To: Planning Committee Request for Decision Application for rezoning in order to permit an automotive lube shop in the southeasterly corner of the Lasalle Court Mall property, 900 Lasalle Boulevard, Sudbury - Laurentian Shield

More information

Compulsory Land Acquisition Delegations

Compulsory Land Acquisition Delegations Board Meeting 30 May 2013 Agenda item no. 10(iii) Closed Session Compulsory Land Acquisition Delegations Recommendations It is recommended that the Board: i. Receive this report; ii. Grant delegated authority

More information

10 Affordable Housing Measuring and Monitoring Guidelines

10 Affordable Housing Measuring and Monitoring Guidelines Clause 10 in Report No. 11 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on June 25, 2015. 10 Affordable Housing Measuring

More information

ELECTORAL AREA DIRECTORS REPORT

ELECTORAL AREA DIRECTORS REPORT ELECTORAL AREA DIRECTORS REPORT TO: Chair and Directors File No: BL 641-2 SUBJECT: All Electoral Areas: Subdivision Servicing Amendment (CSRD) Bylaw No. 641-2 DESCRIPTION: Report from Dan Passmore, Senior

More information

THE TOWN OF BANCROFT REQUEST FOR PROPOSAL (RFP) COMMERCIAL REAL ESTATE BROKERAGE SERVICES

THE TOWN OF BANCROFT REQUEST FOR PROPOSAL (RFP) COMMERCIAL REAL ESTATE BROKERAGE SERVICES THE TOWN OF BANCROFT REQUEST FOR PROPOSAL (RFP) 2016-02 COMMERCIAL REAL ESTATE BROKERAGE SERVICES Proposals will be received at the Town of Bancroft Municipal Office, 24 Flint Ave., Bancroft, Ontario,

More information

PUBLIC MEETING AGENDA THE CORPORATION OF THE MUNICIPALITY OF SIOUX LOOKOUT MUNICIPAL OFFICE COUNCIL CHAMBERS AUGUST 21, 2014, 5:30 P.M.

PUBLIC MEETING AGENDA THE CORPORATION OF THE MUNICIPALITY OF SIOUX LOOKOUT MUNICIPAL OFFICE COUNCIL CHAMBERS AUGUST 21, 2014, 5:30 P.M. PUBLIC MEETING AGENDA THE CORPORATION OF THE MUNICIPALITY OF SIOUX LOOKOUT MUNICIPAL OFFICE COUNCIL CHAMBERS AUGUST 21, 214, 5:3 P.M. 1. Call Meeting to Order 2. Agenda a) Introduction of Amendments to

More information