1 FINAL ASSESSMENT 2014 DAY 1 Wednesday, 17 th September, 2014

2 NOTES TO CANDIDATES A. Headings to questions are for ease of identification only and do not form part of the questions. B. The number of main questions is as follows: (1) First day Questions with varying marks but the aggregate mark is 50 marks (2) Second day Questions with varying marks but the aggregate mark is 50 marks DAY 1 Question No. 1 Cost Estimate 22 marks Question No. 2 Bulk-checking of Quantities 13 marks Question No. 3 Editing of BQ Descriptions 10 marks Question No. 4 Insurance 5 marks marks C. All Main Questions and Sub-Questions are compulsory. D. The total mark of each day s paper is 50. The passing mark of each day s paper is 55% of the total mark of that paper. Candidates who have passed both days papers will be considered as having passed the APC Practice Problems. E. Refer also to INSTRUCTIONS TO CANDIDATES, which were issued to you in advance. Page 2

3 FIVE COMMON CRITERIA Candidates are expected to demonstrate a reasonable level of professional competence against five common criteria outlined below, sufficient for the Assessors to answer the question Would I employ the Candidate to work as a qualified Quantity Surveyor with the ability to resolve problems in a professional manner? However, it should be recognized that not all these criteria apply to every problem, nor do they carry equal weight. 1. Perception: A full understanding of the problem posed, evidenced by a response to each item in the question. Candidates should also show foresight by anticipating additional problems not specifically mentioned. 2. Imagination: The assumption of essential supplementary information so as to provide a full response; also the use of imaginary telephone inquiries, quotations, notes, etc. 3. Technical skills: The correct use of measurement principles, prices, discount factors, etc. The use of appropriate short cuts, rounding off of figures, etc. to suit the scale of the problem. The provision of analysis to a depth appropriate to the stage reached by Candidates and the time constraints imposed on Candidates. 4. Judgement: The provision of sound professional advice indicative of professional knowledge and experience gained by Candidates. The advice should be firm and unhesitating, except where suitable caveats are essential. 5. Communication: Free of ambiguity, with clear expression and an absence of irrelevant or inappropriate technical details, particularly when provided to a lay Employer. Correct syntax and good professional style in letters and reports are important. Candidates should clearly convey their interpretations and proposals. Page 3

4 DAY 1 17 th SEPTEMBER 2014 Page 4

5 Question No. 1 Cost Estimate Venus Ltd. is the Owner of Sunny Serviced Apartments ( SSA ) at Tsim Sha Tsui. Since SSA was built 20 years ago, it is the first time that major renovation works are to be carried out to SSA. During the project meeting yesterday, Venus requested the design consultant team to review whether it would be feasible to incorporate the following additional work as part of the renovation works: a. Adding an additional passenger lift travelling between G/F and 2/F of the podium; b. Upgrading the podium facades by replacing all existing wall tiles (approximate facade area 1,000 m2); and c. Upgrading the interior of all existing 150 no. apartment units (100 no. studio units, 40 no. 1-bedroom suites and 10 no. 2-bedroom suites). Venus is particularly interested in knowing the rough indication of costs of the additional work. The Architect has confirmed that it is technically feasible to carry out the additional work without the need for major MEP equipment upgrading and foundation modification. As per Venus requirement, the serviced apartments and all common areas will still be in operation during the course of the renovation works. Page 5

6 You are the Project QS of the QS consultant in charge of the renovation works and you have just received the below from Venus financial controller. Please respond to his request. Dear Project QS, a. Additional passenger lift and b. Upgrading the podium facade by replacing the existing external wall tiles Please find attached draft cost estimates prepared by our project coordinator for your comment. Feel free to point out any potential deficiencies in the draft estimates of items (a) and (b). Please also provide your cost estimate of item (b). c. Upgrading of the interior of all existing 150 no. apartment units (100 no. studio units, 40 no. 1-bedroom suites and 10 no. 2-bedroom suites). Please use the fitting out costs of a new-build serviced apartment (also owned by our company) in the same district as the base because we would like to negotiate with the same Contractor to carry out the renovation works of the apartment units. Attached are the elemental costs analysed from the fitting out contract for that serviced apartment. That serviced apartment has 100 no. 1-bedroom suites. The size, layout and fitting out standard of the 1-bedroom unit are the same as those in SSA. The fitting out contract was tendered 3 years ago. I also attach the floor plan of each room type of SSA for your reference. The Architect has advised that the associated building services installation and their ancillary builder s works are being investigated and are not required to be included in the cost estimate at this stage. Please provide your cost estimate of item (c). I also need to know the renovation cost per room type for my financial modelling. Please prepare your reply for discussion later today. Regards, Donny Chan Financial Controller [22 Marks] Page 6

7 Attachment to Question No. 1 DRAFT COST ESTIMATE (a) Adding an additional passenger lift between G/F and 2/F HK$ Supply and install a passenger lift (based on lift contractor's recent quotation HK$1,000,000 for similar) 1,000,000 (b) Podium facades upgrading by replacing all existing wall tiles (approximate total façade area 1,000 m2) Supply and install new external wall tiles (supply only $300/m2 as suggested by the Architect) 1,000m2 x $360/m2 = 360,000 (c) Fitting out costs of 1-bedroom suites of another serviced apartment HK$/unit Doors 20,000 Partitions 20,000 Floor finishes Bedroom, living room 40,000 Floor finishes Bathroom 10,000 Wall finishes Bedroom, living room 30,000 Wall finishes Bathroom 30,000 Ceiling finishes Bedroom, living room 25,000 Ceiling finishes Bathroom 5,000 Kitchen cabinet 25,000 Furniture 60,000 Sanitary fittings 30,000 Lighting fittings 20,000 AV equipment 30,000 Miscellaneous e.g. curtains, signage, decoration, etc. 20,000 Preliminaries 37,000 Total HK$ 402,000 Page 7

8 Attachment to Question No. 1 (Cont d) Page 8

9 Attachment to Question No. 1 (Cont d) Page 9

10 Attachment to Question No. 1 (Cont d) Page 10

11 Question No. 2 Bulk-checking of Quantities You are a Consultant QS working on a building project. You are asked to carry out a bulk-check exercise on measurement prepared by your assistants. A copy of the draft BQ is attached (Attachment A ). You should provide all working details in your answer and summarize your findings in a logical manner. (Note: You are not required to identify any missing items, if any, from Attachment A ) [13 marks] Page 11

12 Page 12

13 Page 13

14 Page 14

15 Page 15

16 Page 16

17 Question No. 3 Editing of BQ Descriptions You are a Consultant QS currently preparing the tender documents for piling works. Your assistant QS, John, has completed a draft BQ (Attachment B ) for your review and editing. You should write notes of comments with reasons for his attention. You are not required to make any adjustment to the quantities. Background information: Type of piles No. of Piles Type of tests Method of measurement : 1.50 m diameter bored piles without lining or bell-out : 10 No. piles : Pending Engineer s specification and items to be added later : In accordance with HKSMM4 Section V(e) Bored Piles (a copy of Pages 33 to 35 is attached) [10 marks] Page 17

18 Page 18

19 Page 19

20 Page 20

21 Page 21

22 Question No. 4 Insurances You are the Consultant QS for a residential building project. The tender documents for the Superstructure Main Contract is scheduled to be issued to the tenderers by the end of the coming month and you have just submitted a draft of the front parts of the tender documents to the Project Manager for comment. It comes to the Project Manager s attention that the Contractors All Risks Insurance of the Works and the Third Party Liability Insurance to be procured by the Contractor as required by your proposed front parts are for different Periods of Insurance. The former is to last till 14 days after Substantial Completion while the latter is to last till the issuance of the Defects Rectification Certificate. The Project Manager doubted if such a variance in the required Periods of Insurances is appropriate. He is thinking of extending the Period of Insurance of the Contractors All Risks Insurance of the Works to cover the entire Defects Liability Period. You are required to draft a letter to advise the Project Manager in this connection. [5 marks] Page 22

How to Read a Real Estate Appraisal Report

How to Read a Real Estate Appraisal Report How to Read a Real Estate Appraisal Report Much of the private, corporate and public wealth of the world consists of real estate. The magnitude of this fundamental resource creates a need for informed

More information

Request for Proposal(RFP) for Planning Services

Request for Proposal(RFP) for Planning Services Request for Proposal(RFP) for Planning Services Issued December 18, 2017 Population (2010 census) 2,454 Area.55 square miles No. of Households 731 SUMMARY The Charter Township of Royal Oak requests proposals

More information

Building Control (Amendment) Regulations 2013 Legal implications. Deirdre Ní Fhloinn Consultant Reddy Charlton Solicitors

Building Control (Amendment) Regulations 2013 Legal implications. Deirdre Ní Fhloinn Consultant Reddy Charlton Solicitors Building Control (Amendment) Regulations 2013 Legal implications Deirdre Ní Fhloinn Consultant Reddy Charlton Solicitors Outline Have the industry s concerns in relation to the draft Regulations of 2012

More information

Application Form for Alterations. Property Address: Daytime tel No: Evening tel no: Mobile: address(es): Alternative mailing address:

Application Form for Alterations. Property Address: Daytime tel No: Evening tel no: Mobile:  address(es): Alternative mailing address: Application Form for Alterations Name Property Address: Daytime tel No: Evening tel no: Mobile: E-mail address(es): Alternative mailing address: Details of all proposed contractors, consultants, architects

More information

Rawlinson House, Lewisham, London SE13 5EL

Rawlinson House, Lewisham, London SE13 5EL Rawlinson House, Lewisham, London SE13 5EL Client: Lewisham Homes Old Town Hall Catford London SE6 4RU Date: 18 February 2016 Job No: 2540-MA-N-RP-0001-D00 Martin Arnold Ltd 4 Gunnery Terrace The Royal

More information

Release: 1. CPPDSM4011A List property for lease

Release: 1. CPPDSM4011A List property for lease Release: 1 CPPDSM4011A List property for lease CPPDSM4011A List property for lease Modification History Not Applicable Unit Descriptor Unit descriptor This unit of competency specifies the outcomes required

More information

Real Estate Institute of Tasmania Assignment Cover Sheet

Real Estate Institute of Tasmania Assignment Cover Sheet Real Estate Institute of Tasmania Assignment Cover Sheet Unit (s) of competency CPPDSM4080A Work in the Real Estate Industry Name of candidate Attempt number Method of Delivery Attended class Date of Training:

More information

BOUNDARY LINE ADJUSTMENT APPLICATION

BOUNDARY LINE ADJUSTMENT APPLICATION OFFICE 518.747.5212 --------------FAX 518.747.2493 (Clerk s Office Use Only) BOUNDARY LINE ADJUSTMENT APPLICATION APPLICATION NO: DATE : FEE PAID: Requirements, Fees and Instructions (Please use dark blue

More information

Arbitration and Dispute Resolution

Arbitration and Dispute Resolution and Dispute Resolution Page 1 of 7 Why Attend Effective dispute resolution helps minimize the costs and adverse effects to relationships that often arise from the commercial disputes. If informal negotiation

More information

PPP Project Realization Roadmap for Public Entities. based on the PPP Act and the Act on Concessions for Construction Work or Services

PPP Project Realization Roadmap for Public Entities. based on the PPP Act and the Act on Concessions for Construction Work or Services PPP Project Realization Roadmap for Public Entities based on the PPP Act and the Act on Concessions for Construction Work or Services 1. Identification of needs and possibilities to fulfil them by means

More information

NZQF NQ Ref 1731 Version 3 Page 1 of 9. This qualification has been reviewed. The last date to meet the requirements is 31 December 2019.

NZQF NQ Ref 1731 Version 3 Page 1 of 9. This qualification has been reviewed. The last date to meet the requirements is 31 December 2019. NZQF NQ Ref 1731 Version 3 Page 1 of 9 National Diploma in Real Estate (Agent) (Level 5) Level 5 Credits 170 This qualification has been reviewed. The last date to meet the requirements is 31 December

More information

GUIDANCE FOR LANDOWNERS AND OCCUPIERS ON CONTRIBUTIONS TOWARDS PROFESSIONAL COSTS

GUIDANCE FOR LANDOWNERS AND OCCUPIERS ON CONTRIBUTIONS TOWARDS PROFESSIONAL COSTS GUIDANCE FOR LANDOWNERS AND OCCUPIERS ON CONTRIBUTIONS TOWARDS PROFESSIONAL COSTS In order to meet the growing demand for reliable electricity supplies, we at Northern Powergrid are continually working

More information

The Bonus Zoning policy will be applied in conjunction with the Implementation policies contained within the Official Plan.

The Bonus Zoning policy will be applied in conjunction with the Implementation policies contained within the Official Plan. Policy Title: Bonus Zoning Policy Number: 07-03-01 Section: Community Development Subsection: Planning Tools Effective Date: September 26, 2012 Last Review Date: Approved by: Council Owner Division/Contact:

More information

Village of Bremen 9090 Marietta Road, SE Bremen, Ohio (740)

Village of Bremen 9090 Marietta Road, SE Bremen, Ohio (740) Village of Bremen 9090 Marietta Road, SE Bremen, Ohio 43107 (740) 569-4788 http://bremenvillage.com The Village of Bremen, Ohio invites applications for the position of: Zoning Inspector Part-Time, Permanent

More information

REQUEST FOR PROPOSALS Professional Engineering Services for Lift Station In the Rural Municipality of Wellington

REQUEST FOR PROPOSALS Professional Engineering Services for Lift Station In the Rural Municipality of Wellington REQUEST FOR PROPOSALS Professional Engineering Services for Lift Station In the Rural Municipality of Wellington Issue Date: March 2, 2018 Prepared By: Rural Municipality of Wellington Wellington, PEI

More information

ToR Tender Specifications

ToR Tender Specifications ToR Tender Specifications Feasibility Study of an office and housing Development Project in Nairobi for the Delegation of the European Union to Kenya December 2013 TERMS OF REFERENCE 1. BACKGROUND INFORMATION...

More information

City of Altamonte Springs Developer s Guide

City of Altamonte Springs Developer s Guide Section 6 SUBDIVISION PLAN & PLAT REVIEW PROCESS This section contains information, applications, and checklists related to the subdivision development plan and plat review process in Altamonte Springs.

More information

SUBJECT: Unacceptable Assignment Conditions in Real Property Appraisal Assignments

SUBJECT: Unacceptable Assignment Conditions in Real Property Appraisal Assignments 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 ADVISORY OPINION 19 (AO-19) This communication by the Appraisal Standards Board (ASB) does not establish new standards

More information

ANNEX DEFINITION OF THE METHODOLOGY TO BE FOLLOWED BY THE SERVICES OF THE COMMISSION FOR PROSPECTING AND NEGOTIATING FOR BUILDINGS

ANNEX DEFINITION OF THE METHODOLOGY TO BE FOLLOWED BY THE SERVICES OF THE COMMISSION FOR PROSPECTING AND NEGOTIATING FOR BUILDINGS ANNEX DEFINITION OF THE METHODOLOGY TO BE FOLLOWED BY THE SERVICES OF THE COMMISSION FOR PROSPECTING AND NEGOTIATING FOR BUILDINGS 1. INTRODUCTION In its communication on buildings policy 1 the Commission

More information

PERRY CITY UTAH REQUEST FOR PROPOSALS REAL ESTATE BROKER SERVICES

PERRY CITY UTAH REQUEST FOR PROPOSALS REAL ESTATE BROKER SERVICES PERRY CITY UTAH REQUEST FOR PROPOSALS REAL ESTATE BROKER SERVICES Overview The City of Perry, Utah is hereby requesting proposals from qualified, real estate brokers to assist with the sale of approximately

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS Administration & Planning Planning & Real Estate 200 McCracken Power Plant 2003 Millikin Road Columbus, OH 43210 ap.osu.edu pare.osu.edu REQUEST FOR PROPOSALS TO GROUND LEASE UNIVERSITY PROPERTY IN ORDER

More information

Town Centre Community Improvement Plan

Town Centre Community Improvement Plan 2012 Town Centre Community Improvement Plan City of Greater Sudbury Growth and Development Department 1.0 PLAN BACKGROUND 1.1 Introduction The following Community Improvement Plan (CIP) has been prepared

More information

PLANNED UNIT DEVELOPMENTS (Ordinance No.: 3036, 12/3/07; Repealed & Replaced by Ordinance No.: 4166, 10/15/12)

PLANNED UNIT DEVELOPMENTS (Ordinance No.: 3036, 12/3/07; Repealed & Replaced by Ordinance No.: 4166, 10/15/12) 159.62 PLANNED UNIT DEVELOPMENTS (Ordinance No.: 3036, 12/3/07; Repealed & Replaced by Ordinance No.: 4166, 10/15/12) A. PURPOSE 1. General. The Planned Unit Development (PUD) approach provides the flexibility

More information

Building Control (Amendment) Regulations. ASFP Ireland Fire Protection Module At FMI Conference & Exhibition. RDS 6 March 2013

Building Control (Amendment) Regulations. ASFP Ireland Fire Protection Module At FMI Conference & Exhibition. RDS 6 March 2013 1 Building Control (Amendment) Regulations ASFP Ireland Fire Protection Module At FMI Conference & Exhibition RDS 6 March 2013 Martin Vaughan, Assistant Principal Architecture/Building Standards Department

More information

ACADEMIC COURSE SYLLABUS

ACADEMIC COURSE SYLLABUS ACADEMIC COURSE SYLLABUS COURSE TITLE: REAL PROPERTY COURSE NUMBER: LAW 702A Real Property - 1st semester of two-semester course* LAW 702B Real Property - 2nd semester of two-semester course* * Denotes

More information

ANNUAL GENERAL MEETING MINUTES STRATA PLAN LMS 2946 SEASTAR 1003 PACIFIC STREET, VANCOUVER, BC

ANNUAL GENERAL MEETING MINUTES STRATA PLAN LMS 2946 SEASTAR 1003 PACIFIC STREET, VANCOUVER, BC ANNUAL GENERAL MEETING MINUTES STRATA PLAN LMS 2946 SEASTAR 1003 PACIFIC STREET, VANCOUVER, BC HELD: Wednesday, May 6, 2009 PLACE: Amenity Room, Seastar, 1003 Pacific Street, Vancouver, BC REGISTRATION

More information

MARKET VALUE BASIS OF VALUATION

MARKET VALUE BASIS OF VALUATION 4.2 INTERNATIONAL VALUATION STANDARDS 1 MARKET VALUE BASIS OF VALUATION This Standard should be read in the context of the background material and implementation guidance contained in General Valuation

More information

REAL ESTATE OFFICER, SENIOR REAL ESTATE OFFICER, 1961

REAL ESTATE OFFICER, SENIOR REAL ESTATE OFFICER, 1961 REAL ESTATE OFFICER, 1960 8-16-91 SENIOR REAL ESTATE OFFICER, 1961 Summary of Duties: Negotiates for the acquisition, rental, or sale of real property rights; makes valuation appraisals of real property

More information

THE TOWN OF BANCROFT REQUEST FOR PROPOSAL (RFP) COMMERCIAL REAL ESTATE BROKERAGE SERVICES

THE TOWN OF BANCROFT REQUEST FOR PROPOSAL (RFP) COMMERCIAL REAL ESTATE BROKERAGE SERVICES THE TOWN OF BANCROFT REQUEST FOR PROPOSAL (RFP) 2016-02 COMMERCIAL REAL ESTATE BROKERAGE SERVICES Proposals will be received at the Town of Bancroft Municipal Office, 24 Flint Ave., Bancroft, Ontario,

More information

TERMS OF ENGAGEMENT FOR A VALUATION REPORT FOR SALE BY MORTGAGEE (Institute of Surveyors of Trinidad and Tobago Version )

TERMS OF ENGAGEMENT FOR A VALUATION REPORT FOR SALE BY MORTGAGEE (Institute of Surveyors of Trinidad and Tobago Version ) Name of Firm: 1. The Requirement for Terms of Engagement: Terms of Engagement are mandatory according to the RICS Valuation Professional Standards (Global) July 2017 and the International Valuation Standards

More information

MOTION NO. M Roosevelt Station Central TOD Site Property Transaction Agreements PROPOSED ACTION

MOTION NO. M Roosevelt Station Central TOD Site Property Transaction Agreements PROPOSED ACTION MOTION NO. M2017-143 Roosevelt Station Central TOD Site Property Transaction Agreements MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Board 11/16/2017 Final Action Don Billen, Acting Executive Director,

More information

Chapter 11. Competitive Negotiation: Procedure

Chapter 11. Competitive Negotiation: Procedure Chapter 11. Competitive Negotiation: Procedure Summary This chapter provides an overview of the procedure for procuring goods and services using the competitive negotiation procedure. The competitive negotiation

More information

APES 225 Valuation Services

APES 225 Valuation Services APES 225 Valuation Services [Supersedes APES 225 Valuation Services issued in July 2008 and revised in May 2012] Prepared and issued by Accounting Professional & Ethical Standards Board Limited REVISED:

More information

Charter Township of Shelby Parks & Recreation Department Request for Proposals Gene Shepherd Park Splash Pad

Charter Township of Shelby Parks & Recreation Department Request for Proposals Gene Shepherd Park Splash Pad Charter Township of Shelby Parks & Recreation Department Request for Proposals Gene Shepherd Park Splash Pad The Charter Township of Shelby is issuing this Request for Proposal (RFP) for construction of

More information

capability statement

capability statement company profile Aalto Projects Pty Ltd. is a Development Management Service company that offers the unique background knowledge and skill of Property Law with hands on experience in Property Development.

More information

First Exposure Draft of proposed changes for the edition of the Uniform Standards of Professional Appraisal Practice

First Exposure Draft of proposed changes for the edition of the Uniform Standards of Professional Appraisal Practice TO: FROM: RE: All Interested Parties Sandra Guilfoil, Chair Appraisal Standards Board First Exposure Draft of proposed changes for the 2012-13 edition of the Uniform Standards of Professional Appraisal

More information

CHECKLIST FOR CUSTOMER Lawful Lot Determination

CHECKLIST FOR CUSTOMER Lawful Lot Determination CHECKLIST FOR CUSTOMER Lawful Lot Determination (LDO Section 10.2.1A) The following material must be submitted with a request for a lawful lot determination. Check off each item that you have included

More information

SCOTTISH EPISCOPAL CHURCH PROVINCIAL BUILDINGS ADVISORY COMMITTEE GUIDANCE ON QUINQUENNIAL BUILDING CONDITION REPORTS

SCOTTISH EPISCOPAL CHURCH PROVINCIAL BUILDINGS ADVISORY COMMITTEE GUIDANCE ON QUINQUENNIAL BUILDING CONDITION REPORTS SCOTTISH EPISCOPAL CHURCH PROVINCIAL BUILDINGS ADVISORY COMMITTEE GUIDANCE ON QUINQUENNIAL BUILDING CONDITION REPORTS This paper is issued to provide guidance to congregations (and their inspecting Architects

More information

Report on Inspection of KBL, LLP (Headquartered in New York, New York) Public Company Accounting Oversight Board

Report on Inspection of KBL, LLP (Headquartered in New York, New York) Public Company Accounting Oversight Board 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8433 www.pcaobus.org Report on 2014 (Headquartered in New York, New York) Issued by the Public Company Accounting

More information

Land rights requirements relating to assets to be installed or adopted by SEPD or SHEPD for new connections

Land rights requirements relating to assets to be installed or adopted by SEPD or SHEPD for new connections Land rights requirements relating to assets to be installed or adopted by SEPD or SHEPD for new connections Information for SEPD and SHEPD Staff, ICPs, IDNOs and connection customers v1.1 August 2016 Background

More information

Town of Bristol Rhode Island

Town of Bristol Rhode Island Town of Bristol Rhode Island Subdivision & Development Review Regulations Adopted by the Planning Board September 27, 1995 (March 2017) Formatted: Highlight Formatted: Font: 12 pt Table of Contents TABLE

More information

REQUEST FOR PROPOSAL MV COMBERMERE COMMUNITY CENTRE ACCESSIBLE LIFT SYSTEM For The Corporation of the Township of Madawaska Valley

REQUEST FOR PROPOSAL MV COMBERMERE COMMUNITY CENTRE ACCESSIBLE LIFT SYSTEM For The Corporation of the Township of Madawaska Valley REQUEST FOR PROPOSAL MV2015 05 COMBERMERE COMMUNITY CENTRE ACCESSIBLE LIFT SYSTEM For The Corporation of the Township of Madawaska Valley Proposal Closing Date and Time Friday, June 5, 2015 At 3:00 p.m.

More information

THE APPRAISAL OF REAL ESTATE 3 RD CANADIAN EDITION BUSI 330

THE APPRAISAL OF REAL ESTATE 3 RD CANADIAN EDITION BUSI 330 THE APPRAISAL OF REAL ESTATE 3 RD CANADIAN EDITION BUSI 330 REVIEW NOTES by CHUCK DUNN CHAPTER 17 Copyright 2010 by the Real Estate Division and Chuck Dunn. All rights reserved CHAPTER 17- THE COST APPROACH

More information

DIOCESE OF CHELMSFORD DIOCESAN ADVISORY COMMITTEE

DIOCESE OF CHELMSFORD DIOCESAN ADVISORY COMMITTEE DIOCESE OF CHELMSFORD DIOCESAN ADVISORY COMMITTEE APPOINTMENT OF ARCHITECTS OR SURVEYORS AND THEIR FEES GUIDELINES TO ASSIST PARISHES Updated January 2018 APPOINTMENT OF ARCHITECTS OR SURVEYORS AND THEIR

More information

Collateral Valuation Matters Improving Client s Appraisal Experience with Farmer Mac

Collateral Valuation Matters Improving Client s Appraisal Experience with Farmer Mac Collateral Valuation Matters Improving Client s Appraisal Experience with Farmer Mac April 20, 2017 Collateral Valuation Matters Workshop Objectives Aid lenders/clients in how to obtain acceptable appraisals

More information

VALUATION REPORTING REVISED Introduction. 3.0 Definitions. 2.0 Scope INTERNATIONAL VALUATION STANDARDS 3

VALUATION REPORTING REVISED Introduction. 3.0 Definitions. 2.0 Scope INTERNATIONAL VALUATION STANDARDS 3 4.4 INTERNATIONAL VALUATION STANDARDS 3 REVISED 2007 1.0 Introduction 1.1 The critical importance of a Valuation Report, the final step in the valuation process, lies in communicating the value conclusion

More information

GUIDE FOR VARIANCE AND PLANNING ADVISORY COMMITTEE APPLICATIONS

GUIDE FOR VARIANCE AND PLANNING ADVISORY COMMITTEE APPLICATIONS GUIDE FOR VARIANCE AND PLANNING ADVISORY COMMITTEE APPLICATIONS VARIANCES TERMS AND CONDITIONS RULINGS OF COMPATIBILITY TEMPORARY USES NON-CONFORMING USES June 2015 Planning Advisory Committee (PAC) Applications

More information

REQUEST FOR PROPOSAL FOR SERVICED APARTMENTS FOR: 1. CONCEPT DESIGN CONSULTATION AND/OR 2. OPERATION OF SERVICED APARTMENTS, FOR,

REQUEST FOR PROPOSAL FOR SERVICED APARTMENTS FOR: 1. CONCEPT DESIGN CONSULTATION AND/OR 2. OPERATION OF SERVICED APARTMENTS, FOR, REQUEST FOR PROPOSAL FOR SERVICED APARTMENTS FOR: 1. CONCEPT DESIGN CONSULTATION AND/OR 2. OPERATION OF SERVICED APARTMENTS, FOR, SERVICED APARTMENTS BRAND SPONSORED BY CYTONN INVESTMENTS MANAGEMENT LIMITED

More information

Town of North Castle New York REQUEST FOR PROPOSALS REAL ESTATE BROKER SERVICES

Town of North Castle New York REQUEST FOR PROPOSALS REAL ESTATE BROKER SERVICES Town of North Castle New York REQUEST FOR PROPOSALS REAL ESTATE BROKER SERVICES 1. Overview The Town of North Castle, New York is hereby requesting proposals from qualified, real estate brokers to assist

More information

Page 1 of 5. Name of Firm:

Page 1 of 5. Name of Firm: Name of Firm: 1. The Requirement for Terms of Engagement: Terms of Engagement are mandatory according to the RICS Valuation Professional Standards (Global) July 2017 and the International Valuation Standards

More information

Anthony Banfield, FRICS Banfield Real Estate Solutions Ltd

Anthony Banfield, FRICS Banfield Real Estate Solutions Ltd Anthony Banfield, FRICS Banfield Real Estate Solutions Ltd } RICS Practice Statement GN13/2010 Contamination, the environment and sustainability What is it and why should we care? What does it cover? Implications

More information

BUILDING PATHOLOGY & DILAPIDATION. Unit 1: Key Concepts of Dilapidations Law

BUILDING PATHOLOGY & DILAPIDATION. Unit 1: Key Concepts of Dilapidations Law BUILDING PATHOLOGY & DILAPIDATION Unit 1: Key Concepts of Dilapidations Law Learning Objectives Explain what is building pathology and its relevance Understand how the concepts of dilapidation relate to

More information

Government Management Committee. P:\2011\Internal Services\Fac\Gm11008Fac- (AFS 10838)

Government Management Committee. P:\2011\Internal Services\Fac\Gm11008Fac- (AFS 10838) STAFF REPORT ACTION REQUIRED Old City Hall Future Uses Date: April 14, 2011 To: From: Wards: Reference Number: Government Management Committee Chief Corporate Officer Ward 27, Toronto Centre Rosedale P:\2011\Internal

More information

Alternative plans review and inspection.-- (1) As used in this section, the term:

Alternative plans review and inspection.-- (1) As used in this section, the term: 553.791 Alternative plans review and inspection.-- (1) As used in this section, the term: (a) "Applicable codes" means the Florida Building Code and any local technical amendments to the Florida Building

More information

Certificate in Commercial Real Estate

Certificate in Commercial Real Estate Certificate in Commercial Real Estate Duration: 9 months Price: 1,465 + VAT (members), 1,745 + VAT (non-members) Course Summary Commercial real estate serves a vast array of purposes, supporting public

More information

Architectural Process & Standard for Parish Construction Project Canons of the Episcopal Church in the Diocese of Alabama: Canon 6 Section 6

Architectural Process & Standard for Parish Construction Project Canons of the Episcopal Church in the Diocese of Alabama: Canon 6 Section 6 Canons of the Episcopal Church in the Diocese of Alabama: Canon 6 Section 6 The Diocese and each of its Parishes and other organization shall submit to the Department, for its review and recommendations,

More information

Domestic Energy Assessor Quality Assurance Requirements England & Wales and Northern Ireland Regions Effective Date 1 st August 2012

Domestic Energy Assessor Quality Assurance Requirements England & Wales and Northern Ireland Regions Effective Date 1 st August 2012 Domestic Energy Assessor Quality Assurance Requirements England & Wales and Northern Ireland Regions Effective Date 1 st August 2012 Sampling Approach Random Sampling Overall, a minimum of 2% of lodged

More information

Real Estate Reference Material

Real Estate Reference Material Valuation Land valuation Land is the basic essential of property development and unlike building commodities - such as concrete, steel and labour - it is in relatively limited supply. Quality varies between

More information

Operating Standards Attachment to Development Application

Operating Standards Attachment to Development Application Planning & Development Services 2255 W Berry Ave. Littleton, CO 80120 Phone: 303-795-3748 Mon-Fri: 8am-5pm www.littletongov.org Operating Standards Attachment to Development Application 1 PLANNED DEVELOPMENT

More information

Sample Renewal Additional Information Request

Sample Renewal Additional Information Request Sample Renewal Additional Information Request February 25, 2015 Jim Smith Green Acres Land Trust 123 Main Street Anywhere, NY 12345 Dear Jim: Thank you for submitting your organization s application for

More information

Nottingham City Council Development Department

Nottingham City Council Development Department Nottingham City Council Development Department SUPPLEMENTARY PLANNING " GUIDANCE Planning Guidelines For the Provision of Local Open Space in New Residential Development original date: October 1997 UPDATE:July

More information

Minimum Educational Requirements

Minimum Educational Requirements Minimum Educational Requirements (MER) For all persons elected to practice in each Member Association With effect from 1 January 2011 1 Introduction 1.1 The European Group of Valuers Associations (TEGoVA)

More information

BUSI 398 Residential Property Guided Case Study

BUSI 398 Residential Property Guided Case Study BUSI 398 Residential Property Guided Case Study PURPOSE AND SCOPE The Residential Property Guided Case Study course BUSI 398 is intended to give the real estate appraisal student a working knowledge of

More information

Re: Lands at Inchanny, Strabane. Belfast 12 th March Lands Tribunal - Henry M Spence MRICS Dip.Rating IRRV (Hons)

Re: Lands at Inchanny, Strabane. Belfast 12 th March Lands Tribunal - Henry M Spence MRICS Dip.Rating IRRV (Hons) LANDS TRIBUNAL FOR NORTHERN IRELAND LANDS TRIBUNAL AND COMPENSATION ACT (NORTHERN IRELAND) 1964 BUSINESS TENANCIES (NORTHERN IRELAND) ORDER 1996 IN THE MATTER OF AN APPLICATION BT/26/2013 BETWEEN READY

More information

REQUEST FOR PROPOSAL RFP # TOC17-001

REQUEST FOR PROPOSAL RFP # TOC17-001 REQUEST FOR PROPOSAL RFP # TOC17-001 April 25, 2017 157 NW Columbia Avenue P. O. Box 183 Chapin, SC 29036 Tel.: (803) 345-2444 Fax: (803) 345-0427 April 25, 2017 REQUEST FOR PROPOSAL RFP # TOC17-001 The

More information

Peters Township Planning Commission September 15, :00 p.m.

Peters Township Planning Commission September 15, :00 p.m. 1. Roll Call Commissioners Present: Commissioners Absent: Planning Director: Assistant Planner: Gateway Engineers: Jeff Mills, David Wylie, Aaron Smith, Daniel Germain, Conrad Tselepis Rocco Magrino, Ted

More information

1 Adopting the Code. The Consumer Code Requirements and good practice Guidance. 1.1 Adopting the Code. 1.2 Making the Code available

1 Adopting the Code. The Consumer Code Requirements and good practice Guidance. 1.1 Adopting the Code. 1.2 Making the Code available The Non-mandatory Good Practice for Home Builders along The Consumer Code s and good practice 1 Adopting the Code 1.1 Adopting the Code Home Builders must comply with the s of the Consumer Code and have

More information

THE TOWN OF VAIL EMPLOYEE HOUSING GUIDELINES

THE TOWN OF VAIL EMPLOYEE HOUSING GUIDELINES THE TOWN OF VAIL EMPLOYEE HOUSING GUIDELINES 10-19-99 10/19/99 Page 1 of 11 I. PURPOSE The purpose of the (Guidelines) is to set forth the occupancy requirements, re-sale procedures, and resale price limitations

More information

Scrutiny Team Review of Grounds Maintenance. July 2015 October The Scrutiny Team

Scrutiny Team Review of Grounds Maintenance. July 2015 October The Scrutiny Team Scrutiny Team Review of Grounds Maintenance July 2015 October 2015 Prepared by: The Scrutiny Team Introduction and Objectives There has been no grounds maintenance review since the start of the current

More information

9 Hanna Ave Establishment of Public Lane System

9 Hanna Ave Establishment of Public Lane System STAFF REPORT ACTION REQUIRED 9 Hanna Ave Establishment of Public Lane System Date: February 18, 2010 To: From: Wards: Reference Number: Toronto and East York Community Council Director, Community Planning,

More information

A Demonstration Appraisal Report. Of a. Located at. Date of Appraisal. Prepared for. Prepared by

A Demonstration Appraisal Report. Of a. Located at. Date of Appraisal. Prepared for. Prepared by A Demonstration Appraisal Report Of a Located at Date of Appraisal Prepared for Prepared by International Association of Assessing Officers Professional Designation Subcommittee 314 West 10 th Street Kansas

More information

Riverton Properties Ltd Proposed Special Housing Area

Riverton Properties Ltd Proposed Special Housing Area Riverton Properties Ltd Proposed Special Housing Area Housing Accords and Special Housing Areas Act 2013 Expression of Interest 1 This Expression of Interest is made on behalf of Riverton Properties Ltd,

More information

RFP REQUEST FOR PROPOSAL. for TAX CREDIT ADVISOR SERVICES. for BOULDER HOUSING PARTNERS. March 6, 2012 Requested Return: March 15, 2010

RFP REQUEST FOR PROPOSAL. for TAX CREDIT ADVISOR SERVICES. for BOULDER HOUSING PARTNERS. March 6, 2012 Requested Return: March 15, 2010 RFP 06-2012 REQUEST FOR PROPOSAL for TAX CREDIT ADVISOR SERVICES for BOULDER HOUSING PARTNERS March 6, 2012 Requested Return: March 15, 2010 Boulder Housing Partners 4800 Broadway Boulder, CO 80304 (720)

More information

REDAN CAPITAL LTD 13 Ikeja Close, Off oyo St, Area 2, Garki-, Abuja, Nigeria GUIDELINES FOR PREPARING PROJECT PROPOSALS

REDAN CAPITAL LTD 13 Ikeja Close, Off oyo St, Area 2, Garki-, Abuja, Nigeria GUIDELINES FOR PREPARING PROJECT PROPOSALS GUIDELINES FOR PREPARING PROJECT PROPOSALS INTRODUCTION SHELTER-AFRIQUE's major objective is to promote housing in Africa. In order to achieve this objective, the Company cooperates with private sector,

More information

RESOLUTION 5607 (10) NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Lompoc as follows:

RESOLUTION 5607 (10) NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Lompoc as follows: RESOLUTION 5607 (10) A Resolution of the Council of the City of Lompoc County of Santa Barbara, State of California, Approving County Of Santa Barbara Resolution Of Intention, Consenting To Participation

More information

PART ONE - GENERAL INFORMATION

PART ONE - GENERAL INFORMATION Corrected Date: Page 7 Date of Submittal Changed to Coincide with Submittal Date on Page 5 PART ONE - GENERAL INFORMATION A. INTRODUCTION B. Background Miami Shores Village is soliciting responses to this

More information

STAATSKOERANT, 30 JANUARIE 2009 GOVERNMENT NOTICE DEPARTMENT OF MINERALS AND ENERGY ELECTRICITY REGULATION ACT, 2006 ELECTRICITY REGULATION

STAATSKOERANT, 30 JANUARIE 2009 GOVERNMENT NOTICE DEPARTMENT OF MINERALS AND ENERGY ELECTRICITY REGULATION ACT, 2006 ELECTRICITY REGULATION STAATSKOERANT, 30 JANUARIE 2009 No.31849 3 GOVERNMENT NOTICE No.R.79 DEPARTMENT OF MINERALS AND ENERGY ELECTRICITY REGULATION ACT, 2006 30.January 2009 ELECTRICITY REGULATION I, Buyelwa P Sonjica, Minister

More information

United States Small Business Administration Office of Hearings and Appeals

United States Small Business Administration Office of Hearings and Appeals Cite as: NAICS Appeal of BLB Resources, Inc., SBA No. NAICS-5855 (2017) United States Small Business Administration Office of Hearings and Appeals NAICS APPEAL OF: BLB Resources, Inc., Appellant, SBA No.

More information

To establish the structure and content of contracts.

To establish the structure and content of contracts. Page No: 1 of 7 I. Purpose To establish the structure and content of contracts. II. Scope Applies to all contract procurements. III. Procedure In accordance with the Escambia County Purchasing Ordinance,

More information

THE CHAIRPERSON. Hans Hoogervorst Chairman International Accounting Standard Board 30 Cannon Street London EC4M 6XH.

THE CHAIRPERSON. Hans Hoogervorst Chairman International Accounting Standard Board 30 Cannon Street London EC4M 6XH. Floor 18 Tower 42 25 Old Broad Street London EC2N 1HQ United Kingdom t +44 (0)20 7382 1770 f +44 (0)20 7382 1771 www.eba.europa.eu THE CHAIRPERSON +44(0)20 7382 1765 direct andrea.enria@eba.europa.eu Hans

More information

INDEPENDENT AUDITOR S REPORT

INDEPENDENT AUDITOR S REPORT INDEPENDENT AUDITOR S REPORT TO THE SHAREHOLDERS OF KERRY PROPERTIES LIMITED (incorporated in Bermuda with limited liability) OPINION What we have audited The consolidated financial statements of Kerry

More information

West 1st Avenue By-law No (Being a By-law to Amend By-law 3575, being the Zoning and Development By-law)

West 1st Avenue By-law No (Being a By-law to Amend By-law 3575, being the Zoning and Development By-law) City of Vancouver Zoning and Development By-law Community Services, 453 W. 12th Ave Vancouver, BC V5Y 1V4 F 604.873.7000 fax 604.873.7060 planning@vancouver.ca CD-1 (483) 236-298 West 1st Avenue By-law

More information

Okinawa Institute of Science and Technology School Corporation Contract Management Stipulations

Okinawa Institute of Science and Technology School Corporation Contract Management Stipulations Okinawa Institute of Science and Technology School Corporation Contract Management Stipulations Table of Contents Article 1... 3 Article 2... 3 Article 3... 3 Article 4... 4 Article 5... 5 Article 6...

More information

Building more and better homes. Looking after you and your new home

Building more and better homes. Looking after you and your new home Building more and better homes Looking after you and your new home Issued September 2017 Looking after you and your new home While each of the estates that will be rebuilt is at different stages, we want

More information

ALABAMA REAL ESTATE COMMISSION ADMINISTRATIVE CODE CHAPTER 790 X 3 DISCIPLINARY ACTIONS TABLE OF CONTENTS

ALABAMA REAL ESTATE COMMISSION ADMINISTRATIVE CODE CHAPTER 790 X 3 DISCIPLINARY ACTIONS TABLE OF CONTENTS Real Estate Commission Chapter 790 X 3 ALABAMA REAL ESTATE COMMISSION ADMINISTRATIVE CODE CHAPTER 790 X 3 DISCIPLINARY ACTIONS TABLE OF CONTENTS 790 X 3.01 Change Of Address 790 X 3.02 Returned Check Fee

More information

EVALUATION OF THE REAL ESTATE PROPERTIES - NOVELTIES WITHIN THE COST APPROACH

EVALUATION OF THE REAL ESTATE PROPERTIES - NOVELTIES WITHIN THE COST APPROACH EVALUATION OF THE REAL ESTATE PROPERTIES - NOVELTIES WITHIN THE COST APPROACH METHOD OF ASSETS Lect. Raluca Florentina Creţu Ph. D The Bucharest University of Economic Studies Faculty Accounting and Management

More information

THE APPRAISAL OF REAL ESTATE 3 RD CANADIAN EDITION BUSI 330

THE APPRAISAL OF REAL ESTATE 3 RD CANADIAN EDITION BUSI 330 THE APPRAISAL OF REAL ESTATE 3 RD CANADIAN EDITION BUSI 330 REVIEW NOTES by CHUCK DUNN CHAPTER 12 Copyright 2010 by the Real Estate Division and Chuck Dunn. All rights reserved ARE 3 RD EDITION REVIEW

More information

PLANNED UNIT DEVELOPMENT (PUD) AREA PLAN/REZONING REVIEW PROCEDURE

PLANNED UNIT DEVELOPMENT (PUD) AREA PLAN/REZONING REVIEW PROCEDURE PLANNED UNIT DEVELOPMENT (PUD) AREA PLAN/REZONING REVIEW PROCEDURE Professional inquiries will be made to our Township Planning Consultant, Township Engineer, and Township Attorney to get their opinions

More information

May 2012 Professional (Cadastral) Examination

May 2012 Professional (Cadastral) Examination Page 1 of 6 Question 1 a) Name five (5) types of plans for which the limits may be un-dimensioned. (5 marks) b) Name five (5) types of plans that create geographic fabric. (5 marks) Question 2 A client

More information

Report on Inspection of Ferlita, Walsh, Gonzalez & Rodriguez, P.A. (Headquartered in Tampa, Florida) Public Company Accounting Oversight Board

Report on Inspection of Ferlita, Walsh, Gonzalez & Rodriguez, P.A. (Headquartered in Tampa, Florida) Public Company Accounting Oversight Board 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8433 www.pcaobus.org Report on 2017 Gonzalez & Rodriguez, P.A. (Headquartered in Tampa, Florida) Issued by the Public

More information

Below Market Rate Program Administrator. Request for Proposals

Below Market Rate Program Administrator. Request for Proposals Below Market Rate Program Administrator Request for Proposals Housing and Community Development 7351 Rosanna Street Gilroy, CA 95020 Page 1 Introduction and Important Dates The City of Gilroy is seeking

More information

SENIOR FACULTY APARTMENT RENOVATION POLICY. Effective Date: April 1, 2009

SENIOR FACULTY APARTMENT RENOVATION POLICY. Effective Date: April 1, 2009 SENIOR FACULTY APARTMENT RENOVATION POLICY Effective Date: April 1, 2009 Policy Statement This policy describes the process by which the University determines the work to be done at University expense

More information

ADMINISTRATIVE GUIDANCE

ADMINISTRATIVE GUIDANCE 11 ADMINISTRATIVE GUIDANCE ON CONTAMINATED SITES Effective date: April 1, 2013 Version 1.1 May 2013 Expectations and Requirements for Contaminant Migration Introduction This guidance focusses on the ministry

More information

IN RE CLINTON TOWNSHIP, ) NEW JERSEY COUNCIL HUNTERDON COUNTY ) ON AFFORDABLE HOUSING

IN RE CLINTON TOWNSHIP, ) NEW JERSEY COUNCIL HUNTERDON COUNTY ) ON AFFORDABLE HOUSING IN RE CLINTON TOWNSHIP, ) NEW JERSEY COUNCIL HUNTERDON COUNTY ) ON AFFORDABLE HOUSING ) ) OPINION This matter arises as a result of an Order to Show Cause issued by the New Jersey Council on Affordable

More information

Protection for Residents of Long Term Supported Group Accommodation in NSW

Protection for Residents of Long Term Supported Group Accommodation in NSW Protection for Residents of Long Term Supported Group Accommodation in NSW Submission prepared by the NSW Federation of Housing Associations March 2018 Protection for Residents of Long Term Supported Group

More information

Use of Comparables. Claims Prevention Bulletin [CP-17-E] March 1996

Use of Comparables. Claims Prevention Bulletin [CP-17-E] March 1996 March 1996 The use of comparables arises almost daily for all appraisers. especially those engaged in residential practice, where appraisals are being prepared for mortgage underwriting purposes. That

More information

SP Energy Networks Fee Scale

SP Energy Networks Fee Scale SP Energy Networks Fee Scale Introduction SP Energy Networks (the Company), which is formed by the licensed and regulated companies known as SP Distribution Plc, SP Transmission Plc and SP Manweb Plc,

More information

Summary Siri Nørve and Lillin Knudtzon New lifts in old multi-family dwellings - gaining support for common investments NIBR-rapport: 2009:21

Summary Siri Nørve and Lillin Knudtzon New lifts in old multi-family dwellings - gaining support for common investments NIBR-rapport: 2009:21 Summary Siri Nørve and Lillin Knudtzon New lifts in old multi-family dwellings - gaining support for common investments Background There has been a particularly strong focus in recent years on policies

More information

Bridging Research and Practice

Bridging Research and Practice Bridging Research and Practice the VLA experience Edited by Victor Li Order for this Publication can be made through the Centre for Research & Professional Development Room 1103 Kowloon Investment Co Ltd

More information

VILLAGE OF GREENDALE 6500 NORTHWAY GREENDALE, WI (414) (414) FAX REQUEST FOR PROPOSAL RENOVATION AND REUSE

VILLAGE OF GREENDALE 6500 NORTHWAY GREENDALE, WI (414) (414) FAX  REQUEST FOR PROPOSAL RENOVATION AND REUSE VILLAGE OF GREENDALE 6500 NORTHWAY GREENDALE, WI 53129 (414) 423-2100 (414) 423-2107 FAX WWW.GREENDALE.ORG REQUEST FOR PROPOSAL RENOVATION AND REUSE OF THE FORMER POLICE AND FIRE STATION (6600 Schoolway,

More information