1 CITY OF PORTLAND, MAINE PLANNING BOARD Carol Morrissette, Chair Stuart G. O Brien, Vice Chair Joe Lewis Lee Lowry, III Michael J. Patterson David Silk Bill Hall February 3 rd, 2012 Gregory Mitchell City of Portland Economic Development Dept. City of Portland 389 Congress Street Portland, Maine David Senus, PE Project Manager Woodard & Curran 41 Hutchins Drive Portland Maine Project Name: Portland Technology Park Project ID: Project Address: 300 Rand Road (aka 1581 Westbrook Street) CBL: 249 A001 & A002; 250 A001; 251 A005& A009; 255 A002 Applicant: City of Portland Economic Development Department Planner: Jean Fraser Dear Mr Mitchell and Mr Senus: On January 24 th, 2012 the Portland Planning Board considered and approved a Level III Final Site Plan and Subdivision proposal to construct an Office Park Planned Unit Development comprising 7 units, with a total of 122,000 sq ft, on a 26.2 acre parcel at 300 Rand Road. The proposal includes the provision of a 1400 linear foot long roadway and the creation of a separate but associated Conservation Easement on the abutting 13.8 acre woodlands. The Planning Board reviewed the proposal for conformance with the standards of the Traffic Movement Permit, Subdivision Ordinance and Site Plan Ordinance. The building architecture, site landscaping, site pedestrian circulation, bicycle parking, lamp specifications and signage within the limited common element areas of each unit will be subject to review and approval by the Planning Board for conformance with the Portland Technology Park Design Guidelines and City of Portland Code of Ordinances, Chapter 14 Land Use, Article v. Site Plan. The Planning Board approved the application with the following motions, waivers and conditions as presented below. On the basis of the application, plans, reports and other information submitted by the applicant, findings and recommendations contained in Planning Board Report # for the Portland Technology Park, Rand Road relevant to the Site Plan and Subdivision reviews and other regulations, and the testimony presented at the Planning Board hearing, the Planning Board finds the following: SIDEWALK WAIVER The Planning Board voted 5-1 (Lowry recused; Lewis opposed) that the following criteria do apply, and therefore waives the requirement for a sidewalk along the frontage of the Portland Technology Park site with Rand Road, subject to the provision of the internal sidewalk and crosswalk to the opposite side of Rand Road being constructed as part of phase 1 of the development: C) A safe alternative-walking route is reasonably available, for example, by way of a sidewalk on the other side of the street. F) Strict adherence to the sidewalk requirement would result in the loss of significant site features related to landscaping or topography that are deemed to be of a greater public value.

2 Page 2 of 7 TRAFFIC MOVEMENT PERMIT SUBDIVISION: The Planning Board voted 6-0 (Lowry recused) that the plan is in conformance with 23 MRSA 704-A and Chapter 305 Rules and Regulations pertaining to Traffic Movement Permits. The Planning Board voted 6-0 (Lowry recused) that the plan is in conformance with the subdivision standards of the Land Use Code, subject to the following eleven (11) conditions of approval: i. That the Subdivision Plat shall be finalized to the satisfaction of the Planning Authority and Corporation Counsel and include revisions to the phasing references, easements (including that to Portland Trails), the Condominium Association documents and relevant conditions; and ii. iii. iv. That the Condominium Association documents, including references to the Stormwater Management Inspection and maintenance requirements, shall be finalized to the satisfaction of the Corporation Counsel prior to the recording of the Subdivision Plat; and That the applicant shall submit for review and approval by Corporation Counsel, and show on the Subdivision Plat, all final documents containing easements and encumbrances as represented in the application and on the plans; and This approval entitles the applicant and future developers of the office park units to develop the maximum number and size of parking spaces as shown on the Subdivision Plat and Overall Site Plan subject to providing confirmation of the need for these spaces and space dimensions (via a parking analysis) at the time that the unit is under site plan review; and v. That the condominium association shall develop and manage a Transportation Demand Management (TDM) plan acceptable to the Planning Authority, reviewed as part of the initial and subsequent site plan approvals for each building unit within the limited common element areas; and vi. That the development of limited common element areas is subject to review and approval by the City of Portland Planning Authority for conformance with the Portland Technology Park Design Guidelines and City of Portland Code of Ordinances, Chapter 14 Land Use, Article v. Site Plan for building architecture, site landscaping, site pedestrian circulation, bicycle parking, lamp specifications and signage and any changes or alterations to approved traffic, parking, access, utility, exterior lighting, tree preservation and stormwater features; and vii. The clearing limits shall be restricted to Limited Common Element (LEC) areas, Easement Area 1 associated with the site roadway; Easement Area 2 associated with access to the trail head parking, and Easement Area 3 associated with the trail head parking; and viii. That the applicant and all assigns shall comply with the conditions of Chapter 32 Stormwater including Article III, Post-Construction Storm Water Management, which specifies the annual inspections and reporting requirements. The developer/contractor/subcontractor must comply with conditions of the construction stormwater management plan and sediment & erosion control plan based on City standards and state guidelines; and ix. That the applicant shall submit large scale Tree Preservation Plan and Forest Management Plan within three months of this approval. The Forest Management Plan would contain existing conditions and management recommendations that the condominium owners and easement holders would follow in sustainable forestry management with goals of protecting habitat, forest health and recreation; and x. That the proposed Limited Common Elements, shown as "LCE" on the plan, be marked with permanent markers such as FENO markers in the field prior to any work on the site to ensure that the limits of clearance and tree preservation areas are clear on the site; and xi. That the RPZ Zone line, trailhead parking area, significant tree areas and particular tree saves (as identified on the Tree Preservation Plan) be marked or located in the field prior to any site work.

3 Page 3 of 7 SITE PLAN REVIEW The Planning Board voted 5-1 (Lowry recused; Lewis opposed) that the plan is in conformance with the site plan standards of the Land Use Code, subject to the following four (4) conditions of approval: i. That the applicant receives and submits all required State and Federal permits prior to the issuance of a building permit; and ii. iii. iv. That the applicant shall submit revised plans/documents that address the comments from Tom Errico, Traffic Engineering Reviewer, regarding the four items under Additional Comments for review and approval by the Planning Authority prior to the issuance of a building permit; and That when individual units are proposed for site plan review the applicants should submit detailed specifications for snow storage management/protection of gravel wetlands, exterior lamp fixtures (including wall mounted), and consider the opportunity for trail links with the wider trail network on the RPZ open space part of the site; and That the site plans for individual units shall be brought before the Planning Board for review and approval, and the Board reserves the right to review individual units under the standards of the site plan ordinance. STANDARD CONDITIONS OF APPROVAL Please note the following standard conditions of approval and requirements for all approved site plans: 1. Develop Site According to Plan: The site shall be developed and maintained as depicted on the subdivision plat and site plan and in the written submission of the applicant. Modification of any approved site plan or alteration of a parcel which was the subject of site plan approval after May 20, 1974, shall require the prior approval of a revised site plan by the Planning Board or Planning Authority pursuant to the terms of Chapter 14, Land Use, of the Portland City Code. Modification of an approved subdivision plan requires the prior review and approval of an amended subdivision plan by the Planning Board or Planning Authority. 2. Separate Building Permits Are Required: This approval does not constitute approval of any associated building or road plans, which must be reviewed and approved by the City of Portland s Inspection Division. 3. Recording of Waivers: Pursuant to 30-A MRSA section 4406(B)(1), any waiver must be specified on the subdivision plan or outlined in a notice. The plan or notice must be recorded in the Cumberland County Registry of Deeds within 90 days of the final subdivision approval. 4. Mylar Recording Plat: The final revised and approved subdivision recording plat must be signed by the Planning Board prior to recording in the Cumberland County Registry of Deeds. A mylar copy and 5 paper copies of the recorded plat (with dates and details of the recording) must be submitted to the Planning Division prior to the release of any associated building permit. 5. Final Plan Meeting Conditions of Approval: Seven (7) final sets of plans must be submitted to and approved by the Planning Division prior to the release of a building permit, street opening permit or certificate of occupancy for site plans. If you need to make any modifications to the approved plans, you must submit a revised site plan/subdivision application for prior review and approval by the Planning Authority or Planning Board. 6. Expiration of Approvals: The site plan approval will be deemed to have expired unless work has commenced within one (1) year of the approval. Requests to extend approvals must be received before the one (1) year expiration date. The subdivision approval is valid for three (3) years. 7. Inspection Fee: An Inspection Fee of $300 is required for the site inspections conducted by the Planning Division, unless waived by the City Manager. 8. Preconstruction Meeting: Prior to construction, a pre-construction meeting shall be held at the project site. This meeting will be held with the contractor, Development Review Coordinator, Public Service's

4 Page 4 of 7 representative and owner to review the construction schedule and critical aspects of the site work. At that time, the Development Review Coordinator will confirm that the contractor is working from the approved plans. The site/building contractor shall provide three (3) copies of a detailed construction schedule to the attending City representatives. It shall be the contractor's responsibility to arrange a mutually agreeable time for the pre-construction meeting. 9. Department of Public Services Permits: If work will occur within the public right-of-way such as utilities, curb, sidewalk and driveway construction, a street opening permit(s) is required for your site. Please contact Carol Merritt at , ext (Only excavators licensed by the City of Portland are eligible.) 10. As-Built Final Plans: Final sets of as-built plans shall be submitted digitally to the Planning Division, on a CD or DVD, in AutoCAD format (*,dwg), release AutoCAD 2005 or greater. The Development Review Coordinator must be notified five (5) working days prior to the date required for final site inspection. The Development Review Coordinator can be reached at the Planning Division at All site plan requirements must be completed and approved by the Development Review Coordinator prior to issuance of a Certificate of Occupancy. Please schedule any property closing with these requirements in mind. If there are any questions, please contact Jean Fraser at (207) Sincerely, Carol Morrissette, Chair Portland Planning Board Attachments: Tom Errico, Traffic Engineering Reviewer comments 2. Planning Board Report #04-12 Electronic Distribution: Gregory A Mitchell, Acting Director of Planning and Urban Development Alexander Jaegerman, Planning Division Director Barbara Barhydt, Development Review Services Manager Jean Fraser, Planner Philip DiPierro, Development Review Coordinator Marge Schmuckal, Zoning Administrator Tammy Munson, Inspections Division Director Danielle West-Chuhta, Associate Corporation Counsel Gayle Guertin, Inspections Division Lannie Dobson, Inspections Division Michael Bobinsky, Public Services Director Hard Copy: Project File Kathi Earley, Public Services Bill Clark, Public Services David Margolis-Pineo, Deputy City Engineer Greg Vining, Public Services John Low, Public Services Jane Ward, Public Services Chris Pirone, Fire Department Jeff Tarling, City Arborist Tom Errico, TY Lin Nelle Hanig, Economic Development Department Assessor's Office Approval Letter File

5 Page 5 of 7 Attachment 1 From: To: CC: Date: Subject: Tom Errico <thomas.errico@tylin.com> Jean Fraser <JF@portlandmaine.gov> Katherine Earley <KAS@portlandmaine.gov>, David Margolis-Pineo <DMP@portlandmaine.gov>, Jeff Tarling <JST@portlandmaine.gov> 1/19/2012 6:22 PM Portland Technology Park Jean - I have reviewed the Site Plan Application dated December 31, 2011 prepared by Woodard & Curran and offer final comments. * The project meets requirements for a Traffic Movement Permit (TMP). The Applicant has submitted a TMP Application and I have determined that it is complete. Accordingly, a Traffic Movement Permit Scoping meeting has been scheduled for November 29th at 3:00pm in the Planning Conference Room. I would note that specific traffic study comments will be issued upon completion of the traffic study following the Scoping Meeting. Status: A traffic impact study has been submitted by the applicant and I find the methods and conclusions to be acceptable. In general, I agree with the conclusion that a traffic signal is not warranted at the site drive and the proposed improvements provide reasonable accommodations for site traffic. January 19, 2012 Status: No comment necessary. * The applicant should provide information supporting a waiver for the provision of a sidewalk on Rand Road along their property frontage. Related to this issue will be the appropriate provision of how pedestrians will safely walk between the site and the sidewalk on the north side of Rand Road. Status: The applicant has provided supporting information for a sidewalk waiver. I do not support item 1, that there is no reasonable expectation for pedestrian usage coming from, going to and traversing the site. I do support criteria 3 as noted in their letter. Jeff Tarling should provide expertise on whether criteria 6 is satisfied. January 19, 2012 Status: It is my understanding that this issue has been resolved and a sidewalk waiver is supported by DPS. * The applicant should provide information that supports the parking supply provided. Upon receipt of this information I will render a decision on issuing a waiver from the City's Technical Standards for parking stall size. Status: I would suggest that additional supporting technical information be provided that supports the parking supply being proposed. One possible approach, if supporting documentation is not available, would be to design and permit the project for the assumed full parking supply as requested by the applicant. Only parking spaces that meet zoning requirements will be displayed on the plans for construction. Future expansion parking areas will be illustrated and can be constructed if tenant characteristics required the additional parking spaces. January 19, 2012 Status: I support the condition of approval drafted by the Planning Department noting an upset limited on parking supply with final totals to be determined during site plan review. * The applicant should provide information justifying the traffic circle on the project driveway. It does not seem to serve any traffic control purpose and requires addition pavement area that seems to run counter to project sustainability goals. If it is to remain, adjustments to the design may be required. Status: The applicant has appropriately responded to this comment and I have no further comment. January 19, 2012 Status: No comment necessary. * The driveway approach to Rand Road indicates two approach lanes. I would note that the design criteria (storage length) for these lanes will be a function of analyses performed in conjunction with the traffic impact study, which has yet to be provided. Status: The traffic study indicates the 95th% storage of the egress lane to be 80 feet and the left-turn ingress lane to be 70 feet. The proposed design provides in excess of the noted requirement and therefore I find the design to be acceptable. January 19, 2012 Status: No comment necessary.

6 Page 6 of 7 * I have an expectation that large tractor trailers will make occasional deliveries to individual building sites. The applicant should provide information on where these deliveries will occur and their ability to maneuver on-site without leaving the pavement. Status: The applicant has provided turning template graphics that display adequate space for maneuvering and therefore I have no further comment. January 19, 2012 Status: No comment necessary. * The parking aisle near Building 6 and the motorcycle parking spaces is only 20 feet wide and does not meet City Technical Standards. Status: The plan has been revised and I have no further comment. January 19, 2012 Status: No comment necessary. * The Layout plans illustrate "block" style crosswalks, but the details provide information for parallel line crosswalks. The detail should be revised. January 19, 2012 Status: The detail has been added and I have no further comment. * The location of the crosswalk nearest Rand Road concerns me. I need to evaluate this further before providing some guidance to the applicant. January 19, 2012 Status: The revised crosswalk location is acceptable and I have no further comment. * Further details on the layout of the trailhead parking lot should be provided. Specifically, what is the intended parking layout for an area that is proposed to be 58 feet wide by 60 feet long. January 19, 2012 Status: The plans clearly note the parking lot details and I find them to be acceptable. I have no further comment. * Coordination with the Maine Turnpike Authority is still outstanding and will need to be conducted. I will contact them as it relates to any potential traffic impact fee contribution. January 19, 2012 Status: No action by the Maine Turnpike Authority is required for this project. * The Design Guidelines document suggests providing parking spaces that are 8'-2" x 18' in size and therefore do not meet City standards. I would suggest that the project incorporate a combination of standard (9'x18') and compact (7.5'x15') sized parking spaces that will minimize pavement area and avoid the requirement of a technical waiver. January 19, 2012 Status: I support the condition of approval drafted by the Planning Department that the reduced size parking stall will be permitted, but a final decision will be determined during site plan review when specific tenant needs are known. * The provision of the a sidewalk on one side of the site driveway is based upon the assumption that it is private and does not need to following City standards for providing sidewalks on all property frontages, unless waiver criteria can be met. Corporation council should confirm that in fact the City ownership of the road does not require the City's sidewalk provision standards to be applied. January 19, 2012 Status: It is my understanding that this issue has been addressed by Corporation Council. **Additional Comments** * Through pavement arrows are not required on Rand Road and should be deleted. * The applicant should confirm that adequate illumination will be provided at the proposed crosswalk on Rand Road. * Signage at nose of island on Rand Road should be provided. * A lane assignment sign for proposed left-turn lane on Rand Road shall be installed.

7 Page 7 of 7 If you have any questions, please contact me. Best regards, Thomas A. Errico, PE, Senior Associate Traffic Engineering Director T.Y. Lin International 12 Northbrook Drive Falmouth, ME direct mobile fax thomas.errico@tylin.com<mailto:thomas.errico@tylin.com>

8 From: To: Date: Subject: Jeff Tarling Barbara Barhydt; David Margolis-Pineo; Jean Fraser 1/22/2015 8:30 AM Re: Proposed Gas Easement Route for the Portland Technology Park Hi David - I am supportive of the project given the limited other options to gain access to the site. The impact to the forest should be minimal in the RPZ zone. I would recommend that the right of way be over-seeded with the appropriate restoration seed mix. See: Jeff >>> David Margolis-Pineo 1/21/2015 3:08 PM >>> Please see attached. Please be aware that Jeff Tarling has walked this site several times and is fully aware and I believe supportive of this proposal.

9 From: David Margolis-Pineo To: Barbara Barhydt; Jean Fraser; Jeff Tarling Date: 1/7/2015 8:13 AM Subject: Re: draft approval letter for marine ramp at GDI ( ) No comments on my end Jean. Thanks >>> Jean Fraser 1/6/2015 4:43 PM >>> Hi This is fairly minor, but please see the attached draft- just checking that we are all set re this. Pl let me know if you think it needs some revisions. Thanks Jean

10 From: Keith Gautreau To: Jean Fraser CC: Craig Messinger; David Petruccelli Date: 3/2/2015 8:52 AM Subject: Re: Amend to PTP Subdiv Plat re gas line easement Hi Jean, Fire approves. Let me know if you need anything else. Keith Keith Gautreau, Acting Asst. Chief Fire Prevention Portland Fire Department 380 Congress Street Portland, ME (207)

CITY OF PORTLAND, MAINE PLANNING BOARD

CITY OF PORTLAND, MAINE PLANNING BOARD CITY OF PORTLAND, MAINE PLANNING BOARD Elizabeth Boepple, Chair Sean Dundon, Vice Chair Carol Morrissette David Eaton Kristien Nichols Lisa Whited Maggie Stanley July 29, 2016 Andrew Kraus M & A Lowcountry

More information

Town of Windham. Planning Department 8 School Road Windham, ME voice fax

Town of Windham. Planning Department 8 School Road Windham, ME voice fax Town of Windham Planning Department 8 School Road Windham, ME 04062 voice 207.894.5960 fax 207.892.1916 MEMO DATE: September 3, 2013 TO: Tony Plante, Town Manager FROM: Ben Smith, Assistant Town Planner

More information

PLANNING BOARD REPORT PORTLAND, MAINE

PLANNING BOARD REPORT PORTLAND, MAINE PLANNING BOARD REPORT PORTLAND, MAINE India Newbury Residences Subdivision & Conditional Use Review 2016-096 India Newbury Residences, LLC Submitted to: Portland Planning Board Date: May 20, 2016 Public

More information

Approval of a conditional use to allow construction of a rehabilitation hospital at 5115 N. Biltmore Lane in the American Center.

Approval of a conditional use to allow construction of a rehabilitation hospital at 5115 N. Biltmore Lane in the American Center. Department of Planning & Community & Economic Development Planning Division Katherine Cornwell, Director Madison Municipal Building, Suite LL-100 215 Martin Luther King, Jr. Boulevard P.O. Box 2985 Madison,

More information

Draft Model Access Management Overlay Ordinance

Draft Model Access Management Overlay Ordinance Draft Model Access Management Overlay Ordinance This model was developed using the City of Hutchinson and the Trunk Highway 7 corridor. The basic provisions of this model may be adopted by any jurisdiction

More information

Town of Bristol Rhode Island

Town of Bristol Rhode Island Town of Bristol Rhode Island Subdivision & Development Review Regulations Adopted by the Planning Board September 27, 1995 (March 2017) Formatted: Highlight Formatted: Font: 12 pt Table of Contents TABLE

More information

New Private Way Ordinance Westbrook Planning Board Workshop , Planning Board Public Hearing Definitions

New Private Way Ordinance Westbrook Planning Board Workshop , Planning Board Public Hearing Definitions 201 Definitions Private Right of Way; Private way A strip of land at least fifty feet wide, meeting the minimum standards for the construction of a gravel base for a public road, over which abutters may

More information

PLANNING BOARD REPORT PORTLAND, MAINE

PLANNING BOARD REPORT PORTLAND, MAINE PLANNING BOARD REPORT PORTLAND, MAINE Four-Lot Subdivision 158 Fore Street Portland Gateway Project Level III Subdivision Ara Aftandilian, Portland Norwich Group, LLC Submitted to: Portland Planning Board

More information

The City Engineering Division has reviewed the subject development and has the following comments.

The City Engineering Division has reviewed the subject development and has the following comments. DATE: May 27, 2008 TO: FROM: SUBJECT: Plan Commission Larry D. Nelson, P.E., City Engineer 1126 Huxley Street and 1910 Roth Street Demolition The City Engineering Division has reviewed the subject development

More information

Section 1: US 19 Overlay District

Section 1: US 19 Overlay District Section 1: US 19 Overlay District Section 1.1 Intent and Purpose The purpose of the US Highway 19 Overlay District is to manage access to land development along US Highway 19 in a manner that preserves

More information

Financial Impact Statement There are no immediate financial impacts associated with the adoption of this report.

Financial Impact Statement There are no immediate financial impacts associated with the adoption of this report. STAFF REPORT Planning and Development Department Subject: Application by RYC Property to rezone a portion of lands on John Murray Dr. and Megan Lynn Dr. from R2 to R3 and to enter into a Development Agreement

More information

COMMERCIAL SITE PLAN & CONDITIONAL USE PERMIT REVIEW PROCESS & CHECKLIST

COMMERCIAL SITE PLAN & CONDITIONAL USE PERMIT REVIEW PROCESS & CHECKLIST Community Development 110 South Main Street Springville, UT 84663 COMMERCIAL SITE PLAN & CONDITIONAL USE PERMIT REVIEW PROCESS & CHECKLIST 801.491.7861 www.springville.org Prior to the issuance of a building

More information

CHAPTER XVIII SITE PLAN REVIEW

CHAPTER XVIII SITE PLAN REVIEW CHAPTER XVIII SITE PLAN REVIEW Section 18.1 Section 18.2 Description and Purpose. The purpose of this chapter is to provide standards and procedures under which applicants would submit, and the Township

More information

a. provide for the continuation of collector streets and thoroughfare streets between adjacent subdivisions;

a. provide for the continuation of collector streets and thoroughfare streets between adjacent subdivisions; Section 7.07. Intent The requirements of this Section are intended to provide for the orderly growth of the Town of Holly Springs and its extra-territorial jurisdiction by establishing guidelines for:

More information

Guide to Combined Preliminary and Final Plats

Guide to Combined Preliminary and Final Plats Guide to Combined Preliminary and Final Plats Introduction The Douglas County is committed to providing open, transparent application processes to the public. This Guide is provided to assist anyone interested

More information

Guide to Minor Developments

Guide to Minor Developments Guide to Minor Developments Introduction The Douglas County (DCD) is committed to providing open, transparent application processes to the public. This Guide is provided to assist anyone interested in

More information

Chapter 100 Planned Unit Development in Corvallis Urban Fringe

Chapter 100 Planned Unit Development in Corvallis Urban Fringe 100.100 Scope and Purpose. Chapter 100 Planned Unit Development in Corvallis Urban Fringe (1) All applications for land divisions in the Urban Residential (UR) and Flood Plain Agriculture (FPA) zones within

More information

Level III Preliminary and Final Site Plans Development Review Application Portland, Maine Planning and Urban Development Department Planning Division

Level III Preliminary and Final Site Plans Development Review Application Portland, Maine Planning and Urban Development Department Planning Division Level III Preliminary and Final Site Plans Development Review Application Portland, Maine Planning and Urban Development Department Planning Division Portland s Planning and Urban Development Department

More information

Medical Marijuana Special Exception Use Information

Medical Marijuana Special Exception Use Information Medical Marijuana Special Exception Use Information The Special Exception Use information below is a modified version of the Unified Development Code. It clarifies the current section 5:104 Special Exceptions

More information

PREPARED FOR THE URBAN DESIGN COMMISSION AND PLAN COMMISSION

PREPARED FOR THE URBAN DESIGN COMMISSION AND PLAN COMMISSION PLANNING DIVISION STAFF REPORT PREPARED FOR THE URBAN DESIGN COMMISSION AND PLAN COMMISSION Project Address: Application Type: Prepared By: Demolition Permit and Conditional Use Kevin Firchow, AICP, Planning

More information

PLANNING BOARD REPORT PORTLAND, MAINE

PLANNING BOARD REPORT PORTLAND, MAINE PLANNING BOARD REPORT PORTLAND, MAINE, 636 Riverside Street Level III Subdivision and Site Plan Review 2016-047 Submitted to: Portland Planning Board Date: June 23, 2016 Public Hearing Date: June 28, 2016

More information

II. What Type of Development Requires Site Plan Review? There are five situations where a site plan review is required:

II. What Type of Development Requires Site Plan Review? There are five situations where a site plan review is required: I. What is a Site Plan Review? Site Plan Review is a process where the construction of new buildings, new additions, and certain types of canopies and/or tax-exempt institutions are reviewed by the City

More information

ARTICLE 24 PRIVATE ROAD, SHARED PRIVATE DRIVEWAY AND ACCESS EASEMENT STANDARDS

ARTICLE 24 PRIVATE ROAD, SHARED PRIVATE DRIVEWAY AND ACCESS EASEMENT STANDARDS ARTICLE 24 PRIVATE ROAD, SHARED PRIVATE DRIVEWAY AND ACCESS EASEMENT STANDARDS SECTION 24.00 INTENT AND PURPOSE The standards of this Article provide for the design, construction and maintenance of private

More information

PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: July 20, 2017

PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: July 20, 2017 PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: July 20, 2017 DEVELOPMENT NAME SUBDIVISION NAME LOCATION Rangeline Crossing III Subdivision Rangeline Crossing III Subdivision 5289 Halls Mill

More information

SECTION 16. "PUD" PLANNED UNIT DEVELOPMENT OVERLAY DISTRICT

SECTION 16. PUD PLANNED UNIT DEVELOPMENT OVERLAY DISTRICT SECTION 6. "PUD" PLANNED UNIT DEVELOPMENT OVERLAY DISTRICT Subsection. Purpose. This district is established to achieve the coordinated integration of land parcels and large commercial and retail establishments

More information

CHARLOTTE PLANNING COMMISSION FINDINGS OF FACT AND DECISION IN RE APPLICATION OF

CHARLOTTE PLANNING COMMISSION FINDINGS OF FACT AND DECISION IN RE APPLICATION OF Background CHARLOTTE PLANNING COMMISSION FINDINGS OF FACT AND DECISION IN RE APPLICATION OF Henrietta Ober 2296 Greenbush Road and Stephen and Margaret Foster 1259 Lime Kiln Road Final Plan Review For

More information

DAUPHIN CREEK ESTATES SUBDIVISION

DAUPHIN CREEK ESTATES SUBDIVISION # 12 SUB-000076-2017 DAUPHIN CREEK ESTATES SUBDIVISION Engineering Comments: FINAL PLAT COMMENTS (should be addressed prior to submitting the FINAL PLAT for review and/or signature by the City Engineer):

More information

SECTION 7000 LAND DEVELOPMENT REQUIREMENTS

SECTION 7000 LAND DEVELOPMENT REQUIREMENTS SECTION 7000 LAND DEVELOPMENT REQUIREMENTS 7000 LAND DEVELOPMENT REQUIREMENTS... 1 7001 LEGISLATIVE AUTHORITY... 1 7001.1 LAND DEVELOPMENT... 1 7001.1.1 Title 40, Idaho Code... 1 7001.1.2 Idaho Code 40-1415

More information

Operating Standards Attachment to Development Application

Operating Standards Attachment to Development Application Planning & Development Services 2255 W Berry Ave. Littleton, CO 80120 Phone: 303-795-3748 Mon-Fri: 8am-5pm www.littletongov.org Operating Standards Attachment to Development Application 1 PLANNED DEVELOPMENT

More information

M-43 CORRIDOR OVERLAY ZONE

M-43 CORRIDOR OVERLAY ZONE ARTICLE 26.00 M-43 CORRIDOR OVERLAY ZONE Section 26.01 Findings A primary function of the M-43 state highway is to move traffic through the Township and to points beyond. As the primary east-west arterial

More information

APPLICATION PROCEDURE

APPLICATION PROCEDURE ANTRIM PLANNING BOARD P. O. Box 517 Antrim, New Hampshire 03440 Phone: 603-588-6785 FAX: 603-588-2969 APPLICATION FORM AND CHECKLIST FOR MINOR OR MAJOR SITE PLAN REVIEW File Date Received By APPLICATION

More information

Cover Letter with Narrative Statement

Cover Letter with Narrative Statement Cover Letter with Narrative Statement March 31, 2017 rev July 27, 2017 RE: Rushton Pointe Residential Planned Unit Development Application for Public Hearing for RPUD Rezone PL2015 000 0306 Mr. Eric Johnson,

More information

Guide to Preliminary Plans

Guide to Preliminary Plans Guide to Preliminary Plans Introduction The Douglas County is committed to providing open, transparent application processes to the public. This Guide is provided to assist anyone interested in the procedures

More information

SITE PLAN REVIEW ADMINISTRATIVE REVIEW. Please Note: Once submitted to the County, all application materials become a matter of public record.

SITE PLAN REVIEW ADMINISTRATIVE REVIEW. Please Note: Once submitted to the County, all application materials become a matter of public record. 200 W. Oak Street, 3rd Floor Fort Collins, CO 80521 (970) 498-7683 / larimer.org/planning SITE PLAN REVIEW ADMINISTRATIVE REVIEW The submittal requirements listed in this packet are intended to collect

More information

I. Requirements for All Applications. C D W

I. Requirements for All Applications. C D W 108-16.1. Application checklists. Checklist for Required Submissions to the Planning Board or Zoning Board of Adjustment of Monroe Township All required submissions are to be made to the Administrative

More information

CHAPTER 26 PLANNING AND ZONING ARTICLE VII. MOBILE HOMES AND RECREATIONAL VEHICLE (RV) PARKS. Recreational Vehicle (RV) Park Development Standards

CHAPTER 26 PLANNING AND ZONING ARTICLE VII. MOBILE HOMES AND RECREATIONAL VEHICLE (RV) PARKS. Recreational Vehicle (RV) Park Development Standards CHAPTER 26 PLANNING AND ZONING ARTICLE VII. MOBILE HOMES AND RECREATIONAL VEHICLE (RV) PARKS. Section 26-VII-1. Section 26-VII-2. Section 26-VII-3. Section 26-VII-4. Section 26-VII-5. Purpose Permitted

More information

ARTICLE IV: DEVELOPMENT STANDARDS

ARTICLE IV: DEVELOPMENT STANDARDS ARTICLE IV: DEVELOPMENT STANDARDS IV-53 409 PRIVATE STREETS A private street means any way that provides ingress to, or egress from, property by means of vehicles or other means, or that provides travel

More information

PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: November 17, 2016

PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: November 17, 2016 PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: November 17, 2016 DEVELOPMENT NAME SUBDIVISION NAME LOCATION Autonation Ford of Mobile Autonation Ford of Mobile Subdivision 901, 909, and 925

More information

(voice) (fax) (voice) (fax) Site Plan Review

(voice) (fax) (voice) (fax) Site Plan Review Town of South Boston PO Box 417 455 Ferry Street South Boston Virginia 24592 Planning Department Public Works Department (Engineering) 434.575.4241 (voice) 434.575.4275 (fax) 434.575.4260 (voice) 434.575.4275

More information

REPORT. Chair & Members of Community Affairs Committee John McMulkin, Planner Development Review REPORT TO: REPORT FROM:

REPORT. Chair & Members of Community Affairs Committee John McMulkin, Planner Development Review REPORT TO: REPORT FROM: REPORT TO: REPORT FROM: REPORT DATE: September 11, 2017 REPORT NO.: RE: RECOMMENDATION: Chair & Members of Community Affairs Committee John McMulkin, Planner Development Review PLS-2017-0013 RECOMMENDATION

More information

Condominium Unit Requirements.

Condominium Unit Requirements. ARTICLE 19 CONDOMINIUM REGULATIONS Section 19.01 Purpose. The purpose of this Article is to regulate projects that divide real property under a contractual arrangement known as a condominium. New and conversion

More information

COMMERCIAL SITE DEVELOPMENT GUIDE FOR UNINCORPORATED ST. CHARLES COUNTY

COMMERCIAL SITE DEVELOPMENT GUIDE FOR UNINCORPORATED ST. CHARLES COUNTY COMMERCIAL SITE DEVELOPMENT GUIDE FOR UNINCORPORATED ST. CHARLES COUNTY GENERAL INFORMATION: This brochure is to be used as a guide and is not intended to amend or supersede the corresponding County ordinances

More information

PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT August 18, 2016

PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT August 18, 2016 PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT August 18, 2016 DEVELOPMENT NAME SUBDIVISION NAME Mullinax Ford Subdivision Mullinax Ford Subdivision LOCATION CITY COUNCIL DISTRICT District 6 Southeast

More information

Town of Cary, North Carolina Site Plan Staff Report Centregreen Park at Weston (13-SP-067) Town Council Quasi-Judicial Hearing April 3, 2014

Town of Cary, North Carolina Site Plan Staff Report Centregreen Park at Weston (13-SP-067) Town Council Quasi-Judicial Hearing April 3, 2014 Town of Cary, North Carolina Site Plan Staff Report Centregreen Park at Weston (13-SP-067) Town Council Quasi-Judicial Hearing April 3, 2014 REQUEST Withers and Ravenel, on behalf of Highwoods Realty Limited

More information

ARTICLE III GENERAL PROCEDURES, MINOR PLANS AND FEE SCHEDULES

ARTICLE III GENERAL PROCEDURES, MINOR PLANS AND FEE SCHEDULES ARTICLE III GENERAL PROCEDURES, MINOR PLANS AND FEE SCHEDULES 301. Prior to Submission a. Copies of this Ordinance shall be available on request, at cost, for the use of any person who desires information

More information

ZONING AMENDMENT & SUBDIVISION STAFF REPORT Date: November 3, 2016

ZONING AMENDMENT & SUBDIVISION STAFF REPORT Date: November 3, 2016 ZONING AMENDMENT & SUBDIVISION STAFF REPORT Date: November 3, 2016 APPLICANT NAME SUBDIVISION NAME David Shumer 5955 Airport Subdivision CITY COUNCIL DISTRICT District 6 5955 Airport Boulevard, 754 Linlen

More information

PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: April 18, 2019

PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: April 18, 2019 PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: April 18, 2019 DEVELOPMENT NAME SUBDIVISION NAME Springhill Village Subdivision Springhill Village Subdivision LOCATION 4350, 4354, 4356, 4358,

More information

ARTICLE 7: PLOT PLANS AND SITE PLAN REQUIREMENTS AND REVIEW

ARTICLE 7: PLOT PLANS AND SITE PLAN REQUIREMENTS AND REVIEW ARTICLE 7: PLOT PLANS AND SITE PLAN REQUIREMENTS AND REVIEW Section 7.0 - Purpose The purpose of this article is to specify the documents and/or drawings required for a Site Plan Review or a Plot Plan

More information

DRAFT Findings of Fact Major Development Review Final Subdivision Plan September 10, 2015

DRAFT Findings of Fact Major Development Review Final Subdivision Plan September 10, 2015 DRAFT Findings of Fact Major Development Review Final Subdivision Plan September 10, 2015 Project Name: Meadow Rose Farm Subdivision Case Number: 15-015 Tax Map: Map 17, Lot 126 Applicant: Two Clarks,

More information

BYRON TOWNSHIP ZONING APPLICATION

BYRON TOWNSHIP ZONING APPLICATION BYRON TOWNSHIP ZONING APPLICATION Phone: (616) 878-9104 * Fax: (616) 878-3980 * Website: www.byrontownship.org This application will not be accepted if incomplete. APPLICATION FOR & REQUIRED COPIES Private

More information

THE CITY OF MOBILE, ALABAMA

THE CITY OF MOBILE, ALABAMA THE CITY OF MOBILE, ALABAMA LETTER OF DECISION March 9, 2018 Byrd Surveying, Inc. 2609 Halls Mill Road Mobile, AL 36606 Re: 4439 Rangeline Road (Northwest corner of Rangeline Road and Halls Mill Road).

More information

SUBDIVISION APPLICATION

SUBDIVISION APPLICATION SUBDIVISION APPLICATION Community Planning and Economic Development Development Services Division 250 South 4 th Street, Room 300 Minneapolis MN 55415-1316 612-673-3000 This application packet is used

More information

THE CITY OF MOBILE, ALABAMA

THE CITY OF MOBILE, ALABAMA THE CITY OF MOBILE, ALABAMA LE 'I IER OF DECISION Kimberly Clark Mobile Operations 200 Africatown Blvd. Prichard, AL 36610 Re: 100 & 200 Africatown Boulevard (Northeast corner of Bay Bridge Road and Paper

More information

ZONING AMENDMENT, PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: August 8, 2013

ZONING AMENDMENT, PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: August 8, 2013 ZONING AMENDMENT, PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: August 8, 2013 NAME SUBDIVISION NAME PV-Magnolia, LLC Twelve Trees Subdivision LOCATION 2860, 2862 and 2866 Pleasant Valley Road

More information

AGENDA URBAN COUNTY PLANNING COMMISSION SUBDIVISION ITEMS. May 14, 2015

AGENDA URBAN COUNTY PLANNING COMMISSION SUBDIVISION ITEMS. May 14, 2015 AGENDA URBAN COUNTY PLANNING COMMISSION SUBDIVISION ITEMS May 14, 2015 I. CALL TO ORDER - The meeting will be called to order at 1:30 p.m. in the Council Chambers, Urban County Government Building, 200

More information

TOWN OF WATERVILLE VALLEY NEW HAMPSHIRE SITE PLAN REVIEW REGULATIONS

TOWN OF WATERVILLE VALLEY NEW HAMPSHIRE SITE PLAN REVIEW REGULATIONS TOWN OF WATERVILLE VALLEY NEW HAMPSHIRE Effective date March 17, 1981 Revised March 16, 1982 Revised March 13, 1986 Revised March 10, 1987 Revised March 14, 2013 Revised March 8, 2016 TOWN OF WATERVILLE

More information

Department of Planning & Community & Economic Development Planning Division

Department of Planning & Community & Economic Development Planning Division Kirk Keller Plunkett Raysich Architects LLP 2310 Crossroads Dr., Suite 2000 Madison, WI 53718 RE: Department of Planning & Community & Economic Development Planning Division Website: www.cityofmadison.com

More information

PLANNING & COMMUNITY DEVELOPMENT DEPARTMENT STAFF REPORT

PLANNING & COMMUNITY DEVELOPMENT DEPARTMENT STAFF REPORT PLANNING & COMMUNITY DEVELOPMENT DEPARTMENT STAFF REPORT DATE: TO: Hearing Officer SUBJECT: Minor Variance #11876 LOCATION: APPLICANT: ZONING DESIGNATION: GENERAL PLAN DESIGNATION: CASE PLANNER: STAFF

More information

Moore Township Planning Commission 2491 Community Drive, Bath, Pennsylvania Telephone: FAX: Rev:12/23/2013

Moore Township Planning Commission 2491 Community Drive, Bath, Pennsylvania Telephone: FAX: Rev:12/23/2013 2491 Community Drive, Bath, Pennsylvania Telephone: 610-759-9449 FAX: 610-759-9448 Rev:12/23/2013 APPLICATION FORM FOR A SITE PLAN PER MOORE TOWNSHIP ZONING ORDINANCE SECTION 200-58.1 NORTHAMPTON COUNTY,

More information

ARTICLE 15 - PLANNED UNIT DEVELOPMENT

ARTICLE 15 - PLANNED UNIT DEVELOPMENT Section 15.1 - Intent. ARTICLE 15 - PLANNED UNIT DEVELOPMENT A PUD, or Planned Unit Development, is not a District per se, but rather a set of standards that may be applied to a development type. The Planned

More information

Guide to Replats. Step 1. Step 2. Step 3. Step 4. Step 5. Step 6. Step 7. Step 8. Step 9. Step 10

Guide to Replats. Step 1. Step 2. Step 3. Step 4. Step 5. Step 6. Step 7. Step 8. Step 9. Step 10 Guide to Replats Introduction Douglas County is committed to providing open, transparent application processes to the public. This Guide is provided to assist anyone interested in the procedures and expectations

More information

Waseca County Planning and Zoning Office

Waseca County Planning and Zoning Office Waseca County Planning and Zoning Office 300 North State Street Waseca, Minnesota 56093 Phone: 507-835-0650 Fax: 507-837-5310 Form no. PZ 081009 Web Site: www.co.waseca.mn.us FEES: 1) CUP FEE- $400.00

More information

Zoning Variances. Overview of

Zoning Variances. Overview of Overview of Zoning Variances City of Bishop Planning Department Purpose: Each zoning classification indicates specific development standards such as setbacks or parking requirements. There are occasions,

More information

ARTICLE 24 SITE PLAN REVIEW

ARTICLE 24 SITE PLAN REVIEW ARTICLE 24 SITE PLAN REVIEW 24.1 PURPOSE: The intent of these Ordinance provisions is to provide for consultation and cooperation between the land developer and the Township Planning Commission in order

More information

Charter Township of Garfield Grand Traverse County

Charter Township of Garfield Grand Traverse County Charter Township of Garfield Grand Traverse County 3848 VETERANS DRIVE TRAVERSE CITY, MICHIGAN 49684 PH: (231) 941-1620 FAX: (231) 941-1588 GUIDE FOR THE SUBMISSION OF AN APPLICATION FOR SITE PLAN REVIEW

More information

THE CI FY OF MOBILE, ALABAMA

THE CI FY OF MOBILE, ALABAMA THE CI FY OF MOBILE, ALABAMA LETTER OF DECISION DewberryiPreble-Rish 9949 Bellaton Avenue Daphne, AL 36526 Re: Area bounded by Foxtail Drive, Lace Bark Drive and Whitebark Drive Council District 6 SUB-000323-2017

More information

Administrative Application Duplex Subdivisions

Administrative Application Duplex Subdivisions Department of Community Development 75 South Frontage Road Vail, CO 81657 Tel: 970-479-2128 www.vailgov.com Development Review Coordinator Administrative Application Duplex Subdivisions General Information:

More information

MOBILE CITY PLANNING COMMISSION LETTER OF DECISION. June 3, 2011

MOBILE CITY PLANNING COMMISSION LETTER OF DECISION. June 3, 2011 MOBILE CITY PLANNING COMMISSION LETTER OF DECISION P.O. Box 421 Mobile, AL 36601 Re: Case #SUB2011-00029 (Subdivision) Alabama West Subdivision, Unit Four 2600 McVay Drive North (North side of McVay Drive

More information

Preliminary Subdivision Application (Minor) (Three (3) lots or less)

Preliminary Subdivision Application (Minor) (Three (3) lots or less) Gunnison City Offices www.gunnisoncity.org 38 West Center Gunnison, Utah 84634 (435) 528 7969 Date of Application: Preliminary Subdivision Application (Minor) (Three (3) lots or less) APPLICANT INFORMATION

More information

DEVELOPMENT PLAN ORDINANCE

DEVELOPMENT PLAN ORDINANCE DEVELOPMENT PLAN ORDINANCE CITY OF GLASGOW Ordinance No. 2026 SECTION A. Section 1. INTENT AND PURPOSE The purpose of this Ordinance is to establish and define development plans, which may be utilized

More information

Town of Lincolnville Subdivision Ordinance

Town of Lincolnville Subdivision Ordinance Town of Lincolnville Subdivision Ordinance November 8, 2005 Amended: 06-10-2008---Article 4, Section 4.4.1 Conceptual Plan 06-11-2015---Article 5, Section 5.2.3.i., Article 6.2.3.l., Article 8 & 12 Access

More information

Please contact Janet Dailey of the City Engineering Division, at if you have questions regarding the following twenty-four (24) items:

Please contact Janet Dailey of the City Engineering Division, at if you have questions regarding the following twenty-four (24) items: Planning Division J. Randy Bruce Knothe & Bruce Architects, LLC 7601 University Avenue, Suite 201 Middleton, Wisconsin 53562 RE: Approval of a request to rezone a portion of from C2 (General Commercial

More information

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MCPB Item No. Date: 12/4/14 Preliminary Plan No. 120140200, Northwood Knolls Description Patrick Butler,

More information

Town of Norwich, Vermont SUBDIVISION REGULATIONS

Town of Norwich, Vermont SUBDIVISION REGULATIONS Town of Norwich, Vermont SUBDIVISION REGULATIONS Adopted: August 6, 2002 Amended: February 8, 2006 Prepared by Norwich Planning Commission with the assistance of: Burnt Rock Inc. A ssociates in Community

More information

May 21, ACHD Board of Commissioners Stacey Yarrington, Planner II DRH /DRH

May 21, ACHD Board of Commissioners Stacey Yarrington, Planner II DRH /DRH Development Services Department May 21, 2013 TO: FROM: SUBJECT: ACHD Board of Commissioners Stacey Yarrington, Planner II DRH13-00106/DRH13-00108 Executive Summary: This is a design review application

More information

WESTMINSTER PARK PLACE SUBDIVISION

WESTMINSTER PARK PLACE SUBDIVISION WESTMINSTER PARK PLACE SUBDIVISION Engineering Comments: FINAL PLAT COMMENTS (should be addressed prior to submitting the FINAL PLAT for review and/or signature by the City Engineer): A. Provide all of

More information

Staff Report for Council Public Meeting

Staff Report for Council Public Meeting Agenda Item 3.3 Staff Report for Council Public Meeting Date of Meeting: September 27, 2017 Report Number: SRPRS.17.134 Department: Division: Subject: Planning and Regulatory Services Development Planning

More information

CITY OF OAK HARBOR Development Services Department

CITY OF OAK HARBOR Development Services Department CITY OF OAK HARBOR Development Services Department Shortt Subdiiviisiions Shorrtt Pllatt Reviiew Prrocess IIII What is a Short Plat, and when is it necessary? A short plat is a map that represents a short

More information

ACTION SHEET PLANNING BOARD PORTSMOUTH, NEW HAMPSHIRE CITY HALL, MUNICIPAL COMPLEX, 1 JUNKINS AVENUE 7:00 P.M. NOVEMBER 17, 2016

ACTION SHEET PLANNING BOARD PORTSMOUTH, NEW HAMPSHIRE CITY HALL, MUNICIPAL COMPLEX, 1 JUNKINS AVENUE 7:00 P.M. NOVEMBER 17, 2016 ACTION SHEET PLANNING BOARD PORTSMOUTH, NEW HAMPSHIRE CITY HALL, MUNICIPAL COMPLEX, 1 JUNKINS AVENUE 7:00 P.M. NOVEMBER 17, 2016 MEMBERS PRESENT: ALSO PRESENT: MEMBERS ABSENT: John Ricci, Chairman; Elizabeth

More information

Application for Sketch Plan Review

Application for Sketch Plan Review Town of Standish 175 Northeast Road Standish, ME - 04084 Phone: (207)642-3461 Fax: (207) 642-5181 Application for Sketch Plan Review Applicant & Owner Information 1) Name of Applicant: Address: Phone:

More information

Draft Zoning Changes for the 2nd Planning Board Public Hearing, January 22, 2018.

Draft Zoning Changes for the 2nd Planning Board Public Hearing, January 22, 2018. Draft Zoning Changes for the 2nd Planning Board Public Hearing, January 22, 2018. No changes were made at the 1st Public Hearing. Proposed wording for the 1 st Public Hearing in red, eliminated text in

More information

ARTICLE 9 SPECIFICATIONS FOR DOCUMENTS TO BE SUBMITTED

ARTICLE 9 SPECIFICATIONS FOR DOCUMENTS TO BE SUBMITTED ARTICLE 9 SPECIFICATIONS FOR DOCUMENTS TO BE SUBMITTED SECTION 950 GENERALLY All applications shall be properly signed and filed by the owner or, with the owner s specific written consent, a contract purchaser

More information

THE CITY OF MOBILE, ALABAMA MOBILE Crry PLANNING COMMISSION

THE CITY OF MOBILE, ALABAMA MOBILE Crry PLANNING COMMISSION THE CITY OF MOBILE, ALABAMA MOBILE Crry PLANNING COMMISSION LETTER OF DECISION MLK Avenue Redevelopment Corp. Attn: Michael Pierce P.O. Box 2204 Mobile, AL 36652 Re: Case #SUB2014-00040 (Subdivision) MLK

More information

Township of Little Egg Harbor Planning Board 665 Radio Road Little Egg Harbor, New Jersey Phone: ext. 221 Fax:

Township of Little Egg Harbor Planning Board 665 Radio Road Little Egg Harbor, New Jersey Phone: ext. 221 Fax: BLOCK(S) LOT(S) Township of Little Egg Harbor Planning Board 665 Radio Road Little Egg Harbor, New Jersey 08087 Phone: 609-296-7241 ext. 221 Fax: 609-294-3040 Development Application Amended Development

More information

PLANNED UNIT DEVELOPMENT, SIDEWALK WAIVER, & SUBDIVISION STAFF REPORT Date: November 6, 2008

PLANNED UNIT DEVELOPMENT, SIDEWALK WAIVER, & SUBDIVISION STAFF REPORT Date: November 6, 2008 PLANNED UNIT DEVELOPMENT, SIDEWALK WAIVER, & SUBDIVISION STAFF REPORT Date: November 6, 2008 DEVELOPMENT NAME SUBDIVISION NAME LOCATION Frascati Shops, Inc. Frascati Subdivision 1120 Paper Mill Road CITY

More information

City of Sanibel. Planning Department STAFF REPORT

City of Sanibel. Planning Department STAFF REPORT City of Sanibel Planning Department STAFF REPORT Planning Commission Meeting: July 23, 2013 Planning Commission Agenda Item: No 7b. Application Number: 13-7438DP Applicant Name: Attorney Beverly Grady

More information

Municipality of Colchester. Subdivision Bylaw. March 31, Colchester

Municipality of Colchester. Subdivision Bylaw. March 31, Colchester Municipality of Colchester Subdivision Bylaw March 31, 2010 Colchester Municipality of the County of Colchester Subdivision Bylaw (Consolidated Edition) Revisions Adopted by Council January 28, 2010 Effective

More information

CHARTER TOWNSHIP OF SUPERIOR WASHTENAW COUNTY, MICHIGAN PRIVATE ROAD ORDINANCE ORDINANCE NO. 163

CHARTER TOWNSHIP OF SUPERIOR WASHTENAW COUNTY, MICHIGAN PRIVATE ROAD ORDINANCE ORDINANCE NO. 163 PAGE 163-1 CHARTER TOWNSHIP OF SUPERIOR WASHTENAW COUNTY, MICHIGAN PRIVATE ROAD ORDINANCE ORDINANCE NO. 163 AN ORDINANCE OF THE CHARTER TOWNSHIP OF SUPERIOR ESTABLISHING PROVISIONS FOR APPROVAL OF PRIVATE

More information

MAJOR SUBDIVISION APPLICATION

MAJOR SUBDIVISION APPLICATION Revised 2.26.18 The Department is here to assist you with your development application pursuant to the Community Development Code (CDC). This publication outlines the Major Subdivision Development Application

More information

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MCPB Item No. Date: 10-11-12 Subdivision Review Waiver SRW 2011001: Big Woods Road Richard Weaver, Acting

More information

LOCATION AND EXTENT REVIEW FOR DEVELOPMENT OF PUBLIC FACILITIES (Revised 3/1/2017)

LOCATION AND EXTENT REVIEW FOR DEVELOPMENT OF PUBLIC FACILITIES (Revised 3/1/2017) LOCATION AND EXTENT REVIEW FOR DEVELOPMENT OF PUBLIC FACILITIES (Revised 3/1/2017) Lana Gallegos, AICP Senior Planner 970-524-1729 Cindy Schwartz, Assistant Planner 970-524-1750 DATE APPLICATION SUBMITTED:

More information

CITY OF ST. CLOUD DEVELOPMENT REVIEW COMMITTEE AGENDA th STREET, BUILDING A, 2 nd FLOOR THURSDAY, DECEMBER 28, 2017, 2:00 PM

CITY OF ST. CLOUD DEVELOPMENT REVIEW COMMITTEE AGENDA th STREET, BUILDING A, 2 nd FLOOR THURSDAY, DECEMBER 28, 2017, 2:00 PM CITY OF ST. CLOUD DEVELOPMENT REVIEW COMMITTEE AGENDA 1300 9 th STREET, BUILDING A, 2 nd FLOOR THURSDAY, DECEMBER 28, 2017, 2:00 PM NEW BUSINESS: 1. Case #17-60.17 Tohoqua South of Neptune Road, west of

More information

Guidelines for the Approval of New Homes Sales Offices (Building Permits, Agreements, Securities)

Guidelines for the Approval of New Homes Sales Offices (Building Permits, Agreements, Securities) Guidelines for the Approval of New Homes Sales Offices (Building Permits, Agreements, Securities) ENCLOSURES: Site Plan Application Building Permit Application Grading and Drainage Approval Requirements

More information

CONDOMINIUM REGULATIONS

CONDOMINIUM REGULATIONS ARTICLE 37 CONDOMINIUM REGULATIONS SECTION 37.01. Purpose The purpose of this Article is to regulate projects that divide real property under a contractual arrangement known as a condominium. New and conversion

More information

TORONTO Archives NORTH YORK BY-LAW NUMBER BOX NUMBER tif [ naming convention for oversize scans ] SUPPLEMENTARY FILE

TORONTO Archives NORTH YORK BY-LAW NUMBER BOX NUMBER tif [ naming convention for oversize scans ] SUPPLEMENTARY FILE TORONTO Archives NORTH YORK BY-LAW NUMBER 29607 BOX NUMBER 395694 Produced according to archival standards for the creation of electronic records by the City of Toronto Archives, 255 Spadina Road, Toronto,

More information

ARTICLE XI CONDITIONAL USE PERMITS

ARTICLE XI CONDITIONAL USE PERMITS ARTICLE XI CONDITIONAL USE PERMITS 11.1 Purpose. The City of Hailey recognizes that certain uses possess unique and special characteristics with respect to their location, design, size, method of operation,

More information

Re: Case # ZP Preplanning Application for 8 townhomes at 1526 Ingalls Street in Lakewood, CO.

Re: Case # ZP Preplanning Application for 8 townhomes at 1526 Ingalls Street in Lakewood, CO. Planning Department Civic Center North 480 South Allison Parkway Lakewood, Colorado 80226-3127 303.987.7505 303.987.7057 TTY/TDD Lakewood.org/Planning February 27, 2017 Nathan Taylor 601 S Jason Street

More information

ARTICLE 585. PD 585.

ARTICLE 585. PD 585. ARTICLE 585. PD 585. SEC. 51P-585.101. LEGISLATIVE HISTORY. PD 585 was established by Ordinance No. 24302, passed by the Dallas City Council on June 28, 2000. Ordinance No. 24302 amended Ordinance Nos.

More information

Staff Report. November 16, 2016 Page 1 of 6

Staff Report. November 16, 2016 Page 1 of 6 November 16, 2016 Page 1 of 6 Report No.: PDSD-P-62-16 Meeting Date: November 16, 2016 Submitted by: Subject: Ben Puzanov, RPP, Senior Planner Applications for Consent (B-21/16) and Zoning By-law Amendment;

More information

PLANNING AND ZONING DEPARTMENT

PLANNING AND ZONING DEPARTMENT Town of Minturn Development Review Process: Guide To Planned Unit Developments (Concept Plan) This guide describes the Planned Unit Development Process. This guide should be utilized in conjunction with

More information