1 SUNY 2020 Advanced Manufacturing Institute (AMI) Building Addendum #1 Revised budget for construction project Notes from pre-proposal site visit held Tuesday, May 19, 2015 Responses to written questions received by May 20, 2015 deadline Additional scope of work Revised budget for construction project Our revised budget for this construction project will be $10,600,000. This excludes DASNY fees, construction management, geotechnical, and access road construction. Notes from Pre-proposal Site Visit Held Tuesday, May 19, 2015: In attendance at Pre-proposal Site Visit Tuesday, May 19, 2015: Name Phone# Dwight Wethey (315) Chris Jahn (585) Jerry Young (518) Randy Collin/CSArch (518) Aaron Schwartz (646) David Whitford (518) Carl Schoder (518) Tenee Casaccio (518) Jared Heinl (518) Steve Boisvert (518) Question: Would it be possible to provide your best estimate of what the Minority and Women-Owned Business participation requirements or goals will be prior to proposals being submitted? Answer: Approximately 30% (probably 15% women/15% minority). This will need to be confirmed Question: Will your estimate of 30% Minority and Women-Owned Business participation be included in the design stage or just construction? 1
2 Answer: Probably not much of an opportunity to incorporate this in the design stage but would like to encourage it. Respondents are encourage to stipulate what portion of their fees are estimated to be M/WBE participation. Question: Will the project be subject to public bidding in accordance with Wick s Law? Answer: Wick s Law is not applicable. Single prime allowed. Question: Will LEEDS certification be required? Answer: Due to nature of the building, LEEDS certification will hot have to be met; however, a minimum of 26 points towards LEEDS certification will be required. Question: Will DASNY s fees come out of the budget for this project? Answer: Yes, approximately $175,000, but this will be confirmed once final funding approval is received. Question: Does the budget for the construction project include furnishings? Answer: Yes; however, it does not include approximately $800,000 for specialized equipment. Not looking for any frills on this building we need quality. Question: Any idea what the $800,000 equipment will be and the utilities it may require? Answer: One thing may be a small machine shop. Need to think about making industrial utilities available for the design of the first floor. Should be all set as far as electrical utilities. Will need to consider new PRV station for natural gas. Question: Are you expecting a pre-engineered building or conventional? Answer: Leaning toward conventional. Question: How much of the space is dedicated to manufacturing training/education? What kind of stuff is going on in the building in regards to noise and vibration? Answer: Approximately half will be used in manufacturing training/education. Definitely need flexibility. Question: Clarify the fee structure? Answer: It will be based on a percentage of construction budget, excluding geotechnical, construction management, and DASNY participation. Question: How much additional site work around the building? Will additional parking be needed? Answer: Additional site work is unknown at this time. Additional parking will probably not be needed. Question: Are there utilities already serving that area? Answer: 150 (+/-) available north for gas main, and sanitary waste line leaving the property Power available on the entry approximately 150 away Water only a 12 inch main going to the main academic building, will need to tie into this 12 inch main. The main is located approximately 600 from construction site. Water is received from the town water tower. Static pressure is pounds the distribution system supply pumps and fire pumps will need to be looked at to make sure there is adequate flow. 2
3 Question: Do you have a current site survey? Answer: No Question: If a variance is needed for the height of the building who would that be filed with? Answer: At this time, we do not know. As per DASNY, there should be no other agency review. Question: Are you expecting industry, traditional student, and corporate training? Answer: Yes all of the above. Question: Will there be a municipal or SEQR review? Answer: DASNY will want to review the project and will be the permitting agency. Question: The RFP states that design and bid ready documents are to be completed by November 1, 2015, is there any flexibility? Answer: Yes. Depends on how long it will take the state to provide us with the approval of the funds. Would like to break ground by April Question: Where is the access road? Answer: Near where the two storage containers are. We would like to build the access road this summer. The cost of the access road would come out of the construction budget. Question: Are soil boring tests coming out of this budget? Answer: Yes Question: Do you want to include industry in the programming and planning in the building? Answer: Yes. We do have partners (includes Clarkson University, SUNY Plattsburgh, and local manufacturers). Question: Will your current Industrial Tech/Engineering program be moved to the new building? Answer: Yes. This department currently takes up 7,500 square feet. Question: Will this be a DASNY contract or standard AIA contract? Answer: Yes, AIA contract. Question: Will the college hire a construction manager to oversee the day-to-day activities of the contractors? Answer: Not certain. Question: Should the existing parking lot be paved as part of the project? Answer: Yes. Question: Is there a retention basin? Answer: Yes, north side of site. Question: How deep is the bedrock? Answer: Found at 18 where we dug. Appears to be limestone. 3
4 Question: In the evaluation criteria, where does cost rank? Answer: Cost will be a consideration; however, as stated on page 4 of the RFP, the lowest cost respondent may not be determined to be the most responsive one when all factors of evaluation of the proposal have been considered. However, the quoted fee structure will be an important factor in the determination of the successful proposal. Question: Are you thinking about a future expansion with this project? Answer: Possible Responses to Written Questions Received by May 20, 2015 Deadline Written Question: Item 9 says the bid documents must be completed by November 1, That means bids would be due in December with perhaps a January award and start of construction a time of year when foundations are unable to proceed due to weather. What is driving the accelerated design time line? Answer: The time line is accelerated. Tentative time line, subject to change: Dec 2015 Preparation of bid documents Jan 2016 Bid released Feb 2016 Bid award Apr 2016 Start construction Written Question: Item 11 says the project must be completed by August A project of this size can be completed in one calendar year, so can we assume that bid documents could be completed in January or February so that construction could actually start in spring of 2016? Answer: Tentative time line, subject to change: Dec 2015 Preparation of bid documents Jan 2016 Bid released Feb 2016 Bid award Apr 2016 Start construction Written Question: How does the college propose to handle the cost of soil borings, geotechnical analysis, additional site survey work (if necessary), testing during construction, special inspections, procurement of FF&E, etc.? These are not usually part of the architect s fee but could be handled by the architect for the convenience of the owner at an additional cost. Answer: The college will manage soil borings, geotechnical analysis, and additional site survey work (if necessary), and they will be funded through the project. Testing during construction, special inspections, and procurement of FF&E will be handled by the architect Written Question: Per the discussion at the pre-proposal meeting on 5/19, it is understood that DASNY will be the Authority Having Jurisdiction and that they will be conducting design reviews. Please confirm anticipated milestones (i.e. 30%, 65%, etc ) and approximate review timelines. Answer: DASNY will review drawings at 60% and 100% completion. Review and response time will be five to six weeks. 4
5 Written Question: Per the discussion at the pre-proposal meeting on 5/19 please confirm requirements for site plan review/approvals by agencies other than DASNY (i.e. Town of Plattsburgh Planning/Zoning, Clinton County Planning Board, etc ) Answer: As per DASNY, there should be no other agency review. Written Question: Per the discussion at the pre-proposal meeting on 5/19 please confirm that a new roadway is to be developed between the existing campus loop road and the existing gravel parking area/proposed building site and the this roadway may be bid as a separate project in summer/fall of Answer: The awarded architectural firm will be responsible for the design/engineering of the access road. The college will be responsible for the bidding of the road. Road construction will be deducted from total construction budget. Written Question: Can existing site survey and utility information be provided electronically to assist in design and survey scoping? Answer: An copy is included with this addendum (see last two pages). Written Question: Per the discussion at the pre proposal meeting on 5/19, it is understood that additional information on project requirements is expected from DASNY in the near future. If this information could potentially impact the RFP responses, please consider extending the deadline so firms can respond accordingly. Answer: The information from DASNY concerns their fee, so upon receiving the final approval it will not warrant a change in the deadlines outlined in the RFP. Written Question: Is the access road to be designed as part of the project? If yes, is the fee to be included in the overall fee or separated out? If the access road is done as an early bid package does the fee need to include weekly site observations and other typical Construction administration tasks? Answer: Yes, the access road is to be designed as part of the project and it will be included in the overall fee. The fee for the access road does not need to include weekly site observations and other typical construction administration tasks. Written Question: Is the study to bring water to the building site and evaluate the water availability and capacity included in this scope? If yes, should the fee be separated out or included in the overall fee? Answer: Yes it is included in this scope. The fee for this should be included in the overall fee. Written: Evaluation criteria on page 4 shows proposal scoring to include 25 points for Location of Firm Relative to the Project. Is there a specific range of scoring planned based on radius, mileage, time, or other factor? Are you looking for this subject to be addressed in the proposal as far as responsiveness capability? Answer: This is part of our evaluation criteria as stated in RFP. 5
6 Written: Also with respect to the evaluation criteria, the five criteria listed amount to 100 points, absent pricing submittal. Can you explain the weighted factor(s) of the listed criteria versus pricing? Answer: This is part of our evaluation criteria as stated in RFP. Additional Scope of Work Generator installation Parking lot expansion Site utilities ( water, sewer, storm water, natural gas) Access road Sidewalks and landscaping Installation of a small scale wind turbine (already owned by college and on premises) Installation of small photovoltaic array 6
7 Scale 1" = 175' Plot Date: 04/06/2015 Plot Time: 9:45 AM
8 The site location of the AMI is in location 2. To the north you will see that there is gas and sanitary available at approximately 150 feet from the site. To the west on the access road you will find primary three phase power coming up the hill, again located about 150 feet from the site. To the east approximately 600 feet away would be the location of the closest water main.
CLAYTON COUNTY WATER AUTHORITY. Sewer System Evaluation Surveys
Dated: September 22, 2017 Acknowledgment of receipt of this addendum MUST BE SIGNED AND INCLUDED IN YOUR RESPONSE TO THE RFP. QUESTIONS: 1. Will CCWA be answering questions periodically or will responses
More informationREQUEST FOR PROPOSALS Professional Engineering Services for Lift Station In the Rural Municipality of Wellington
REQUEST FOR PROPOSALS Professional Engineering Services for Lift Station In the Rural Municipality of Wellington Issue Date: March 2, 2018 Prepared By: Rural Municipality of Wellington Wellington, PEI
More informationREQUEST FOR PROPOSAL RFP # TOC17-001
REQUEST FOR PROPOSAL RFP # TOC17-001 April 25, 2017 157 NW Columbia Avenue P. O. Box 183 Chapin, SC 29036 Tel.: (803) 345-2444 Fax: (803) 345-0427 April 25, 2017 REQUEST FOR PROPOSAL RFP # TOC17-001 The
More informationTEMPORARY EMPLOYMENT SERVICES, OFFICE AND CLERICAL 06-X-37778
TEMPORARY EMPLOYMENT SERVICES, OFFICE AND CLERICAL 06-X-37778 Question No 1 What are the duties and responsibilities for these temp workers? What are the requirements for their qualification? High school?
More informationNeighborhood Stabilization Program Frequently Asked Questions
Neighborhood Stabilization Program Frequently Asked Questions Q: Are the insurance requirements (in XVIII) uniform to all applicants, including the non-profits? Yes, the insurance requirements are required
More informationEAST BATON ROUGE REDEVELOPMENT AUTHORITY ADMINISTRATIVE POLICY PROCUREMENT CONTRACTING AND DBE POLICY FOR FEDERALLY FUNDED PROJECTS.
EAST BATON ROUGE REDEVELOPMENT AUTHORITY ADMINISTRATIVE POLICY PROCUREMENT CONTRACTING AND DBE POLICY FOR FEDERALLY FUNDED PROJECTS February 5, 2013 East Baton Rouge Redevelopment Authority 801 North Blvd,
More informationMASSACHUSETTS CONVENTION CENTER AUTHORITY OWNER S PROJECT MANAGER SERVICES ADDENDUM NO. 1
Owner s Project Manager Addendum No. 1 May 1, 2013 MASSACHUSETTS CONVENTION CENTER AUTHORITY OWNER S PROJECT MANAGER SERVICES ADDENDUM NO. 1 This Addendum forms a part of and modifies the Request for Proposals
More informationAnswer: No survey exists and proposer should include in their proposal.
NUTRITION BUILDING ARCHITECTURAL/ENGINEERING SERVICES RFP ADDENDUM NO. 1 January 20, 2017 This Addendum, issued to bid document holders of record, indicates changes to the documents for the NUTRITION BUILDING
More informationReal Estate Commercial Advisory RFP. Information session 11/8/2017
Real Estate Commercial Advisory RFP Information session 11/8/2017 RFP Scope Retainer RFP for commercial real estate advisory services Scope of services is defined as follows: - Valuation: determine values
More informationREQUEST FOR ROPOSALS LANDLORD AND TENANT LEGAL SERVICES Issued: September 20, 2017
REQUEST FOR ROPOSALS LANDLORD AND TENANT LEGAL SERVICES Issued: September 20, 2017 The Village of Hempstead Housing Authority (VHHA), Hempstead, New York is requesting proposals from qualified organizations
More informationCOUNTY OF TANEY, MISSOURI
COUNTY OF TANEY, MISSOURI REQUEST FOR BID For COUNTY TAX SALE Release Date: February 22, 2012 Submittal Deadline: March 22, 2012 Not later than 9:00 AM, Central Time Taney County Purchasing Ron Erickson,
More informationREQUEST FOR QUALIFICATIONS
REQUEST FOR QUALIFICATIONS FOR EXECUTIVE ARCHITECT/ARCHITECT OF RECORD SERVICES FOR HOMECOMINGS INC. WESTVIEW VILLAGE REDEVELOPMENT Issued February 4, 2016 SUBMITTAL DEADLINE Wednesday, February 17, 2016
More informationChapter 11. Competitive Negotiation: Procedure
Chapter 11. Competitive Negotiation: Procedure Summary This chapter provides an overview of the procedure for procuring goods and services using the competitive negotiation procedure. The competitive negotiation
More information1. Canyon Pointe 2. Glen Willow 3. Madison. ISSUED: November 15, 2017
4800 N. Broadway, Boulder, CO 80304 Phone: 720-564-4610 Fax: 303-939-9569 www.boulderhousing.org Hearing Assistance: 1-800-659-3656 Boulder Housing Partners Request for Proposals: RFP #32-2017 Physical
More informationRequest for Qualifications (RFQ) # On-Call Land Surveying Services November 21, 2018
Request for Qualifications (RFQ) #2018-54 On-Call Land Surveying Services November 21, 2018 Electronic Submittals are due by 3:00 PM on December 10 th, 2018 The EVERETT HOUSING AUTHORITY is soliciting
More informationRequest for Proposals HQS Inspection Services May 21,
MAILING ADDRESS: Arlington Housing Authority 4 Winslow Street Arlington, MA 02474 ATTENTION: John J. Griffin Executive Director REQUEST FOR PROPOSALS Inspectional Services for Housing Choice Voucher Program
More informationCharter Township of Shelby Parks & Recreation Department Request for Proposals Gene Shepherd Park Splash Pad
Charter Township of Shelby Parks & Recreation Department Request for Proposals Gene Shepherd Park Splash Pad The Charter Township of Shelby is issuing this Request for Proposal (RFP) for construction of
More informationQuestions and Answers Residential Technical Assistance Pilot Program, Request for Proposals: Multifamily Specific Resiliency Technical Assistance
Questions and Answers Residential Technical Assistance Pilot Program, Request for Proposals: Multifamily Specific Resiliency Technical Assistance Q: Define Project Start Date on p. 4 A: Project Start Date
More informationREQUEST FOR RATE QUOTE. Financial Services for the Guaranteed Savings Agreement In The City of La Puente, California
REQUEST FOR RATE QUOTE Financial Services for the Guaranteed Savings Agreement In The City of La Puente, California CITY OF LA PUENTE Robbeyn Bird Administrative Services Director 15900 East Main Street
More informationADDENDUM #1 TO BID # BID NUMBER: ISSUE DATE: Wednesday, March 21, 2018
Georgetown County, South Carolina 129 Screven Street, Suite 239, Georgetown, SC 29440-3641 Post Office Drawer 421270, Georgetown, SC 29442-4200 (843) 545-3083 Fax (843) 545-3500 E-Mail purch@gtcounty.org
More informationREQUEST FOR QUALIFICATIONS FOR HOUSING ACQUISITION, RELOCATON, DEMOLITION CONSULTANT/REHABILITATION SPECIALIST WISE COUNTY, VIRGINIA
REQUEST FOR QUALIFICATIONS FOR HOUSING ACQUISITION, RELOCATON, DEMOLITION CONSULTANT/REHABILITATION SPECIALIST WISE COUNTY, VIRGINIA Project Description The County of Wise, Virginia has been awarded CDBG
More informationSolar Power Purchase Agreement
Request for Proposal Solar Power Purchase Agreement Cedar Rapids/Linn County Solid Waste Agency 1954 County Home Road Marion, Iowa 52302 www.solidwasteagency.org Issued: September 18, 2015 Proposals Due:
More informationQuestions and Answers to the RFP for Professional Property Management Bid
Questions and Answers to the RFP for Professional Property Management Bid Will UCDHS please provide a list of all UCDHS locations subject to this RFP? A list of all lease properties will be provided. Successful
More informationTHE HOUSING AUTHORITY OF THE CITY OF BOULDER dba BOULDER HOUSING PARTNERS
REQUEST FOR PROPOSALS for AS-NEEDED APPRAISAL SERVICES for THE HOUSING AUTHORITY OF THE CITY OF BOULDER dba BOULDER HOUSING PARTNERS MARCH 24, 2015 RFP #3-2015 Boulder Housing Partners 4800 Broadway Boulder,
More informationFinal proposals, as further described herein, should be addressed to:
REQUEST FOR QUALIFICATIONS Land Survey Services RFQ# 2018-01 Georgetown Housing Authority, GHA, is requesting qualified persons, firms, partnerships, corporations, or professional organizations to provide
More informationADDENDUM NO. 1 January 26, 2018 JOB ORDER CONTRACT FLEET AND FACILTY MANAGEMENT
ADDENDUM NO. 1 January 26, 2018 JOB ORDER CONTRACT FLEET AND FACILTY MANAGEMENT SPECIFICATION NO: 152948N REPAIR AND REHABILITATION OF CITY FACILITIES MADISON STREET AND NORTH OF MADISON STREET For Which
More informationBrandywine Farms Sewer Extension SEP
On March 12, 2009, the Metropolitan Government of Nashville and Davidson County, Tennessee (Metro) entered into a Consent Decree with the United States and the State of Tennessee. The reporting requirements
More informationPERRY CITY UTAH REQUEST FOR PROPOSALS REAL ESTATE BROKER SERVICES
PERRY CITY UTAH REQUEST FOR PROPOSALS REAL ESTATE BROKER SERVICES Overview The City of Perry, Utah is hereby requesting proposals from qualified, real estate brokers to assist with the sale of approximately
More informationScope of Work for Asset Management Plan
Village of Hermon Dissolution Implementation Committee (Post Study Phase) Meeting #7 6/16/2016 @ 6:00 p.m. @ the Hermon Town Hall Minutes 1. Status of DOS Implementation Grants Town and Village have received
More informationCity of Lawrence Office of the Purchasing Agent
DANIEL RIVERA MAYOR RITA V. BROUSSEAU CHIEF PROCUREMENT OFFICER City of Lawrence Office of the Purchasing Agent City Hall, Room 301 200 Common Street Lawrence, Massachusetts 01840 BID ADDENDUM #1 TEL:
More informationIn Development. Consultant Selection. Consultant - Scope of Work. Design-Permitting. Planning. Construction. Closeout
CAPITAL IMPROVEMENT PROGRAM REPORT - AUGUST 2018 PROJECT LIST by PHASE In Development 999-16 Property Acquisition - RW 33 RPZ 999-17 Wetland Mitigation Phase 2 of 2 999-19 Property Acquisition - RW 22
More informationRequest for Proposals For Village Assessment Services
Request for Proposals For Village Assessment Services INQUIRIES AND PROPOSALS SHOULD BE DIRECTED TO: Jesse Thyes Village Administrator 860 Badger Circle Grafton, WI 53024 Introduction The Village of Grafton
More informationMARCH GUIDE TO BUILDING CONDITION ASSESSMENTS and RESERVE FUND STUDIES
MARCH 2018 GUIDE TO BUILDING CONDITION ASSESSMENTS and RESERVE FUND STUDIES Contents What This Guide Covers... 3 Why Your Co-op Needs a BCA and RFS... 3 The BCA and RFS... 4 What is a building condition
More informationFebruary 22, RFQ No. 1 California WaterFix Real Estate Services ADDENDUM NO. 2
February 22, 2018 RFQ No. 1 California WaterFix Real Estate Services ADDENDUM NO. 2 This Addendum is meant to address Questions and Answers to the Real Estate Services Request for Qualifications (RFQ)
More informationADDENDUM #3. REQUEST FOR PROPOSAL (the RFP ) Fee Developer
ADDENDUM #3 REQUEST FOR PROPOSAL 1878-18 (the RFP ) Fee Developer Original Notice of RFP Issued on: January 25, 2019 Response Due Date: Thursday, March 14, 2019 @ 2:00pm February 11, 2019 To All Prospective
More informationThe Ultimate Guide To: DC CONDO CONVERSIONS. Authored by the Washington Capital Partners Team
The Ultimate Guide To: DC CONDO CONVERSIONS Authored by the Washington Capital Partners Team So, what is a condo conversion? Added 4th Floor Unit 2 Existing Structure (Floors 1, 2, &3) Unit 1 Washington,
More informationCentral Kentucky Educational Cooperative
Central Kentucky Educational Cooperative Name of Co-operative PROCUREMENT PLAN CHILD NUTRITION PROGRAM This procurement plan contained on the following pages 1 through 10 will be implemented on _April
More informationSPECIFICATIONS AND PROPOSAL FOR GENERAL BANKING SERVICES FOR THE TOWNSHIP OF DEERFIELD September 1, 2013 August 31, 2016
SPECIFICATIONS AND PROPOSAL FOR GENERAL BANKING SERVICES FOR THE TOWNSHIP OF DEERFIELD September 1, 2013 August 31, 2016 The Township of Deerfield is issuing a Request for Proposals (RFP) to financial
More informationRFP # PROPOSAL DUE DATE: JUNE 11, 2014 BY 4:00PM. Susan Garcia, Director
REQUEST FOR QUALIFICATIONS/PROPOSALS FOR PROGRAMMING & MASTER PLANNING AND ARCHITECTURAL/ENGINEERING AND OTHER SERVICES FOR PROPOSED NEW INTAKE FACILITY REPLACEMENT FOR CHEROKEE COUNTY ANIMAL SHELTER INTAKE
More informationREQUEST FOR PROPOSALS (A )
CITY OF TUSCALOOSA ) STATE OF ALABAMA ) REQUEST FOR PROPOSALS (A18-1471) TO: FROM: RE: Qualified Firms The City of Tuscaloosa, Alabama Request for Proposals for Development of Analysis of Impediment to
More informationTown of Manchester, Connecticut General Services Department. Request for Qualifications
Town of Manchester, Connecticut General Services Department Request for Qualifications Purchase of a Senior Citizens Housing Complex 208 North Elm St., Manchester, CT RFQ 16/17-10 Proposals Due: August
More informationREQUEST FOR QUALIFICATIONS (RFQ ) PRE-QUALIFY TO BID ALL BHP RENOVATION CONSTRUCTION GENERAL CONTRACTOR SERVICES
REQUEST FOR QUALIFICATIONS (RFQ 04-2012) PRE-QUALIFY TO BID ALL BHP RENOVATION CONSTRUCTION 2012-2014 GENERAL CONTRACTOR SERVICES Issued: February 6, 2012 Twin Pines Apartments OWNER: Boulder Housing Partners
More informationBelow Market Rate Program Administrator. Request for Proposals
Below Market Rate Program Administrator Request for Proposals Housing and Community Development 7351 Rosanna Street Gilroy, CA 95020 Page 1 Introduction and Important Dates The City of Gilroy is seeking
More informationSubject: Addendum No. 2 Request for Expressions of Interest (RFEI) for Development of Brooklyn College School of Business.
Subject: Addendum No. 2 Request for Expressions of Interest (RFEI) for Development of Brooklyn College School of Business. Date: August 9, 2018 Facilities Planning, Construction, and Management Office
More informationDEVELOPER SELECTION PROCESS
QUESTIONS ANSWERS DEVELOPER SELECTION PROCESS 1. What time is the response deadline on March 10? All required materials must be received in the University s Planning and Real Estate office no later than
More informationQuestions from Tampa Machinery:
4050 Esplanade Way Tallahassee, FL 32399-0950 Tel: 850-488-2786 Fax: 850-922-6149 Rick Scott, Governor Craig J. Nichols, Agency Secretary Addendum Number 1 to the following Request for Proposals (RFP):
More informationCity of O Fallon Project Management
City of O Fallon Project Management Request for Qualifications 2018 Storm Water Improvements Projects Design December 2017 RFQ# 18-008 REQUEST FOR QUALIFICATIONS FOR ENGINEERING SERVICES In compliance
More informationNYS HOME Local Program
NYS HOME Local Program Homebuyer Assistance With or Without Housing Rehabilitation Technical Assistance Webinar November 17, 2016 Welcome and Introductions Ann M. Petersen, Director (Albany Regional Office)
More informationADDENDUM #2. September 14, 2018
ADDENDUM #2 September 14, 2018 PROJECT: Virginia Polytechnic Institute & State University, Blacksburg, Virginia Perry Street Steam System Improvements IFB: 0057278 Changes and Clarifications - General
More informationADDENDUM NUMBER FIVE
ADDENDUM NUMBER FIVE April 17, 2019 RFP #19-912-07 PHASE I AND PHASE II CULTURAL RESOURCES SURVEYS AND ARCHAEOLOGICAL TESTING SERVICES AT IBERVILLE SCATTERED SITES THIS ADDENDUM IS BEING ISSUED TO INCORPORATE
More informationHousing Commission Report
Housing Commission Report To: From: Subject: Housing Commission Meeting: July 21, 2016 Agenda Item: 4-B Chair and Housing Commission Barbara Collins, Housing Manager Draft Request for Proposals for Mountain
More informationTOWN OF MANSFIELD RULES AND REGULATIONS FOR THE EXTENSION OF PUBLIC SEWERS
TOWN OF MANSFIELD RULES AND REGULATIONS FOR THE EXTENSION OF PUBLIC SEWERS BOARD OF WATER & SEWER COMMISSIONERS Mansfield Board of Selectmen Adopted April 3, 1996 CONTENTS DEFINITIONS... Page 2 POLICY
More informationRFP # Request for Proposals Canyon Pointe Parking Lot Replacement
RFP #2-2015 Request for Proposals Canyon Pointe Parking Lot Replacement Boulder Housing Partners, identified hereafter as BHP, is requesting bid proposals from general contractors to replace a concrete
More informationCounty Tax Sale PLEASE MARK YOUR ENVELOPE "SEALED BID # RETURN ONE (1) ORIGINAL AND THREE (3) COPIES TO:
REQUEST FOR BID No. 201303-216 TANEY COUNTY MISSOURI Purchasing Department 132 David Street / P. O. Box 1630 Forsyth, Missouri 65653 Attn: Ron Erickson, Director of Purchasing Phone: 417-546-7281 / FAX:
More informationINFORMATION FOR VENDORS DOING BUSINESS WITH THE CITY OF CORAL SPRINGS, FLORIDA FINANCIAL SERVICES DEPT
Updated 11/21/2014 VENDOR HANDBOOK INFORMATION FOR VENDORS DOING BUSINESS WITH THE CITY OF CORAL SPRINGS, FLORIDA FINANCIAL SERVICES DEPT./PURCHASING DIVISION 9551 W SAMPLE RD CORAL SPRINGS, FL 33065 TABLE
More informationTown of North Castle New York REQUEST FOR PROPOSALS REAL ESTATE BROKER SERVICES
Town of North Castle New York REQUEST FOR PROPOSALS REAL ESTATE BROKER SERVICES 1. Overview The Town of North Castle, New York is hereby requesting proposals from qualified, real estate brokers to assist
More informationCITY OF GROVER BEACH COMMUNITY DEVELOPMENT DEPARTMENT Tentative Map Checklist
CITY OF GROVER BEACH COMMUNITY DEVELOPMENT DEPARTMENT Tentative Map Checklist The following list includes all of the items you must submit for a complete application. Some specific types of information
More informationEDGERTON CITY HALL PLANNING COMMISSION MEETING REGULAR SESSION March 12, 2019
EDGERTON CITY HALL PLANNING COMMISSION MEETING REGULAR SESSION The met in regular session with Chair John Daley calling the meeting to order at 7:00 p.m. All present participated in the Pledge of Allegiance.
More informationREQUEST FOR PROPOSAL FOR ENGINEERING DESIGN SERVICES. Channel Reconstruction at Short Hills Garden Apartments Site Millburn, New Jersey
REQUEST FOR PROPOSAL FOR ENGINEERING DESIGN SERVICES Channel Reconstruction at Short Hills Garden Apartments Site Millburn, New Jersey Diane Thall-Eglow, Mayor Issue Date: March 21, 2019 Jackie Benjamin
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS for Engineering, Procurement and Construction of a 4.99 MW-AC Solar Photovoltaic Project in Vermont RFP Participant Instructions November 17, 2017 TABLE OF CONTENTS ARTICLE ONE. GENERAL
More informationEffingham County Health Department Environmental Health Division. Business Hours
Effingham County Health Department Environmental Health Division Effingham County Annex Building P.O. Box 350 (Mailing) 768 Highway 119 South (Street) Springfield, GA 31329 (912) 754-6850 (Phone) (912)
More informationMINUTES OF MEETING SIX MILE CREEK COMMUNITY DEVELOPMENT DISTRICT
MINUTES OF MEETING SIX MILE CREEK COMMUNITY DEVELOPMENT DISTRICT The regular meeting of the Board of Supervisors of the Six Mile Creek Community Development District was held on Tuesday, at 2:05 p.m. at
More informationREVISED REQUEST FOR REDEVELOPMENT PROPOSALS (RFP) 62 nd STREET INDUSTRIAL PARK IN THE UPPER LAWRENCEVILLE NEIGHBORHOOD OF THE CITY OF PITTSBURGH
REVISED REQUEST FOR REDEVELOPMENT PROPOSALS (RFP) 62 nd STREET INDUSTRIAL PARK IN THE UPPER LAWRENCEVILLE NEIGHBORHOOD OF THE CITY OF PITTSBURGH Proposal Due Date: Accepting Proposals on a Rolling Basis
More informationTOWN OF LEWISTON PLANNING BOARD APPLICATION
TOWN OF LEWISTON PLANNING BOARD APPLICATION DESCRIPTION OF PROPOSED REQUEST: Name of Property Owner: Phone #: Name of Applicant:Phone #: Address or Location of Proposal:_SBL# Size of Parcel or Structure:Existing
More informationREQUEST FOR PROPOSAL FOR STATION EQUIPMENT AND UPGRADES
Channels 99/993 Hamburg Township Television Government Access Cable Television Carried Over the Charter Communications Cable TV Network 10405 Merrill Road - P.O. Box 157 Hamburg, Michigan 48139 USA Phone:
More informationOnsite Wastewater Treatment System Remediation Project
APPLICANT CHECKLIST Onsite Wastewater Treatment System Remediation Project Must be in the Upper White River Basin in Missouri 1. Do NOT replace the failed system until your application is approved by Ozarks
More information1. Question: In regards to the facilities are they all Monday thru Friday cleaning? Any facilities Saturday and or Sunday cleaning?
Proposal No. P18/9957 Custodial Services Answers to Vendor Questions Questions are in black, Answers are in red 1. Question: In regards to the facilities are they all Monday thru Friday cleaning? Any facilities
More informationEASTERN WEST VIRGINIA COMMUNITY & TECHNICAL COLLEGE REGULATION No. AR- 7.10
EASTERN WEST VIRGINIA COMMUNITY & TECHNICAL COLLEGE REGULATION No. AR- 7.10 TITLE: PURCHASE OR ACQUISITION OF MATERIALS, SUPPLIES, EQUIPMENT, SERVICES AND PRINTING General Summary Statement of Administrative
More informationNYS HOME Local Program Small Rental Development Initiative (SRDI) Application Technical Assistance Webinar Questions and Answers
Program Small Rental Development Initiative (SRDI) Application Technical Assistance Webinar Questions and Answers 1. Question: Are there subsidy caps similar to HTF? Or just the max subsidy limits? The
More informationChapter 5. Competitive Sealed Bidding: Procedure
Chapter 5. Competitive Sealed Bidding: Procedure Summary This chapter provides an overview of the procedure for procuring goods and nonprofessional services using the competitive sealed bidding procedure.
More informationPORT OF TACOMA REQUEST FOR PROPOSALS No Conservation Easement Holder for Upper Clear Creek Mitigation Bank
PORT OF TACOMA REQUEST FOR PROPOSALS No. 070878 Conservation Easement Holder for Upper Clear Creek Mitigation Bank Issued by Port of Tacoma One Sitcum Plaza P.O. Box 1837 Tacoma, WA 98401-1837 RFP INFORMATION
More informationAttachment 2 Civil Engineering
A. Phase 1, Programming and Schematic Design: The CONSULTANT shall for each project: 1. Ascertain the project s requirements through a meeting with the COUNTY, and a review of an existing schematic layout
More informationNYS HOME Local Program
NYS HOME Local Program Homebuyer Development Projects Technical Assistance Webinar October 10, 2018 Welcome and Introductions Ann M. Petersen, LEED AP Director NYS HOME Program (Albany Regional Office)
More informationChapter 9. Competitive Sealed Bidding: Evaluating Bids
Chapter 9. Competitive Sealed Bidding: Evaluating Bids Summary This chapter describes the steps to be taken in order to properly evaluate each bid received in response to an invitation for bids. The two
More informationAllegheny County Sanitary Authority REQUEST FOR QUALIFICATIONS. for
Allegheny County Sanitary Authority REQUEST FOR QUALIFICATIONS for PROPERTY AND RIGHT OF WAY ACQUISITION SERVICES CLEAN WATER PLAN CAPITAL PROJECT S-451 November 2017 1.0 INTRODUCTION ALCOSAN has agreed
More informationREQUEST FOR PROPOSALS RFP # September 16, 2011 Proposals Due on October 5, 4:00 pm
Development Division 4800 N Broadway, Boulder, CO 80304 Phone: 720-564-4610 Fax: 303-544-9553 TDD/TTY: 1-800-659-3656 www.boulderhousing.org REQUEST FOR PROPOSALS RFP #13-2011 September 16, 2011 Proposals
More informationRequest For Proposal RFP # Capital Lease Financing for Enterprise Software. City of Greenville, Texas. October 13, 2010
Request For Proposal RFP #10-11-01 Capital Lease Financing for Enterprise Software City of Greenville, Texas October 13, 2010 Proposals Due by 3:00 P.M. Central Standard Time November 1, 2010 Please Label
More informationThe Lawrenceville Community Land Trust: A Scattered Site, Single- Family, For- Sale Housing Development Lawrenceville Corporation
REQUEST FOR PROPOSALS (RFP) FOR ARCHITECTURAL OR DESIGN BUILD SERVICES The Lawrenceville Community Land Trust: A Scattered Site, Single- Family, For- Sale Housing Development Lawrenceville Corporation
More informationREQUEST FOR PROPOSAL 2017 ASPHALT PAVING SERVICES
REQUEST FOR PROPOSAL 2017 ASPHALT PAVING SERVICES RELEASE DATE: Monday, May 15, 2017 DEADLINE: Thursday, May 25, 2017 at 2:00 pm Hartland Township Public Works Department 2655 Clark Road Hartland, MI 48353
More informationMissouri Housing Development Commission
REQUEST FOR QUALIFICATIONS and PROPOSALS Real Estate Broker Missouri Housing Development Commission Response Deadline: Three copies and one electronic copy on a CD-ROM to MHDC No later than 4:00 p.m. on
More informationThis Addendum incorporates the following items: 1. Pre Proposal Summary along with the sign-in sheet (attached).
ADDENDUM No. 1 Commercial Real Estate Brokerage and Marketing Services Project No. 19-009 Date Issued: August 10, 2018 This Addendum is hereby made a part of the Contract Documents dated August 1, 2018
More informationREAL ESTATE BROKER SERVICES : DUPLEXES Request For Proposal # October 30, 2018
REAL ESTATE BROKER SERVICES : DUPLEXES Request For Proposal #2018-53 October 30, 2018 Electronic Submittals are due by 2:00 PM on November 21, 2018 Everett Housing Authority (EHA) is requesting proposals
More informationSITE PLAN REVIEW ADMINISTRATIVE REVIEW. Please Note: Once submitted to the County, all application materials become a matter of public record.
200 W. Oak Street, 3rd Floor Fort Collins, CO 80521 (970) 498-7683 / larimer.org/planning SITE PLAN REVIEW ADMINISTRATIVE REVIEW The submittal requirements listed in this packet are intended to collect
More informationCommunity Dev. Coord./Deputy City Recorder
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 NORTH OGDEN PLANNING COMMISSION MEETING MINUTES December 18, 2013 The North
More informationVILLAGE OF MUNDELEIN NORTH LAKE STREET FAÇADE IMPROVEMENT PROGRAM ARCHITECTURAL DESIGN SERVICES
VILLAGE OF MUNDELEIN NORTH LAKE STREET FAÇADE IMPROVEMENT PROGRAM ARCHITECTURAL DESIGN SERVICES Owner: Village of Mundelein Community Development Department 300 Plaza Circle Mundelein, Illinois 60060 REQUEST
More informationPreliminary Plat Application & Submittal Checklist
Planning & Community Development Department 550 Landa Street New Braunfels, Texas 78130 (830) 221-4050 www.nbtexas.org Preliminary Plat Application & Submittal Checklist Applicant Name: *Signature. * By
More informationSpringbrook Estates Sewer Improvement Area Informational Meeting Presented By Allen County Sanitary Engineering Department August 28, 2013
Springbrook Estates Sewer Improvement Area Informational Meeting Presented By Allen County Sanitary Engineering Department August 28, 2013 Overview Of Tonight s Meeting 1. Project Introduction and Meeting
More informationAPPLICATION PACKET SINGLE FAMILY CLUSTER HOUSING OPTION REVIEW
APPLICATION PACKET SINGLE FAMILY CLUSTER HOUSING OPTION REVIEW COMMUNITY DEVELOPMENT DEPARTMENT CHARTER TOWNSHIP OF PLYMOUTH 9955 N. Haggerty Road Plymouth, MI 48170 Fees Revised 9.13.2017 1. PURPOSE APPLICATION
More informationHousing and Community Development
Housing and Community Development April 11, 2014 Addendum to Appendix J for Request for Proposals for the Development of Affordable Seniors Housing This Addendum shall be read in conjunction with Manitoba
More informationPART ONE - GENERAL INFORMATION
Corrected Date: Page 7 Date of Submittal Changed to Coincide with Submittal Date on Page 5 PART ONE - GENERAL INFORMATION A. INTRODUCTION B. Background Miami Shores Village is soliciting responses to this
More informationPROPOSAL CONTENT AND FORMAT
PROPOSAL CONTENT AND FORMAT The Borough recognizes that respondents are likely to commit significant resources in preparation of their proposals. Further, it is in the Borough s best interest to have maximum
More informationPROCUREMENT DEPARTMENT 2 MONTGOMERY STREET, 3 rd FLOOR JERSEY CITY, NJ ADDENDUM # 4, Revised TO PROSPECTIVE RESPONDENTS TO RFQ# 31224
PROCUREMENT DEPARTMENT 2 MONTGOMERY STREET, 3 rd FLOOR JERSEY CITY, NJ 07302 ADDENDUM # 4, Revised TO PROSPECTIVE RESPONDENTS TO RFQ# 31224 Date: December 24, 2012 LAGUARDIA AIRPORT CENTRAL TERMINAL BUILDING
More informationSpecial Use Permit Application to Allow Short Term Rental
Planning & Community Development Department Planning Division 550 Landa St. New Braunfels, Tx 78130 (830) 221-4050 www.nbtexas.org CC/Cash/Check No.: Amount Recd. $ Receipt No.: Case No.: Submittal date
More informationCITY OF LAREDO Environmental Services Department
CITY OF LAREDO Environmental Services Department April 4, 2016 Request for Qualifications Project: Provide consulting services, equipment, and personnel for the monitoring and ongoing oversight of the
More informationRequest for Proposals (RFP) for. The construction of a new pole barn addition for the AuSable Township Department of Public Works
Request for Proposals (RFP) for The construction of a new pole barn addition for the AuSable Township Department of Public Works Issued: Monday February 26, 2018 Deadline for Final Submission of Questions:
More informationSTATE OF MINNESOTA OFFICE OF THE STATE AUDITOR
REBECCA OTTO STATE AUDITOR STATE OF MINNESOTA OFFICE OF THE STATE AUDITOR SUITE 500 525 PARK STREET SAINT PAUL, MN 55103-2139 (651) 296-2551 (Voice) (651) 296-4755 (Fax) state.auditor@osa.state.mn.us (E-mail)
More informationWe look forward to working with you to build on our collaboration and enhance our partnership on behalf of all Minnesotans.
Date: February 27, 2017 To: County Assessors, Auditors, and Treasurers From: Cynthia Rowley, Director Property Tax Division Subject: Property Tax Services Report The Property Tax Division of the Minnesota
More informationROXBURY COMMUNITY CENTER
APPENDIX A FORM OF CONTRACT This contract ("Contract") is entered into by and between the ("City"), a California municipal corporation, and, a, whose address is. In consideration of the agreements herein
More informationRFP REQUEST FOR PROPOSAL. for TAX CREDIT ADVISOR SERVICES. for BOULDER HOUSING PARTNERS. March 6, 2012 Requested Return: March 15, 2010
RFP 06-2012 REQUEST FOR PROPOSAL for TAX CREDIT ADVISOR SERVICES for BOULDER HOUSING PARTNERS March 6, 2012 Requested Return: March 15, 2010 Boulder Housing Partners 4800 Broadway Boulder, CO 80304 (720)
More informationA Septic-to-Sanitary Sewer System Conversion Packet
A Septic-to-Sanitary Sewer System Conversion Packet Information Meeting June 9, 2014 Mayfield Village Civic Center 6622 Wilson Mills Road Mayfield Village, OH 44143 440-461-2210 INTRODUCTION In 1995, the
More information