Projects Completed FY16, FY17 and FY18 (arranged alphabetically) Abrams Planetarium Install automatic door opener on main doors of the Planetarium. Completed: Summer 2016 Cost: $13,000 Bessey Hall 1 st and 2 nd Floors Classroom Wing Renovated classrooms and corridor on the 1 st and 2 nd floors of Bessey Hall. Variety of accessible seating provided in classrooms and corridors. Single occupant accessible toilet room, personal health room and two quiet study/testing rooms added. Accessible drinking fountain and bottle filling station installed on the floor as well. Completed: Fall 2017 Cost: $2.9 Million (Total project cost) Business College Complex Install automatic door opener to vestibule doors outside of room N130. Completed: Fall 2016 Cost: $12,000 Demonstration Hall: Renovate and expand restrooms in the Arena for barrier-free access. Install automatic door opener. Completed: August 2016 Cost: $200,000 Giltner Hall Install automatic door opener to doors on the North Side of Giltner Hall. Completed: Fall 2016 Cost: $16,000 Jenison Install automatic door opener to women s locker room. Completed: Summer 2017 Cost: $11,000 Office of Planning and Budgets Facilities Planning and Space Management 1
Music Practice Building Install automatic door opener and changed double doors to a single entry door. Completed: Winter 2016 Cost: $35,000 Spartan Stadium South End Zone Addition of 236 bathroom fixtures, including barrier-free stalls and 3 single occupant toilet rooms. Completed: August 2017 Cost: $13 Million (Total project cost) Trout Food Science Building Install automatic door opener to the exterior door at the rear of the building. Install magnet hold-opens on three interior doors. Completed: Summer 2016 Cost: $15,000 Veterinary Medical Center Install automatic door opener to the entrance of the G-Wing (closest to classroom G150). Completed: Summer 2016 Cost: $15,000 Install automatic door opener to the entrance of the E-Wing (closest to classroom E100). Created a single occupant accessible restroom and quiet study/testing room outside of classroom E100 as part of the E100 classroom renovation. Completed: Fall 2017 Cost: $ 1.5 Million (Total Project Cost of E100 Renovation) New Construction All new construction adheres to ADA standards. 1855 Place Phase I Aug 2016, Phase II Fall 2017 FRIB Office Addition III Fall 2016 Golf Facility Jan 2016 Interdisciplinary Science & Tech. Fall 2019 Bio Engineering Building Fall 2016 Business Pavilion Fall 2019 STEM Building Spring 2020 Music Building Addition Schedule TBD Grand Rapids Research Center Fall 2017 Office of Planning and Budgets Facilities Planning and Space Management 2
Accessibility Projects Funded and In Process (arranged alphabetically) ADA Route Site Improvements Shaw Lane Route is part of a multiphase improvement plan to improve accessibility of all persons, and in particular, people with disabilities. Status: Anticipated completion June 2018 Estimated Cost: $600,000 (Total cost of Shaw Lane Route Improvements) Biochemistry Existing restroom vestibule converted to a single occupant accessible toilet room. Status: Anticipate completion winter 2017 Cost: $50,000 Breslin Center Barrier-free stalls and fixtures added to existing north and south restrooms. New single occupancy toilet rooms added. Barrier free entry and exit corridors to and from all public restrooms. New Concession stands designed to be accessible. New barrier-free ramp created at the north end of the site. Power assisted doors added. Upgrades to current lighting meet standards for ADA visibility requirements. Status: In progress (scheduled to be complete Oct 2017) Cost: $50 Million (Total Project Cost) Wharton Center: Path of travel and companion seating modifications associated with the seat replacement project at the Great Hall and Pasant Theater. Status: In progress BOT approved. Anticipate May September 2018 construction. Estimated Cost: $1.5 Million (Total Project Cost) Wills House: Modify site to provide ramped entry with snowmelt to the west entry of the building, automate entry doors as necessary, ensured availability of barrier-free parking, installation of new single occupant accessible restroom at first floor, and provide comprehensive interior finish renovations, ADA signage, as required. Status: In progress anticipate completion February 2018 (interior work) and May 2018 (exterior work) Estimated Cost: $600,000 Office of Planning and Budgets Facilities Planning and Space Management 3
Accessibility Projects In-Planning/Under Review (arranged alphabetically) ADA Route Site Improvements Various Locations Modify site in various pedestrian routes/areas on campus that require site improvements. These site related projects across campus impact accessibility of all persons, and in particular, people with disabilities. Shaw Lane Route funded and in process, reference page 3 of report. South of Shaw Lane Status: Awaiting identification of funding Estimated Cost: $72,000 Various Remaining Locations Status: Awaiting identification of funding Estimated Cost: $3.1 Million (remaining total project cost) Auditorium Field The Rock Relocation of the rock on the current site with associated site improvements for accessibility including accessible walk, lower field level drainage improvements and SE bridge stair removal. Status: Under Review Estimated Cost: $350,000 $375,000 (Total Project Cost) Cook Hall Building: Modify site to provide grade level entry with snowmelt system at new accessible entrance to the building, automate entry doors as necessary, ensured availability of barrier-free parking, installation of new elevator, installation of new single occupant accessible restrooms at first and second floors, ADA signage and fire alarm modifications, as required. Status: In Planning anticipate BOT action to proceed Estimated Cost: $3.8 - $4.8 Million (Total Project Cost) Cowles House Planning in process for barrier-free improvements, including elevator. Status: In Planning anticipate August 2018 completion of Elevator Office of Planning and Budgets Facilities Planning and Space Management 4
Jenison Renovation of the 2 nd, 3 rd and 4 th floors to provide new coaching offices, student athlete space and classroom space. Addition of two single occupant accessible restrooms, personal health room and ADA signage. Status: In Planning anticipate October 2017 BOT action to proceed Estimated Cost: $5.0 - $8.0 Million (Total Project Cost) Library Modify north main entry to provide ramped/grade level entry to the building, automate entry doors as necessary and evaluate the need for snowmelt system. Status: Scope & Estimate TBD Old Botany Building Modify site to provide ramped/grade level entry to the building, automate entry doors as necessary, evaluate need for snow melt system, check availability of barrier-free parking, install elevator, provide toilet room modifications, ADA signage and fire alarm modifications as required. Status: Barrier-free access study in process Packaging Building Modify site to provide ramped/grade level entry to the building, automate entry doors as necessary, evaluate need for snowmelt system, check availability of barrier-free parking, and provide toilet room modifications and ADA signage. Status: Scope & Estimate TBD Urban Planning and Landscape Architecture Building Modify site to provide ramped/grade level entry to the building, automate entry doors as necessary, evaluate need for snow melt system, check availability of barrier-free parking, provide toilet room modifications, ADA signage and fire alarm modifications as required. Status: Awaiting identification of funding Estimated Cost: $1.2 Million Office of Planning and Budgets Facilities Planning and Space Management 5
Wonders Hall Renovations to the center section of Wonders Hall to create modern teaching and learning spaces. This will include conversion of a freight elevator to a passenger elevator for accessibility, new accessible toilet rooms and accessible signage. Status: In Planning BOT approval to plan. Schedule in development. Estimated Cost: $12-13 Million (Total Project Cost) Office of Planning and Budgets Facilities Planning and Space Management 6