Design Development Presentation New North Richland Middle School // Birdville ISD ARCHITECTURE // ENGINEERING // PLANNING // TECHNOLOGY // FACILITY CONSULTING 972-233-1323 // PBK.COM
ACKNOWLEDGEMENT
The PBK Team wishes to express our sincere appreciation to the Board of Trustees and Birdville ISD Administration and Staff for allowing our firm the opportunity to be involved in the design of the New North Richland Middle School. We also extend our utmost gratitude to the individuals who have attended numerous meetings and provided vital information during the design process. Their input and assistance has been most valuable to the success of this very important project. Board of Trustees Jack McCarty Dolores Webb Joe Tolbert Brad Greene Richard Davis Ralph Kunkel Cary D. Hancock President Vice President Secretary Trustee Trustee Trustee Trustee Administration Dr. Darrell G. Brown Elizabeth A. Clark Joe Cammarata Mike Seale Randy Sumrall Mark Thomas Superintendent Associate Superintendent Curriculum & Instruction Associate Superintendent - Student Services Associate Superintendent - Finance Executive Director of Technology Communications Officer Campus Design Review Ann Newhouse John Hughes Mary Huston Beverly Goodman Karen Sanchez Matthew Cho Brandi Black Kathryn Hummer Michaela Blackmon Cheryl Burch Kathy Harvell Paula Stephenson Conan Mathson Kelly DeLeon Rebekah Luckett Danny Detrick Leslie Detrick Rhett Peel Dawna Schewitzer Mark Ashley Stephanie Maupin Ernie Valamides Thank You!
ARCHITECTURAL DRAWINGS & IMAGES
Composite Site and 1 st Floor Plan
SCIENCE SPED LEARNING COMMONS 8 TH GRADE ART COURTYARD COMMONS ADMIN MAIN ENTRY DINING SERVICE YARD DRAMA BOYS LOCKERS GIRLS LOCKERS SPED CHOIR COMP GYM AUX GYM WR FR BAND Composite 1 st Floor Plan
6 TH GRADE SPED CTE 7 TH GRADE Composite 2 nd Floor Plan
ENTRY VESTIBULE REG REC CONF STOR SEC CLINIC PRIN CONF WKRM LOU SRO ACAD COACH PLC ISS AP CONF AP COUN COUN Main Entry & Administration
PREP SCIENCE SCIENCE CM SCIENCE SCIENCE SCIENCE SCIENCE ART Science & Art
COMP BK LEARNING COMMONS WKRM OF WKRM COLLAB SPACE EL MAKER SPACE 8 TH Grade & Learning Commons
COLL & CAREERS BK OPEN TO BELOW WKRM WKRM COLLAB SPACE ENGR TECH EL CTE & 7 TH Grade
COLL & CAREERS READING MATH LAB RES COLLAB SPACE WKRM RES 6 th Grade
OUTDOOR LEARNING KITCHEN SERVING DINING ST STAGE SERVICE YARD ST BLACK BOX ST ST Cafeteria & Drama
PASS KIT SEEC CONF DIA SPE ENS CHOIR P P P P ST ST LIB OFF OFF ENS BAND Fine Arts & Special Ed
OUT STO BOYS ATH BOYS PE GIRLS PE GIRLS ATH CONC ST ST COACH ST ST COACH CON ST CON STO STO LAUN ST ST WEIGHT RM COMPETITION GYM FITNESS RM Athletics & PE
Main Entry View
View from Redondo Street
Exterior Library View
Library View
Library View
Learning Commons View
Learning Commons View
Collaboration Area View
Collaboration Area View
Service Yard View
INTRODUCING
Click to view video
PROJECT SCHEDULE
SCHEMATIC DESIGN PHASE MARCH 23 APRIL 25, 2015 Design Charrette. April 13, 14 & 15, 2015 Present Schematic Design to Board of Trustees... April 25, 2015 DESIGN DEVELOPMENT PHASE APRIL 26 JUNE 25, 2015 Present Design Development to Board of Trustees... June 25, 2015 CONSTRUCTION DOCUMENTS PHASE JUNE 26 OCTOBER 30, 2015 100% Issue for Proposals... October 30, 2015 BIDDING PHASE OCT. 30 - DECEMBER 17, 2015 Receive Proposals. December 1, 2015 Present Proposals to Board of Trustees. December 17, 2015 CONSTRUCTION PHASE DEC. 18, 2015 JUNE 30, 2017 Substantial Completion Date.... June 30, 2017 First Day of School. August 28, 2017 Athletic Fields Complete. October 31, 2017 Project Schedule
PHASE 1 DEMO EXIST. ATHLETIC FIELD ERECT CONSTRUCTION FENCING Phasing Plan
PHASE 2 BUILD NEW MIDDLE SCHOOL Phasing Plan
PHASE 3 REMOVE EXISTING PORTABLES DEMOLITION OF EXISTING MIDDLE SCHOOL Phasing Plan
PHASE 4 BUILD NEW PARKING AND ATHLETIC FIELDS Phasing Plan
Phasing Plan
BOND PROJECT BUDGET
New North Richland Middle School (1,000 students): Construction Cost: 160,000 SF @ $190/SF $30,400,000 Soft Costs @ 18% $ 5,472,000 Includes Furniture, Fixtures, A/E Fees, Technology, Reimbursables, Permits Demolition and Abatement Costs $ 250,000 Total $36,122,000 Bond Project Budget