NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction February 2019 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING Jim Berg AIA DIRECTOR OF FACILITIES CONSTRUCTION 1
ADDITIONS AND RENOVATION PROJECTS IN CONSTRUCTION 2
OLIVER WENDELL HOLMES HS FINE ARTS NEW AUDITORIUM Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager Thomas Curiel Contractor Bartlett Cocke Contract Amount - $32,014,460 Construction Period June 2017 January 2019 Construction Status 97% Package 2 (Building) Project Scope Fine Arts Building Replacement Substantial Completion Interior January 11, 2019. Rendering of New Auditorium 3
OLIVER WENDELL HOLMES HS FINE ARTS NEW AUDITORIUM 4
OLIVER WENDELL HOLMES HS - FINE ARTS NEW AUDITORIUM Bus Loop Auditorium Bandhall Auditorium Lobby 5
SAM RAYBURN MIDDLE SCHOOL Building Replacement Architect Marmon Mok Project Architect Monty Howard NISD Project Manager James Evans Contractor Turner Construction GMP Amount $13,900,000 Tentative Construction Period - June 2018 - August 2019 Construction Status - 40% Project Scope - Building Replacement (Gym, Band and Library) Superstructure work in progress. 6
SAM RAYBURN MIDDLE SCHOOL Building Replacement Band Hall and Courtyard New Gym and Boys Lockers Location New Library Location 7
SAM RAYBURN MIDDLE SCHOOL Building Replacement Gym Building lower level Gym Building - Lower Level Stairwell New Library - Foundation Band Hall 8
F.R. SCOBEE ELEMENTARY SCHOOL Additional Student Canopy Architect Chesney Morales Partners, Inc. Project Architect Richard Morales NISD Project Manager James Evans Contractor Breda Construction, Inc. Contract Amount - $468,095 Construction Period June 2018 March 2019 Construction Status 60% Project Scope Additional Student Canopy Steel framing install in progress. Rendering of Student Canopy 9
F.R. SCOBEE ELEMENTARY SCHOOL Additional Student Canopy Canopy Steel Flatwork Canopy Steel Canopy Steel 10
BRAUN STATION ELEMENTARY SCHOOL Cafeteria/Kitchen Renovations & Window Upgrades Architect Nextgen Architects Project Architect Joel Hernandez NISD Project Manager Thomas Curiel Contractor WR Griggs Construction Co. Contract Amount - $2,671,000 Construction Period June 2018 February 2019 Construction Status 95% Project Scope Cafeteria/Kitchen Renovations and Window Upgrades Substantially Complete in February 4, 2019. 11
BRAUN STATION ELEMENTARY SCHOOL Cafeteria/Kitchen Renovations & Window Upgrades Kitchen Equipment Kitchen Equipment Cafeteria - Serving Line Gates Serving Line 12
JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation Architect Garza Bomberger & Associates Project Architect Roy Lewis NISD Project Manager James Evans Contractor CGC General Contractors, Inc. Contract Amount - $4,249,000 Construction Period June 2018 August 2019 Construction Status 40% Project Scope Cafeteria / Kitchen Renovation Kitchen renovation work in progress. Underground utilities in progress. Rendering of Caf eteria Interior 13
JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation RENOVATED CAFETERIA NEW KITCHEN ADDITION Aerial of Site 14
JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation Kitchen Exterior Kitchen Exterior Kitchen Interior 15
E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades Architect Garza Architects Project Architect Jesse Garza NISD Project Manager Thomas Curiel Contractor Webber Commercial Construction Co. Contract Amount - $2,784,000 Construction Period June 2018 February 2019 Construction Status 95% Project Scope Fine Arts Addition, Bus Canopy & Drainage Upgrades Fine Arts Classroom & Interior Substantial Completion Jan.15, 2019 Exterior Canopies, landscape & irrigation underway. Rendering of Band Room Addition at Fine Arts Classrooms 16
E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades Aerial Vi ew of Campus 17
E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades Existing Front Entrance and Fine Arts Classrooms Rendering of Band Room Addition at Fine Arts Classrooms 18
E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades Fine Arts Building - Exterior Canopies Fine Arts Building - Exterior Canopies 19
TOM C. CLARK HIGH SCHOOL Cafeteria / Kitchen Renovation Architect Garza Architects Project Architect Jesse Garza NISD Project Manager Chris Parker Contractor Central Builders, Inc. Contract Amount - $3,892,000 Construction Period June 2018 February 2019 Construction Status 92% Project Scope Cafeteria / Kitchen Renovation Kitchen Renovation punch inspections in progress. Completion scheduled February 18, 2019. Renovated Cafeteria 20
TOM C. CLARK HIGH SCHOOL Cafeteria / Kitchen Renovation Kitchen Area - Equipment Kitchen Area - Serving Lines Office Area Kitchen Equipment 21
KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation Architect Pfluger Architects Project Architect Carr Hornbuckle NISD Project Manager Chris Parker Contractor WR Griggs Construction Contract Amount - $6,141,000 Construction Period May 2018 August 2019 Construction Status 55% Project Scope Science Classroom, Library Renovation and Classroom Addition Plumbing, HVAC & Electrical in progress. Building Addition Framing & Masonry in progress. 22
KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation Site Plan 23
KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation Classroom Addition Prep Room Science Classroom Renovation Science Classroom Renovation 24
2014 BOND PROJECTS IN BID/DESIGN PHASE SUMMER 2018 25
KALLISON RANCH AREA MIDDLE SCHOOL New Middle School Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager Thomas Curiel Contractor Bartlett Cocke General Contractors, LLC Construction Budget - $48,000,000 Construction Period July 2019 May 2021 Status - Schematic Design in progress Project Scope New Middle School 26
RANCHO DEL LAGO AREA ELEMENTARY SCHOOL New Elementary School Architect Garza Bomberger Project Architect Roy Lewis NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget $23,000,000 Construction Period March 2019 May 2020 Status Approval of Contractor to be recommended at February Board Project Scope New Elementary School Rendering of Rancho Del Lago Elementary School 27
NORTHSIDE NATATORIUM Pool Replacement Architect Nextgen Architects NISD Project Manager James Evans Contractor Henock Construction, LLC Contract Amount - $2,430,000 Construction Period March 2019 July 2019 Status Demolition (March 15, 2019) Project Scope Pool Replacement Existing Pool 28
NORTHSIDE SPORTS GYM PLAZA OF INFLUENCE PYLONS Architect Marmon Mok Project Architect Monty Howard NISD Project Manager Thomas Curiel Contractor Spaw Glass Contract Amount - $350,000 Construction Period March 2019 April 2019 Status Construction Project Scope Plaza Pylons Flanking Steel Pylons 29
2014 BOND PROJECTS IN BID/DESIGN PHASE SUMMER 2019 30
JOHN MARSHALL HIGH SCHOOL Library Upgrades Architect Garza Bomberger & Associates NISD Project Manager James Evans Contractor TBD Construction Budget - $3,000,000 Construction Period Spring 2019 Spring 2020 Status Construction Drawings in Progress Project Scope Library Addition & Renovation Interior View 31
NORTHSIDE ALTERNATIVE MIDDLE SCHOOL Science Classroom Addition Architect C.J. Lammers & Associates Project Architect Chris Lammers NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $600,000 Construction Period June 2019 October 2019 Status - Bidding Project Scope Science Classroom Addition & Renovation 32
NEW CONSTRUCTION PROJECTS IN DESIGN 2018 BOND PROJECT 33
"GALM ROAD AREA" HIGH SCHOOL Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager James Berg Contractor Joeris Contractors Construction Budget - $112,000,000 Construction Period February 2020 June 2022 Project Scope New High School Schematic Design in progress 34
2018 BOND PROJECTS ADDITIONS/RENOVATIONS IN DESIGN 35
2019 SECURITY LOBBIES FOR 21 CAMPUSES Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $2,980,000 Construction Period June 2019 December 2019 Status - Approval of Contractor to be recommended at February Board. Project Scope Security Lobbies Behlau ES Fisher ES Martin ES Burke ES Galm ES Murnin ES Carson ES Hatchett ES Oak Hills Terrace ES Driggers ES Langley ES Ott ES Elrod ES Lewis ES Raba ES Evers ES Lieck ES Westwood ES Fernandez ES Martin ES Northside Police Department 36
GLENOAKS ELEMENTARY SCHOOL Library and Classroom Building Architect Nextgen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor TBD Contract Amount - $4,000,000 Construction Period June 2019 July 2020 Status Bidding Project Scope Library and Classroom Building Front Entry Library - Reading Area 37
NORTHWEST CROSSING ELEMENTARY SCHOOL Cafeteria / Kitchen Renovation Architect Pfluger Architects Project Architect Carr Hornbuckle NISD Project Manager Chris Parker Contractor TBD Construction Budget - $2,000,000 Construction Period June 2019 December 2019 Status - Bidding Project Scope Cafeteria / Kitchen Renovation Cafeteria Proscenium - Prespective View 38
PAT NEFF MIDDLE SCHOOL Cafeteria Upgrades Architect Garza Architects Project Architect Jesse Garza NISD Project Manager Thomas Curiel Contractor TBD Construction Budget - $3,200,000 Construction Period June 2019 February 2020 Status - Master Plan and Schematic Design in progress Project Scope Cafeteria Upgrades 39
MEADOW VILLAGE ELEMENTARY SCHOOL ALE & Mechanical Upgrades Architect Chesney Morales Partners, Inc. Project Architect Richard Morales NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $3,400,000 Construction Period June 2019 November 2019 Status - Approval of Contractor to be recommended at February Board. Project Scope ALE and Mechanical Upgrades 40
WILLIAM P. HOBBY MIDDLE SCHOOL Bus / Student Covered Walkway Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $2,800,000 Construction Period June 2019 December 2019 Status - Bidding Project Scope Bus / Student Covered Walkway and Front Entry Canopy Rendering 41
SANDRA DAY O'CONNOR HIGH SCHOOL Agricultural Facility Upgrade Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Chris Parker Contractor TBD Construction Budget - $1,275,000 Construction Period March 2019 July 2019 Status - Approval of Contractor to be recommended at February Board. Project Scope Agricultural Facility Upgrade New Configuration of Building P 42
SANDRA DAY O'CONNOR HIGH SCHOOL Flooring Replacement Architect Callins Watts Sendejo Architects Project Architect Robert Watts NISD Project Manager Chris Parker Contractor TBD Construction Budget - $150,000 Construction Period June 2019 August 2019 Status - Approval of Contractor to be recommended at February Board. Project Scope Flooring Replacement 43
OLIVER WENDELL HOLMES HS & JOHN JAY HS Paint Booth Replacement Architect Pfluger Architects Project Architect Carr Hornbuckle NISD Project Manager Chris Parker Contractor TBD Construction Budget - $300,000 Construction Period June 2019 August 2019 Status - Approval of Contractor to be recommended at February Board. Project Scope Paint Booth Replacement 44
2019 DOOR HARDWARE PROJECT Various Campuses Architect Huckabee Associates Project Architect Jeff Rodriguez NISD Project Manager Chris Parker Contractor TBD Construction Budget - $461,000 Construction Period June 2019 August 2019 Status - Approval of Contractor to be recommended at February Board. Project Scope Door Hardware R.R. Cable ES Leon Valley ES Northwest Crossing ES William J. Thornton ES Eduardo Villarreal ES Anson Jones MS 45
ROOFING PROJECTS 46
LIST OF SC HOOLS 2016 Hail Damage Roofing Projects Phase I - Complete Phase II Complete Phase III In Construction Beard Elementary School Carnahan Elementary School Clark High School Stevenson Middle School Carlos Coon Elementary School Elrod Elementary School Portable Roofs - (Substantial Completion) South Transportation Station Fernandez Elementary School Esparza Elementary School (Closed out) Nichols Elementary School (Closed out) Connally Middle School (Closed out) Howsman Elementary School (2014 Bond) Leon Valley Elementary School (Closed out) Scarborough Elementary School (Closed out) Alternative ES & MS - North (Closed out) Burke Elementary School (Closed out) Brauchle Elementary School Leon Springs Elementary School Raba Elementary School Burke Elementary School (2014 Bond) Clark High School Helotes Elementary School O Connor High School (1st Phase) Rhodes Elementary School Sul Ross Middle School Steubing Elementary School Portable Roofs Phase II (102) MEP Hail Damage - Various Campuses (54) Phase IV - In Construction Vale Middle School Zachry Middle School Driggers Elementary School Briscoe Middle School Colonies North Elementary School Hoffmann Elementary School Scobee Elementary School Family Engagement Center Northwest Crossing Elementary Henderson Elementary School Knowlton Elementary School Maintenance Building (2014 Bond) 47
2016 Hail Damage Roofing Projects Phase V - Design O'Connor High School (2nd Phase) Brandeis High School (1st Phase) Stinson Middle School Kuentz Elementary School John Jay High School (2014/2018 Bond) Hobby Middle School John Glenn Elementary School (2014 Bond) Adams Hill Elementary School (2018 Bond) Phase VI Future Support Services Center Oak Hills Terrace Elementary School Kelly Smith Technology Center Taft High School Northside Activity Center North Transportation Station Pease Middle School Health Careers High School Northside Tennis Center Jefferson Middle School Mireles Elementary Brennan High School Holmes High School Rhodes Transportation Center Ward Elementary School McDermott Elementary School Mead Elementary School Myers Elementary School 48