NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction October 2017 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING Jim Berg AIA DIRECTOR OF FACILITIES CONSTRUCTION 1
HARLAN HIGH SCHOOL Architect Garza Bomberger & Associates Project Architect Roy Lewis NISD Project Manager James Berg Contractor Joeris General Contractor GMP - $110,800,000 Construction Period October 2014 July 2017 Construction Status Complete Project Scope New 2800 Student High School 2
KALLISON ELEMENTARY SCHOOL Architect Garza Bomberger Project Architect Roy Lewis NISD Project Manager Marilyn Sevedge Contractor Guido Construction Contract Amount - $24,640,000 Construction Period March 2016 July 2017 Construction Status Complete Project Scope New 800 Student Elementary School 3
DR. LINDA G. MORA ELEMENTARY SCHOOL Architect Noonan Rittiman Project Architect John Rittiman NISD Project Manager Chris Parker Contractor DL Bandy Constructors, Inc. Contract Amount - $22,465,000 Construction Period March 2017 May 2018 Construction Status 26% Project Scope New 800 Student Elementary School (Prototype of Boldt ES and Cole ES) Masonry in Progress. Utilities and Foundation in progress. Concrete columns and Second Floor being constructed. North Elevation Area 1 South Elevation Area 2 4
DR. LINDA G. MORA ELEMENTARY SCHOOL 5
ADDITIONS AND RENOVATION PROJECTS IN CONSTRUCTION 6
GLENOAKS ELEMENTARY - Administration Upgrades/Security Lobby Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor McGoldrick Construction Co. Contract Amount - $3,477,000 Construction Period June 2016 August 2017 Construction Status Complete Project Scope New Administration Building Front Entrance 7
NORTHSIDE ACTIVITY CENTER RENOVATIONS Architect Richard Sanchez Architects, Inc. Project Architect Richard Sanchez NISD Project Manager Thomas Curiel Contractor O Haver Contractors Co. Contract Amount - $5,319,485 Construction Period February 2017 January 2018 Construction Status 32% Project Scope Addition/Renovation Building Envelope in Progress. MEP Systems in Progress. Exterior Building Envelope New Chillers Interior Framing 8
PAUL TAYLOR FIELD HOUSE RENOVATIONS Architect Garza Bomberger Architects Project Architect Roy Lewis NISD Project Manager Thomas Curiel Contractor Stoddard Construction Management, Inc. Contract Amount - $3,400,000 Construction Period February 2017 September 2017 Construction Status 92% Project Scope ADA Interior/Exterior Renovations Interior and Exterior Finishes. Display Corridor Gymnasium Court Area 9
CHILD NUTRITION CENTER Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager James Evans Contractor Workman Commercial Contract Amount - $5,726,500 Construction Period July 2016 2017 Construction Status Complete Project Scope Warehouse Renovation Rendering of Renovated Warehouse 10
2017 SECURITY LOBBIES at (9) ELEMENTARY SCHOOLS Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor CGC General Contractors Contract Amount - $1,293,000 Construction Period June 2017 August 2017 Construction Status Complete Project Scope New Security Lobby for (9) Elementary Schools: Adams Hill Elementary School Allen Elementary School Beard Elementary School Braun Station Elementary School Forester Elementary School Hoffmann Elementary School Knowlton Elementary School Timberwilde Elementary School Villarreal Elementary School Closeout in Progress. 11
2017 SUMMER FLOORING REPLACEMENTS Carson ES, Neff MS, & Warren HS Architect Huckabee Architects Project Architect Jeff Rodriguez NISD Project Manager Chris Parker Contractor SAFFI Contract Amount $339,120 Construction Period June 2017 August 2017 Construction Status Complete Project Scope Replacement of Flooring Warren HS - Library 12
COLONIES NORTH ELEMENTARY Window Upgrades / ADA Work Architect Huckabee Architects Project Architect Jeff Rodriquez NISD Project Manager Chris Parker Contractor Central Builders Contract Amount - $2,022,000 Construction Period June 2017 October 2017 Construction Status 85% Project Scope Window Upgrades and ADA Work Masonry, windows and finishes in progress. Classrooms are complete. Front Windows 13
KNOWLTON ELEMENTARY Cafeteria / Kitchen Renovations / Library Addition Architect Pfluger Project Architect Carr Hornbuckle NISD Project Manager Chris Parker Contractor O Haver Contract Amount $2,335,100 Construction Period June 2017 November 2017 Construction Status 43% Project Scope Renovations and Additions to Cafeteria, Kitchen & Library Library Complete Kitchen work ongoing. Story Telling Area Kitchen Interior Work Area 14
NEFF MS COMPETITION GYM FLOORING AND BLEACHERS Architect Garza Architects Project Architect Jesse Garza NISD Project Manager Chris Parker Contractor Henock Construction, LLC Contract Amount $243,600 Construction Period June 2017 August 2017 Construction Status Complete Project Scope Replacement of Flooring and Bleachers School Logo New Bleachers at Gym 15
GLENOAKS ELEMENTARY - Window Upgrades / ADA Work Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor Central Builders, Inc. Contract Amount - $1,100,000 Construction Period June 2017 August 2017 Construction Status Complete Project Scope Window Upgrades and ADA Work Renovated Restroom ADA Accessible 16
GLENN ELEMENTARY School Building Replacements / Security Lobby Architect LPA Project Architect Mark Oppelt / Lowell Tacker NISD Project Manager Marilyn Sevedge Contractor Suburban Construction Contract Amount - $6,850,000 Tentative Construction Period June 2017 August 2018 Construction Status 17% Project Scope Replacement of Administration/Classroom Building Site Utilities and Foundation Piers in Progress. Foundation Construction Rendering of Building Replacement Foundation Construction 17
HOLMES HS FINE ARTS - AUDITORIUM Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager Thomas Curiel Contractor Bartlett Cocke Contract Amount - $32,014,460 Construction Period June 2017 December 2018 Construction Status 13% Project Scope Fine Arts Building Replacement Foundation Piers and Utilities work in Progress Rendering of New Auditorium 18
HOLMES HS FINE ARTS - AUDITORIUM 19
BOONE ELEMENTARY SCHOOL Architect Garza Architects Project Architect Jesse Garza NISD Project Manager James Evans Contractor Central Builders, Inc. Contract Amount - $5,562,000 Construction Period June 2017 August 2018 Construction Status 26% Project Scope New Administration Area and New Bus/Student Walkway Canopy Interior work ongoing in new Administration addition. Interior Construction Rendering of New Administration Entrance Steel Frame Construction 20
2017 DOOR HARDWARE Glass ES, Westwood Terrace ES and Holmes HS Architect Chesney Morales Project Architect Richard Morales NISD Project Manager James Evans Contractor Central Builders, Inc. Contract Amount $117,000 Tentative Construction Period June 2017 August 2017 Construction Status Complete Project Scope Replacement of Door Hardware for Accessibility New Door Hardware 2017 FLOORING REPLACEMENTS Elrod, Glenn, Glenoaks, & Michael Elementary Architect CWS Architect Project Architect Robert Watts NISD Project Manager Chris Parker Contractor San Antonio Floor Finishers, Inc. Contract Amount $133,900 Construction Period June 2017 August 2017 Construction Status Complete Project Scope Replacement of Flooring New Flooring at Michael Elementary 21
2014 BOND PROJECTS IN BID/DESIGN PHASE SUMMER 2018 22
PROJECTS IN DESIGN 1. Colby Glass Elementary Window Upgrades / ADA 2. Glenoaks Elementary Library, Classroom Renovation, Cafeteria and Gym 3. Stinson Middle School Science Classrooms / Library Upgrades 4. Rayburn Middle School Gym, Band and ALE Upgrades 5. Mary Hull Elementary, Linton ES and Scobee ES Bus Canopy Upgrades 6. Pease Middle School Fine Arts and Canopy Upgrades 7. Braun Station Elementary Cafeteria / Kitchen / Window Upgrades 8. Clark High School Cafeteria / Kitchen Upgrades 9. Evers Elementary Flooring Upgrades 10. Kallison Ranch Area Middle School New Middle School 11. Rancho Del Lago Area Elementary New Elementary School 23
ROOFING PROJECTS 24
ROOFING PROJECTS 2014 BOND PROGRAM - COMPLETED 2016 HAIL DAMAGE ROOFING 1. Boone Elementary School 2. Cable Elementary School 3. Howsman Elementary School 4. Anson Jones Middle School 5. Lewis Elementary School 6. Linton Elementary School 7. Mary Hull Elementary School 8. May Elementary School 9. Taft High School 10. Paul Taylor Field House 11. Villarreal Elementary School Phase I In Construction 1. Carnahan Elementary School (75%) 2. Beard Elementary School (95%) 3. Clark High School (90%) 4. Carlos Coon Elementary School (75%) 5. Fernandez Elementary School (95%) 6. Elrod Elementary School (90%) 7. Stevenson Middle School (75%) 8. South Transportation (98%) Phase II Bidding 1. Esparza Elementary School 2. Connally Middle School 3. Nichols Elementary School 4. Howsman Elementary School 5. Burke Elementary School 6. Leon Valley Elementary School 7. Alternative MS North 8. Scarborough Elementary School 9. Brauchle Elementary School 10. Raba Elementary School 11. Leon Springs Elementary School 25
ROOFING PROJECTS 2014 BOND PROGRAM - COMPLETE Howsman Elementary School May Elementary School Paul Taylor Field House Boone Elementary School 26
ROOFING PROJECTS 2016 HAIL DAMAGE ROOFING In Construction Clark High School Carlos Coon Elementary School Fernandez Elementary School Elrod Elementary School 27
2016 GROWTH & IMPROVEMENT 28
2017 GROWTH IMPROVEMENT 1. 2017 Athletic Areas Upgrades Hobby MS, and Taft HS 2017 Athletic Areas Upgrades Pease MS Complete 2. Interior Painting Project Jordan Middle School - Complete 3. Athletic Storage Building Taft HS Complete and John Jay HS 60% Complete 29