Renovation Progress. June 2-15, Weeks 35 & 36

Similar documents
Renovation Progress. May 5 11, Week 31

Renovation Progress. July 21 Aug 3, Week 42 & 43

Renovation Progress. July 7-13, Week 40

Renovation Progress. Apr , Week 29

Renovation Progress. Nov. 4 9, Week 57

Renovation Progress. Sep , Week 51

The Benezet House. 13 Penn Center Circle E Director-Walter Mack Emergency contact Robert Lee Johnson

FICO Realty Group Presents 485 Washington Street Woburn MA 01801

NOTICE OF SALE. Old Mill Townhomes 725 Mill Stream Lane Lynchburg, VA 24502

20294 E. Maplewood Pl. Centennial, CO List Of Custom Property Features & Amenities

46 WOODS AMMONS ROAD Adorable 1960 s Historic Bungalow Mars Hill

MEDICAL OFFICE PORTFOLIO SALE

Saint Cloud Business Center

17 N Centre Ave Leesport, PA 19533

7130 County Road County Road 121, Fredericktown, Ohio 43019

1. PRESENTATION OF THE PROJECT

19 RED OAK ROAD Renovated Brick Ranch Lakeview Park

Kieran Boughan. San Francisco Architect RESIDENTIAL

RIDDLE RIDDLE ASSOCIATES, INC.

690 Monashee Road. House MAIN FLOOR. Living Room. Dining Room

BEFORE

DESCRIPTION OF LANDLORD'S WORK & TENANT'S WORK

1,600+/- Acres Macon County, Missouri

THE OAKWOOD. $342,500 lot cost not included in pricing ANGELA CLARK VICE P RE S I DENT O F SALES

10' - 0" 6' - 0" Bedroom 2 99 SF 12' - 7" Master Bedroom 287 SF. 3' - 4" 3' - 4" Living / Hall 294 SF 35 SF 6' - 0"

Southlands 52 Burnham Road Epworth Northern Lincolnshire DN9 1BY

Single Family Property Information for Listing Fax

MULTI-USE COMMERCIAL PROPERTY

Riddell Gardens. Investment Package P HASE ONE - 18 UNITS CONDOMINIUM TOWNHOMES. 225 Riddell Street, Woodstock, Ontario VALOUR CAPITAL

For Additional Information:

1 B Swanson Road Auburn, MA (508)

Residencial El Prado - "Viviendas desde *. Plaza y Trastero Incluido" Ensanche de Vallecas (caseta nº 1)

4472 LAKE SHORE DRIVE BOLTON LANDING, NEW YORK

Multi-Family Properties Available

Accessible drinking fountain does not have a clear 30 wide floor space centered on the drinking fountain (centerline to the counter edge is 12 ).

Residencial Cármenes Balcón de Granada c/ Zahareña (Barranco del Abogado),

414 BRANNAN ST SAN FRANCISCO, CA

21-BEDROOM MOTEL INVESTMENT THREE-LEVEL MULTIFAMILY OPPORTUNITY

Solicitation for Offers: 135 Allen Brook Lane Williston, Vermont

Riddell Gardens. Tenant Package CONDOMINIUM TOWNHOMES Riddell Street Woodstock

Investigation Reference No. Investigation Status. Investigation Description

ReNOVATION à la carte Program

Rénovation. municipal

Foxwood 2048 Cardwell Road, Crozier, VA 23039

We Bring Real Estate to Life

Residencial Jardins del Castellarnau - Fase VII C/ Walter Benjamin 27, 08206

SITEMAP. (775)

Exceptional Multi-Tenant

Residencial Puerta de Levante c/ Enric Valor 2,

Rock Island County Courthouse History & Significance

RESIDENCES EFFORTLESS LUXURY IN ONE OF CANBERRA S MOST PRESTIGIOUS SUBURBS BY VILLAGE BUILDING CO. 15 CURLEWIS CRESCENT GARRAN

Kevin J. Maher Homes by Emerson 1B Swanson Road Auburn, MA 01501

HOUSING CODE CHECKLIST FOR RENTAL INSPECTIONS

Camelot Associates Corporation:

332 MacKay Street - New Edinburgh/Lindenlea

~ Farms & Estates Realty ~ Premier Properties. The Cuckoo s Nest

The. Conveniently Located on Heydenreich, Just North of Hall Road

AREA AND COMMUNITY HIGHLIGHTS

48 MALVERN WALK (LOT 12) GreenBuilt and EnergyStar Home by JAG Construction

J ILL BROWN & COMPANY, REALTORS. e j JILL BROWN BROKER/OWNER

Residencial Altos del Sabinal - "Viviendas desde *. Plaza y Trastero Incluido"

Smith Douglas Homes Presents MORGAN S RUN

Riddell Gardens. Investment Package CONDOMINIUM TOWNHOMES. 255 Riddell Street, Woodstock, Ontario VALOUR. Mortgages #12051

Four Bedroom 2.5 Bath Colonial: The Grand Maple 2,319 sq. ft. Starting at $329,990

The Peaks Features List

528 3rd Street E., Sonoma GardenHomeSonoma.com Offered at $3,200,000

Renovating older apartment buildings A multi-disciplinary international project. Architectural design & construction

KING RICHARD DEVELOPMENT

The Historic Raleigh Times Building Restoration Project

39 Holly Street, Maugerville

CUMBERLAND SCHOOLS WORK PROPOSED 2018

!"#$%$&'!"!#$!#%&$'%())%$'* Recreation. Recreation. Storage. Storage. Mech. Mech. Bath. Bath. Bedroom 4. Bedroom 4. Area Schedule.

THE TEN AT LAKE FORREST. FROM THE $850's

DEER HAVEN FARM Acres

By Emerson Homes. Kevin J. Maher Emerson Homes 1B Swanson Road Auburn, MA 01501

Welcome to HeatherBrook

BACH HOUSE CORE TOUR. -Interpreters should be familiar with material at each stop, as they will operate on a rotating basis.

NEW HAMPSHIRE HISTORIC PROPERTY DOCUMENTATION DINARDO-DUPUIS HOUSE NH STATE NO Wight Street, Berlin, Coos County, New Hampshire

Castle Gate Towers. Windsor s Newest Luxury Condo. Our vision of what maintenance free living should be

CITY OF NORTH MANKATO CAPITAL ASSET POLICY ADOPTED: JANUARY 1, 2003 REVISED EFFECTIVE: _JANUARY 1, 2016

4921 HIDDEN RIVER DRIVE Fayette County, Kentucky Acres

For Additional Information:

Feature Package Option

Charles Kozminski Elementary Community Academy

The Peaks Features List

2-STORIES. Our 2-Story. American traditional WINSTON A. designed homes. boast of modern. spectacular floor. plans that create an.

HUDSON COUNTY NEW CONSTRUCTION MULTI-FAMILY RESIDENTIAL: NEWARK AVE JERSEY CITY, NJ BLOCK:11010, LOT:4. Design:

U.S. Department of Housing and Urban Development Office of Public and Indian Housing. A Good Place to Live!

APPROPRIATION STRUCTURE APPRAISAL

SETX Environmental, Inc. Environmental Consulting & Testing Asbestos - Mold Lead ESA s

Property ID: Englantilaisaukio 10, Helsinki

8 LAUREN LANE Newly Remodeled Home with Lower Level Apartment

43 Gunning Point Avenue, Sippewissett

flexible spaces all the right places... fogg.com ...Euclid Corridor Industrial Mall 1100 East 222nd St., Euclid, Ohio I-90 E. 222 St.

518 3 rd Avenue South St. Petersburg, Florida

OBTAINING A CERTIFICATE OF OCCUPANCY FOR UNAPPROVED DWELLING UNITS

RELAX... You re at the Village

St Peter's Way, Mickle Trafford, Chester, Cheshire CH2 4EJ

Crescent Heights in St. Petersburg, FL

For Sale by Owner Photos Historic Curry Derr House 405 East Cambridge Avenue in Greenwood, SC Built between 1936 & square feet

Transcription:

Renovation Progress June 2-15, 2012 Weeks 35 & 36

Jun 2 Sisters investigate the progress and ponder the finished arrangement of the reception area (right) and the residence area on 2 nd Ottilia (below)

Jun 5 The Sisters are on silence of a week of retreat but the work carries on all around them outside and inside

Jun 5 Sheetrock crew installs framing system to which the ceiling sheetrock will be attached

Jun 5 Composite photo shows the wood decking yet to be completed so that the roofers can begin their job of adding flashing and shingles

Jun 5 Installation of exterior plywood around the BSRC Dining Area

Jun 5 Wooden framing around the north porch and south side mini-slab are finally dismantled

Jun 5 3 rd Ottilia bedrooms get new signage to indicate that soon and very soon we re going get moving again

Jun 5 Thresholds cleared of jagged brick and mortar so that filler material can be poured to transition from the hallway into rooms where new doorways were cut

Jun 5 Busting door openings through four layers of brick for the elevator & egress stairwell completed on 3 rd Ottilia (left) and the new private bathroom (right)

Jun 5 Wiring up roll-down doors on the center stairwell to the fire alarm system

Jun 5 Painting walls in the Infirmary bedrooms begins

Jun 5 Bathroom tile work ready to begin in the Infirmary

Jun 6 It is a beautiful day in the neighborhood to get the roof decking and felt installation finished!

Jun 6 North porch entrance doorframe is being installed

Jun 6 Roofing crew hard at work on the south side of the new kitchen

Jun 6 Ceiling framing progresses into the new BSRC Dining Area

Jun 6 Trench dug along south wall for sealing the foundation bricks and re-working the access road to the Ottilia tower area

Jun 6 More masonry sealant is applied to Ottilia tower and the new porch extension; preparing for red brick

Jun 6 Doorway to staff restroom beneath center stairwell of Ottilia being opened; 1 st Ottilia Offices get a coat of paint; sprinkler heads installed in 1 st Ottilia hallway

Jun 6 3 rd floor tower scaffolding is removed while final closure of windows above lintels to elevator & stairwell access doorway is underway on 2 nd floor

Jun 6 A view from the former stage door into the new kitchen and food service area

Jun 6 A view from the former stage door into the new kitchen and food service area looking to the south (right) and north (below)

Jun 6 A look down the Passageway (left) and the north porch (right)

Jun 6 BSRC Dining Area entrance (left) and the two dining areas (below)

Jun 6 Another angle looking back toward the kitchen entrance from the former stage

Jun 7 Roofers at work on flashing and shingle installation

Jun 7 Roofers at work on flashing and shingle installation south side view

Jun 7 Down on 1 st Ottilia with the jackhammer opening the access to the elevator and stair tower

Jun 7 Ottilia tower finally getting red brick façade on the north side

Jun 7 Furring strips going up in private retreatant common room

Jun 7 Wood roof decking on Ottilia tower beginning to appear; remaining scaffolding begins to disappear (for now)

Jun 7 With a roof over the kitchen elevator, the pit has been cleaned out of water and debris

Jun 7 Finalizing and sealing the kitchen foundation on the south wall

Jun 7 New baseboards in the antique parlors

Jun 7 New doorway underneath the center staircase

Jun 7 Roll-down door on 2 nd Ottilia finally closed in

Jun 7 Access openings to Ottilia tower on 2 nd floor (hallway and bathroom)

Jun 7 Access openings to Ottilia tower on 3 rd floor (hallway and bathroom)

Jun 7 Kitchenette cabinetry arrives for 2 nd and 3 rd Ottilia

Jun 7 Kitchenette arrangement for 3 rd Ottilia

Jun 7 Infirmary tile work has begun in bathrooms

Jun 7 More Infirmary bedrooms are painted

Jun 8 The great Ottilia tower cleanup begins as the last of the 1 st floor opening is being completed

Jun 8 Roofers make it to the north side of the new construction

Jun 8 2 nd Ottilia door-to-window proceeding with exterior red brick installation

Jun 8 Roofing shingles continue to go on at a fast pace

Jun 9 The Sisters investigate the new kitchen and BSRC Dining Area for the first time with much excitement and many questions

Jun 9 Sisters behold the new views for the north porch and the BSRC Dining Room wonder, awe, and excitement fill the air

Jun 11 A new water line to be installed from Convent Rd to the south end of Ottilia Hall

Jun 11 Clean tap water is on the way! Bless you, boys!

Jun 11 Window frame installation for the new passageway and dining area

Jun 11 Ceiling sheetrock begins to go up in the kitchen and the BSRC Dining Area

Jun 11 Masonry progress on the south wall of the kitchen (top) and the north wall of the Ottilia tower (bottom)

Jun 11 Installation of ceiling sheetrock and office doors on 1 st Ottilia

Jun 11 Demolition of old Passageway lowered ceiling grid and remaining tiles there is a light at the end of the tunnel!

Jun 12 In goes the new natural gas line for the Infirmary backup generator around Mary Hall and the lake, then across Janeway Dr.

Jun 12 Incoming water line dodging the old tennis court and the numerous trees on the front lawn

Jun 12 Welding continues to secure metal flooring to joists and other steel framing before concrete can be poured in the Ottilia tower

Jun 12 Ceiling grids are being installed in Infirmary bedrooms

Jun 12 Bathroom floor tile continues to be installed in the Infirmary

Jun 12 Doorway framing and baseboards are installed in 1 st Ottilia offices

Jun 12 Ceiling supports go up on the north porch; what a mighty fine structure going up to serve the People of God in our area!

Jun 12 Measured from this sidewalk and that, X marks the spot for the new fire hydrant

Jun 12 Following the pink line to locate the new drop-off curb for the circular drive

Jun 12 Being careful not to disturb the electrical lines while trying to get the gas line in

Jun 12 Filling the Ottilia porch extension with gravel one scoop at a time

Jun 12 Plaster patches around electrical boxes on Ottilia s center stairwell

Jun 12 Infirmary baseboards old and new are installed in bedrooms

Jun 12 2 nd Ottilia kitchenette & laundry cabinetry is installed

Jun 12 Transition thresholds are set in between Ottilia hallway and bedrooms where necessary

Jun 12 Cabinetry for the new mailroom on 2 nd Ottilia) being installed; phone booth glass wall will provide much needed privacy for conversations while allowing natural light to brighten the inner hallway during the daytime hours

Jun 13 Replacing broken window panes on 1 st Ottilia s south and west sides

Jun 13 Digging trenches and holes for the new water vault on the south side of Ottilia Hall; drilling underground preserves the asphalt road

Jun 13 Drying out and waterproofing the north porch masonry

Jun 13 Metal roof is fabricated and then installed on the north porch

Jun 13 Insulation goes up in the Sisters new gathering and dining area

Jun 13 Ceiling of the Passageway extension is being installed

Jun 13 Ceiling progress in the kitchen and BSRC dining area

Jun 13 Marking off where interior walls of the kitchen will be located wall between BSRC serving and the kitchen wall between dishwashing area and the kitchen

Jun 13 3 rd Ottilia kitchenette and laundry cabinets

Jun 13 3 rd Ottilia phone booth; painters on 3 rd Ottilia painting trim

Jun 13 3 rd Ottilia entrances to the new tower: elevator & stairwell (left) and the private bathroom (right)

Jun 13 3 rd Ottilia narrow wall trim is being installed

Jun 13 2 nd Ottilia bathroom light and plumbing fixtures being installed

Jun 13 In goes the water vault

Jun 14 Supply delivery new and old (Ottilia s doors and transoms gradually make their way back from storage in the barn)

Jun 14 Ceiling sheetrock gets installed in the hallway before moving into bedrooms and offices on 1 st Ottilia

Jun 14 The new fire hydrant goes into the ground

Jun 14 Masonry crew back to the red brick and the preparations for the concrete floor pouring goes on inside the Ottilia tower

Jun 14 Sprinkler system water line being plumbed to the Ottilia basement

Jun 15 Cement pump truck is in place and hose is hoisted up the stairwell to begin pumping concrete on the 3 rd floor level for the bathrooms and the elevator/stairwell access

Jun 15 Masonry crew continues to set red brick in place

Jun 15 Sisters Dining Room ceiling along with insulation is nearing completion

Jun 15 Interior walls of the kitchen and dishwashing area are now in place

Jun 15 Views of the dishwashing area from the entrance (left) and the exit (right)

Jun 15 These interior walls demarcate the public restrooms with the BSRC serving area behind them

Jun 15 Sprinkler system pipes are much easier to install here than in Annunciata Hall!

Jun 15 Testing the water for the new hydrant; a view inside the new water vault

Jun 15 Electrical and sheetrock work in 1 st Ottilia north hallway

Jun 15 A meeting of the minds about getting the new phone and data systems installed

Jun 15 1 st Ottilia door return from the barn to serve as access to hallway closets in the Infirmary

Jun 15 Bathroom tile work in the Infirmary bathrooms continues

Jun 15 Electrical wiring on 3 rd Ottilia is completed, awaiting hallway fixtures

Jun 15 Cement flooring process on 3 rd Ottilia and on 1 st Ottilia

Jun 15 Insulation and sheetrock being installed in the private retreatant area

Jun 15 Private retreatant hallway (left) and the new laundry room (below)

Jun 15 Doorframe installation to mechanical room and minimaintenance area beneath the kitchen

Jun 15 A finished product DANGER elevator shaft straight ahead

Jun 15 Masonry crew erects its scaffolding and continues to set red brick in place