Intermediate Government Furnished

Size: px
Start display at page:

Download "Intermediate Government Furnished"

Transcription

1 Intermediate Government Furnished Presented by: Property for Contracting Carol Vigna, OSD AT&L DPAP David Guinasso, supporting OSD AT&L DPAP Professionals Defense Procurement and Acquisition Policy (DPAP) 7 JAN

2 Topics The areas covered in this training are recurring areas of concern for audit, accountability and ensuring that contracts protect the governments assets and public s interests. -Contractor Acquired Property -Bailment -Exchange or Sale -Performance Based Logistics 2

3 Definitions Government Furnished Property (GFP) is defined as property in the possession of or acquired by the Government and subsequently furnished to the Contractor for performance of a contract. It includes items like spares and property furnished for repair, maintenance, overhaul, or modification. It can be items taken or requisitioned from Government inventory or purchased by the Government specifically to be provided on a contract. GFP also includes contractor-acquired property if the contractoracquired property is a deliverable under a cost contract that has been accepted by the Government for continued use under that contract or a future contract. Contractor Acquired Property (CAP) - is property purchased or fabricated by a contractor for use on a contract to which the Government has title. 3

4 Not considered GFP Government property that is incidental to the place of performance, when the contract requires contractor personnel to be located on a Government site or installation, and when the property used by the contractor within the location remains accountable to the Government. Located on a Government site or installation Used within the location Remains accountable to the Government 4

5 Contractor Acquired Property 5

6 Cost Contract Title Provision in GP Clause FAR Government Property Title under Cost-Reimbursement or Time-and-Material Contracts or Cost- Reimbursable contract line items under Fixed-Price contracts. (i) Title to all property purchased by the Contractor for which the Contractor is entitled to be reimbursed as a direct item of cost under this contract shall pass to and vest in the Government upon the vendor's delivery of such property. (ii) Title to all other property, the cost of which is reimbursable to the Contractor, shall pass to and vest in the Government upon (A) Issuance of the property for use in contract performance; (B) Commencement of processing of the property for use in contract performance; or (C) Reimbursement of the cost of the property by the Government, whichever occurs first Must be in all Cost Reimbursable and T&M contracts 6

7 An Illustration Deliverable CAP 7

8 Important Things to Remember Title is not changed by incorporation of Government property into property owned by the contractor. Title to cost reimbursable line items on Fixed Price contracts is the same as title under a cost contract. CAP can not be used on a different contract unless it is:» Delivered and accepted and provided as GFP» Repurchased or credited by the contractor* *Subject to the requirements of the Materials Management and Accounting System (MMAS) 8

9 What Happens to CAP May be consumed in production of the deliverable May be delivered May be credited to the contract and charged to a different contract if needed on the succeeding contract» (Reasonable, Allocable, and Allowable test) May be repurchased by the contractor - At full cost; or, - Returned to suppliers less reasonable restock costs If not consumed, repurchased or delivered, must be reported to the Government for plant clearance whenever no longer required for performance» Either during or at the completion of the contract May be provided to succeeding contracts as GFP after inspection and acceptance and delivery 9

10 How CAP is Delivered PGI Delivery of contractor-acquired property.» (1)(i) When delivery of contractor-acquired property is required, the contracting officer shall direct that the delivery be accomplished by contract line item, except as described in paragraph (1)(ii) of this section.» (2) Each contract line item of contractor-acquired property shall include the following information: Contractor-Acquired Property Delivery Contract Line Item CLIN Item Description/ Nomenclature Type Designation NSN PIN Quantity Unit of Measure Serial Number (UII)* Original Unit Acquisition Cost Date Placed in Service by the Contractor x x As required x x x x If known x x *Contractor-acquired property items shall be marked as required by DFARS clause

11 Delivery of CAP Once Contract Line Items are created, CAP will be delivered as any other deliverable line item, using WAWF irapt in accordance with:» DFARS (b) Except as provided in paragraph (c) of this clause, the Contractor shall submit payment requests and receiving reports using WAWF, in one of the following electronic formats that WAWF accepts: Electronic Data Interchange, Secure File Transfer Protocol, or World Wide Web input. Information regarding WAWF is available on the Internet at DFARS "(b) Contractor submission of the material inspection and receiving information required by Appendix F of the Defense FAR Supplement by using the Wide Area WorkFlow (WAWF) electronic form (see paragraph (b) of the clause at < ) fulfills the requirement for a material inspection and receiving report (DD Form 250).» DFARS Appendix F (b) The use of the DD Form 250 is on an exception basis (see DFARS < (a)) because use of the WAWF RR is now required by most DoD contracts 11

12 Bailment 12

13 Bailment What is a Bailment? DFARS PGI 217_75 defines bailment as:» The process whereby a part is loaned to a recipient with the agreement that the part will be returned at an appointed time. The government retains legal title to such material even though the borrowing agency has possession during the stated period.» Items remain accountable to the DoD activity that loans them (Loaning Activity) and will be recorded in accountable property system of record as required by DoDI When do you use it? Under PGI 217_75» used to loan parts to a contractor that DoD believes qualified to become a second source for items which are only available sole source (Spare Parts Breakout Program) To provide military unique items for contractors to use in IR&D and B&P Should Not be used to provide property for use in performing a contract» If there is a contract, the property should be provided as GFP» Bailment agreements and loans are not governed by FAR Part 45 and associated DFARS clauses 13

14 Bailment Agreements Loaning Activity must work with counsel to prepare a bailment or loan agreement Bailment/Loan agreement should: Specify the allowed use for the item (and disallow any other use) Set the term of the loan (beginning and ending dates) Specify transportation arrangements and costs Reserve the right for the government to inspect the item at reasonable times Require regular confirmation of the existence of the item (physical inventory) Allow for government to require return of the property at any time, without compensation to the contractor Discuss responsibility for liability associated with the use or loss of the property Require reporting of any loss of government property Specify any export restrictions or intellectual property considerations 14

15 Exchange or Sale 15

16 Exchange or Sale Exchange most commonly thought of as a trade in Sell disposal sales as part of the federal disposal process - Plant Clearance under FAR and Federal Management Regulations (FMR) FMR Disposal Process under FMR

17 Exchange or Sale Legal Authority - 40 USC 503. Exchange or sale of similar items (a) Authority of Executive Agencies. In acquiring personal property, an executive agency may exchange or sell similar items and may apply the exchange allowance or proceeds of sale in whole or in part payment for the property acquired. (b) APPLICABLE REGULATION AND LAW (1) REGULATIONS PRESCRIBED BY ADMINISTRATOR OF GENERAL SERVICES. A transaction under subsection (a) must be carried out in accordance with regulations the Administrator of General Services prescribes, subject to regulations prescribed by the Administrator for Federal Procurement Policy under division B (except sections 1704 and 2303) of subtitle I of title 41. (2) IN WRITING A transaction under subsection (a) must be evidenced in writing. (3) SECTION 6101(b) to (d) OF TITLE 41 Section 6101(b) to (d) of title 41 applies to a sale of property under subsection (a), except that fixed price sales may be conducted in the same manner and subject to the same conditions as are applicable to the sale of property under section 545(d) of this title. 17

18 Personal Property [Exchange or Sale] FMR Personal property means any property, except real property. For purposes of this part, the term excludes records of the Federal Government, and naval vessels of the following categories: battleships, cruisers, aircraft carriers, destroyers, and submarines. FAR Personal property means property of any kind or interest in it except real property, records of the Federal Government, and naval vessels of the following categories: (1) Battleships; (2) Cruisers; (3) Aircraft carriers; (4) Destroyers; and (5) Submarines. 18

19 Similar Items [Exchange or Sale] Defined in FMR Similar means the acquired item(s) and replaced item(s): (1) Are identical; or (2) Fall within a single Federal Supply Classification (FSC) Group of property (includes any and all forms of property within a single FSC Group); or (3) Are parts or containers for similar end items; or (4) Are designed or constructed for the same purpose (includes any and all forms of property regardless of the FSC Group to which they are assigned). 19

20 When You Can Do An Exchange Replacement of property that is still required, but is no longer functional due to wear or obsolescence May be accomplished as part of the acquisition of new property May be used to acquire property under a service contract provided the property is similar to that being exchanged or sold 20

21 Prohibitions on Exchange or Sale Prohibited Federal Supply Groups 10 Weapons (DoD exception for all except FSC 1005 Guns) 11 Nuclear ordnance 42 Firefighting, rescue, and safety equipment 44 Nuclear reactors (FSC Class 4470 only ) 51 Hand tools 54 Prefabricated structure and scaffolding FSC 5410 Prefabricated and Portable Buildings FSC 5411 Rigid Wall Structures FSC 5419 Collective Modular Support System only 68 Chemicals and chemical products, except medicinal chemicals 84 Clothing, individual equipment, and insignia 21

22 22 More Prohibitions on Exchange or Sale Materials in the National Defense Stockpile NRC Controlled materials (except for ) Controlled substances (except for ) Scrap condition property except Property that had utility when exchange/sale authority was determined Property that was determined in scrap condition due to damage after exchange/sale determination Scrap gold for fine gold Other agency excess, forfeited property or property not obtained from an acquisition, unless it has been in use for no less than 1 year since obtaining

23 Still More Prohibitions on Exchange or Sale Dangerous property not rendered innocuous Combat material without demil or other DoD authorization Flight Safety Critical Aircraft Parts and Critical Safety Items» Unless meeting the provisions of For acquisition of unauthorized replacement property Acquisition of replacement property that violates any» Restriction on procurement of a commodity or commodities» Replacement policy of standard prescribed by the President, Congress or the Administrator of GSA» Contractual Obligation Vessels subject to 40USC548 Aircraft and aircraft parts, unless there is full compliance with all exchange/sale provisions in Part of the FMR 23

24 Conducting an Exchange Procurements may carry a line item which identifies the value of items to be traded in In order to comply with 40 USC and FMR annual reporting requirements transactions must be documented 24

25 Aircraft Parts in Exchange or Sale Special requirements for acquiring military Flight Safety Critical Aircraft Parts (FSCAP) When you acquire Flight Safety Critical Aircraft Parts (FSCAP), you must (a) Accept a FSCAP only when it is documented or traceable to its original equipment manufacturer (a FSCAP s DOD FSCAP Criticality Code should be marked or tagged on the part or appear on its invoice/transfer document; see for further explanation of the FSCAP Criticality Codes); and (b) Not install undocumented, but traceable FSCAP until you have the parts inspected and recertified by the original equipment manufacturer or FAAapproved production approval holder (see on FSCAP) Special requirements for acquiring life-limited parts When you acquire new or used life-limited parts, you must (a) Identify and inspect the parts, ensuring that they have civil or militarycertified documentation (i.e., complete life histories); and (b) Mutilate and dispose of any expired life-limited parts (see on handling life-limited parts). 25

26 Exchange or Sale Summary Agencies are encouraged to utilize the proceeds from sale or trade-in of existing property when purchasing replacement property. Under contracts, even service contracts, property must be acquired. Property must be similar, but need not be equivalent in quantity, as long as the function remains the same, e.g. several small trucks could be sold or exchanged for one large truck that can haul the same or better volume Agencies must report exchange/sale transactions in list form to GSA annually List form implies that individual transactions are recorded AND reported 26

27 Performance-Based Logistics (PBL) 27

28 PBL & CLS The use of Performance Based Logistics (PBL) and Contractor Logistics Support (CLS) contracts is increasing Audits have uncovered reoccurring issues relating to property» Failure to identify or recognize GFP» Acceptance and transfer of title» Excess inventory 28

29 Failure to Recognize GFP in PBL Two areas have been repeatedly identified as points of failure on PBL contracts: Initial lay in of long lead material becomes GFP once accepted Material requisitioned by the contractor and paid for by the Government is GFP. 29

30 Acceptance and Transfer of Title PGI (1)(ii) In some circumstances, such as contractor-performed logistics support or performance-based logistics support contracts, contract deliverables consist of non-hardware items, such as operational readiness rate goals or mean-time-between failures of a system. In order to meet these deliverables, contractors are required to provide certain property items to the Government. In such cases, the contract does not include specific delivery line items requiring formal delivery of the property. By extension, the Government will not have title to the property at the time contractor provides the property. Rather, in such cases, title to the property passes to the Government upon Government acceptance (as defined in FAR ) of the items at the destination stated in the contract. Contracting officers shall ensure that the contract (A) Clearly defines how and when acceptance will be performed; and (B) Includes applicable requirements for quality assurance, part marking, anti-counterfeiting, or other requirement for the delivery of the property. 30

31 Excess Inventory There have been multiple audit findings where contractors were meeting performance goals by maintaining inventory levels far in excess of need. This resulted in significant loss to the Government through obsolescence or continually buying un-needed inventory. Accessing and monitoring demand and inventory levels need to be part of PBL arrangements. Regulatory coverage in process 31

32 PBL: Other Items to Remember Contractors cannot perform acceptance Certificate of Conformance cannot be used in lieu of acceptance If it is GFP, it must be on a Government property book If it is delivered, it is not CAP If transferred to another contract, it is not CAP 32

33 PBL Summary There are many situations involving contractors and property All offer benefits to the Government, but come with their own controls Consider the benefits, know the controls and think through the implications when constructing contracts 33

34 For more information GFP Policy Training, Procedures, Tools

35 Training Certificates Please send your request to Niki Sollinger: Please include the date of the webinar and if you want to be on the GFP Training distribution list. 35

36 Any Questions? 36

Disposal Requirements for Government Property

Disposal Requirements for Government Property IND 105 Contract Property Fundamentals TLO #13 Disposal Requirements for Government Property IND 105 Contract Property Fundamentals The Learning Objectives for Lesson 13 are: TLO 13-Given an incident of

More information

GFP (Government Furnished Property) and CAP (Contractor Acquired Property) Basics

GFP (Government Furnished Property) and CAP (Contractor Acquired Property) Basics GFP (Government Furnished Property) and CAP (Contractor Acquired Property) Basics presented by Amber Barber Property and Equipment Policy April 30, 2010 KNOWLEDGE. CONFIDENCE. TRUST. Defense Property Accountability

More information

IND 205 LESSON #2 TITLE AND GOVERNMENT PROPERTY

IND 205 LESSON #2 TITLE AND GOVERNMENT PROPERTY IND 205 LESSON #2 TITLE AND GOVERNMENT PROPERTY PROPERTY TLO-2: Determine how the Government may take title to property under a contract. ELOs: 1. Define title and related terms 2. Determine who has title

More information

GFP Reporting Under DFARS Clause Cleared For Public Release. Revision of

GFP Reporting Under DFARS Clause Cleared For Public Release. Revision of GFP Reporting Under DFARS Clause 252.211-7007 Revision of 11-07-2013 Cleared For Public Release Presented by: Tom Ruckdaschel Deputy Director, Govt Property tom.ruckdaschel@dcma.mil 804-734-0505 This information:

More information

EXHIBIT B. GOVERNMENT SPECIAL PROVISIONS APPLICABLE TO PRIME CONTRACT F C-0031 [include as applicable to your subcontract]

EXHIBIT B. GOVERNMENT SPECIAL PROVISIONS APPLICABLE TO PRIME CONTRACT F C-0031 [include as applicable to your subcontract] Boeing Information, Space & Defense Systems Date: July 1998 SECTION H SPECIAL CONTRACT REQUIREMENTS INDEX EXHIBIT B GOVERNMENT SPECIAL PROVISIONS APPLICABLE TO PRIME CONTRACT F33657-97-C-0031 [include

More information

IDS Terms and Conditions Guide Section E Clause Number: E000 Effective: 7/24/2004 Page: 1 of 11

IDS Terms and Conditions Guide Section E Clause Number: E000 Effective: 7/24/2004 Page: 1 of 11 Page: 1 of 11 SUPPLIER ACCOUNTABILITY REQUIREMENTS FOR BUYER/GOVERNMENT PROPERTY 1. PURPOSE AND SCOPE a. This document provides instructions to all Buyer subcontractors (Seller) to ensure compliance with

More information

Accountability and Custody for Government Property and Contract Property

Accountability and Custody for Government Property and Contract Property OUSD(AT&L) Acquisition Resources & Analysis (ARA) Property and Equipment Policy Accountability and Custody for Government Property and Contract Property Accountability for Government Property Objective:

More information

THE GOVERNMENT PROPERTY CLAUSE FAR

THE GOVERNMENT PROPERTY CLAUSE FAR TLO #7 IND LESSON #7 THE GOVERNMENT PROPERTY CLAUSE FAR 52.245-1 1 LESSON #7 THE GOVERNMENT PROPERTY CLAUSE TLO 7-Given a contract with the Government property clause, explain FAR 52.245-1. 1. Identify

More information

Common Terms and Conditions Guide Section 3 Administrative Clauses Clause Number: 3068 Effective: 01/26/2005 Page: 1 of 18

Common Terms and Conditions Guide Section 3 Administrative Clauses Clause Number: 3068 Effective: 01/26/2005 Page: 1 of 18 Page: 1 of 18 Government Property Control Seller will be directly responsible and accountable for all Buyer/Government property in accordance with the provisions of the contract and these terms and conditions.

More information

Addendum 529, Rev. 1 (3/14) Page 1 of 5

Addendum 529, Rev. 1 (3/14) Page 1 of 5 Additional Terms and Conditions E-2D Full Rate Production (FRP) Lot 2 (Prime Contract No. N00019-13-C-9999) All of the additional terms and conditions set forth below are incorporated in and made part

More information

US Government owned Property Control Manual Iowa State University Table of Contents. Page. Table of Contents 1. Section 1 Introduction 2

US Government owned Property Control Manual Iowa State University Table of Contents. Page. Table of Contents 1. Section 1 Introduction 2 Table of Contents Table of Contents 1 Section 1 Introduction 2 Section 2 Definitions 3 Section 3 Acquisition 4 Section 4 Receiving 7 Section 5 Property Records 8 Section 6 Physical Inventory 9 Section

More information

Prepared by Office of Procurement and Real Property Management. This replaces Administrative Procedure No. A8.215 dated November 2012 A8.

Prepared by Office of Procurement and Real Property Management. This replaces Administrative Procedure No. A8.215 dated November 2012 A8. Prepared by Office of Procurement and Real Property Management. This replaces Administrative Procedure No. A8.215 dated November 2012 A8.215 A8.215 Definitions A8.200 Procurement October 2013 The words

More information

Government Furnished Property (GFP) and DPAS: Post Session Report

Government Furnished Property (GFP) and DPAS: Post Session Report Government Furnished Property (GFP) and DPAS: Post Session Report Executive Summary: This Webinar covered the proper handling of Government Furnished Property (GFP). It provided background information

More information

PROPERTY MANAGEMENT REFERENCE MANUAL

PROPERTY MANAGEMENT REFERENCE MANUAL PROPERTY MANAGEMENT REFERENCE MANUAL OFFICE FOR SPONSORED PROGRAMS BOSTON COLLEGE Chestnut Hill, MA 02467 April 2007(rev. 9/2014, 4/2016) Table of Contents FOREWORD 1 Page A. Definitions 2 B. Responsibility

More information

Government Furnished Property What Is It???

Government Furnished Property What Is It??? 1 Government Furnished Property What Is It??? Barbara A Finnegan, CPPM CF 2 Government Furnished Property What Is It??? Agenda Introduction Topics Define GFP Acquisition Control of GFP Scheduling: receipt

More information

UAS GM 12: Property Standards

UAS GM 12: Property Standards Overview The UA Statewide Accounting Manual definition of capital expenditures is found in Revenue and Expenditure Account Codes, Section 5000, and for UA purposes, is defined as over $5,000 and having

More information

ADMINISTRATION & FINANCE August 2010 FEDERAL PROPERTY MANAGEMENT STANDARDS

ADMINISTRATION & FINANCE August 2010 FEDERAL PROPERTY MANAGEMENT STANDARDS [ FEDERAL PROPERTY MANAGEMENT STANDARDS 3-0127 ADMINISTRATION & FINANCE August 2010 1.01 The Director of Budget Operations through the Associate Vice President for Administration and Finance is designated

More information

(c) 2012 GP Consultants LLC

(c) 2012 GP Consultants LLC ACQUISITION AND TITLE TO GOVERNMENT PROPERTY UNDER GOVERNMENT CONTRACTS Presented by: Dr. Douglas N. Goetz, CPPM, CF NPMA Fall Conference Series Berkeley, CA PRELUDE Think about your life and your acquisitions

More information

CUSTOMER CONTRACT REQUIREMENTS Transactional Spares CUSTOMER CONTRACT SPM4A1-09-G-0004 DO 8009

CUSTOMER CONTRACT REQUIREMENTS Transactional Spares CUSTOMER CONTRACT SPM4A1-09-G-0004 DO 8009 Page 1 of 7 CUSTOMER CONTRACT REQUIREMENTS Transactional Spares CUSTOMER CONTRACT SPM4A1-09-G-0004 DO 8009 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract

More information

Title: Government-Furnished Property

Title: Government-Furnished Property Title: Government-Furnished Property Date: 9 July 2009 Number: 4.08 rev 0 Approved: Dennis M. McCarley, President 1. Policy: The government may provide or permit purchase of property for use on a contract.

More information

AUBURN UNIVERSITY PROCEDURES FOR THE MANAGEMENT OF GOVERNMENT PROPERTY

AUBURN UNIVERSITY PROCEDURES FOR THE MANAGEMENT OF GOVERNMENT PROPERTY AUBURN UNIVERSITY PROCEDURES FOR THE MANAGEMENT OF GOVERNMENT PROPERTY REVISED: October 2013 Table of Contents 1. INTRODUCTION..3 2. ORGANIZATION..3 3. DEFINITIONS.4 4. PROPERTY SYSTEM..6 5. PROPERTY RECORDS.12

More information

Additional Terms and Conditions E-2D Advanced Hawkeye Low Rate Initial Production (LRIP) 3 and 4 (Contract No. N C-0044)

Additional Terms and Conditions E-2D Advanced Hawkeye Low Rate Initial Production (LRIP) 3 and 4 (Contract No. N C-0044) Additional Terms and Conditions E-2D Advanced Hawkeye Low Rate Initial Production (LRIP) 3 and 4 (Contract No. N00019-10-C-0044) All of the additional terms and conditions set forth below are incorporated

More information

Contract Risk Allocation Working Group. Recommended Practice for Managing Risks in Contracts Involving OWNER-FURNISHED PROPERTY

Contract Risk Allocation Working Group. Recommended Practice for Managing Risks in Contracts Involving OWNER-FURNISHED PROPERTY Contract Risk Allocation Working Group Recommended Practice for Managing Risks in Contracts Involving OWNER-FURNISHED PROPERTY INTRODUCTION This document is a guideline for managing risks in contracts

More information

Contracts, Agreements. What s the difference to the property manager? Mike Showers Asset Management Assistance, L.L.C.

Contracts, Agreements. What s the difference to the property manager? Mike Showers Asset Management Assistance, L.L.C. Contracts, Agreements. What s the difference to the property manager? Mike Showers Asset Management Assistance, L.L.C. Agenda Legal Background Regulatory Background Property Requirements Disclaimer I am

More information

Foreign Military Sales

Foreign Military Sales Chapter 8 Foreign Military Sales Contractual Agreements Introduction Basic contract law concepts are evident in the government-to-government agreements for security assistance (SA). This chapter examines

More information

CUSTOMER CONTRACT REQUIREMENTS Subcontractor CUSTOMER CONTRACT P

CUSTOMER CONTRACT REQUIREMENTS Subcontractor CUSTOMER CONTRACT P Page 1 of 7 CUSTOMER CONTRACT REQUIREMENTS Subcontractor CUSTOMER CONTRACT P010121612 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent indicated

More information

TC-05 Terms and Conditions of Purchase (Purchase Order International Terms and Conditions Fixed Price Procurement)

TC-05 Terms and Conditions of Purchase (Purchase Order International Terms and Conditions Fixed Price Procurement) The Orbital ATK, Inc. terms and conditions referenced in the Purchase Order (TC-01, TC-04, TC-06, or TC-07), hereafter ( ) are modified by the following additional or replacement clauses as indicated:

More information

Additional Terms and Conditions E-2D Advanced Hawkeye Low Rate Initial Production (LRIP) Lots 3 and 4 (Prime Contract No.

Additional Terms and Conditions E-2D Advanced Hawkeye Low Rate Initial Production (LRIP) Lots 3 and 4 (Prime Contract No. Additional Terms and Conditions E-2D Advanced Hawkeye Low Rate Initial Production (LRIP) Lots 3 and 4 (Prime Contract No. N00019-10-C-0044) All of the additional terms and conditions set forth below are

More information

THIS APPENDIX APPLIES TO REQUESTS FOR QUOTATION, PURCHASE ORDERS OR PURCHASE AGREEMENTS ISSUED UNDER GOVERNMENT CONTRACTS.

THIS APPENDIX APPLIES TO REQUESTS FOR QUOTATION, PURCHASE ORDERS OR PURCHASE AGREEMENTS ISSUED UNDER GOVERNMENT CONTRACTS. CONTENTS I. Far and Far Supplement Clauses II International Orders Supplement III Experimental, Development, Research Work or Engineering Services Work Supplement ***********************************************************************

More information

DFARS Procedures, Guidance, and Information

DFARS Procedures, Guidance, and Information (Revised May 16, 2013) PGI 245.6 REPORTING, REUTILIZATION, AND DISPOSAL PGI 245.602-70 Plant clearance procedures. (1) Upon receipt of acceptable inventory schedules, the plant clearance officer (PLCO)

More information

QUALITY REQUIREMENTS SELLER QUALITY REQUIREMENTS

QUALITY REQUIREMENTS SELLER QUALITY REQUIREMENTS Page 1 of 11 QUALITY REQUIREMENTS SELLER QUALITY REQUIREMENTS Notice: A hard copy of this document may not be the document currently in effect. The current version is always the version on the Lockheed

More information

ACQUISITION AND TITLE TO GOVERNMENT PROPERTY UNDER GOVERNMENT CONTRACTS. Presented by Dr. Douglas N. Goetz, CPPM, CF, MIAM.

ACQUISITION AND TITLE TO GOVERNMENT PROPERTY UNDER GOVERNMENT CONTRACTS. Presented by Dr. Douglas N. Goetz, CPPM, CF, MIAM. ACQUISITION AND TITLE TO GOVERNMENT PROPERTY UNDER GOVERNMENT CONTRACTS Presented by Dr. Douglas N. Goetz, CPPM, CF, MIAM This Presentation WHAT may a contractor acquire? To WHAT does the Government take

More information

CHAPTER 1 GENERAL PROVISIONS

CHAPTER 1 GENERAL PROVISIONS CHAPTER 1 GENERAL PROVISIONS NOTE: Guam Procurement Regulations authorized by 5 Guam Code Annotated Chapter 5 (Guam Procurement Act) 1101. Purpose. 1102. Policy. 1103. Advance Payments Prohibited. 1104.

More information

Contract Modification Actions ========================================================== Office of Primary

Contract Modification Actions ========================================================== Office of Primary DCMA Manual 2501-02 Contract Modification Actions ========================================================== Office of Primary Responsibility Effective: May 31, 2018 Contract Maintenance Capability Releasability:

More information

EXHIBIT A GOVERNMENT PROVISIONS APPLICABLE TO PRIME CONTRACT DAAJ09-95-C-A001

EXHIBIT A GOVERNMENT PROVISIONS APPLICABLE TO PRIME CONTRACT DAAJ09-95-C-A001 Date: October 1999 EXHIBIT A GOVERNMENT PROVISIONS APPLICABLE TO PRIME CONTRACT DAAJ09-95-C-A001 The clauses contained in the following Government regulations are incorporated by reference. Where necessary

More information

SUPPLIER REQUIREMENTS FOR BUYER/GOVERNMENT/CUSTOMER PROPERTY MANAGEMENT (VARIABLE)

SUPPLIER REQUIREMENTS FOR BUYER/GOVERNMENT/CUSTOMER PROPERTY MANAGEMENT (VARIABLE) Page: 1 of 5 SUPPLIER REQUIREMENTS FOR BUYER/GOVERNMENT/CUSTOMER PROPERTY MANAGEMENT (VARIABLE) Provided Property authorized for use in support of this contract is identified in paragraph 6 below and is

More information

GOVERNMENT PROPERTY IN THE PRE-AWARD PROCESS, GP CLAUSES and other STUFF!

GOVERNMENT PROPERTY IN THE PRE-AWARD PROCESS, GP CLAUSES and other STUFF! GOVERNMENT PROPERTY IN THE PRE-AWARD PROCESS, GP CLAUSES and other STUFF! Breakout Session # CO7 Dr. Douglas N. Goetz, President GP CONSULTANTS LLC Date: 28 JULY 2014 Time:4:00 5:15PM Government Property

More information

CHAPTER 8 ABANDONMENT OR DESTRUCTION

CHAPTER 8 ABANDONMENT OR DESTRUCTION CHAPTER 8 ABANDONMENT OR DESTRUCTION A. GENERAL 1. This chapter prescribes general policies on the disposition of nonhazardous surplus and FEPP by A/D, or donation instead of A/D. A/D actions must consider

More information

CUSTOMER CONTRACT REQUIREMENTS EATTS3 CUSTOMER CONTRACT W911W6-12-D-0006

CUSTOMER CONTRACT REQUIREMENTS EATTS3 CUSTOMER CONTRACT W911W6-12-D-0006 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS EATTS3 CUSTOMER CONTRACT W911W6-12-D-0006 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent indicated

More information

Additional Terms and Conditions E-2D Full Rate Production (FRP) (Prime Contract No. N C-0063)

Additional Terms and Conditions E-2D Full Rate Production (FRP) (Prime Contract No. N C-0063) Additional Terms and Conditions E-2D Full Rate Production (FRP) (Prime Contract No. N00019-12-C-0063) All of the additional terms and conditions set forth below are incorporated in and made part of this

More information

Property Services. Self Assessment

Property Services. Self Assessment Property Services Self Assessment Version 1.0.1 March 13, 2018 Self-Assessment The Self-Assessment provides Property Services with an opportunity to review business processes associated with all the facets

More information

Reporting Excess Personal Property

Reporting Excess Personal Property U.S. General Services Administration Reporting Excess Personal Property Tara Caldwell Area Property Officer GSA FAS - Personal Property Management June 2015 Use of Special Authorities Exchange/Sale property

More information

The Front End of the Property Management Life Cycle

The Front End of the Property Management Life Cycle Cover Article by Steven F. Holland, CPPM FEDERAL NOVA Chapter PROPERTY ACCOUNTABILITY: THE FRONT END OF THE PROPERTY MANAGEMENT LIFE CYCLE by Steven F. Holland, CPPM NOVA Chapter Federal Property Accountability:

More information

SP SECTION TOOLING AND TEST EQUIPMENT

SP SECTION TOOLING AND TEST EQUIPMENT SP 6003 (10/03) SP SECTION 6000 - TOOLING AND TEST EQUIPMENT CPL. Government Special Tooling. Special Tooling. This provision establishes responsibilities of McDonnell Douglas Helicopter Systems (Buyer)

More information

(3) RAYTHEON GENERAL TERMS AND CONDITIONS OF PURCHASE SUPPLEMENT 2, TC 003 (10/15)

(3) RAYTHEON GENERAL TERMS AND CONDITIONS OF PURCHASE SUPPLEMENT 2, TC 003 (10/15) SOLICITATION ATTACHMENT STANDARD HARD-CODED PURCHASE ORDER TERMS AND CONDITIONS TC-HARDCODE (01/17) The requirements set forth in this Solicitation Attachment are in addition to and not in place of Buyer

More information

CUSTOMER CONTRACT REQUIREMENTS UAE PBL CUSTOMER CONTRACT W58RGZ-16-C-0051

CUSTOMER CONTRACT REQUIREMENTS UAE PBL CUSTOMER CONTRACT W58RGZ-16-C-0051 Page 1 of 10 CUSTOMER CONTRACT REQUIREMENTS UAE PBL CUSTOMER CONTRACT W58RGZ-16-C-0051 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent indicated

More information

Federal Grants Manual Webinar Series: Property Management

Federal Grants Manual Webinar Series: Property Management Federal Grants Manual Webinar Series: Property Management June 24, 2015 The content and materials are not to be shared or distributed unless you have written permission from TASBO to do so. That includes:

More information

Appendix C to Part 37-What is the Desired Coverage for Periodic Audits of For-Profit Participants to be Audited by IPAs?

Appendix C to Part 37-What is the Desired Coverage for Periodic Audits of For-Profit Participants to be Audited by IPAs? Appendix C to Part 37-What is the Desired Coverage for Periodic Audits of For-Profit Participants to be Audited by IPAs? You may provide the following guidance to a for-profit participant and its IPA on

More information

Addendum 517 (12/11) Page 1 of 6

Addendum 517 (12/11) Page 1 of 6 Additional Terms And Conditions Basic Ordering Agreement for Repair and/or Modification E-2/C-2; EA-6B and EA-18G Aircraft (Prime Contract No. N00383-12-G-034G) All of the additional terms and conditions

More information

CUSTOMER CONTRACT REQUIREMENTS DARPA ACT CUSTOMER CONTRACT HR C-0001

CUSTOMER CONTRACT REQUIREMENTS DARPA ACT CUSTOMER CONTRACT HR C-0001 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS DARPA ACT CUSTOMER CONTRACT HR0011-14-C-0001 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent

More information

ADDITIONAL PROVISIONS FOR ORDERS USING THE GENERAL PROVISIONS FOR PROCURING IT PRODUCTS AND SERVICES NEWPORT NEWS SHIPBUILDING DIVISION SUPPLEMENT

ADDITIONAL PROVISIONS FOR ORDERS USING THE GENERAL PROVISIONS FOR PROCURING IT PRODUCTS AND SERVICES NEWPORT NEWS SHIPBUILDING DIVISION SUPPLEMENT ADDITIONAL PROVISIONS FOR ORDERS USING THE GENERAL PROVISIONS FOR PROCURING IT PRODUCTS AND SERVICES NEWPORT NEWS SHIPBUILDING DIVISION SUPPLEMENT (This document is to be used in conjunction with Huntington

More information

Additional Terms and Conditions EA-18G Airborne Electronic Attack (AEA) Kits for the Royal Australian Air Force (RAAF) (Boeing PO Number )

Additional Terms and Conditions EA-18G Airborne Electronic Attack (AEA) Kits for the Royal Australian Air Force (RAAF) (Boeing PO Number ) Additional Terms and Conditions EA-18G Airborne Electronic Attack (AEA) Kits for the Royal Australian Air Force (RAAF) (Boeing PO Number 669561) All of the additional terms and conditions set forth below

More information

SOUTHERN METHODIST UNIVERSITY

SOUTHERN METHODIST UNIVERSITY SOUTHERN METHODIST UNIVERSITY SPONSORED PROJECT PROPERTY MANAGEMENT PROCEDURE January 15, 2015 TABLE OF CONTENTS Topic Page Purpose 1 Who Must Comply 1 Procedures 1 I. Equipment Classifications 1 II. Acquisition/Purchase

More information

ALL PURCHASE ORDERS ARE SUBJECT TO THE FOLLOWING TERMS AND CONDITIONS

ALL PURCHASE ORDERS ARE SUBJECT TO THE FOLLOWING TERMS AND CONDITIONS ALL PURCHASE ORDERS ARE SUBJECT TO THE FOLLOWING TERMS AND CONDITIONS (1) ACCEPTANCE This purchase order constitutes Buyer s offer to Seller, and is a binding contract on the terms and conditions set forth

More information

CUSTOMER CONTRACT REQUIREMENTS DLA Spares CUSTOMER CONTRACT SPRPA1-14-D-002U

CUSTOMER CONTRACT REQUIREMENTS DLA Spares CUSTOMER CONTRACT SPRPA1-14-D-002U Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS DLA Spares CUSTOMER CONTRACT SPRPA1-14-D-002U CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent

More information

GENERAL TERMS AND CONDITIONS OF SALE. December 2010

GENERAL TERMS AND CONDITIONS OF SALE. December 2010 GENERAL TERMS AND CONDITIONS OF SALE December 2010 SCOPE OF ACCEPTANCE: THE TERMS AND CONDITIONS HEREIN ARE THOSE OF GLOBAL TUNGSTEN & POWDERS CORP. (THE SELLER), AND MAY IN SOME INSTANCES BE IN CONFLICT

More information

Introduction to the Personal Property Securities Register

Introduction to the Personal Property Securities Register PPSA Introduction to the Personal Property Securities Register Sydney Perth Commercial in confidence 2014 Allion Legal Introduction to the Personal Property Securities Register What is the PPS Register?

More information

SEATTLE UNIVERSITY. Disposal of Equipment Purchased with Sponsor Funds. Policy and Procedures Manual

SEATTLE UNIVERSITY. Disposal of Equipment Purchased with Sponsor Funds. Policy and Procedures Manual SEATTLE UNIVERSITY Disposal of Equipment Purchased with Sponsor Funds Policy and Procedures Manual As of August 11, 2014 1 Table of Contents I. Policy Statement... 3 II. Determination of Ownership and

More information

AN-C57 MODIFICATIONS TO GENERAL TERMS AND CONDITIONS GOVERNMENT PRIME CONTRACT F D-0006

AN-C57 MODIFICATIONS TO GENERAL TERMS AND CONDITIONS GOVERNMENT PRIME CONTRACT F D-0006 MODIFICATIONS TO GENERAL TERMS AND CONDITIONS GOVERNMENT CONTRACT REQUIREMENTS GOVERNMENT PRIME CONTRACT F42610-99-D-0006 If Form GP1 is applicable to this procurement, this Attachment constitutes the

More information

Capital Asset Accounting Policies POLICY STATEMENT

Capital Asset Accounting Policies POLICY STATEMENT Responsible Executive: Controller Responsible Department: A&FS Review Date: February, 2015 Accounting & Financial Services Capital Asset Accounting Policies POLICY STATEMENT I. Capital Asset Policy A.

More information

NORTHROP GRUMMAN CORPORATION

NORTHROP GRUMMAN CORPORATION NORTHROP GRUMMAN CORPORATION PURCHASE ORDER TERMS AND CONDITIONS (TOOLING - BOEING 747 PROGRAM, HAWTHORNE) 1. DEFINITIONS. A. ACCOUNTABLE TOOLING is tooling title to which rests with The Boeing Company.

More information

Purchase Order Requirements

Purchase Order Requirements Page: 1 of 5 PURCHASE ORDER TERMS AND CONDITIONS I. ACCEPTANCE: This Purchase Order constitutes Buyer's offer to Seller upon the terms and conditions stated herein. This offer expressly limits acceptance

More information

A. IF SPECIAL TOOLING AND/OR SPECIAL TEST EQUIPMENT IS REQUIRED FOR WHICH THE PURCHASER WILL NOT BE CHARGED, SELLER S QUOTE TO INCLUDE:

A. IF SPECIAL TOOLING AND/OR SPECIAL TEST EQUIPMENT IS REQUIRED FOR WHICH THE PURCHASER WILL NOT BE CHARGED, SELLER S QUOTE TO INCLUDE: REQUIREMENT D78 12/12/2017 RFQ INSTRUCTIONS - REPRESENTATIONS AND CERTIFICATIONS COMMERCIAL AND GOVERNMENT - PARAGRAPHS 1 THROUGH 9 GOVERNMENT ONLY - PARAGRAPHS 10 THROUGH 21 1. QUOTE BY REQUESTED RESPONSE

More information

Department of Defense INSTRUCTION

Department of Defense INSTRUCTION Department of Defense INSTRUCTION NUMBER 5000.64 August 13, 2002 USD(AT&L) SUBJECT: Defense Property Accountability References: (a) Under Secretary of Defense (Acquisition, Technology and Logistics) and

More information

SABIC INNOVATIVE PLASTICS ARGENTINA CONDITIONS OF SALE

SABIC INNOVATIVE PLASTICS ARGENTINA CONDITIONS OF SALE Conditions of Sale SABIC INNOVATIVE PLASTICS ARGENTINA CONDITIONS OF SALE 1. DEFINITIONS. As used below, Seller means SABIC Innovative Plastics Argentina S.R.L., an affiliated company of SABIC Innovative

More information

LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDERS UNDER

LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDERS UNDER LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDERS UNDER JSF LRIP 3 CONTRACT NUMBER N00019-08-C-0028 Generated using

More information

Protecting the Government's Interests When Subcontracting With Contractors Debarred, Suspended or Proposed

Protecting the Government's Interests When Subcontracting With Contractors Debarred, Suspended or Proposed Page 1 of 7 CUSTOMER CONTRACT REQUIREMENTS Navy ManTech CUSTOMER CONTRACT ACIT-EMTC-11-0002 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent

More information

CUSTOMER CONTRACT REQUIREMENTS DLA Spares CUSTOMER CONTRACT SPRPA1-14-D-002U

CUSTOMER CONTRACT REQUIREMENTS DLA Spares CUSTOMER CONTRACT SPRPA1-14-D-002U Page 1 of 10 CUSTOMER CONTRACT REQUIREMENTS DLA Spares CUSTOMER CONTRACT SPRPA1-14-D-002U CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent

More information

DCAA Audit Guidance Discusses Limits on Indirect Costs Allocated to Basic Research Contracts

DCAA Audit Guidance Discusses Limits on Indirect Costs Allocated to Basic Research Contracts On December 10, 2009 the Defense Contract Audit Agency (DCAA) issued guidance to its auditors, reminding them that Congress had implemented statutory limits on the percentage of indirect costs that could

More information

CUSTOMER CONTRACT REQUIREMENTS DLA CUSTOMER CONTRACT SPE4A1-15-G-0001

CUSTOMER CONTRACT REQUIREMENTS DLA CUSTOMER CONTRACT SPE4A1-15-G-0001 Page 1 of 9 CUSTOMER CONTRACT REQUIREMENTS DLA CUSTOMER CONTRACT SPE4A1-15-G-0001 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent indicated

More information

BFB-BUS-38: Disposition of Excess Property and Transfer of University-Owned Property

BFB-BUS-38: Disposition of Excess Property and Transfer of University-Owned Property BFB-BUS-38: Disposition of Excess and Transfer of University-Owned Responsible Officer: AVP - Chief Procurement Officer Responsible Office: PS - Procurement Services Issuance Date: 2/2/2011 Effective Date:

More information

CUSTOMER CONTRACT REQUIREMENTS Proprietary CUSTOMER CONTRACT 11-G-1031 DO 0014

CUSTOMER CONTRACT REQUIREMENTS Proprietary CUSTOMER CONTRACT 11-G-1031 DO 0014 Page 1 of 10 CUSTOMER CONTRACT REQUIREMENTS Proprietary CUSTOMER CONTRACT 11-G-1031 DO 0014 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent

More information

CUSTOMER CONTRACT REQUIREMENTS

CUSTOMER CONTRACT REQUIREMENTS Page 1of 21 CUSTOMER CONTRACT REQUIREMENTS BOA for Supplies/Services in Support of USN/USMC CUSTOMER CONTRACT N00019-05-G-0026 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements

More information

H. UNIVERSITY PROCUREMENT CODE

H. UNIVERSITY PROCUREMENT CODE Page 1 H. UNIVERSITY PROCUREMENT CODE 3-801 General A. Applicability 1. This Article H ( University Procurement Code ) shall consist of rules prescribing procurement policies and procedures for the Arizona

More information

TEXAS GENERAL LAND OFFICE PROCUREMENT GUIDANCE FOR RECIPIENTS AND SUBRECIPIENTS UNDER 2 CFR PART 200 (UNIFORM RULES)

TEXAS GENERAL LAND OFFICE PROCUREMENT GUIDANCE FOR RECIPIENTS AND SUBRECIPIENTS UNDER 2 CFR PART 200 (UNIFORM RULES) TEXAS GENERAL LAND OFFICE COMMUNITY DEVELOPMENT & REVITALIZATION PROCUREMENT GUIDANCE FOR RECIPIENTS AND SUBRECIPIENTS UNDER 2 CFR PART 200 (UNIFORM RULES) This checklist will assist the Texas General

More information

CUSTOMER CONTRACT REQUIREMENTS DLA Spares CUSTOMER CONTRACT SPRPA1-14-D-002U

CUSTOMER CONTRACT REQUIREMENTS DLA Spares CUSTOMER CONTRACT SPRPA1-14-D-002U Page 1 of 9 CUSTOMER CONTRACT REQUIREMENTS DLA Spares CUSTOMER CONTRACT SPRPA1-14-D-002U CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent

More information

Central Kentucky Educational Cooperative

Central Kentucky Educational Cooperative Central Kentucky Educational Cooperative Name of Co-operative PROCUREMENT PLAN CHILD NUTRITION PROGRAM This procurement plan contained on the following pages 1 through 10 will be implemented on _April

More information

QUALITY POLICY & PROCEDURE MANUAL

QUALITY POLICY & PROCEDURE MANUAL PURCHASE ORDER REQUIREMENTS The following Purchase Order requirements are applicable for all purchases of materials, semi-finished components or services, testing or the calibration of equipment required

More information

CUSTOMER CONTRACT REQUIREMENTS Survivabilty Enhancement CUSTOMER CONTRACT W15P7T-13-C-C003

CUSTOMER CONTRACT REQUIREMENTS Survivabilty Enhancement CUSTOMER CONTRACT W15P7T-13-C-C003 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS Survivabilty Enhancement CUSTOMER CONTRACT W15P7T-13-C-C003 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract

More information

How Does 15 Go Into 10? Functions To Outcomes. presented by: Marlene Lynn, CPPM Manager of Asset Management BAE SYSTEMS

How Does 15 Go Into 10? Functions To Outcomes. presented by: Marlene Lynn, CPPM Manager of Asset Management BAE SYSTEMS How Does 15 Go Into 10? Functions To Outcomes presented by: Marlene Lynn, CPPM Manager of Asset Management BAE SYSTEMS 15 Functions of Property Per the Old DoD 4161.2M 1. Property Management 2. Acquisition

More information

T-57 PURCHASE ORDER TERMS AND CONDITIONS TOOLING - BOEING 747 PROGRAM, HAWTHORNE

T-57 PURCHASE ORDER TERMS AND CONDITIONS TOOLING - BOEING 747 PROGRAM, HAWTHORNE TERMS T-57 (7-00) PAGE 1 OF 6 T-57 PURCHASE ORDER TERMS AND CONDITIONS TOOLING - BOEING 747 PROGRAM, HAWTHORNE 1. DEFINITIONS. A. ACCOUNTABLE TOOLING is tooling title to which rests with The Boeing Company.

More information

Dcma Guidebook For Contract Property Administration

Dcma Guidebook For Contract Property Administration Dcma Guidebook For Contract Property Administration (ad) DCMA-INST 124, Contract Property Management, March 31, 2014. (ar) FAR Ensure contract administration actions comply with this Instruction. 2.1.2.

More information

CUSTOMER CONTRACT REQUIREMENTS VTOL X-PLANE CUSTOMER CONTRACT HR

CUSTOMER CONTRACT REQUIREMENTS VTOL X-PLANE CUSTOMER CONTRACT HR Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS VTOL X-PLANE CUSTOMER CONTRACT HR0011-14-9-0002 CUSTOMER CONTRACT REQUIREMENTS 1. Prime Contract Special Provisions The following prime contract special provisions

More information

Patricia Dodson & Thao Tsuda Office of Contracts and Grants (OCG): Compliance Team November 30, 2017

Patricia Dodson & Thao Tsuda Office of Contracts and Grants (OCG): Compliance Team November 30, 2017 Sponsored Projects Property Management Training Patricia Dodson & Thao Tsuda Office of Contracts and Grants (OCG): Compliance Team November 30, 2017 Session Training Goals Terms and Conditions How and

More information

SIKORSKY AIRCRAFT CORPORATION SELLER QUALITY REQUIREMENTS

SIKORSKY AIRCRAFT CORPORATION SELLER QUALITY REQUIREMENTS SIKORSKY AIRCRAFT CORPORATION SELLER QUALITY REQUIREMENTS Preamble: SECTION I PREAMBLE & DEFINITIONS For all Orders referencing the applicable Supplemental Clauses for Subcontracting, the provisions of

More information

CUSTOMER CONTRACT REQUIREMENTS Proprietary CUSTOMER CONTRACT Loki

CUSTOMER CONTRACT REQUIREMENTS Proprietary CUSTOMER CONTRACT Loki Page 1 of 7 CUSTOMER CONTRACT REQUIREMENTS Proprietary CUSTOMER CONTRACT Loki CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent indicated

More information

---------------------------------------------------------------------------------------------- AIFC IMPLIED TERMS IN CONTRACTS AND UNFAIR TERMS REGULATIONS AIFC REGULATIONS No. 6 of 2017 December 20, 2017

More information

TERMS & CONDITIONS STANDARD PAGE 1 OF 5 DATE: 6 AUGUST 2014

TERMS & CONDITIONS STANDARD PAGE 1 OF 5 DATE: 6 AUGUST 2014 PAGE 1 OF 5 TIME IS OF THE ESSENCE WITH RESPECT TO THE PERFORMANCE OF EACH OF THE COVENANTS AND AGREEMENTS SET FORTH HEREIN. 1. DEFINITIONS. As used in this Purchase Order, the below terms shall have the

More information

The New Personal Property Securities Register How Does it Effect Your Business?

The New Personal Property Securities Register How Does it Effect Your Business? April 2012 The New Personal Property Securities Register How Does it Effect Your Business? Stephens Lawyers & Consultants Newsletter: April 2012 The Personal Property Securities Act 2009 (Cth) (PPS) came

More information

CUSTOMER CONTRACT REQUIREMENTS MQ-25 CUSTOMER CONTRACT N C-0084

CUSTOMER CONTRACT REQUIREMENTS MQ-25 CUSTOMER CONTRACT N C-0084 Page 1 of 11 CUSTOMER CONTRACT REQUIREMENTS MQ-25 CUSTOMER CONTRACT N00019-16-C-0084 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent indicated

More information

SCHEDULE B Contract Clauses Non-DVD

SCHEDULE B Contract Clauses Non-DVD SCHEDULE B Contract Clauses Non-DVD PART II Contract Clauses Specific for Purchase Orders Issued Under Buyer s Prime Contract No. SPM4AR-07-D-0001 (Applicable to Purchase Orders for Items Shipped to Buyer

More information

EARLY LEARNING COALITION OF OSCEOLA COUNTY

EARLY LEARNING COALITION OF OSCEOLA COUNTY Page of 1 of 9 POLICY STATEMENT The Coalition shall adhere to Federal and state laws, regulations, and rules requiring the implementation of proper controls related to the management, maintenance, reporting,

More information

GENERAL TERMS AND CONDITIONS OF SALE

GENERAL TERMS AND CONDITIONS OF SALE LINCOLN ELECTRIC BESTER SP Z O.O. HARRIS CALORIFIC SP. Z O.O. WELDING CONSUMABLES FACTORY GENERAL TERMS AND CONDITIONS OF SALE 1. DEFINITIONS Buyer means the person, whose order for Goods is accepted by

More information

CUSTOMER CONTRACT REQUIREMENTS AV-8 CUSTOMER CONTRACT N D-1000

CUSTOMER CONTRACT REQUIREMENTS AV-8 CUSTOMER CONTRACT N D-1000 Page 1 of 9 CUSTOMER CONTRACT REQUIREMENTS AV-8 CUSTOMER CONTRACT N00019-15-D-1000 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract to the extent indicated

More information

(1) "Lessor" means an owner, lessor, sublessor, or managing agent of a self-service storage facility.

(1) Lessor means an owner, lessor, sublessor, or managing agent of a self-service storage facility. NOTICE: This version of the Statute has been prepared by Katz, Greenberger & Norton, LLP, from review of the official Statute with the recent bill and is NOT an official version. No claim to copyright

More information

SENIOR AEROSPACE ABSOLUTE MANUFACTURING TERMS AND CONDITIONS OF PURCHASE

SENIOR AEROSPACE ABSOLUTE MANUFACTURING TERMS AND CONDITIONS OF PURCHASE Page 1 of 7 SENIOR AEROSPACE ABSOLUTE MANUFACTURING TERMS AND CONDITIONS OF PURCHASE 1. ACCEPTANCE: This order is for the purchase and sale of the goods and services described on the front side hereof

More information

CUSTOMER CONTRACT REQUIREMENTS S100 Robotic Landing Gear CUSTOMER CONTRACT HR C-0066

CUSTOMER CONTRACT REQUIREMENTS S100 Robotic Landing Gear CUSTOMER CONTRACT HR C-0066 Page 1 of 9 CUSTOMER CONTRACT REQUIREMENTS S100 Robotic Landing Gear CUSTOMER CONTRACT HR0011-16-C-0066 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements apply to this contract

More information

What We Will Cover. What Governs the Program Services Charges Where to Find Property On-line Search Methods On-site Search Methods

What We Will Cover. What Governs the Program Services Charges Where to Find Property On-line Search Methods On-site Search Methods May 6, 2015 What We Will Cover What Governs the Program Services Charges Where to Find Property On-line Search Methods On-site Search Methods Each State and US Territory has a State Agency for Surplus

More information

Maury Microwave Quality Clauses / Standard Terms & Conditions of Purchase ----

Maury Microwave Quality Clauses / Standard Terms & Conditions of Purchase ---- Maury Microwave Quality Clauses / Standard Terms & Conditions of Purchase - // NOVEMBER 2017 Quality Clauses Form 6.2.2 C Product/Service Purchased Raw Material Hardware Heat Treated/Metal Finishing Outside

More information

CUSTOMER CONTRACT REQUIREMENTS DESIGN, DEVELOPMENT, DEMONSTRATION, AND INTEGRATION (D3I) CUSTOMER CONTRACT 18S-0509

CUSTOMER CONTRACT REQUIREMENTS DESIGN, DEVELOPMENT, DEMONSTRATION, AND INTEGRATION (D3I) CUSTOMER CONTRACT 18S-0509 Page 1 of 11 CUSTOMER CONTRACT REQUIREMENTS DESIGN, DEVELOPMENT, DEMONSTRATION, AND INTEGRATION (D3I) CUSTOMER CONTRACT 18S-0509 CUSTOMER CONTRACT REQUIREMENTS The following customer contract requirements

More information