Locally Administered Projects Overview

Similar documents
Task Central Office Real Estate Responsibilities District Responsibilities

OFFICE OF REAL ESTATE

Allegheny County Sanitary Authority REQUEST FOR QUALIFICATIONS. for

TABLE OF CONTENTS General Legal Authority for Certification of Right of Way Control 24-2

Putting it all together. Presented by: RIGHT OF WAY SERVICES

Frequently Asked Questions From the Certification of R/W Training Sessions

DESIGN BUILD PROJECTS

State of Florida Department of Transportation EXHIBIT A, SCOPE OF SERVICES

REQUEST FOR QUALIFICATIONS FOR HOUSING ACQUISITION, RELOCATON, DEMOLITION CONSULTANT/REHABILITATION SPECIALIST WISE COUNTY, VIRGINIA

INDEX. of subrecipients, VIII -2 records, VI-1, 4, 13. OMB Circular A-122, VIII- 3 certification: I-28

Right of Way Acquisition

Figures List for New LPA Manual

EAST BATON ROUGE REDEVELOPMENT AUTHORITY ADMINISTRATIVE POLICY PROCUREMENT CONTRACTING AND DBE POLICY FOR FEDERALLY FUNDED PROJECTS.

REDFOOT ROAD BRIDGE 1416 SCOPE OF WORK

RECORDKEEPING PROCESS. All ACEDP grantees are required to develop a recordkeeping system that is comprehensive, well-organized and easy to review.

MnDOT Contract No Exhibit B. Scope of Work. Scope of Work

Right-of-Way Acquisition and

City Of Oakland HOUSING AND COMMUNITY DEVELOPMENT DEPARTMENT

PROJECT: P 0037(129)207 PCN: 039K BROWN COUNTY. S.D. Highway 37 From Aspen Ave to U.S. Highway 12 in Groton

SECTION 4(F) & CHAPTER 26. TxDOT Environmental Conference 2017

Ohio Department of Transportation. Division of Engineering. Office of Real Estate. Synergy. Real Estate Business Analysis

ADVANCE FUNDING AGREEMENT FOR A TRANSPORTATION ALTERNATIVES PROGRAM PROJECT

MOTION NO. M Property Exchange Agreement with the University of Washington for the Northgate Link Extension

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of February 12, 2011

The Uniform Act. CDBG Disaster Recovery Regional Training Acquisition Rehabilitation Demolition Displacement August 2015

Ohio Department of Transportation. Division of Engineering. Office of Real Estate. Synergy. Real Estate Business Analysis

Brad Faiman, NDDOT Right of Way Raymond Barchenger, NDDOT Right of Way

Annual Pass-Through Grant Training

Federal Aid Acquisition Guide. For Property Owners

RESOLUTION NO A RESOLUTION ENDORSING A BIKE/ PEDESTRIAN BRIDGE ACROSS THE DAVIDSON RIVER

REQUEST FOR PROPOSALS (RFP) SECTION 8 CONTRACT ADMINISTRATION SERVICES

The Uniform Act. Acquisition, Relocation & Demolition. Disaster Recovery CDBG Administration Training. February 14, 2012

Internal Audit Report

PUBLIC HEARING. Loop 88 Segment 3 Thursday, October 12, 2017 Lubbock-Cooper Performing Arts Center at 6:00p.m. Date. Footer Text

RESOLUTION NO. R To Acquire Real Property Interests Required for the Downtown Redmond Link Extension

Common Audit Findings Related to Purchasing and How to Avoid Them

State of Florida Department of Transportation

RIGHT OF WAY PRIMARY ROLES & RESPONSIBILITIES

5.5 Relocations and Displacements

Request for Proposal House for Therapeutic Court Programs

5.5 Relocations and Displacements

Boot Camp Breakout Session #3. September 19, 2018 Carolyn France Moderator Transportation Alternatives Program Manager, Central Office

Okaloosa County BCC. Okaloosa County BCC. MSBU / MSTU Policy. Municipal Service Benefit Units Municipal Service Taxing Units.

RIGHT OF WAY LIFE CYCLE

All proposals must include a current Business Registration Certificate, W-9 Form and a Certificate of Employee Information Report

Ohio Department of Transportation. Division of Engineering. Office of Real Estate. Synergy. Real Estate Business Analysis

Troy D. Byers Assistant State ROW Administrator Georgia Department of Transportation

Hank's Exchange Road Bridge Replacement Project

Sidewalk Program Policy Revised: 06 November 13

REQUEST FOR PROPOSALS RFP # September 16, 2011 Proposals Due on October 5, 4:00 pm

Another local AGENCY with a.roved rocedures or a ualified consultant. Another local AGENCY with approved procedures or a qualified consultant

LOCAL PUBLIC AGENCY MANUAL

GLOSSARY. Acquisition The process of obtaining right of way necessary to construct or support your project.

Neighborhood Stabilization Program Frequently Asked Questions

REQUEST FOR QUALIFICATIONS REAL ESTATE BROKER SERVICES

CITY OF WEST BEND. Quote: Q15-02

OVERALL & CONTRACT DBE GOAL METHODOLOGY. Goal Period FY /01/17 to 9/30/20 AIP No XXXX Corrie Esvelt-Siegford, T-O Engineers

Sound Transit. Performance Audit Report Real Property Acquisition

Responsibilities of the Grant Recipient LAND AND WATER CONSERVATION FUND PROGRAM

Appendix B. North Carolina Parks and Recreation Trust Fund. Submitting Requests for Reimbursement for Land Acquisition

Meetinghouse Facilities Department Real Estate Acquisition Process Instructions - Meetinghouse

JAMES R. HALL, SR. REALTY OFFICER FEDERAL HIGHWAY ADMINISTRATION OFFICE PHONE:

MIAMI-DADE EXPRESSWAY AUTHORITY PROPERTY ACQUISITION POLICY

NSP DEVELOPER ARRESALE PROGRAM PROCEDURES

PROJECT NH 0050(99)381 PCN 6926 YANKTON COUNTY. SD HWY 50 (4 th Street) from Broadway Ave to Archery Road in Yankton, SD

Township of Ligonier Westmoreland County, Pennsylvania REQUEST FOR PROPOSALS PROFESSIONAL FINANCIAL AND ADMINISTRATIVE AUDITING SERVICES

REQUEST FOR PROPOSAL RFP # TOC17-001

State Revolving Fund Loan Programs Guidance for Project Land Acquisition For SRF Financed Projects

PROPERTY MANAGEMENT MANUAL

ED-900C EDA Application Supplement for Construction Programs

Township of Salisbury Lehigh County, Pennsylvania REQUEST FOR PROPOSALS PROFESSIONAL FINANCIAL AND ADMINISTRATIVE AUDITING SERVICES

PROJECTS: P 0083(74)56; 036E; JONES COUNTY NH 0083(79)45; 04E7; MELLETTE COUNTY NH 0083(80)44; 04E8; MELLETTE COUNTY

Publications Transmittal

FLORIDA DEPARTMENT OF TRANSPORTATION

BLUEPRINT REAL ESTATE POLICY

Chapter 1. Introduction

Accelerated ROW Process for Sidewalks FAQ s

RESOLUTION NO. R To Acquire Real Property Interests Required for the Lynnwood Link Extension

Request for Proposals for Professional Services. Affordable Housing Administrative Agent

PROPOSED FINAL RULE: DISPOSAL OF REAL PROPERTY INTERESTS 23 CFR PART 710. Melani Millard, Realty Officer,FHWA

HOME Investment Partnerships Program & Affordable Housing Trust Fund APPLICATION Training Workshop

A REPORT FROM THE OFFICE OF INTERNAL AUDIT

RELOCATION ASSISTANCE PROGRAM (RAP) BOOKLET THE 10 MINUTE MANAGER

REQUEST FOR PROPOSALS Professional Engineering Services for Lift Station In the Rural Municipality of Wellington

SERC-NAHRO ANNUAL CONFERENCE RENTAL ASSISTANCE DEMONSTRATION (RAD)

LAP Manual 16 C-13 May 2011 Right of Way

TABLE OF CONTENTS. Page No. MSBU Background Highlights 1. General Guidelines 4. Detailed Procedures: Construction Districts 13

REQUEST FOR PROPOSAL (RFP) RFP AS. Appraisal Services Valuation of DBHA Properties

Request for Proposals

NSP Rental Basics: A Primer on Using Rental Projects to Meet NSP Obligation and 25% Set-Aside Requirement. About this Tool

Capital Improvement Program

RFP REQUEST FOR PROPOSAL. for TAX CREDIT ADVISOR SERVICES. for BOULDER HOUSING PARTNERS. March 6, 2012 Requested Return: March 15, 2010

State of Florida Department of Transportation EXHIBIT A, SCOPE OF SERVICES

DESIGN PUBLIC HEARING

EXHIBIT "A" SCOPE OF SERVICES CONTINUING SERVICES CONTRACT FOR RIGHT OF WAY CONSULTANT SERVICES. FP1D No. TO BE DETERMINED

MHDC General Relocation Assistance Policy. For Projects Funded with MHDC, Non-Federal Dollars

Town of Littleton Sale of Town Owned Property Policy & Procedure

Funding package incomplete; public and political controversy; Interstate traffic impacts

HIGHLANDS COUNTY BOARD OF COUNTY COMMISSIONERS

METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN Phone (651) TDD (651)

Transcription:

Locally Administered Projects Overview

Locally Administered Projects Overview What you will learn from this Presentation: Major Steps of administering a federal-aid project by a local government agency Highlights of more complex steps Resources available for local government agencies 2

General Oversight Requirements Federal-aid funding is cost-reimbursement Funding Authorization is required prior to each phase of work Local Government Agency (LGA) has the responsibility to deliver the project NCDOT has the responsibility to provide oversight to LGAs and ensure appropriate use of funds 3

Resources https://connect.ncdot.gov/municipalities/funding/pages/default.aspx 4

Resources 5

Local Projects On-Line Project Management Tool 6

Local Project On-Line Project Management Tool 7

Initial Project Idea Before you ask for Funding Identify project scope from Long-Range Plan, citizen input, etc. Do your Due Diligence: Environmental Concerns ROW issues Utility relocations Project delivery Budget/Schedule Identify funding source (i.e. MPO, NCDOT, etc.) &and the process for approval/allocation of funds 8

Pre-Construction Steps (climb the mountain!) Final Plans, Specifications, and Estimate Right of Way Certification Right of Way (ROW) Authorization Right of Way Acquisition (and Utility Relocation) Right of Way Plans / Location & Design Approval Environmental Document Preliminary Engineering (PE) Authorization Procuring Professional Services Agreement Programming (includes Schedule) 9

Construction Steps (another mountain!) Maintenance Final Voucher Date Final Inspection and Project Acceptance Construction Engineering & Inspection Construction Construction (CON) Authorization Bidding, Letting and Awarding Construction Contract 10

Programming All projects must be programmed into the Metropolitan or Local Improvement Program (TIP) and the State Improvement Program (STIP) Your MPO takes the lead on programming with the concurrence of appropriate Business Units at NCDOT Programming includes scope, funding type(s) and amounts, and Federal Fiscal Year. 11

On-Line STIP 12

Agreement Executed between NCDOT and the Local Governmental Agency Includes provisions that LGA must comply with in order to receive reimbursement Includes funding, time frames, scope of work, and responsibilities Funding Authorizations cannot occur until a fully executed agreement is in place. 13

Large Image 14

Funding Authorizations Authorizations are made for: PE preliminary engineering ROW/UTIL right of way and/or utility relocation CON construction. The authorization request is based on an estimate provided by the LGA. Authorization is requested BY NCDOT TO FHWA and generally takes about two weeks for approval. Authorization requests should not occur until the LGA is ready to begin work. If any work occurs prior to funding authorization, it will not be reimbursed. 15

Pre-Construction Steps Final Plans, Specifications, and Estimate Right of Way Certification Right of Way (ROW) Authorization Right of Way Acquisition (and Utility Relocation Right of Way Plans Environmental Document Preliminary Engineering (PE) Authorization Procuring Professional Services Agreement Programming (includes Schedule) 16

PE Funding Authorization LGA will request through Local Project System or from NCDOT Project Manager. Requires an executed Agreement and an estimate of costs from LGA. The estimate, ideally, should be a breakdown of tasks and manhours needed to complete the pre-construction phase (i.e. design, environmental analysis) PE can pay for environmental analysis, design, and the professional services to produce those items 17

Professional Services LGA is responsible for soliciting and selecting consultants in accordance with federal regulations, state statutes, and NCDOT policy. Standard Template for advertisement and other form letters are available on our website. LGA should follow a qualifications based selection process and must document that process and obtain concurrence before negotiating a contract. 18

Professional Services Steps Solicit for services (using approved template for advertisement) Select the most qualified firm Send to NCDOT for concurrence Negotiate a cost proposal (tasks, man-hours, rates) Send to NCDOT for review Professional Services Management Unit External Audit Adjust/modify/or finalize as needed and draft contract Send to NCDOT for review Execute contract and provide NCDOT a copy Any supplemental agreements need to be reviewed by NCDOT prior to execution 19

Questions or Comments? 20

Environmental Documentation Must be in conformance with NEPA National Environmental Policy Act. Must also comply with other Federal environmental laws. Most projects qualify as a Programmatic Categorical Exclusion (PCE) Document 21

Environmental Documentation Guidance on the Local Programs Website PCE Checklist Guidance on who to consult Ensure that you have qualified people undertaking the work Documents may be reviewed at the Division or may be sent to Raleigh for review This step should occur early in the design process 22

Design Follow NCDOT Design Standards for Roadways and Structures Use NCDOT details, for example wheelchair ramps, curb and gutter, etc. Plans should be submitted at 25% for review, continuing on to 100% for final review Review may occur solely at the Division or certain reviews may occur in Raleigh 23

Right of Way Right of Way is probably the biggest unknown when an LGA is working on a Project Any kind of ROW, whether it s acquisition in fee simple, or you re entering into an easement (temporary or permanent), or an encroachment, must be properly documented and then certified 24

Right of Way If ROW is an eligible expense per the agreement, then submit ROW plans for review (usually about 75%) ROW Plans show the limits of the project and what property is needed The Division will issue a LADA Location and Design Approval memo 25

Questions or Comments? 26

Pre-Construction Steps Final Plans, Specifications, and Estimate Right of Way Certification Right of Way (ROW) Authorization Right of Way Acquisition (and Utility Relocation Right of Way Plans Environmental Document Preliminary Engineering (PE) Authorization Procuring Professional Services Agreement Programming (includes Schedule) 27

Right of Way Funding Authorization LGA will request through Local Project System or from NCDOT Project Manager Requires an executed Agreement, an approved environmental document, a Location and Design Approval, and an estimate of ROW costs from LGA The estimate can be developed from tax values, comparable sales, etc. If utility costs are eligible, an estimate for utility costs should also be submitted 28

Right of Way Acquisition All acquisition must be in conformance with the Uniform Act, whether ROW Acquisition is being reimbursed with Federal funds or not Appraisals must be reviewed by NCDOT, even if ROW is not an eligible expense NCODT will provide a concurrence in just compensation 29

Utility Relocation Most utility relocation should occur in the pre-construction phase and be complete prior to construction Exception: if plans for relocation are included in the construction contract, then relocation can occur during the construction phase 30

Right of Way Certification Certification ensures that LGA has control of all ROW needed for project and the ROW is clear from all obstructions. Either the LGA owns outright or has a lease, easement, or other legal document to control ROW. LGA submits all documentation to the Division ROW Agent for certification. 31

Questions or Comments? 32

Proposal and Estimate Contract Proposal is prepared in accordance with the 2012 North Carolina Standard Specifications for Roads and Structures. Proposal will include federal provisions that will be part of the contract. The engineer s estimate is a line-item estimate that references the Spec Book or special provisions. The engineer s estimate is also used to set a goal for Disadvantaged Business Enterprise firms. 33

Pre-Construction Steps Right of Way (ROW) Authorization Preliminary Engineering (PE) Authorization Final Plans, Specifications, and Estimate Right of Way Certification Right of Way Acquisition (and Utility Relocation Right of Way Plans Environmental Document Procuring Professional Services Agreement Programming (includes Schedule) 34

Construction Steps Maintenance Final Voucher Date Final Inspection and Project Acceptance Construction Engineering & Inspection Construction Construction (CON) Authorization Bidding, Letting and Awarding Construction Contract 35

Construction Procurement Advertising and Letting a Construction Contract can only occur after Construction funds are authorized. NCDOT must review and concur in the LGA s proposal to award a construction contract. We have template letters and forms to use when requesting concurrence. 36

Construction Construction Administration and Engineering & Inspection is accomplished by the LGA in accordance with the NCDOT Construction Manual. NCDOT will provide oversight through the Division Office or the Resident Engineer s Office. NCDOT must concur with the LGA s acceptance of the project before final reimbursement can be made. 37

Reimbursement Can occur throughout the project as costs are incurred LGA pays full invoice; NCDOT reimburses 80% of eligible costs up to amount in agreement Final Reimbursement will not occur until project is complete, accepted by NCDOT, and all reporting and other requirements have been accomplished 38

Close-Out and Final Voucher Date Department will process several items related to closing out the LGA project Ensuring that LGA has all appropriate records Calculating any costs that the LGA owes the Department Certifying materials permanently incorporated in the Project Once these items are accomplished, NCDOT will request FHWA close the project and issue a Final Voucher Date Final Voucher date will start retention of records period 39

Recap of Important Items to Remember The following slides are a recap of some of the areas where we see challenges and the need to think ahead about certain issues. 40

Remember! Initial Project Idea Have you done due diligence? Do you own the Right of Way? Do utilities need to be moved? What is the environmental situation? Is your schedule realistic? Have you included some breathing room in your Budget? 41

Professional Services Remember! Need to be pre-qualified by DOT in all the work codes listed OR have subs that are pre-qualified. Average length of time to sign a contract with a PEF once funding is authorized? 8 months. City holds the contract with the consultant, not NCDOT. 42

Professional Services Remember! Need to be pre-qualified by DOT in all the work codes listed OR have subs that are pre-qualified. Average length of time to sign a contract with a PEF once funding is authorized? 8 months. City holds the contract with the consultant, not NCDOT. 43

Funding Authorization Remember! No costs can be incurred prior to authorization. Certain deliverables need to be complete prior to requesting the authorization. Once funds are authorized, move quickly to incur costs and request reimbursement to keep project active. 44

Remember! Right of Way All acquisition must follow the Uniform Act, even if you re not receiving reimbursement for Right of Way. Acquisition of Right of Way always takes longer than you think. 45

Contract/Bid Proposal Remember! Must use NCDOT Standard Specifications (unless project is one that NCDOT does not have standards for). Construction Be familiar with NCDOT Construction Manual. Ask the Division for assistance in setting up records for consistent documentation. 46

Remember! Close-Out Be aware of costs that LGA may need to reimburse to NCDOT. Keep all records in a safe place for future audits. 47

Questions or Comments? 48

THANK YOU Local Programs Management Office Program Management Unit North Carolina Department of 49