Integrated Township namely Mohali Hills at Sectors 98, 99, 105, 106, 108, 109 and 110, SAS Nagar, Mohali, Punjab by M/s. Emaar MGF Land Ltd. PROPOSAL NO. SIA/PB/NCP/17831/2016 EDS REPLY DATED 8 th December, 2016 SI. No. Description 1. Being expansion project certified compliance from Northern Region, Chandigarh of Ministry of Environment, Forest and Climate change, New Delhi is required to be submitted. 2. The project proponent is required to certify the distance of its project site from Sukhna WildLife Sanctuary if it falls between the radius of 10 KM, then the project proponent is required to submit a copy of acknowledgement along Reply Earlier Environmental Clearance was accorded by MoEF, GoI for developing 888.50 acres (or 359.56 hectares) vide Letter No. 21-171/2007-IA.III dated 18 th June, 2008. Copy of earlier EC is enclosed as Annexure 1(a). Subsequently during the sector demarcation procedure, project area initially envisioned to be Sector-98, 105, 108 & 109 covering 888.50 acres (or 359.56 hectares) of area for which EC has been obtained, has instead been marked in Sector-98, 99, 104, 105, 106, 108, 109 & 110. It is clarified by Northern Regional Office, MoEF Chandigarh vide Letter No. 5-131/2008-RO (NZ) d ated 08.02.2012 that the geographical features of these are identical, as only the nomenclature of sectors have changed. Copy of MoEF letter is enclosed as Annexure 1(b). Out of this total 888.50 acres (or 359.56 hectares) of area, initially development was planned for 601.50 acres as mentioned in MoEF letter. Accordingly, development work was started on site but due to recession in market and financial crisis, project could not be completed and construction work was stopped at site. Now, planning has been finalized for 625.35 acres (or 253.07 hectares) for which layout has been approved by Chief Town Planner, Chandigarh. Approved Layout Plan is enclosed as Annexure 9. Also, validity of Environmental Clearance has been expired; thus, fresh application has been filed for Environmental Clearance for 625.35 acres (or 253.07 hectares) of land. Thus, this point is not applicable as this is the fresh application for the Environmental Clearance. Sukhna Wildlife Sanctuary is approx. 15 km away from the project site. Thus, there is no need of obtaining NBWL clearance. Thus, this point is not applicable.
with set of application applied to NBWL for obtaining permission. 3. Existing layout to be super imposed 4. List of activities to be undertaken for finalization of TORs by SEAC. 5. Copy of MoA & certified list of directors. Layout showing the expansion & revision part is enclosed as Annexure 10. List of Activities to be undertaken in three phases i.e. Pre-construction, Construction & Operation phases have already been mentioned in the proposed TOR file. Copy of MOA has already been attached as Annexure 4(a). While, list of Directors are attached as Annexure 4(b).
LIST OF ANNEXURES S.No Description Annexure 1. EC Letter Annexure 1(a) 2. MoEF Letter Annexure 1(b) 3. CLU Annexure 2 4. BOR Annexure 3 5. MOA Annexure 4(a) 6. List of Directors Annexure 4(b) 7. Undertaking Annexure 5 8. Construction Status Annexure 6 9. PERT Chart Annexure 7 10. Master Plan of Mohali showing project location Annexure 8 11. Approved Layout Pan Annexure 9 12. Layout showing existing & revision Annexure 10 13. Consultant Document Annexure 11
Project Description Infrastructure Development Works Sectors Services Completion (%age) PHYSICAL PROGRESS MOHALI HILLS PROJECT Sector 99, 104, 105, 106, 108 & 109 1. 30 no.s houses have been constructed and customers started residing. 2. STP with initial module capacity of 01 lakh liters each in sector 105 & 108 and 10 thousand liters in sector 109 installed. Sewerage Drainage Water supply Flushing Roads Street lighting Feeder pillars UG water tanks Parks development work 90% 90% 90% 90% 90% 85% 85% 100% 80% The Views Sec. 105 (Multi storey apartments) Total units 696 nos. 1. Tower J (84 units) Finishing work completed. Occupation certificate received from GMADA. 66 units handed over to customers. 2. Tower G (112 units) Finishing work completed. Occupation certificate received from GMADA. 32 units handed over to customers. 3. Tower H (148 units) Structure work completed. 4. Tower K (112 units) Structure work completed. 5. Tower L (136 units) Structure work completed. 6. Tower F (104 units) Structure work completed. Central Plaza Sec.105 (Commercial) The Bungalows Sec. 105, 108 & 109 (Single storey unit) Total units 286 nos. 1. Structure/finishing work completed. 2. Occupation certificate received from GMADA. 3. 06 units handed over to customers. Total units 68 nos. 1. 51 units in sector 108 & 109 completed. 2. Structure works for 17 units completed. 3. Occupation certificates received from GMADA for 50 units. 4. 14 units handed over to customers. The Villas Sec. 106, 108 & 109 (Three storey unit) Total units 99 nos. 1. Structure works of 99 units completed. 2. Occupation certificates received from GMADA for 57 units. 3. 09 units handed over to customers. The Terraces Sec. 108 (Independent floors) Total units 54 nos. 1. Structure work of 54 units completed 2. Occupation certificate received from GMADA for 48 units. 3. 21 units handed over to customers.
PERT/CPM CHART OF MOHALI HILLS PROJECT S. No Description 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 1 Purchase of Land 2 Approvals Grant of EC & CTE Approval of CLU Approval of layout Approval of building plans 3 Excavation Group Housing/Central Plaza 4 Construction GH/CP/VILLA/BUNGALOWS/TERRACES 5 Installation of DG set/stp 6 Grant of Consent to Operate 7 Maintenance a Roads / Parks b Villa c Bungalow d Terraces e Group housing f Central plaza 8 Development after grant of EC a Roads / Parks/Infrastructure b Villa c Bungalow d Terraces e Group housing f club house
MASTER PLAN OF MOHALI SHOWING PROJECT LOCATION Mullanpur Chandigarh Zirakpur To Ropar Kharar Project Site Banur To Tepla To Sirhind To Patiala 5
NORTH ZONE
SOUTH ZONE
INTEGRATED TOWNSHIP WITH SPECIAL EDUCATION AND WELLNESS ZONE SECTOR- 98,99,104,105&106 SAS NAGAR PROMOTERS MGF Emaar MGF Land Limited REVISION DELETION EXPANSION PLANNING CHANGE REVISION DELETION REVISION DELETION EXPANSION PLANNING CHANGE EXPANSION PLANNING CHANGE LEGEND RESERVED AREA ( TO BE PLANNED LATER) OTHER'S LAND COMMERCIAL AREA PUBLIC/INSTT. SCHEME BOUNDARY VILLAGE RASTA AREA DEDUCTED UNDER ROAD AREA PARTIALLY OWNED & BALANCE UNDER GOVT. ACQUISITION AREA FULLY UNDER GOVT. ACQUISITION N 09 Nov. 2014
INTEGRATED TOWNSHIP WITH SPECIAL EDUCATION AND WELLNESS ZONE SECTOR- 108,109&110 SAS NAGAR PROMOTERS MGF Emaar MGF Land Limited REVISION/ DELETION REVISION/ DELETION REVISION DELETION EXPANSION PLANNING CHANGE PLANNING CHANGE PLANNING CHANGE PLANNING CHANGE PLANNING CHANGE PLANNING CHANGE PLANNING CHANGE REVISION/ DELETION PLANNING CHANGE EXPANSION LEGEND RESERVED AREA ( TO BE PLANNED LATER) OTHER'S LAND COMMERCIAL AREA PUBLIC/INSTT. SCHEME BOUNDARY VILLAGE RASTA AREA DEDUCTED UNDER ROAD AREA PARTIALLY OWNED & BALANCE UNDER GOVT. ACQUISITION AREA FULLY UNDER GOVT. ACQUISITION REVISION/ DELETION N 1'=160'-0" 15 Nov. 2014 EM-MP/SUB/MH/1.01B