Shelter 'Phantom Homes' Research. Planning Permissions, Completions and Profits

Similar documents
Housebuilding Market Report - UK

New Housing Pipeline. Quarterly report. December Analysis of market conditions and prospects prepared by Glenigan.

Local Authority Housing Companies

NEW HOUSING PIPELINE Q REPORT. Published Dec Analysis of market conditions and prospects prepared by Glenigan.

NEW HOUSING PIPELINE Q REPORT. Published April Analysis of market conditions and prospects prepared by Glenigan.

A matter of choice? RSL rents and home ownership: a comparison of costs

Appendix 1: Gisborne District Quarterly Market Indicators Report April National Policy Statement on Urban Development Capacity

Policy Briefing Banish the Bedroom Tax Monster Campaign- Action Plan for Scotland

DCLG consultation. Tackling unfair practices in the leasehold market. Consultation response. shelter.org.uk/policylibrary.

Regulatory Impact Statement

Discussion paper RSLs and homelessness in Scotland

Government Consultation in Tackling Unfair Practices in Leasehold. Response from Association of Retirement Housing Managers (ARHM)

Housing Need in South Worcestershire. Malvern Hills District Council, Wychavon District Council and Worcester City Council. Final Report.

Reg. Section 15a.453-1(c)(2) Installment method reporting for sales of real property and casual sales of personal property

Tackling unfair practices in the leasehold market: A consultation paper Response from NAEA Propertymark September 2017

Reforming the land market

London Tenants Federation Genuinely affordable housing or just more of the affordable housing con?

Housing as an Investment Greater Toronto Area

Housing Revenue Account Rent Setting Strategy 2019/ /22

Fraser of Allander Institute

Strategic Housing Market Assessment South Essex. Executive Summary. May 2016

Performance of the Private Rental Market in Northern Ireland

London Borough of Lewisham Response to Achilles Street Stop and Listen Campaign FACT SHEET

Commercial Real Estate Debt Finance This course is presented in London on: 26 February 2018, 29 November 2018

Residential Planning & The NPPF

Rugby Borough Plan: Housing Delivery Study

UK Housing Awards 2011

US Worker Cooperatives: A State of the Sector

Special Report. Australia s Cheapest Suburbs with the Greatest Potential for Capital Growth. For more reports head to

Funding future homes: Executive summary and discussion

Research & Forecast Report New Zealand Workplace Report. Occupational trends across New Zealand. Accelerating success.

Subject. Date: 2016/10/25. Originator s file: CD.06.AFF. Chair and Members of Planning and Development Committee

CONTROLLING AUTHORITY: Head of Housing & Community Services. DATE: August AMENDED: Changes to Starter Tenancies.

Briefing: National Planning Policy Framework

Lanteglos by Fowey HOUSING NEED SURVEY. Report Date: 1 st March Version: 1.1 Document Status: Final Report

The English Housing Survey

Research report Tenancy sustainment in Scotland

The use of greenfield and brownfield land in Greenbelt housing & commercial projects

roots The Substance of the Standard Contents Changes to the Accounting for Goodwill for Private Companies

Direction for General Regulation Concerning Jointly Owned Properties. Chapter One Definitions and General Provisions

THAT Council receives for information the Report from the Planner II dated April 25, 2016 with respect to the annual Housing Report update.

The survey also examines the underlying causes of FVM and impairment audit

NORTH LEEDS MATTER 2. Response to Leeds Sites and Allocations DPD Examination Inspector s Questions. August 2017

Private Rented Sector Priorities For London

MOBILEHOME PARK RENT STABILIZATION PROGRAM

Cost of owning and running a home at highest level since 2008

Contents SEPTEMBER 2009

West Surrey Strategic Housing Market Assessment

International Financial Reporting Standards. Sample material

Practitioner Article Tenancy Sustainment not just the latest buzz word!

Policy Response Budget 2017

LSL New Build Index. The market indicator for New Builds September The New Build Housing Market

Value for Money. Self Assessment Summary 2017

The private rented housing sector: The UK and ideas from other countries

21 March Development Update

Contents 3/24/2011. New delivery context. HCA role and remit. Delivering for local communities. HCA in North East, Yorkshire and the Humber

H 19. Sustainability Policy. April 2017 April 2020

DCLG consultation on proposed changes to national planning policy

2013 Update: The Spillover Effects of Foreclosures

ON THE HAZARDS OF INFERRING HOUSING PRICE TRENDS USING MEAN/MEDIAN PRICES

acuitas, inc. s survey of fair value audit deficiencies August 31, 2014 pcaob inspections methodology description of a deficiency

Findings: City of Johannesburg

PIA would be pleased to meet with the Department to outline any aspect of our submission. Please contact myself or John Brockhoff on

Assets, Regeneration & Growth Committee 17 March Development of new affordable homes by Barnet Homes Registered Provider ( Opendoor Homes )

CJC response to the DCLG consultation on: TACKLING UNFAIR PRACTICES IN THE LEASEHOLD MARKET

Status of HUD-Insured (or Held) Multifamily Rental Housing in Final Report. Executive Summary. Contract: HC-5964 Task Order #7

No place to live. A UNISON survey report into the impact of housing costs on London s public service workers

Key findings from an investigation into low- and medium-value property sales. National Audit Office September 2017 DP

City Futures Research Centre

THE NON-DOMESTIC PRIVATE RENTED PROPERTY MINIMUM STANDARD

Viability and the Planning System: The Relationship between Economic Viability Testing, Land Values and Affordable Housing in London

Frequently Asked Questions: Residential Property Price Index

B8 Can public sector land help solve the housing crisis?

Briefing Book. State of the Housing Market Update San Francisco Mayor s Office of Housing and Community Development

Guidelines For Creating a TBRA Administrative Plan

ADDRESSING HOUSING AFFORDABILITY IN AUSTRALIA:

ental Market report Vacancy Rate Up Slightly Vacancy Rate Edges Higher in 2004 Charlottetown CA CHARLOTTETOWN Canada Mortgage and Housing Corporation

The Housing Market of Tomorrow: An Expert View

Delivery of Homes in Milton Keynes - Evidence and Analysis of Site Delivery

Full Year Results Presentation for the year ended 31 December March 2015

STRATEGIC HOUSING INVESTMENT PLAN SUBMISSION. 16 October Report by the Service Director Regulatory Services EXECUTIVE COMMITTEE

Technical Description of the Freddie Mac House Price Index

Special Report. Australia s Cheapest Suburbs with the Greatest Potential for Capital Growth. For more reports head to

THE AGGREGATETM 4TH QUARTER 2015

3 November rd QUARTER FNB SEGMENT HOUSE PRICE REVIEW. Affordability of housing

An Assessment of Recent Increases of House Prices in Austria through the Lens of Fundamentals

SUBDIVISION AND LAND DEVELOPMENT ORDINANCE

DETACHED MULTI-UNIT APPROVALS

I. Amount Received Pursuant to Section : This section provides a total amount of funds received pursuant to Section (b)(3)(A).

Report to Barratt Homes 31 October Urban Extensions. Assessment of Delivery Rates. savills.co.uk

Rental housing still not affordable

Housing and Planning Bill + Welfare Reform and Work Bill

TECHNICAL INFORMATION PAPER VALUATION OF SELF STORAGE FACILITIES

INDEPENDENT FINANCIAL AUDIT REPORT OF THE LOW AND MODERATE INCOME HOUSING ASSET FUND FOR FISCAL YEAR PURSUANT TO SECTION 34176

August 2012 Design by Anderson Norton Design

Campaign for Housing and Community Development Funding

Buy-to-let: A bright outlook?

Proposed Strategic Housing and Employment Land Availability Assessment (SHELAA) Methodology 2018

The New House Market in Outer Sydney

Shaping Housing and Community Agendas

Transcription:

Research Briefing Shelter 'Phantom Homes' Research Planning Permissions, Completions and Profits July 2017 /policylibrary 2010 Shelter. All rights reserved. This document is only for your personal, non-commercial use. You may not copy, reproduce, republish, post, distribute, transmit or modify it in any way. This document contains information and policies that were correct at the time of publication. 2017 Shelter

Shelter helps millions of people every year struggling with bad housing or homelessness. We provide specialist advice and support on the phone, face to face and online, and our legal teams can attend court to defend people at risk of losing their home. However, at Shelter we understand that helping people with their immediate problems is not a long-term solution to the housing crisis. That s why we campaign to tackle the root causes, so that one day, no one will have to turn to us for help. We re here so no one has to fight bad housing or homelessness on their own. 2017 Shelter 2 2

Overview of Research Briefing Shelter released new research on the topic of planning and housing development on Friday the 7 th July 2017. This research briefing provides an overview of the key findings and our method. Context Local authorities continue to increase the number of planning permissions they grant. DCLG planning permission statistics released in June 2017 i found that in 2016/17: 6,617 major residential permissions were granted by district planning authorities (59% increase on five years ago). 43,381 minor residential permissions were granted (31% increase on five years ago). However, while private housing developers have increased the number of homes they build, England still haven t built 200,000 new homes a year at any point since the recession ii. It is widely accepted that we need to be building at least 250,000 homes to adequately meet housing need. Housing supply has faltered despite a recent upward trend in the usage of conversions/changes of use to provide new dwellings. This includes office to residential conversions involving the permitted development rights policy an approach to new housing supply which entails significant opportunity costs for enterprise, as well as eroding minimum space standards. In this context, it is clear we have become too reliant on one model of housebuilding. To stop homelessness from rising iii, and meet demand for new homes iv, we need to find new ways of building the quality, genuinely affordable homes the people in this country need. This is what Shelter is calling for, under the banner New Civic Housebuilding. Research Aims Our researchers sought to answer two principal questions to illuminate the extent to which our current approach to housebuilding is failing: 1) How have developers balance sheets matured over the last five years? 2) Is there a shortfall between planning permissions and completions over recent years? The remainder of this briefing will address these questions. Part I: Developer Profits Overview The housing market crash was a chastening experience for some private UK housing developers, including requiring the assistance of the UK government to boost site viability and demand. Over recent years however, there has been a growing debate about the extent to which developers benefit from our current situation of constrained new housing supply, which is tens of thousands of homes per annum fewer than needed. To explore this issues, the following analysis utilises an existing methodology developed by Sheffield Hallam University academics at the Centre for Regional Economic and Social Research (CRESR). A five-year time period was chosen, beginning in 2011, allowing for a period of recovery for developers balance sheets following the previous housing market crash. 2017 Shelter 3 3

Method Developers report differently, sometimes at different times, and their usage of terms such as profit before tax and exceptional items is different. Major developers also often generate revenue from other activities besides UK housebuilding for example development activity in other countries (e.g. Taylor Wimpey in Spain) and commercial non-residential activity (e.g. Barratts). As addressed above, to estimate developer profits arising specifically from UK residential development activity, Shelter used an existing methodology from the Centre for Regional Economic and Social Research (CRESR) at Sheffield Hallam University v. CRESR s segmental approach to attribution was informed by advice from a qualified accountant, and it involved using developers own account and reports. One of the authors of the CRESR report, Dr Tom Archer, was consulted extensively regarding the below calculations. Many thanks to Dr Archer for his kind assistance. Full method contained within CRESR (2016): Profits before volume: Major housebuilders and the crisis of housing supply The profit measure used was profit before tax and exceptional items. This choice is particularly relevant in an analysis of the accounts of large housebuilders following the crisis, as large impairments were included in their accounts, particularly in 2009, which reduced the value of their land and other assets. Including these items gives a sense of the current financial health of developers, but it may conceal the underlying profitability (or otherwise) of their normal functions such as UK housebuilding vi. Therefore, for this research, it was most appropriate to use profit before tax and exceptional items, in order to shed light on the normal activities of developers and profits arising from those activities. The top 5 developers by UK housebuilding revenue at the end of the period under study were (in order): Barratt Developments PLC, Taylor Wimpey PLC, Persimmon PLC, Berkeley Group Holdings PLC, and Bellway PLC. These five developers produced around one third of all new build homes in England in 2015/16. Findings Using the top 5 developers own accounts it is estimated that their UK housebuilding profits before tax and exceptional items increased by 388% between 2011-2016. Profits before tax and exceptional items for the top five developers in 2011 were estimated to be 674m and in 2016 they were estimated to be 3.3bn. NB: Due to different reporting times, the above figures are for calendar years, rather than the financial years utilised in the planning permissions/completions comparison above. Additional: Recent research on Shareholder dividends CRESR (2016) highlighted the emphasis on improving profit margins when selecting sites by housebuilders vii. It also highlighted changes in major developers business models, towards maximising short-term shareholder return viii. The below charts the increase in the dividend share of the top five developers after-tax profits between 2010-15 ix. Note that after-tax profits increased substantially over this period. Dividends therefore are taking an increasing share of an increasing total. 2017 Shelter 4 4

Shareholder dividends from just the top five developers were 936m in 2015. CRESR estimate these 2015 dividends alone could have funded an additional private housing output of nearly 9,000 dwellings. Part II: Planning Permissioned Units / Completions Introduction There has been growing discussion of the build out rates of major developers (for example, see Select Committee on Economic Affairs Building More Homes (2016)) and the extent to which there is a gap between planning permissions and completions. The following analysis uses pre-eminent resources for planning permissioned units and completed units including data from the Home Builders Federation, the voice of the housebuilding industry in England, in order to ascertain the size of any gap between planning permissions and actual completions. 2017 Shelter 5 5

Overview of Statistics Number of units securing detailed planning approval (Source: Home Builders Federation/Glenigan Housing Pipeline reports) Geography Total number of planning permissioned units (2010/11-2014/15) Average per annum England 1,020,000 204,000 London 222,000 44,000 The HBF s definition of a planning approval is x : Approvals are recorded at the detailed planning stage. Where a project has secured outline planning approval and the detailed consent is being resolved through the approval of reserve matters the date of detailed consent is deemed to be that of the approval of reserve matters. In the case of some projects, the reserve matters are approved piecemeal; in these circumstances the earliest approval date has been used in order to avoid double counting. Of this latter category, some of these sites may take a significant length of time before leaving the planning system. But some sites will have been stalled from before our period of study as well, and due to Glenigan s method, those additional detailed consent approvals will not figure in these planning permission numbers. It is hard to know without site-by-site data which one of these influences outweighs the other, particularly given the housing market crash just before our period of analysis, and its stalling impact on planning and development alike. Limitations This data has been challenged by local authority representatives, using London Development Database data as a comparator xi : Appendix one gives more detail, but we particularly draw your attention to a comparison of Glenigan data (as used by DCLG and LGA) with approvals collected through the statutory London Development Database (LDD). This shows that the stock of unimplemented permissions identified by Glenigan excludes some types of development and, significantly underestimates the stock of new homes permitted. Complementary analysis of data for sample authorities in the East of England and South East further illustrates how the Glenigan data underestimates the backlog of unused permissions. Based on this local monitoring we believe the backlog to be much greater than Glenigan s estimate and more in line with the LDD findings. Assuming the same known differences occur in the East and South East and to the same degree, the LGA / Glenigan data would be increased by 128%, giving a total of over 510,000 unimplemented homes in the Wider South East, which is over six years supply for new households (see Table 3 in the Appendices). xii However, as this data is published by the HBF themselves, the decision was made to continue to utilise the HBF/Glenigan data, under the proviso that it may undercount, as we are keen to be fair to the industry. 2017 Shelter 6 6

New completions (Source: DCLG Table 120) Geography Completions (2011/12 to 2015/16) England 696,000 London 117,000 DCLG Table 120 was selected over DCLG Table 208, as Table 120 provides a fuller picture of new homes built (the more timely quarterly statistics which underpin Table 208 under-counts high density development, Small Medium Enterprises (SMEs) and private sale by housing associations. We followed Civitas (2016) and others in this regard xiii. Method and key considerations Time naturally elapses between gaining planning approval, starting on site and actually completing a home. The latest evidence on this from the planning and development consultancy, Nathaniel Lichfield and Partners, establishes xiv that the time taken moving from permission to completion varies with site size. On sites of over 2,000 units, the first homes are completed on average after 10 months. On sites of 500 2000 homes, the first homes are delivered around 12 months on average, and sites of <500 units wait on average 18 months for their first completion. It will be the case that sites given planning permission during the period of study will build out after our period of analysis, thus acting as a downward weight on the ratio of completions/planning permissions. However, it is also the case that sites given planning permission before our period of study, will have been built out during out period of analysis, thus inflating the ratio of completions/planning permissions. It is unclear whether either effect will dominate the other, particularly given the potential backlog of planning permissioned units arising from the period of economic recession. There was also a large housing market downturn in the later part of the 2000s. Housebuilders and housebuilding began to recover in 2010 and 2011. Using a lag of more than one year for this analysis would mean looking at permissions in part of the pre-2010 crisis period. This is a key downside to utilising a lag of greater than one year, as it limits the extent to which we can reflect normal times in the planning system. Factoring in all of these considerations, and without the ability to follow individual sites through the development process, the usage of a lag of one year was deemed the most effective approach to ascertaining any shortfall between planning permissioned units and completions at an aggregate level. The following findings are therefore the result of comparing data on planning permissioned units between 2010/11 and 2014/15, with data on English new build completions between 2011/12 and 2015/16. NB: It is possible that granted residential planning permissions expire after a period of time, and are reapplied for. It is not possible to account for this minority of cases in an aggregate-level analysis. Further, if this is occurring as anything more than an exception, it itself raises serious questions about the health of our current approach to housebuilding. 2017 Shelter 7 7

Findings: National The number of completed homes between 2011/12 and 2015/16 was 68% of the number of planning permissioned units between 2010/11 and 2014/15. This is a shortfall of 324,000 homes. A shortfall was particularly driven by large gaps in London and the North West. Sensitivity of these findings If no lag utilised, completions would only be 63% of planning permissioned units leading the calculated shortfall to be 413,000 homes. If a two-year lag was utilised, completions would only be 73% of planning permissioned units, a shortfall of 252,000 homes. This demonstrates that whilst the numbers can shift, with a 10 percentage point difference between no lag and inclusion of a two year lag the overall headline remains the same the current housebuilding model is seeing shortfalls between permissioned units and completions. NB: Some Changes of use require planning permission, if it involves moving between different use classes. In Civitas (2016) and other previous research into planning permissions and completions, changes of use have not been included. This is presumedly in large part because this enters subjective territory, as it is unclear what changes of use in DCLG Table 120 required planning permission, and also the extent to which Glenigan s data covers these relevant permissions. There is also the point that changes of use utilise existent property to deliver new homes, which is not sustainable indefinitely. Over three years of our period of study, many changes of use have been developed through the permitted development rights policy, which does not require planning permission (45% of the 30,600 change of use homes delivered in 2015/16 were conducted through the development rights policy). Further, according to the DCLG https://www.gov.uk/guidance/when-is-permission-required the need for residential planning permission depends on whether the development materially affects the building and its external appearance and there is no statutory definition of this. Therefore, knowing the number of changes of use is not possible from existing aggregate evidence if evidence on this was made available by housebuilders in the future, that transparency would advance future analysis in this area. However, in order to show the lower-bound of our estimate, if half of changes of use in the last five years required planning permission, and all of these were recorded accurately by Glenigan as permissioned units, our two-year lag estimate of 73% would become 77% and our shortfall would reduce by 31,000 homes from 252,000 to 221,000 homes over a five year period. This would be a shift of nine percentage points from our central published estimate, and is our most conservative estimate of shortfall, as it takes in one year of non-normal activity in the planning and development system pre- 2010. Findings: London The number of completed homes between 2011/12 and 2015/16 was 52% of planning permissioned units between 2010/11 and 2014/15. 2017 Shelter 8 8

This is a shortfall of 107,000. Equivalent to 2.5 years of the current Mayor s annual minimum housing supply target. Sensitivity of these findings If no lag utilised, completions would only be 49% of planning permissioned units leading the calculated shortfall to be 120,000 homes. If a two-year lag was utilised, completions would only be 56% of planning permissioned units, a shortfall of 92,000 homes. This demonstrates that while the numbers can shift, with a 7 percentage point difference between no lag and inclusion of a two year lag the overall headline remains the same the current model is seeing shortfalls between permissioned units and completions. For more information on this research, please contact: Marcus McPhillips Research Officer Shelter e: marcus_mcphillips@ t: 0344 515 2047 2017 Shelter 9 9

i DCLG, Planning Applications in England: January to March 2017 (2017) https://www.gov.uk/government/statistics/planning-applications-in-england-january-to-march-2017 ii DCLG, Table 120: components of new housing supply; net additional dwellings, England 2006/7 to 2015/16 https://www.gov.uk/government/statistical-data-sets/live-tables-on-net-supply-of-housing iii DCLG, Live Tables on homelessness, https://www.gov.uk/government/statistical-data-sets/live-tableson-homelessness iv ONS, English Housing Survey 2015/16 https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/595785/2015-16_ehs_headline_report.pdf v Centre for Regional Economic and Social Research (CRESR), Profits before Volume: Major housebuilders and the crisis of housing supply (2016) https://www4.shu.ac.uk/research/cresr/sites/shu.ac.uk/files/profits-before-volume-housebuilders-crisishousing-supply.pdf vi Ibid. p. 17 vii Ibid. i viii Ibid. ii ix Ibid. p. 19 x HBF and Glenigan, New Housing Pipeline: Q4 2016 report http://www.hbf.co.uk/?eid=dam_frontend_push&docid=25620&filename=hpl_report_2016_q4.pdf xi Unlocking unimplemented housing capacity in the East, London and the South East http://www.secouncils.gov.uk/wp-content/uploads/2012/03/web-final-wse-letter-to-gavin-barwell- MP-31.1.17.pdf xii Unlocking unimplemented housing capacity in the East, London and the South East http://www.secouncils.gov.uk/wp-content/uploads/2012/03/web-final-wse-letter-to-gavin-barwell- MP-31.1.17.pdf p. 2. xiii Civitas Planning approvals v housebuilding activity 2006-2015 (2016) http://www.civitas.org.uk/reports_articles/planning-approvals-vs-housebuilding-activity-2006-2015/ xiv Nathaniel Lichfield and Partners, Start to Finish: How quickly do large-scale housing sites deliver? (2016) http://lichfields.uk/media/1728/start-to-finish.pdf 2017 Shelter 10 10