Marion County Board of County Commissioners

Similar documents
Marion County Board of County Commissioners

MARION COUNTY GROWTH SERVICES

Marion County Board of County Commissioners

Marion County Planning & Zoning Commission

Marion County Planning & Zoning Commission

Marion County Board of County Commissioners

Marion County Board of County Commissioners

Marion County Board of County Commissioners

Cover Letter with Narrative Statement

Marion County Board of County Commissioners

Marion County Board of County Commissioners

Marion County Planning & Zoning Commission

Marion County Board of County Commissioners

Marion County Board of County Commissioners

A. Location. A MRD District may be permitted throughout the County provided it meets the standards established herein.

PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: April 18, 2019

Staff Report: Date: Applicant: Property Identification: Acreage of Request: Current Zoning of Requested Area: Requested Action: Attached:

CITY OF DURHAM DURHAM COUNTY NORTH CAROLINA. Zoning Map Change Report. RR Existing Zoning. Rural Rural Density Residential Site Characteristics

Metropolitan Planning Commission. DATE: April 5, 2016

Planning Department Oconee County, Georgia

NEWTON COUNTY BOARD OF COMMISSIONERS REQUEST FOR REZONING

ARTICLE 3: Zone Districts

Glades County Staff Report and Recommendation Unified Staff Report for Small Scale Plan Amendment and Rezoning

REPORT OF THE PLANNING AND DEVELOPMENT DEPARTMENT FOR APPLICATION FOR REZONING ORDINANCE TO PLANNED UNIT DEVELOPMENT MAY 18, 2017

STAFF REPORT. Permit Number: Porter. Kitsap County Board of Commissioners; Kitsap County Planning Commission

HENDRY COUNTY PLANNING & ZONING DEPARTMENT POST OFFICE BOX S. MAIN STREET LABELLE, FLORIDA (863) FAX: (863)

Plans shall be drawn at a readable scale, signed, and sealed by a Florida Registered Engineer. The application package shall include:

Mohave County General Plan

The following regulations shall apply in the R-E District:

ORANGE BLOSSOM GARDENS PLANNED UNIT DEVELOPMENT PREPARED BY: COASTAL ENGINEERING CONSULTANTS, INC.

PLAINFIELD CHARTER TOWNSHIP COMMUNITY DEVELOPMENT DEPARTMENT PLANNING, ZONING & BUILDING SERVICES MEMORANDUM

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M

Proposed Overland Park Kansas Ordinance RE-1 Residential Estates Community

4.2 RESIDENTIAL ZONING DISTRICTS

REZONING APPLICATION INSTRUCTIONS

A G E N D A. BOARD OF ADJUSTMENT PUBLIC HEARING June 6, :00 PM GROWTH MANAGEMENT TRAINING FACILITY 2710 E. SILVER SPRINGS BLVD.

ORDINANCE NOW THEREFORE, BE IT ENACTED BY THE CITY COMMISSION OF THE CITY OF WINTER GARDEN, FLORIDA, AS FOLLOWS:

CITY OF BELLEVIEW PLANNING & ZONING BOARD AGENDA

Letter of Intent May 2017 (Revised November 2017)

Board of County Commissioners Agenda Request

Glades County Staff Report and Recommendation REZONING

STAFF REPORT. Permit Number: Unlimited. Kitsap County Board of Commissioners; Kitsap County Planning Commission

ORDINANCE # NOW THEREFORE BE IT ORDAINED BY THE BOARD OF COUNTY COMMISSIONERS OF HERNANDO COUNTY, FLORIDA:

13 NONCONFORMITIES [Revises Z-4]

PALM BEACH COUNTY PLANNING, ZONING AND BUILDING DEPARTMENT ZONING DIVISION ZONING COMMISSION VARIANCE STAFF REPORT 03/03/2011

Staff Report: Date: Applicant: Property Identification: Acreage of Request: Current Zoning of Requested Area: Requested Action: Attached:

AGENDA ITEM SUMMARY GLADES COUNTY BOARD OF COUNTY COMMISSIONERS

TOWN OF ORO VALLEY PLANNING & ZONING COMMISSION MEETING DATE: December 6, 2011

Appendix J - Planned Unit Development (PUD)

/

Medical Office Condo FOR SALE $139, SE Hillmoor Drive, Building A, Suite 101, Port St. Lucie, FL 34952

PALM BEACH COUNTY PLANNING, ZONING AND BUILDING DEPARTMENT ZONING DIVISION ZONING COMMISSION VARIANCE STAFF REPORT 06/05/2014

MARION COUNTY COMPREHENSIVE PLAN 2035

A. Preserve natural resources as identified in the Comprehensive Plan.

19.12 CLUSTER RESIDENTIAL DISTRICT

Plan nt Plan Filing and

INDIAN RIVER COUNTY, FLORIDA. The Honorable Members of the Planning and Zoning Commission DEPARTMENT HEAD CONCURRENCE

ORDINANCE WHEREAS, the adoption of this Ordinance shall not be construed as an admission that the aforesaid claim has merit or is correct; and

SPECIAL ZONING DISTRICTS

In order to permit maximum applicability of the PUD District, PUD-1 and PUD-2 Districts are hereby created.

Chapter 100 Planned Unit Development in Corvallis Urban Fringe

Planning and Zoning Commission STAFF REPORT REQUEST. DSA : Zone Change from R-3 (Multi-Family Residential) to B-4 (Community Services).

CITY OF SANTA ROSA COMMUNITY DEVELOPMENT DEPARTMENT STAFF REPORT FOR PLANNING COMMISSION SEPTEMBER 10, 2015 APPLICANT FILE NUMBER MJP

TABLE (A): TABLE OF DIMENSIONAL STANDARDS IN THE RESIDENTIAL ZONE DISTRICTS REQUIRED YARDS [4], [5] SIDE YARD (FT) REAR YARD (FT) R-1 DISTRICT

PINE RIDGE COMMONS PUD AMEND ORDINANCE NUMBER 99-94

PALM BEACH COUNTY PLANNING, ZONING AND BUILDING DEPARTMENT ZONING DIVISION

POLK COUNTY DEVELOPMENT REVIEW COMMITTEE CASE OVERVIEW

ARTICLE 14 PLANNED UNIT DEVELOPMENT (PUD) DISTRICT

Town of Cary, North Carolina Rezoning Staff Report 14-REZ-31 Cary Park PDD Amendment (Waterford II) Town Council Meeting January 15, 2015

Exhibit "A" have applied for a re-zoning and re-classification of that property from OPEN RURAL (OR) to that of a PLANNED UNIT DEVELOPMENT (PUD); and

CHAPTER 14 PLANNED UNIT DEVELOPMENTS

DEPARTMENT OF PLANNING JEFFERSON PARISH, LOUISIANA

CHAPTER34 PRUD - PLANNED RESIDENTIAL UNIT DEVELOPMENT

1. Standards for planned shopping business centers shall be as follows: Shopping Center Standards. Type Characteristics Size

PALM BEACH COUNTY PLANNING, ZONING AND BUILDING DEPARTMENT ZONING DIVISION ZONING COMMISSION VARIANCE STAFF REPORT 8/5/2010

COLLIER COUNTY Growth Management Department

2 April 9, 2014 Public Hearing

RP-2, RP-3, RP-4, AND RP-5 PLANNED RESIDENTIAL DISTRICTS

PLANNING COMMISSION REPORT Regular Agenda Public Hearing Item

STAFF REPORT. Community Development Director PO Box 4755 Beaverton, OR 97076

PLANNING COMMISSION STAFF REPORT

Accessory Dwelling Units PJR-032

Planning & Zoning Commission

PLANNED UNIT DEVELOPMENT (PUD) AREA PLAN/REZONING REVIEW PROCEDURE

Midwest City, Oklahoma Zoning Ordinance

AGENDA ITEM SUMMARY GLADES COUNTY BOARD OF COUNTY COMMISSIONERS

Action Recommendation: Budget Impact:

CHAPTER RESIDENTIAL AND OPEN SPACE ZONING DISTRICTS

Tuss and Lisa Taylor. Agriculture

Chapter SPECIAL USE ZONING DISTRICTS

# Coventry Rezoning, Variation and Preliminary/Final PUD Project Review for Planning and Zoning Commission

LYON COUNTY TITLE 15 LAND USE AND DEVELOPMENT CODE ZONING REGULATIONS CHAPTERS October 19, 2017 Ordinance Draft DRAFT

PINE RIDGE COMMONS PUD AMEND ORDINANCE NUMBER 99-94

ORDINANCE NO LOCATED AT ROAD AND PROPERPT SOUTH TO 1-70 BETWEEN 23 ROAD AND BOOKCLIFF RANCHES SUBDIVISION

Planning Department Oconee County, Georgia STAFF REPORT

City of Tarpon Springs Summary Guide To Zoning Districts

CCC XXX Rural Neighborhood Conservation (NC)

Special Use Permit - Planned Unit Development Checklist. Property Address:

Town of Waxhaw Board of Commissioners. Waxhaw Police Department Community Meeting Room Tuesday January 12, 2016

City of Fayetteville, Arkansas Page 1 of 1

Transcription:

Marion County Board of County Commissioners Date: 12/29/2015 P&Z: 12/28/2015 BCC: 1/12/2016 Item Number 160113Z Type of Application Rezoning Request From: A-1 (General Agriculture) To: PUD (Planned Unit Development) Single- Family Residential w/ Accessory Community and Rec Facilities Concurrent Comp Plan Amendment: 2016-S02 Owner: Villages of Lake- Sumter, Inc. Applicant: Darrin F. Taylor, Carlton Fields Jorden Bert Parcel #/Acreage 48361-000-01 ±32.33 Acres Future Land Use Employment Center Staff Recommendation Approval with Conditions P&Z Recommendation: Approval with Conditions Project Planner Item Summary Staff is recommending Approval with Development Conditions for a rezoning from A-1 (General Agriculture) to PUD (Planned Unit Development) for a residential development with accessory community and recreation facilities on ±32.33 acres in accordance with Marion County Land Development Code, Article 2, Division 7 Zoning Change. The Planned Unit Development Classification is intended to encourage the development of land as a planned residential, commercial or industrial development complex or as a planned mixed-use development; to encourage flexible and creative concepts of site planning which will preserve the natural amenities of the land by allowing an appreciable amount of land for scenic and functional open space; provide for an efficient use of land resulting in a smaller network of utilities and streets, thereby lowering development and housing costs; and provide for a more desirable environment than would be possible through the strict application of minimum zoning requirements. (LDC, Division 2, Section 4.2.6) Public Notice Notice of public hearing was mailed to 26 property owners within 300 feet of the subject property. No written comments in opposition have been received at the time of this report s distribution. Location The subject property is located ± 850 south SE Hwy 42, beginning at SE 73 rd Avenue and extending ±1,000 east. The south site boundary adjoins the Villages of Marion development project s existing golf course. 1 Page

Christopher Rison, Senior Planner Location: ± 850 south SE Hwy 42, beginning at SE 73 rd Avenue and extending ±1,000 east. Code Enforcement Action: None Background The site is currently zoned A-1 with an Employment Center future land use designation that allows residential, commercial retail, commercial office, and light industrial uses, or combinations of such uses in a mixed use development. The Employment Center land use is intended to provide for community and regional level activities with higher densities and intensities of use in Urban Areas. The applicant is proposing a residential development with accessory community and recreation facilities as part of an expansion of the Villages of Marion project. As such, the project will be a senior retirement (55+) community, and will provide for interconnection to the existing Villages of Marion project via private golf cart/multi-use trail. The site is part of the Urban Area along the SE Hwy 42 corridor which is an extension of the S Hwy 441 corridor to the east. It essentially adjoins the Villages of Marion project, and lies southeast of Orange Blossom Hills and south of the Ecclestone residential project site. The Employment Center land use allows for residential densities or equivalents up to 12 DU/AC or a Floor Area Ratio (FAR) of 2.0 for commercial uses. The following table summarizes the site s adjacent future land use designations, zoning districts and existing uses: Direction of Adjacency North Adjacent Property Characteristics Future Land Use Zoning Designation A-1 (General Agriculture) Employment Request 20160116Z Center PUD (Planned Unit Development) South High Residential PUD (Planned Unit Development) East Employment Center A-1 (General Agriculture) Request 20160114Z R-E (Residential Estate) West Rural Land A-1 (General Agriculture) Existing Use (MCPA Property Code) SFR and/or vacant agriculture tracts Villages of Marion (Golf/Open Space) SFR agriculture tracts Flag parcel access; SFR agriculture tracts Request The applicant is requesting to establish a residential PUD for senior housing. The applicant intends to incorporate the site into the existing Villages of Marion PUD and is proposing using the same development standards as established for that project with some additional modifications in response to Marion County s current Land Development Code (LDC) standards. The overall site consists of ±32.33 acres which will be accessed by a new roadway extending south from Hwy 42 which will also provide access for an adjoining mixed use PUD (Rezoning Application 20160116Z). The concept plan and accompanying documents generally propose a maximum density of 5 DU/AC for the project; however the formal project application is for up to 131 residential units for a resulting gross density of 4.05 du/ac. The proposed residential unit type is the current Villages villa unit which features a narrow lot design in a zero-lot-line form with limited front and year yards while allowing limited accessory facilities (e.g., pool/hot tub, pool enclosures, etc.). The gross residential density for the PUD will comply with the 12 DU/AC 2 Page

density of the site s Employment Center future land use designation. No commercial uses are proposed; however community support and recreation facilities including postal collection/kiosk and club house/recreation center will be provided. Additionally, a golf cart path connecting the PUD to the main Villages of Marion project is anticipated and proposed to begin at the rear southeast corner of the site and then extending east across a proposed estate lot subdivision adjoining the site (20160114Z) and the First Baptist Church at the Villages. The applicant has not proposed a maximum gross height limit for residential structures; however, the Villages villa product is typically a single-story residence to meet the needs of the residents. The area s existing zoning classes of A-1 and R-1 establish a 50 building height limit, and a corresponding limit is recommended for this PUD project. Access to the site will be provided by a roadway extending north to Hwy 42 that will be a shared access with the two properties to the north which are undergoing a separate PUD consideration (20160116Z). Final access designs will be coordinated through the development review process, including provisions for cross access and/or access management for Hwy 42. The Conceptual Plan indicates a buffer tract along the west, southwest and southeast boundaries of the PUD project; however, no design standards are proposed by the PUD. The lands west of the site are Rural designated, A-1 zoned, and occupied by active agricultural uses, which requires a minimum Type E Buffer. A reduced setback of 0 is proposed for all setbacks; however, utility and stormwater easement requirements will also functionally increase setbacks in appropriate locations as the project undergoes further detailed plan review (e.g., Master Plan, Preliminary Plat, Final Plat, etc.). The Development Review Committee (DRC) is schedule to consider the PUD Conceptual Plan at its December 21, 2015 meeting. Staff will present DRC s recommendation regarding granting the PUD at the time the Planning & Zoning Commission considers this PUD request. Analysis In reaching its decision, the Planning & Zoning Commission must address the following: a. Granting the proposed zoning change will not adversely affect the public interest. The site is part of an Employment Center designated area within the S Hwy 441/SE Hwy 42 Urban Area and is in proximity to the existing Orange Blossom Hills and Villages of Marion projects, and is proposed for inclusion within the Villages of Marion project. The requested residential PUD will add to the housing diversity in the area and allow expansion of an existing successful development project. The coordinated access with the adjoining property to the north will ensure access management is addressed along with accommodating cross access along Hwy 42. Marion County Fire Services has noted that the Villages Fire Station #10 is currently experiencing significant call volumes and equipment 3 Page

demands related to Emergency Medical Services (EMS) needs. The proposed PUD is expected to create additional demands on EMS call volumes. This is a key concern due given the Rezoning Applications adjoining this site and in the vicinity (20160112Z, 20160114Z, and 201601016Z). It will be necessary for the applicant to coordinate with Marion County Fire Services and the other referenced projects to ensure sufficient capacities are in place to address the proposed PUD development prior to the finalization and recording of the project s Final Plat. The character of the project, once the concerns of Fire Services are suitably addressed, will accommodate diverse housing types for the surrounding community and provide for the expansion of an existing development project. The proposed PUD will not adversely affect the public interest. b. The proposed zoning change is consistent with the current Comprehensive Plan. The FLU Map 1: Marion County 2035 Future Land Use Map of the Comprehensive Plan designates this property as Employment Center. The proposed development intensity will comply with the gross maximum intensity of the land use designation, and is consistent with the Comprehensive Plan. c. The proposed zoning change is compatible with land uses in the surrounding area. The property is part of a larger overall parcel cluster adjoining the Villages of Marion project, and is slated to be an expansion of that project. The PUD will provide for housing diversity for the surrounding communities, while accommodating the expansion of an existing successful project. The development of complimentary uses for the surrounding community will support the Urban Area nature of the surroundings and support a town center effect with the Villages of Mulberry Grove commercial complex. The proposed PUD is compatible with the land uses in the surrounding area. Infrastructure Access to the property is from SE Hwy 42 via a planned future shared roadway and cross access ingress/egress locations as finally determined with the project s final Master Plan or subsequent plans. Existing Conditions Road Classification Maintenance Surface SE Hwy 42 Collector, Arterial (urban) No. Lanes R/W Width R/W Deficiency State Paved 4 80' 40 Water/Sewer services are to be provided on site by Applicant. Utility Service Area Water Marion County Utilities SE Stonecrest Regional Utilities Sewer Marion County Utilities SE Stonecrest Regional Utilities 4 Page

Staff Recommendation - Approval with the following development conditions: 1. The PUD site is approved and authorized for use in the development of 131 detached senior retirement residential dwelling units. The number of units may be increased to 161 (gross density 5 du/ac on 32.33 acres), subject to filing appropriate updates to the Master Plan, or equivalent, consistent with applicable Land Development Code requirements effective at that time for such increases. 2. The maximum structure height for the development shall be 50 for all development within the project (e.g. residence, accessory structures, etc.). 3. The PUD shall provide a minimum Type E Buffer along the site s western boundaries, abutting the existing A-1 zoned properties, within the buffer area shown on the PUD Concept Plan; however, increased buffer designs (width, planting intensity, etc.) may be provided. 4. Development of the PUD shall ensure that mutual cross access for Hwy 42 between the PUD and the adjoining PUD development project to the north (Rezoning Application 20160116Z) is available. 5. Prior to the approval of the project s Final Plat, the applicant/developer shall coordinate with Marion County Fire Services to ensure that the agency may accommodate the proposed development. This coordination may include participation by other parties, including but not limited to, those parties responsible for Rezoning Applications (20160112Z, 20160114Z, and 20160116Z). 5 Page

CURRENT ZONING ZONING DISTRICT A-1 General Agriculture R-3 Multiple Family Dwelling R-O Residential Office RI Rural Industrial A-2 Improved Agriculture R-4 Residential Mixed Use B-1 Neighborhood Business M-1 Light Industrial A-3 Residential Agricultural Estate MH Manufactured Housing B-2 Community Business M-2 Heavy Industrial RR-1 Rural Residential P-MH Mobile Home Park B-3 Specialty Business I-C Industrial Complex R-E Residential Estate P-RV Recreational Vehicle Park B-4 Regional Business G-U Government Use R-1 Single-Family Dwelling RR Recreational Resort B-5 Heavy Business R-PUD Residential Planned Unit Development R-2 One-and Two-Famiy Dwelling RAC Rural Activity Center RC-1 Rural Commercial PUD Planned Unit Development PROPOSED ZONING 6 Page

PUD General Conceptual Plan 7 Page