TRENCHING UNDERGROUND DISTRIBUTION ALL UNDERGROUND DISTRIBUTION DESIGNS ARE TO BE A CUSTOMER PROVIDED TOTAL CONDUIT SYSTEM INSTALLATION.

Similar documents
CHAPTER IV. ELECTRIC

LINE EXTENSION APPLICATION AGREEMENT PROJECT: LINK#

Dallas Sloan General Manager Barron Area Phone: (715) Toll Free: Fax: (715) NEW SERVICE PROCESS

If you have any questions, please contact a Black Hills Energy construction representative in your area.

New Commercial Service Application

Rule No. 15. Distribution Line Extensions Page 1 of 14

a. RIGHTS OF WAY: Utility will own, operate and maintain extension facilities only: ISSUED BY Date Filed: July 2, 1996

If you have any questions, please contact a Black Hills Energy construction representative in your area.

ARTICLE 7 UTILITIES AND EASEMENTS

Underground Electric Distribution Systems for Developments DATE CREATED: 10/01/85 REVISED: 10/14/14

TELECOMMUNICATION STANDARDS Cable Plant and Wireless Networking Standards Updated January 21, 2015

DIVISION 2 - CONSTRUCTION PLAN AND MISCELLANEOUS REQUIREMENTS

-MENDOCINO COUNTY PLANNING AND BUILDING SERVICES- DIVISION OF LAND REGULATIONS TITLE 17

Electric Transmission Right-of-Way Usage Policy

NASSAU COUNTY BUILDING DEPARTMENT MOBILE HOME APPLICATION CHECKLIST

DEVELOPMENT POLICY INFRASTRUCTURE GUIDELINES FOR NEW DEVELOPMENT

Subdivision Backbone Application Packet

Installation and handling instructions PITT cooking in kitchen worktops

REGULATIONS OF WALLER COUNTY, TEXAS

COUNTY OF MOWER HIGHWAY DEPARTMENT th Avenue N.E. Austin, MN Phone (507) /Fax (507) REGISTRATION FORM.

Zoning Permit Application

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

Section 5 SERVICE EXTENSIONS Electric Tariff 1 st Revised Sheet No. 15 Filed with Iowa Utilities Board Cancels Original Sheet No.

a.- ~ ~:fl~wifl*rr. ficer erry Ambrose, Finance Director

CHAPTER 17 STREETS AND SIDEWALKS ARTICLE I TOWNSHIP ROAD OCCUPANCY PERMITS

Condominium Unit Requirements.

TRI-COUNTY RURAL ELECTRIC COOPERATIVE, INC. POLICY BULLETIN NO. 3-4

RIGHT-OF-WAY USE APPLICATION

MAGELLAN PIPELINE COMPANY, L.P.

STATE OF OKLAHOMA TEXAS COUNTY PUBLIC SERVICE/PIPELINE OWNER. LINE INSTALLATION (Revised May 14, 2015)

Property Lines and Easements

B. G E N E R A L L A N D L O R D / T E N A N T REQUIREMENTS

Installation and handling instructions PITT cooking in kitchen worktops

POLICY: Line Extensions for New Services

Tables and worktop extensions

Sub Major Tenant Building Signage (7,000 to 34,999 square feet)

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

SUBDIVISION BACKBONE COVER LETTER

HOME ENROLLMENT NOTIFICATION OF CONSTRUCTION AND INSPECTION BUILDER/SELLER APPLICATION FOR HOME ENROLLMENT

2213 BUTLER PAD SITE NEAR NEW PARKLAND HOSPITAL. Butler Street at Redfield Dallas, Texas EDGE REALTY PARTNERS

PROPERTY OWNER NOTICE AND CONSENT FORM (for Home Charging Station and/or Surge Protector Installation)

3. No buildings or other permanent structures are allowed in Easement Area without Grantee's written consent.

CITY OF HAMMOND ORDINANCE NO.

Two Notch Road. 3 Mile: Popula on: 53,000 Median HH Income: $68, Mile: Popula on: 98,200 Median HH Income: $63,300

Ordinance #68. Highlighted items in bold and underline font to be added. Highlighted items in strikethrough font to be removed.

ARTICLE 13 CONDOMINIUM REGULATIONS

PLANNING CLEARANCE. Planning Clearance is required prior to the submittal of most building and development permit applications.

Towne Center Boulevard William Penn Highway. Lot 2. 1 Mile Population: 3,600 Median HH Income: $36,800


CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF ENGINEERING STANDARD FEE LIST (Effective July 1, 2017)

POLICY: Line Extensions for New Services

The Bolton Fair Inc Commercial License

Developer Guide. Contents. Project Process Flow. Developer Checklist. Will-Serve Letter. Customer Information Sheet

SPRING BROOK TOWNSHIP 966 STATE ROUTE 307 SPRING BROOK TOWNSHIP, PA PHONE (570) FAX (570)

SUMMARY OF SIGN REGULATIONS AND PERMIT PROCESS City of Conroe Code of Ordinances Chapter 90, Section 1-15

Prospective Builders, Utilities, Public Agencies, and Engineering Firms

The Bolton Fair Inc Commercial License

2018 APPLICATION AND PROCESS FOR OBTAINING WATER AND SEWER SERVICES

OTERO COUNTY ELECTRIC COOPERATIVE, INC FOURTH REVISED RULE NO. 15 CANCELING THIRD REVISED RULE NO. 15 EXTENSION POLICY.

JEFFERSON COUNTY, ALABAMA

CHAPTER 620. [History: Repealed and Recreated by Ord ]

Frequently Asked Questions About 20A Undergrounding Updated on June 17, 2014

ITASCA COUNTY OF DEPARTMENT OF HIGHWAYS. APPLICATION FOR UTILITY PERMIT on COUNTY HIGHWAY RIGHT OF WAY

6. No existing structure shall be moved onto any part of the premises within this plat.

PLAT OF SURVEY VICINITY MAP (NOT TO SCALE) N N W E SITE BENCHMARK # 2 W E N&D ON BACK OF CURB NAVD 88 S S 0' 10' 20' 40' 60' 1" = 20' TOP=106.7

Understanding Accessibility Features to Meet Housing Needs

JOHNSON COUNTY PUBLIC WORKS 2 North Mill Street/Suite 305, Cleburne, TX (817)

Construction Permit for Onsite Sewage Treatment System

DOMINION ENERGY VIRGINIA/DOMINION ENERGY NORTH CAROLINA GUIDELINES FOR USE OF REAL ESTATE ENCUMBERED BY ELECTRIC TRANSMISSION RIGHTS OF WAY

APPLICATION FOR MEMBERSHIP

STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES STATE PIPELINE COORDINATOR S OFFICE ANALYSIS OF AMENDMENT APPLICATION AND PROPOSED DECISION

Dry Hydrant Installations. Traditional and Bridge-Mount Dry Fire Hydrant Designs By GBW Associates, LLC

CHAPTER 14: DRIVEWAYS, TOWN HIGHWAYS, AND PRIVATE ROADS

Saf-T-Bar Conductor Bar C Series

SWIMMING POOL PERMIT APPLICATION PACKET

Chapter 21 MOBILE HOME PARK REGULATIONS.

ORANGE TOWNSHIP SIDEWALK CONSTRUCTION, REPAIR AND MAINTENANCE POLICY

1 Mile: Population: 14,200 Median HH Income: $62, Mile: Population: 71,100 Median HH Income: $68,600

SEPTIC PERMIT INFORMATION

Municipality of Anchorage, Alaska Parks & Recreation Department

COLD DARK SHELL LEASE EXHIBIT

CHAPTER 154 RIGHTS OF WAY

PRELIMINARY SUBDIVISION AND LAND DEVELOPMENT PLAN CHECKLIST. Applicant's Name:

Fields of Shorewood HOA Rules & Regulations

Name: Address: City/State Phone: *Please include the Commercial/Industrial/Other Establishment Sheet with permit

Appearance Review Board Staff Report

MAPLETON CITY CORPORATION. Step 7: Upon final approval and prior to plat recording the applicant shall provide the following:

SMITH DOUGLAS H OMES P RE SENT S HIGHLANDS AT MADISON PARK BASE PRICE SHEET. The Benson 3 Beds / 2.5 Baths Approx 1,801 Sq. Ft.

Application for Preliminary Plat Checklist

CHAPTER 68 GEOPHYSICAL/SEISMIC TESTING

FENCE BUILDING PERMIT APPLICATION

Requirements for New Service

LANGLADE COUNTY ANIMAL WASTE STORAGE ORDINANCE

TENANT SIGNAGE CRITERIA. June 12, 2017

DESCRIPTION OF LANDLORD'S WORK & TENANT'S WORK

Committed to Service. License Agreement Application Form

Understanding Accessibility Features to Meet Housing Needs

CARTERET-CRAVEN ELECTRIC MEMBERSHIP CORPORATION MOREHEAD CITY, NORTH CAROLINA Service Rules and Regulations

COASTAL WATER AUTHORITY

SEPTIC PERMIT APPLICATION

Transcription:

TRENCHING UNDERGROUND DISTRIBUTION ALL UNDERGROUND DISTRIBUTION DESIGNS ARE TO BE A CUSTOMER PROVIDED TOTAL CONDUIT SYSTEM INSTALLATION. Clear & 1 12" Min... l Drivable Area Note 2 Note 2 18" Min. 111 ---- Compacted Backfill Compacted Backfill ----1---1~ ~111= Clear & Drivable Area 12" Min..r--1,--- TEP Primary & Secondary Conduit TEP Primary & -+---,,. Secondary Conduit N,..., TEP Only Note 2 *18" Min. 6 11 Min. TEP with Other Utilities Com acted Backfill *Service Trench with Other Utilities Service Trench with Communication cable TEP Service Conduit NOTES: 1. See SR-27 for bedding and backfill requirements. liiti E e Q) Note 6... 'O. ro C L. - (!) ::E - = :g \ M U. Secondary and/ or Service Trench NOTE: TEP designs exclusively with a customer provided and installed total conduit system. 2. Where possible, the trench spoil shall be placed to the opposite side of the access to the trench. Adequate protection shall be provided to protect employees from loose rock or soil that could pose a hazard by falling or rolling into the excavation. Protection can be provided by placing and keeping such materials at least 2 feet from the edge of the excavation, or by other means that provide equivalent protection. This 2 ft. area shall be level and free of debris to permit safe footing during inspection. 3. On-site inspections by TEP are required for open trench, bedding, and shading. Call 918-83 to schedule inspections. 4. A 2 ft. x 5 ft. bell hole must be provided when modifying an existing CIC installation. Bell holes for service trenches must comply with the requirements of SR-312 and SR-21 where applicable. 5. The minimum horizontal radius in a trench prepared for installation of wave rib conduit system shall be 4 ft., and 12'.6" on a schedule 4 PVC continuous conduit system. 6. Service trenches for the continuous conduit system must be 36 inches in depth. 7. Under no circumstances is a trench to be dug closer than 3 ft. to a down guy anchor rod. 8. See SR-21 for sleeve installation where a trench can not remain open. 9. The service conduit shall be installed into the equipment sites at the same time when the primary and/or secondary conduits are installed. All conduits are to be tied up per the equipment detail, and prior to calling for the trench and conduit inspection. 1. Do Not trench under TEP/UES underground equipment without the presence of an Access Crew. For conduit installation into existing underground equipment, contact Access at 918-83 (761-7952 UES) to assist with the conduit....-..._ INITIATED BY DS REVISION NO. 17 UniSouroeEnergy 1------+------1 EsR comm. 1-11 SERVIES i-------------1...-------1 SMTACRUZCDUNTY ESR COMM. 6-78 EFFECTIVE DATE 1-17 Pg. 1 of 9

TRENCHING, URD EQUIPMENT PLACEMENT Transformer Pad~ (42"x42") CATV Pedestal Street Side I... I TELCO Pedestal J _ ---Jt_Placement Trench OFFSET EASEMENT - TRANSFORMER PAD 5'-" With 6'-" strip easement, 4'-" x 1'-" additional easement required Transformer Pad ~ (42"x42") I... - C Q) ~E Q) = :a 9w ~ Street Side ~ STRIP EASEMENT - TRANSFORMER PAD *For 6'-" strip easement only -'l.-----'--...--._ INITIATED BY SC REVISION NO. 15 UniS roeenergy a--------+-----11--------+------1 SERVl:ES 1--ES_R_C_O_M_M_. +-_8_-o_&... SMTACRUZCOUNTY ESR COMM. 5-78 EFFECTIVE DATE 8-6 Pg. 2 of 9

TRENCHING, URD EQUIPMENT PLACEMENT Pedestal D..(36"x36") Easement Line -+-, /(1'-" X 1'-")... s -~.. r Street Side Trench OFFSET EASEMENT - PEDESTAL Pedestal D.. (36"x36") :;::,...c Q) u ~ C ~ l Easement Line : I.J--1.--------------------~~~~ 1 3" TELCO Pedestal ------ Trench J \_ JTax. 'l: Street Side STRIP EASEMENT - PEDESTAL * For 6'-" strip easement only I... - C Q) :: E Q) = l8 9w \ UniSouroeEnergy......-..._ REVISION NO. 13 I_N_IT_IA_TE_o_s_v_-+-_s_c----1... +-------1 SERVIES ESR COMM. 8-6 SMTACRUZCDUNTY ESR COMM. 5-78 EFFECTIVE DATE 8-6 Pg. 3 of 9

TRENCHING URD EQUIPMENT PLACEMENT Sec. Junction Box [QI (28"x41") 5'-" > Easement Line (1'-" X 1'-")... 3"Min. r I 14" I TELCO Pedestal 1 -,+-~-rt,i-fb-f--i:=114... 1--_ Center Of Conduit Tie Up L -- 'l.- Trench OFFSET EASEMENT OPTIONAL SECONDARY JUNCTION BOX 5'-" (typ With 6'-" strip easement, 4'-" x 1'-" additional easement required Sec. Junction Box [QI (28"x41") lo~ 1-' v.... ~ L -- ~.~ co.~ -r Center (V') E """ E t Conduit TELCO Pedestal Of Tie Up a I... - C Q) ~E Q) = :a 9w ~ ----- Trench Mllax.:_'l: --~ Street Side STRIP EASEMENT OPTIONAL SECONDARY JUNCTION BOX * For 6'-" strip easement only,...-..._ REVISION NO. 13 UniSouroaEnargy... I_NI_n_AT_E_D _Bv_---+-_sc----11-------+-------1 SERRES ESR COMM. 8-6 SMTACRUZCOUNTY ESR COMM. 5-78 EFFECTIVE DATE 8-6 Pg. 4 of 9

TRENCHING,URD EQUIPMENT PLACEMENT = C: N -.:t ~ Trench OFFSET EASEMENT J - 1 CABINET J - 1 Cabinet Iii ( 24"x15" ) 5' (Typ.) With 6'-" strip easement, 4'-" x 1'-" additional reasement required CATV Pedestal = C: "' -.:t~ TELCO Pedestal { -r--~...,j.---li:----fa--::t--,,,,.,... Center Of Cable Tie Up TRENCH *18" Max. STRIP EASEMENT J - 1 CABINET * For 6'-" strip easement only I... - C: a., ~E a., = :8 9w \ ---... INITIATED BY SC REVISION NO. 4 UniSouroeEnergy 1------+---_:--------+-----1 SERVl:ES ESR COMM. 8-6 SUTACRUZCOUNTY ESR COMM. 1-91 EFFECTIVE DATE 8-6 Pg. 5 of 9

CONDUIT PLACEMENT EXISTING SINGLE PHASE STEEL PEDESTAL Profile View Final Grade Install the pull rope for the entire service run.> Refer to SR-218 for all service stubs Duct Plug 2 1/2" X 36" X goo Schedule 4 / Electrical PVC sweep 42" 2 1/2" x 5'-" Schedule 4 Electrical PVC stub Secondary Connectors Pedestal Stake Pedestal Top View {Stake Pedestal Duct Plug I Final Grade Front View Conduit Schedule 4 Electric PVC 2 1/2 " x 36" x goo and 5'-" stub Front INITIATED BY GC REVISION NO. ESR COMM. ESR COMM. 8-6 EFFECTIVE DATE 17 7-12 8-12 Pg. 6 of 9

CONDUIT PLACEMENT TIE UP PRIMARY /SERVICE URD Service Conduits 2 1/2" / 4" for 1 to 2 lot applications. 42" 4" conduit systems require the installation of Smooth - Cor conduit system. Center of Equipment The customer to provide the tie-up support & ground wire for total conduit installation Pad Mounted Transformer Plan View Schedule 4 PVC 3'-" x goo & a 5'-" straight stick is preferred for the service stub out. The stub out is to be in place for "f(' l ~r~und the primary trench conduit inspection.\ Ground Rod 6"... Above Final Grade. If using Wave-Rib conduit, leave 4 to 5 extra feet to assist with shaping and holding the conduit in place. Trim the conduit after the transformer backfill inspection has passed. If installing conduit into an existing transformer, a schedule 4 2 1/2" x 36" x 9 will be required. Call for an access appointment at 918-83. 111 "!I' Final Grade Service Conduits Note: Ground Rods are Not Permitted to be cut under any circumstance. If soil conditions prohibit driving the ground rod per the SR, contact TEP's design department. Prima Pad Mounted Transformer Front View ---... UniSouroeEnergy 1-I_N_IT_IA_TE_o_s_v_--1,-_M_s----1 SERVl:ES Conduits SIIJACRUZCOlm ESR COMM. 1-88 REVISION NO. ESR comm. 1 3-16 L-.::~::.::.:..:.:..:.:...-----1~;...;;;.;;,...i EFFECTIVE DATE 4-16 Pg. 7 of 9

I I TRENCHING, URD EQUIPMENT PLACEMENT FOR CONDUIT INSTALLATION NOTES: 1. EASEMENT/ EQUIPMENT IDENTIFICATION Customer is to provide property pins and/ or swing ties (stakes) to the center of equipment at the UG equipment (Transformer, Pedestal, J-1, J-1, J-2, etc.) location. These pins/ stakes will be in place for the trench/ conduit inspection and backfill/ mandrel inspection. 2. CONDUIT PLACEMENT / TRANSFORMER PAD SITE PREPARATION A) Pad and trench sites shall be level and at final grade before calling TEP for a trench/ duct inspection. Driven ground rod to be 6 inches above final grade. B) Customer to utilize the approved TEP conduit template (purchased through TEP) during the backfill process to ensure proper conduit and ground rod final grade. Duct plugs are required for all conduits (no duct tape). C) After the conduits (SR-25) and ground rods are in place, the customer is to install a #6 solid soft drawn copper conductor for Telco bonding from the ground rod 2 ft. above the pad (at the ground rod), 12 inches away from the front of the pad and 36 inches to the right of the pad site. Bury the conductor 12 inches below final grade and coil up approximately 2 ft. of conductor. With the template in place, pour concrete on the conduit (see SR-25 & 215, Pg. 1 of 2) if using PVC and call for an inspection. After passing the inspection, backfill and compact (95%), level the equipment site and install the transformer pad. The conduit shall be cut 1 inch above the top of the pad and covered with the appropriate duct plug. See SR-28 for equipment site preparations, including sites with slopes. D) The customer to call for a transformer pad site, pedestal site, and mandrel inspection, upon approval the customer will pour a slurry of concrete (1/2 inch thick) inside the entire opening for rodent protection. 3. PEDESTAL SITES TEP to provide the pedestal. The customer is to excavate and install per page 9. After the conduits (SR-25) are in place, the customer is to install a #6 solid soft drawn copper conductor for Telco bonding from 2 ft. above the sub grade (next to the right side of the conduits), 12 inches away from the front of the pedestal and 24 inches to the right of the equipment site. Bury the conductor 12 inches below final grade and coil up approximately 2 ft. of conductor. 4. J-1 CABINET SITES TEP to provide the subsurface base. The customer is to excavate and install per SR-235. Install ground wire per note 3 on this page. S. J-2 CABINET SITES TEP to provide the subsurface base. The customer is to excavate and install per SR-234. 6. SECONDARY JUNCTION BOX SITES (J-1) - CUSTOMER OPTION (in place of pedestals) The customer to provide and install the 2K rated J-1 box per page 9. Install ground wire per note 3 on this page. A) After the conduit (SR-25) is installed, the customer to provide, install and level an approved TEP secondary junction box (see below) so the top of the box is 1 inch above final grade. Place the lid on the box. B) Approved secondary junction box (17"x3"): Armorcast Products Co. - Cat. No. 6164-AS CDR Systems - Cat. No. PA3-173-18S Christy Concrete Products - Cat. No. FL36BOX18 Electrimold Inc. - Cat. No. ECAA-17318-1 New Basis - Cat. No. FMA17318TN21P212NOOOOO Quazite - PT173BA (Box), PT173CAOO (Cover) TEP will furnish the transformer pads, pedestals, and ground rods to the job site at the customers' request. Please give TEP a 2 week notice and specify a contact name, phone number and the material staging area. It's the customers' responsibility for the care of this material. The customer must sign for the delivered material. Any lost, or damaged material will be the responsibility of the customer to replace with approved TEP material. Note: Ground Rods are Not Permitted to be cut under any circumstance. If soil conditions prohibit driving the ground rod per the SR, contact TEP's design department...._...-..._ INITIATED BY GC REVISION NO. 5 UniS roaenargy 1------+---_:--------+------1 SERVl:ES ESR COMM. 3-16 SMTACRUZCDUNTY ESR COMM. 6-5 EFFECTIVE DATE 4-16 Pg. 8 of 9

CONDUIT PLACEMENT PRIMARY, SECONDARY, & SERVICE Service Conduits - 2.5" (3'-" X goo & a 5'-" straight stick is to be used for all stub outs, refer to SR-218) Secondary Conduits - 2.5" Center of Equipment Ground Rod Secondary Conduits - 2.5" --Ground Wire L.Ground Wire Secondary Pedestal Plan View Strip Easement Pad Mounted Transformer Plan View - Stlip Easement :... j Ground Wire-... Ground Rod C: X - rtl ::E ::E ~= M~ - - - - - ----1:!!!!!::::::_-l- :::::::::::1-===~~:-- 36" x goo PVC Ell or HOPE Pad Mounted Transformer Front View - Strip Easement Secondary Pedestal Front View Strip Easement Ground Wire * Service Conduits - 2.5" ~ 3" Center of Equipment TOP Service Ducts Secondary Junction Box (Customers Option) ~ n View & Front View Transformer Template Note: Ground Rods are Not Permitted to be cut under any circumstance. If soil conditions prohibit driving the ground rod per the SR, contact TEP's design department..._ ~ T...-... GC UniS roeenergy...i_ni_n_at_e_o_sv_--+------1 SERVl:ES SUTICRUZCOUNTY ESR COMM. 6-5 REVISION NO. ESR COMM. EFFECTIVE DATE 4 3-16 4-16 Pg. 9 of 9