Land Rights For Connection Customers

Similar documents
ICP/IDNO Land Rights Guide

Guidance about Land Rights for connections involving Independent Connection Providers (ICP s) and Independent Distribution Network Operators (IDNO s)

Land rights requirements relating to assets to be installed or adopted by SEPD or SHEPD for new connections

Scotland. Wayleaves guide. New Connections Requirement for Land Rights

Land Rights, Wayleaves and Legal guide

Guide to land rights. Click northernpowergrid.com Call Connect

Independent Connection Providers Legal Process and Statutory Consents

SP Energy Networks Fee Scale

FACT SHEET: Tenure requirements for Major Customer Connections

Land Rights, Wayleaves and Legal guide

Residential property matters

HS2 Phase Two - Land & Property - preparation of Hybrid Bill activities privacy notice

Landowner's rights. When the Crown requires your land for a public work. April 2010

Conveyancing. Pricing. wardhadaway.com. Newcastle Leeds Manchester

CROSSRAIL INFORMATION PAPER C10 - LAND DISPOSAL POLICY

North Ayrshire Council

The System of Land Registration and Third Party Rights

Leases of land and/or buildings to sailing clubs generally fall within the provisions of Part II of the Landlord and Tenant Act 1954.

Your property and compulsory purchase

Equity Release Mortgages (please contact us for a bespoke quote

Our fees for residential conveyancing

Arbon House, 6 Tournament Court, Edgehill Drive, Warwick CV34 6LG T F

GUIDANCE FOR LANDOWNERS AND OCCUPIERS ON CONTRIBUTIONS TOWARDS PROFESSIONAL COSTS

RESIDENTIAL CONVEYANCING. Pricing Information

Your property and compulsory purchase

Tozers guide to selling your home

NFU Consultation Response

Empty Properties Enforcement Protocol

Heathrow Expansion. Land Acquisition and Compensation Policies. Interim Property Hardship Scheme. Policy Terms

Right to Buy Procedure

Standard for the acquisition of land under the Public Works Act 1981 LINZS15005

Historic Environment Scotland Àrainneachd Eachdraidheil Alba

Your property and compulsory purchase

Compulsory Land Acquisition Delegations

Leasehold home ownership: buying your freehold or extending your lease. Law Commission Consultation Paper

INVESTMENT IN COMMERCIAL PROPERTY

IMPORTANT THIS COMMUNICATION AFFECTS YOUR PROPERTY REQUEST FOR INFORMATION

PURCHASE OF FREEHOLD OR LEASEHOLD RESIDENTIAL PROPERTY

Lease Extension Interested in extending your lease? We hope you find this guide useful in informing you of your options and how to go about it.

LC 3: Control of Property Transactions

ENFORCEMENT OF POSSESSION ORDERS

academy conversion land guidance

Assignee Pack. A guide to the assignment process and supporting information

Selling residential property in England and Wales: the basics

Facilities Services Notification FSN 11/08

HOUSING REGENERATION LAND ACQUISITION STRATEGY. Strategy for the acquisition of land for estates undergoing redevelopment

Small Self Administered Scheme. Property Notes

Minister s Function under the Public Works Act 1981

Easements, Covenants and Profits à Prendre Executive Summary

ASSET TRANSFER REQUESTS Community Empowerment (Scotland) Act 2015 Guidance Notes

PLANNING & BUILDING REGULATIONS

Protocol for the Acquisition and Disposal of Property

Property Purchase Questionnaire. Barnett Waddingham Self Invested Personal Pensions

NHSScotland Property Transactions Handbook

Making the Most from your Premises. Gordon Ludlow Ethical Property Foundation

EQ Solicitors: Pricing Information

Guide to buying property in. england and Wales

Buying a residential property in. England and Wales

5 TRANSFER OF PROPERTY RIGHTS TO TTC TORONTO YORK SPADINA SUBWAY EXTENSION, PROJECT 90996

SRA Transparency Rules

Propertymark Qualifications: Level 2 Award in Introduction to Residential Property Management Practice (England & Wales) Qualification Specification

SIPP property questionnaire

PURPOSE FOR WHICH TO BE USED

PROPERTY INVESTMENT NOTES

Native Title Explained

From: Gerard Reiter, EGM/Asset Management Date: 14 April 2015 Peter McIntyre, Managing Director

Property Purchase Guide

RESERVE REVOCATION FOR HUNDERTWASSER PROJECT Ruben Wylie - Manager - Infrastructure Planning

Date: 9 February East Walworth. Deputy Chief Executive

NEW USES FOR CLOSED CHURCH BUILDINGS Guidance from the Church Commissioners for purchasers and lessees

propertymark QUALIFICATIONS LEVEL 3 AWARD IN COMMERCIAL PROPERTY AGENCY (ENGLAND, WALES AND NORTHERN IRELAND) QUALIFICATION SPECIFICATION

C4: LAND ACQUISITION AND DISPOSAL

Date: July All Wards Affected

A Guide to Lease Extensions for the Barbican Estate

Guidance Sheet : Tenancy Deposit Protection in Scotland Information for Landlords, Tenants and Letting Agents

Commonhold: A Call for Evidence Summary

Government Consultation in Tackling Unfair Practices in Leasehold. Response from Association of Retirement Housing Managers (ARHM)

Re: Social Housing Reform Programme, Draft Tenant Participation Strategy

Plain English guide to your lease

1 Retained. 2 Formal Let. 3 Sold/gifted

THE PROCESS OF CONVEYANCING (The Business of Buying and Selling)

Property Notes. Self Invested Personal Pension

1.1 Explain the nature and the characteristics of a lease

Property administration overview and risk warning notice

Guide to buying property in. england and Wales

Land Acquisition and Property

ILM Conflict of Interest Guidance Tutors, Assessors and Internal Verifiers

Housing White Paper Summary. February 2017

Classification: Public. Heathrow Expansion. Land Acquisition and Compensation Policies. Interim Property Hardship Scheme 1.

propertymark QUALIFICATIONS LEVEL 3 AWARD IN RESIDENTIAL LETTING AND PROPERTY MANAGEMENT (ENGLAND AND WALES) QUALIFICATION SPECIFICATION

Property Guide. Strong partnerships, better results DECEMBER Property Guide Ref: 12/16 Page 1 of 17

Living City Initiative

C6: DISPOSAL OF SURPLUS LAND

Housing and Planning Bill + Welfare Reform and Work Bill

APPENDIX 7. Housing Enforcement Policy V May 2003

Making Land Work: Easements, Covenants and Profits à Prendre Executive Summary

Limited Partnerships - Planning for the Future

Regeneration and Property Committee. 16 March 2017

LETTER TO COMPANY - DRAFT CITY OF LONDON LAW SOCIETY LAND LAW COMMITTEE CERTIFICATE OF TITLE (7 TH EDITION 2016 UPDATE)

Plain English guide to your lease

Transcription:

Land Rights For Connection Customers Background The network of overhead lines, underground cables and substations that are owned, operated and maintained by SP Energy Networks ( SPEN ) affect land owned and occupied by thousands of individuals. We have a statutory obligation to connect new customers to the existing network. Developing such connections may require us to place new apparatus on land owned by others. SPEN requires a legal agreement with the landowner before it can install this apparatus to ensure it can be kept there and access remains available for future operation and maintenance. Purpose The purpose of this guide is to explain to customers in what situations land rights may be required as part of your connection, what types of land rights may be required, how long these may take to obtain and who is responsible at the various stages throughout the process. This guide is applicable to connections where we are providing full works. This is where we will complete all of the works in relation to your connection. What are Land Rights? The term land rights is used as a collective term to cover the acquisition of property rights, such as freehold and leasehold interests a lease or purchase or servitudes, easements or wayleaves, that SPEN will require to be in place before we can make a connection for you to our network. In order to ensure the works are undertaken in a lawful manner we may also require statutory planning consents such as a section 37 consent to install an overhead line or a planning consents to construct a substation. Other environmental consents, licences or permits may also be required for work in or around certain sensitive ecological habitats or species, water bodies or cultural heritage sites, some of which may have significant statutory protection. What Land Rights may be required for your connection? We endorse the view that land right requirements for the electrical assets associated with providing your connection, whether obtained by us or through other parties on our behalf, shall be no more onerous than for activities associated with the construction, replacement, renewal, refurbishment, operation and maintenance of our distribution network. Depending upon the location of the existing network and the development seeking connection, we may need to place apparatus on under or across the development site or third party land. We will need legal agreements to do this. The legal agreements required will depend upon the specific requirements of the connection, the apparatus to be installed, the individual circumstances surrounding land ownership and whether the connection may benefit others. Appropriate land rights must be secured with relevant landowner and any associated 3 rd parties for all apparatus including cables overhead lines and substations.

The key principle underpinning SPENS approach to securing land rights is a presumption that a secure right will be sought in the first instance. Such an approach ensures that SPEN can maintain an efficient, co-ordinated and economical system of electricity distribution as required to meet our statutory licence conditions. However, on occasion we recognise that we may require to depart from this presumption in order to secure the most appropriate rights in the circumstance. In certain circumstances we may accept a wayleave as an alternative, but this will be determined on a case by case basis. There are two broad categories of land rights; Wayleaves / Servitudes / Easements (for overhead lines and cables) and Purchase / lease agreements (for substations or other non-linear apparatus) Land Rights for Overhead Lines or Underground Cables Wayleave Agreement A wayleave is a simple form of a personal agreement between us and the landowner that can be used to gain consent for overhead line and underground cable apparatus, along with the required access for inspection maintenance and future operation. It can also be used to secure agreement with an occupier of land who is not also the owner. Wayleaves are not registered against the affected land. Commonly, wayleave agreements usually provide for an annual or one-off payment to be made by us. Payment rates are normally reviewed annually and are based upon the type and size of the structure and the classification of the land. Servitude / Easement A servitude/easement provides us with greater security for our apparatus. A servitude or easement is executed as a Deed. This means that it is registered against the affected property at HM Land Registry and is usually permanently affixed to the land. A servitude or easement for overhead line and underground cable apparatus forms a contract between us and the landowner and will include the required access for inspection maintenance and future operation. Servitudes or easements are processed through solicitors and this reflects the greater security of tenure afforded to us when compared with a wayleave Agreement. Land Rights for Substations and Fixed Site Assets We require the transfer of the freehold or alternatively the grant of long leasehold of any substation site that forms part of the works required to provide your connection. Freehold Transfer Where a substation is required for a connection, such as in the case of housing developments, we would prefer to acquire the freehold interest in the land where the substation is to be built. This means that the land for the installation would be owned by us and we would require Title to be registered at HM Land Registry. The transfer would also include associated rights of access to the land and appropriate land rights for connections such as underground cables.

Lease In some situations where a substation is required in respect of a connection to our network such as for commercial or industrial developments, we may be prepared to secure the substation site by a lease. This is where a landowner allows us the right to occupy their land or building over a period of time (duration determined as appropriate). The lease will include rights for us to access the substation building 24 hours a day, every day, together with rights for underground cables or associated apparatus. A lease is a legal document that we would wish to register with HM Land Registry. What if a voluntary agreement cannot be reached? In some cases a voluntary agreement will not be reached and we may require to rely on our statutory powers to compulsorily secure the relevant land rights. In such circumstances where agreement cannot be reached and no alternative design solution exists. Prior to entering into the use of statutory powers, the circunstances and how to proceed should be reviewed by the SPEN Project Manager, Land Offer and the customer. The costs relating to the use of statutory powers will be in addition to your connection costs Compulsory Purchase We can acquire ownership of, rights in, and rights to, land by way of the compulsory acquisition process set down under schedule 3 of the Electricity At 1989 (as amended). A start to finish compulsory acquisition can take between 9 months to 3 years. As such, the process is only effective in projects where there are sufficiently defined timescales. Furthermore, a compulsory purchase order can only be proposed where there is a sufficient needs case justification for doing so. Necessary Wayleave We can acquire a necessary wayleave for overhead line and cable apparatus under Schedule 4 of the Electricity Act. A necessary wayleave offers more protection than a voluntary wayleave in that it binds the land covered by the necessary wayleave for a stated term and does not fall as a result of a change of owner. The process can take between 6-12 months. What other consents may be required? As well as land rights, other consents may be required as part of your connection. These may relate to: Statutory planning consents for the construction of an overhead line or substation. Other environmental consents, licences or permits which may be required for: o Work in or around water bodies; o Work in or around certain sensitive ecological habitats or species, some of which may have significant statutory protection.

o o Work in or around buildings and sites of historic importance In cases where such sensitives sites are encountered these may trigger the need for particular environmental evaluation or the need for full Environmental Impact Assessment (EIA). The requirement for such consents is obviously dependent on the development type and its location and as such requires to be considered on a case by case basis. Different types of consents will have different programme implications. These consents will require various levels of engagement with statutory authorities and interested parties. Section 37 Consent The Electricity Act contains certain provisions for planning relating to the construction or alteration of overhead lines. Consent relating to 33kV overhead lines and below are required under section 37 of the Act. Section 37 consent is granted by the Scottish Ministers in Scotland and the Secretary of State in England and Wales. Whilst applications are made to The Scottish Government / DECC, these consents requires consultation with the relevant local authorities and other statutory bodies. The Secretary of State Scottish Ministers may take in to account the number of land rights that have been granted prior to the granting of the section 37 consent. The Land Officer appointed to your connection will keep you fully informed as to any consent that may be required to construct the connection. Planning Consent by a customer If a substation is required as part of the customer s connection arrangements, typically for development such as housing or commercial, we expect you to obtain planning permission for the new substation. Before a lease or transfer for a new substation site can be concluded, you must provide evidence to our solicitor that planning permission has been obtained for the new substation. How long will it take to obtain the land rights & other consent? The time to achieve land rights and other necessary consents will depend upon the individual circumstances and the ability to reach agreements with the various parties involved. Timescales for successful negotiations vary greatly but we will try to complete these as efficiently as possible to meet overall project timescales. Any statutory or environmental consent needed will be, where possible, progressed in parallel to the land rights. The timescales for these are in the main out with our control and will also depend on the specifics of the works and the third parties we will have to engage with. Based on our past experiences and the functional processes of both obtaining land rights and statutory consents we have developed a range of indicative lead times. These lead times factor in

such elements as set out above and are primarily dependant on the type of land right being sought e.g. wayleaves or servitudes/easements and what, if any, statutory or other consents are required. Other factors may include where a third party land right is required from an organisation such as local authority or rail operator, where they may have set processes and timescales to deal with such matters. A simple underground connection on your land, for which we seek a wayleave, may take approximately 5 weeks form the point of the Land Team having all the necessary information. Where you do not own the land this may take as long as 7 weeks, extending to 10 weeks where land is owned by an infrastructure operator or local authority. Where permission is required from third party landowners including an infrastructure owner or local authority and perhaps a licence or permit is required in relation to an environmental site, then the land rights and associated consents may take between approximately 18 and 22 weeks. Where an overhead line is required which is less than 33 kv but involves 3 party land owners and requires a section 37 consent involving a licences or permit related to the environment this may take up to 20 weeks. Where a more complex connection requires an overhead line of a significant length and involves a variety of 3 party landowners and requires section 37 consents with sensitive environmental aspects it may take up to 50 weeks for the consents to be granted. The Project Manger appointed to your connection will keep you fully informed as to the progress towards gaining these consents. Who to contact Should you require further information in relation to your connection please click the link below http://www.spenergynetworks.co.uk/pages/connections_contact_us.asp

Who is involved? Customer Where you are also the landowner see below. As part of the connection agreement, request that land rights are to be progressed to enable your connection. Where you are responsible for gaining land rights, ensure you do so as early as possible. Discuss and agree with SPEN what land rights you will obtain. Ensure you keep the Land Officer informed of your progress in gaining consents. If a substation is required as part of your connection arrangements, obtain planning permission for the new substation. You must provide evidence to our solicitor that planning permission has been obtained for the new substation before a lease or transfer can be concluded. SPEN Design & Responsible for the design of the connection Planning Team Responsible for liaison with SPEN Project Manager and Land Officer on any elements of redesign which may be required to achieve a voluntary land right SPEN Project Initiates request to SPEN Land Team Manager Advise customer who the Land Officer will be, the process that will be followed and provide an indicative timescale for the delivery of land rights and other consents Customer s first point of contact in relation to the development. Provide you with regular updates on progress of the connection including land rights Work alongside the Land Officer to ensure appropriate land rights are being obtained Provides technical delivery advice around any land rights activities Liaise with customer on any required changes to design to facilitate a voluntary land right or the need for SPEN to rely upon its statutory powers SPEN Land Officer Establish what types of land rights and other consents are required in consultation with Project Manager Discuss with the customer and agree what land rights you will obtain Progress appropriate land rights, identifying what if any, third party landowners may be affected by the development. Make contact with landowners/occupiers and other interested parties Agrees terms with landowners/occupiers Prepares wayleave documentation and issue to relevant landowners/occupiers Instruct and liaise SPEN Legal Services on servitudes/easements/ lease/purchase Responsible for consultation with statutory consulteees / interested parties to obtain section 37 or planning consent / licences /permits Liaise with customer on land rights matters where required Landowner Grant appropriate consents to SPEN. Where appropriate instruct solicitor as early as possible to work with SPEN to progress agreements. Provide evidence of title. Ensure you tell us of any restrictions in your title or any special agreements that may be in place on the land concerned. Tell us of any changes to ownership which may affect the agreement as soon as possible SPEN Legal Provide advice and support on legal matters to the SPEN team. Services Instruct and liaise with SPEN external solicitors as appropriate Progress servitudes/easements / lease or purchase of sites

Land Rights Process Once your connection agreement goes live, it will trigger the requirements for SPEN to progress the appropriate land rights. An instruction will then be sent to the Land & Planning Team which will be logged on the system allowing a Land Officer to be assigned and a lead time set. The lead time is the approximate time it will take to obtain the necessary land rights and any other consents required for your connection. The SPEN Project Manager will be your key point of contact and will provide updates on the progress of your connection. The Land Officer will progress any required statutory or other consents in parallel with obtaining the necessary land rights. On more complex connections the Land Officer who is dealing with your connection may wish to meet with you at the outset to discuss the land rights process and establish where you can assist with consenting on land you control. The Land Officer will establish the various landowners involved in the connection and discuss the requirements to obtain consent. It is hoped that terms can be agreed to enable SPEN to gain the appropriate land rights. Where a land right cannot be obtained the Land Officer will discuss with the Project Manager to consider whether any alternatives are available. The Project Manger may also discuss these options with you. Where no alternative exists the Land Officer and Project Manager in consultation with you will discuss the possible use of statutory powers. Where the Land Officer has agreed that a servitudes/easements / lease or purchase will be sought, the Land Officer will instruct SPEN legal Team to obtain the agreement(s) Where the Land Officer has agreed a wayleave with the landowner, the Land Officer will send the Landowner the wayleave documentation to be signed and returned On receipt of the completed land rights documentation and any other consents the Land Officer will release the job to the delivery team. The Project Manager will programme the works to begin and liaise with you to what happens