Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Santos Municipality (P104995) Operation Name: Santos Municipality (P104995) Project Stage: Implementation Seq.No: 3 Status: ARCHIVED Last Modified : 31-Jan-2011 Country: Brazil Approval FY: 2010 Product Line: IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Adaptable Program Loan Implementing Agency(ies): Municipality of Santos Key s Board Approval 24-Nov-2009 Original Closing Planned Mid Term Review 30-Oct-2012 Last Archived ISR 03-May-2010 Effectiveness 19-Apr-2010 Revised Closing Actual Mid Term Review Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of the project is to enhance the management capacity of the Santos Municipal Government for local economic development and to improve public services in the Northwest Zone of the Municipality of Santos. The key indicators of the project include: (i) initiation of a plan to address constraints to local economic development by 2011; (ii) provision of urban services to households in slum areas; and (iii) rehabilitation and improvement of the existing macro-drainage system in the Northwest Zone with sufficient capacity to handle 25-year flood levels. Has the Project Development Objective been changed since Board Approval of the Project? losure Authorized Public Disclosure Authorized Yes No Component(s) Component Name Component Cost Municipal Management Enhancement 7.00 Revitalization of the Northwest Zone of Santos and Adjacent Hillside 78.50 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Implementation Status Overview Since effectiveness on April 19, 2010, the project is evolving well. Main terms of reference have been prepared. Some key consultancy services are being selected. The team is in Page 1 of 7
place and trained. Counterpart financed activities are advancing well to assist on the resettlement of inhabitants to improve the livelihood of people living in the project area. But, it is still too early to report on progress toward reaching the development objectives. Results Project Development Objective Indicators Commencement of implementation of plan to address constrains to local economic development by 2011; No LED plan LED plan is being prepared. Strategy prepared and discussed with stakeholders and Master Plan adjustments made. At least 2,400 households in slum areas of the Northwest Zone are provided with a comprehensive package of municipal services (including water and sanitation, street paving, drainage, public lightning Slums in Northwest Zone are not provided with regular urban services First 80 families received new 2,400 additional households in housing units with services after Northwest Zone receive urban resettlement to new complex - Vila services Pele II Establishment of a macro-drainage system that will solve flooding problem in the Northwest Zone and that has sufficient capacity tohandle 25-year flood levels. 2 years flood Selection process to develop detailed engineering designs is under way. 31-Jan-2011 25 years flood Page 2 of 7
Intermediate Results Indicators Preparation of a regional economic development study No regional economic development study Study is being prepared Regional economic development study completed Preparation of a modern land use plan based on best practices for cityport integration No land use plan for city-port integration exists Consultancy selection is being finalized. 31-Jan-2011 Land use plan for city-port integration completed Design and installation of Infovia network in the Northwest Zone No Invfovia network in Northwest Zone Consultancy selection is under way. Infovia network installed in Northwest Zone Preparation of plan to improve macro-processing routines for land cadastre No plan to improve macroprocessing routines for land cadastre exists A proposal by the client to develop this plan will be presented next mission. Plan to improve macro-processing routines for land cadastre completed Page 3 of 7
At least 2, 400 additional households receiving 24-hour water supply services Custom Indicator Number 8 Resettlement of first 80 families to new housing with services completed for Vila Pele II. 240 Increased satisfaction of resettled population with municipal service delivery 01-Jan-2008 Baseline survey needs to be prepared 50% reduction in percent of Santos families living in flood-prone areas Custom Indicator Number Information will be updated next ISR 50% reduction in percent of land area affected by recurrent flooding Custom Indicator Percentage Works have not commenced yet Page 4 of 7
At least 2, 400 additional households with sewage connections Custom Indicator Percentage 8 Resettlement of first 80 families to new housing with services completed 240 Length of Fiber Optic Network Built (km) Core Indicator Kilometers 15-Dec-2009 Northwest Zone Consultancy services is being selected. Number of people in urban areas provided with access to Improved Water Sources under the project Core Indicator Number 8 240 Number of people in urban areas provided with access to Improved Sanitation under the project Core Indicator Number 8 Additional households 240 Additional households Page 5 of 7
Floodgates completely repaired and operating effectively Data on Financial Performance (as of 16-Jun-2010) Financial Agreement(s) Key s Floodgates not operating effectively Works have not commenced yet Floodgates repaired and operating effectively Project Loan No. Status Approval Signing Effectiveness Closing P104995 IBRD-78070 Effective 24-Nov-2009 08-Feb-2010 19-Apr-2010 Disbursements (in Millions) Project Loan No. Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P104995 IBRD-78070 Effective USD 44.00 44.00 0.11 43.89 Disbursement Graph Page 6 of 7
Key Decisions Regarding Implementation It is still too early to report on progress toward reaching the development objectives. The Project is on track. Restructuring History There has been no restructuring to date. Related Projects There are no related projects. Page 7 of 7