FACT SHEET: Tenure requirements for Major Customer Connections

Similar documents
Native Title Explained

Land Rights For Connection Customers

Deed of Agreement for Lease [in relation to Connection Contract Contestable ASP/1 Connection]

Deed of Agreement for Easement [in relation to Connection Contract Contestable ASP/1 Connection]

From: Gerard Reiter, EGM/Asset Management Date: 14 April 2015 Peter McIntyre, Managing Director

Land rights requirements relating to assets to be installed or adopted by SEPD or SHEPD for new connections

Subdivisions and Permit Conditions for Electricity Supplies. A guide to our requirements

Policy: Distribution Subdivision

Guide to Private Water Schemes

ICP/IDNO Land Rights Guide

Guidance about Land Rights for connections involving Independent Connection Providers (ICP s) and Independent Distribution Network Operators (IDNO s)

15 July Ms E Young Team Leader Protected Area Establishment Department of Environment and Natural Resources Adelaide

Guideline: Distribution Pole to Pillar

Cape Environmental Assessment Practitioners (Pty) Ltd

NSW Travelling Stock Reserves Review Public consultation paper

Management of Easement Co-Use Requests Guideline

F R E QUENTLY AS K E D QUESTIONS

SP Energy Networks Fee Scale

Termination (if material defect). Compensation (if material or immaterial defect and buyer gives notice prior to settling).

Copyright and Disclaimer

Pastoral Land Management

REQUEST FOR PROPOSALS FOR SUBSTATION ENGINEERING SERVICES REBUILD OF TYGH VALLEY AND NEW CONSTRUCTION OF EASTSIDE SUBSTATIONS

Land Rights, Wayleaves and Legal guide

3RD PARTY ENQUIRIES TECHNICAL QUESTION GUIDANCE NOTE

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15, (Schedule B);

Update: Directions 2031 and Beyond

Treaty Claims Settlement Acts General Guideline

GUIDANCE FOR LANDOWNERS AND OCCUPIERS ON CONTRIBUTIONS TOWARDS PROFESSIONAL COSTS

Build Over Easement Guidelines

Definitions Expressions highlighted in bold italic type have the same meaning as in the RPI Act or in regulations made under the RPI Act.

WA introduces amending legislation to make significant stamp duty changes

Scotland. Wayleaves guide. New Connections Requirement for Land Rights

What can I do in PEXA? Date: 15 December 2015 Version 1.3

Independent Connection Providers Legal Process and Statutory Consents

Standard for the acquisition of land under the Public Works Act 1981 LINZS15005

CROSSRAIL INFORMATION PAPER C10 - LAND DISPOSAL POLICY

Sharon Harwood. Statutory Land Use Plans and Economic Development Cape York Indigenous Communities

Guide to land rights. Click northernpowergrid.com Call Connect

Real Property Assets Policy and Procedures

Cape York Land Council Aboriginal Corporation ICN 1163 ABN

Guidelines for environmental assessment and consultation procedures for designating land for community infrastructure

Application for Outline Plan / Outline Plan Waiver Section 176A, Resource Management Act

Gisborne District Council

Secure Tenure for Home Ownership on Native Title Lands

The Ironwood proclamation includes the same language and similar language is provided in the Military Lands Withdrawal Act of 1999, which states:

TS 102 EASEMENT STANDARD

CHAPTER IV. ELECTRIC

Introduction. Reshaping the management of property rights, restrictions and responsibilities. Property ownership is well managed

Land Rights, Wayleaves and Legal guide

RESOURCE ACTIVITIES ON AGRICULTURAL LAND

DEVELOPMENT OPPORTUNITY LAND EAST OF NEW ROAD MELBOURN, CAMBRIDGESHIRE, SG8 6BX

South African Council for Town and Regional Planners

Working with Native Title:

Neds Corner Station. What is a Conservation Covenant?

PROPERTY REPORT 1-14/18 Duke Street, St Kilda

BUSI 330 Suggested Answers to Review and Discussion Questions: Lesson 1

DRAFT PROPOSED CHAPTER 21 SPECIFIC PURPOSE - FLAT LAND RECOVERY ZONE

Biodiversity Planning Policy and Guidelines for (LEP) Rezoning Proposals

Secure Tenure for Home Ownership on Native Title Lands

DON T WORRY, WE RE COVERED OUR BACKGROUND INTEGRATED MANAGEMENT SYSTEMS WE WILL LOOK AFTER YOU PROFESSIONAL MEMBERSHIPS

Titles Registry Fees effective 1 July 2017 Land Title Act 1994 Land Title Regulation 2015

Titles Registry Fees effective 1 July 2016 Land Title Act 1994 Land Title Regulation 2015

POLICY & PROCEDURE FOR THE TAKING IN CHARGE OF RESIDENTIAL DEVELOPMENTS

CURRENT THROUGH PL , APPROVED 11/11/2009

5 TRANSFER OF PROPERTY RIGHTS TO TTC TORONTO YORK SPADINA SUBWAY EXTENSION, PROJECT 90996

Community Occupancy Guidelines

Department of Natural Resources and Mines Land Title Practice Manual (Queensland)

Contract for the sale and pu1rchase of water entitlement Edition

This decision is made under sections 130( 1 ) and 133 of the Environment Protection and Biodiversity Conservation Act 1999.

Buying a residential property in. England and Wales

Report April 2001 File: CFO/22/1/1. Review of the Public Works Act Background. 3. Proposed Action

Te Atiawa Claims Settlement Act 2016 registration guideline

Minister s Function under the Public Works Act 1981

IMPORTANT THIS COMMUNICATION AFFECTS YOUR PROPERTY REQUEST FOR INFORMATION

Scheme of Service. for. Housing Officers

Small Self Administered Scheme. Property Notes

Second Land and Real Estate Registration Project. between KYRGYZ REPUBLIC. and INTERNATIONAL DEVELOPMENT ASSOCIATION

Landuse Consent Subdivision Consent Certificate of Compliance Variation/Cancellation of Consent Conditions Outline Plan Waiver

Property Notes. Self Invested Personal Pension

Consulted With Individual/Body Date Head of Finance Financial

ACTIVITIES ON AN EASEMENT POWERLINK QUEENSLAND

STANDARD DEVELOPER WORKS ENTRY ONTO THIRD PARTY PROPERTY SEPTEMBER 2016 VERSION: 1.0

Terms and Conditions of Disposal

Note: these sessions provide an overview of information and should not be used in lieu of legal and other professional advice.

Property Interest Report

Contract for the sale of land 2005 edition MEANING OF TERM. Vendor s agent. Vendor s Solicitor Fax. Folio Identifier

Module 2. Chesapeake Bay Trust Watershed Restoration Project Management Training. Owners & Stakeholders Jim Morris, P.E.

Mineral Resources Regulation 2003

Recommendation to Approve Dominion Virginia Power s Request for an Easement along Route 606 at Washington Dulles International Airport.

BUSINESS PLAN Part 1

MEMORANDUM THE RIGHTS OF LAND OWNERS IN RELATION TO THOSE OF HOLDERS OF RIGHTS IN TERMS OF THE MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT

PUBLIC RIGHTS OF WAY. Guidance for Planners and Developers

Resettlement Policy Framework

CONDOMINIUM PROPERTY REGULATION

Property Purchase Questionnaire. Barnett Waddingham Self Invested Personal Pensions

Minerals and Mining (Compensation And Resettlement) Regulations, 2012 (L.I. 2175)

MEMORANDUM OF UNDERSTANDING. between XXXX. And. The XXXX People

Vendor's Statement KAVANT NOMINEES PTY LTD (ACN ) Property: Lot Mallacoota Drive/Daylesford Crescent/Frome Avenue, Kialla

CHAPTER 7 Property Companies. This chapter defines and sets out the Listing Rules for Property Companies.

EDO-NQ FACTSHEET SERIES

Transcription:

FACT SHEET: for Major Customer Connections Purpose February 2014 Version 1.0 This fact sheet describes the types of underlying land tenure required by Ergon Energy in situations where a Major Customer intends to, as part of a Major Customer connection, construct certain electricity infrastructure and transfer this infrastructure to Ergon Energy upon completion of such infrastructure. This fact sheet should be read in conjunction with Ergon Energy s Major Customer Connection Manual. Glossary Electricity Easement An Electricity Easement is an easement (that is, a bundle of rights) that allows an entity (such as Ergon Energy) to carry out certain activities over a specific section of land (defined through surveys) owned by a landholder, where the beneficiary of the easement is a public utility provider in accordance with the Land Act or Land Title Act and there are no benefited lots (thus rendering the easement a public utility easement. These activities may include the construction, operation and maintenance of the electricity infrastructure within the easement corridor and the clearing of vegetation. As easements are registered on the land title, a separate easement is required for each parcel of land on which the electricity infrastructure is to be located. The relevant landholder retains its ownership of the land, subject to the grant of the easement rights. Easements can be granted over various types of land ownerships and tenures. Transferable Connection Assets General Refers to the electricity infrastructure that is to be constructed by the Major Customer and gifted to Ergon Energy upon completion of the works. Various forms of tenure can apply to the acquisition of rights in land for constructing, operating and maintaining electrical infrastructure, such as: easements (which can be used in conjunction with a variety of existing tenure rights); licence agreements or wayleave agreements; agreements relating to non-freehold land under various legislation (such as the Land Act 1994 (Qld) and Nature Conservation Act 1992 (Qld)), which land can include, among other things, State Forests, National Parks, Unallocated State Land, Road Reserves (either local government or Main Roads) and railway land; and freehold land. page 1

FACT SHEET: Two Sets of Tenure Required As part of the negotiations in respect of the Construction Contract, the Major Customer will have to agree with Ergon Energy upon the location and route of the Transferable Connection Assets (this process will normally take into consideration design, native title, cultural heritage, planning and environmental factors). Therefore, early provision by the Major Customer of relevant information is essential. During this process, Ergon Energy will also advise the Major Customer of what type of tenure it requires in respect of its ownership of the Transferable Connection Assets and the specifications for such tenure. Once the location and type of tenure required by Ergon Energy is confirmed, the Major Customer will need to obtain, or procure, two sets of tenure, namely: sufficient tenure in the Major Customer s name to permit the Major Customer to access the land for construction purposes and to carry out the construction of the Transferable Connection Assets; and the desired tenure for Ergon Energy to operate and maintain the Transferable Connection Assets in the long term. The Major Customer is then responsible for liaising with the relevant landholders to obtain the tenure permitting it to access the land and carry out the works, and to either obtain, or facilitate the grant to Ergon Energy of, the desired tenure in respect of Ergon Energy s ownership of the Transferable Connection Assets. The Major Customer is also responsible for obtaining or entering into, as relevant, all other authorisations or agreements that are required to carry out the relevant works (such as in relation to planning, the environment, cultural heritage, native title, vegetation and so forth). Some of these authorisations may need to be transferred to Ergon Energy (at the Major Customer s cost) with the transfer of the relevant assets (where the authorisation is not automatically transferred with the transfer of the asset or relevant tenure rights). Failure of either party to obtain any necessary authorisation or tenure rights may adversely impact upon the progression of the project. Note that Ergon Energy does not usually exercise its compulsory acquisition rights under the Electricity Act 1994 (Qld) and the Acquisition of Land Act 1967 (Qld) unless there is no other appropriate avenue available, and will not exercise those rights in respect of Transferable Connection Assets. Indicative Requirements for Tenure Type Ergon Energy considers a number of factors when determining its preferred tenure in respect of the Transferable Connection Assets. These factors include items such as: technical parameters, such as line length, route and technical limitations; relevant environmental, cultural heritage or native title considerations; risks associated with future development or increased vegetation resulting in potential relocation or escalated maintenance costs; and the ability to negotiate easements, wayleaves and licence agreements with third parties. Normally, Ergon Energy requires: freehold tenure for Transferable Connection Assets such as substations; and a registered easement for Transferable Connection Assets such as distribution lines and their supporting infrastructure (whether overhead or underground), page 2

FACT SHEET: for the period from transfer of the Transferable Connection Assets, each in the name of Ergon Energy. Suitable access rights will also need to be provided to enable Ergon Energy to lawfully access the Transferable Connection Assets once it acquires the ownership in these assets. Due to the long-term nature of Ergon Energy s ownership of the Transferable Connection Assets and the relatively permanent nature of such assets, Ergon Energy considers that tenure such as licence agreements, mining leases and wayleave agreements are inadequate for Ergon Energy s purposes. However, note that the actual tenure required in each situation will depend upon the particular characteristics of the relevant Transferable Connection Assets. Major Customer Responsible The Major Customer is responsible for acquiring all tenure rights required for it to carry out its works and its costs of doing so. The Major Customer will need to obtain its own independent advice in relation to the necessary tenure from experienced and competent advisors holding appropriate insurances. Such advice should take into consideration matters such as, without limitation: the application of the Mineral Resources Act 1989 (Qld) or the Petroleum and Gas (Protection and Safety) Act 2004 (Qld); the Sustainable Planning Act 2009 (Qld), State and regional planning policies, local government planning schemes, any required development applications and approvals; vegetation clearing requirements including under the Vegetation Management Act 1999 (Qld); the requirements of the Nature Conservation Act 2002 (Qld); environmental requirements and offsets, including under the Environmental Protection Act 1994 (Qld) and the Environment Protection and Biodiversity Conservation Act 1999 (Cth), and environmental management plans; native title requirements under the Native Title Act 1993 (Cth) and indigenous land use agreements; and cultural heritage requirements under the Aboriginal Cultural Heritage Act 2003 (Qld), the Torres Strait Islander Cultural Heritage Act 2003 (Qld) and the Queensland Heritage Act 1992 (Qld) and cultural heritage management plans. Other legislation and government departments may be relevant depending upon the geographic location and nature of the works, for example, legislation dealing with marine environments, workplace health and safety, air quality and so forth. Note also that Ergon Energy has certain requirements in respect of vegetation clearing near its assets, which must be complied with before Ergon Energy will accept ownership of any Transferable Connection Assets. Note that under the terms of the Construction Contract, Ergon Energy will need to be satisfied that the tenure acquired by the Major Customer granted the Major Customer appropriate rights to access and to construct the Transferable Connection Assets, otherwise Ergon Energy may refuse to accept the transfer of such assets. As flagged above, the Major Customer is also responsible for procuring all necessary agreements from landholders and interested parties to facilitate the grant to Ergon Energy of the desired tenures. For the purposes of confirming that: the tenure rights obtained by the Major Customer gave the Major Customer appropriate rights in relation to the construction of the Transferable Connection Assets; and the tenures to be granted to Ergon Energy will be on terms acceptable to Ergon Energy, page 3

Ergon Energy will require copies of relevant documentation, such as: FACT SHEET: relevant authorisations and associated terms and conditions; vegetation offset conditions and obligations, and vegetation clearing permits, and weed surveys; cultural heritage assessments and cultural heritage management plans; details of native title future act compliance; any applicable indigenous land use agreements; relevant negotiated agreements; construction environmental management plans setting out how the Major Customer intends to ensure compliance with each of the above during the course of construction; surveys of protected species carried out under the Environment Protection and Biodiversity Conservation Act 1999 (Cth) or the Nature Conservation Act 1992 (Qld) and reporting and spatial data used and collated for environmental assessments (in a format compatible with Ergon Energy s GIS (Smallworld)), including evidence of compliance with any relevant approvals. Additionally, Ergon Energy is likely to require a detailed inspection of the easement corridor and any off-easement access areas to confirm that these are suitable for Ergon Energy s purposes. Importantly, under the terms of the Construction Contract and relevant transfer provisions, Ergon Energy may not accept a transfer of Transferable Connection Assets where this involves the assumption by Ergon Energy of onerous ongoing liabilities or obligations, whether entered into by the Major Customer or not, and increases Ergon Energy s risk exposure beyond acceptable levels of normal operational risk (as determined by Ergon Energy). For these purposes, the Major Customer should submit to Ergon Energy all relevant documentation surrounding the tenures and development and maintenance before Ergon Energy agrees to accept the transfer of the Transferable Connection Assets. Terms of Easements Where Ergon Energy has determined that an easement is the relevant tenure for all or part of the Transferable Connection Assets, Ergon Energy will give the Major Customer information as to the required width of the easement. Easement widths will vary depending on factors such as the receiving environment, line or cable voltage, number of circuits, circuit layout, structure design, structure height, stay designs, span lengths, conductor swing and clearance requirements, electric and magnetic field considerations, and so forth. Some typical easement widths are as follows: Voltage Overhead Lines 11 kv to 33 kv 10-30 m Underground Cables 66 kv 20-50 m 110 kv and 132 kv 30-60 m Easement Width 1-10 m In respect of such Electricity Easements, the Major Customer is responsible for: undertaking negotiations with the property owner/lessee and interested parties (i.e. other easement holders, mortgagees, trustees of reserves and native title holders); securing any necessary consents from the interested parties and any relevant government department; having the relevant survey plans drawn up in a manner acceptable for registration in the Land Titles Office page 4

FACT SHEET: giving Ergon Energy a copy of the registrable easement survey plan for review prior to lodgement of the plan for registration; ensuring that the easement will result in an Electricity Easement; having the easement documentation prepared in a manner acceptable for registration in the Land Titles Office and referring to the relevant Ergon Energy standard easement terms and conditions set out below; having the easement survey plan and Queensland Land Registry Form 9: Easement executed by the property owner/lessee and Ergon Energy; lodging the easement documentation with the Land Titles Office; and giving Ergon Energy a copy of the Registration Confirmation Statement from the Land Titles Office in respect of the easement. Ergon Energy has standard easement terms and conditions for use for Electricity Easements, which must be incorporated into a specific easement in respect of the Transferable Connection Assets by reference. These terms and conditions are not negotiable. These standard terms are registered with the Land Titles office under the following dealing numbers: combined overhead and underground conditions for freehold land: dealing number 710384570; and combined overhead and underground conditions for State land, Leases and Reserves: dealing number 711950329. Note that the Queensland Land Registry Form 9: Easement is normally to be completed using the following details. Ergon Energy will assist in providing relevant information for the purposes of completing the form: Item 5 is to state ERGON ENERGY CORPORATION LIMITED ACN 087 646 062", and should refer to the appropriate dealing number for Ergon Energy s standard terms (set out below): For freehold properties privately owned for overhead, underground, padmount transformers and RMUs: o Item 7 (Purpose of Easement) is to be shown as Electricity Supply and Incidental Works ; and o Item 8 should refer to Memorandum No: 710384570. For easements over State-controlled land for both overhead and underground: o Item 7 (Purpose of Easement) is to be shown as Electricity Works ; and o Item 8 should refer to Memorandum No: 711950329. For easements over State-controlled land underground only: o Item 7 (Purpose of Easement) is to be shown as "Electricity Works"; and o Item 8 should refer to Memorandum No: 711950324. Note that the standard terms apply only to Electricity Easements where Ergon Energy will be carrying out all of the relevant actions (such as ownership, operation, maintenance etc.). A Major Customer will need to obtain its own advice in respect of any easements that it requires for the purposes of accessing the land for the construction of the Transferable Connection Assets and constructing those assets. All costs and outlays incurred by Ergon Energy that are associated with the preparation and lodgement of the easement documentation are to be borne by the Major Customer. Freehold Requirements Similarly, where Ergon Energy has determined that freehold is the relevant tenure for all or part of the Transferable Connection Assets, the Major Customer is responsible for: undertaking negotiations with the property owner/lessee and interested parties (i.e. other easement holders, mortgagees, trustees of reserves and native title holders; page 5

FACT SHEET: securing any necessary consents from the interested parties and any relevant government department; obtaining any development permit required to subdivide the freehold lot; having the relevant survey plans drawn up in a manner acceptable for registration in the Land Titles Office; carrying out all other steps necessary to provide Ergon Energy with freehold tenure; and paying any registration fees, duty or other costs associated with the provision of freehold tenure. All costs and outlays incurred by Ergon Energy that are associated with the Major Customer providing freehold tenure are to be borne by the Major Customer. Community Engagement Where a Major Customer is proposing to construct substantial Transferable Connection Assets, Ergon Energy recommends that the Major Customer consider undertaking a program to determine any impacts of these works on the community at large and engage the community in respect of any such impacts. Ergon Energy adheres to a community engagement policy that reflects the International Association for Public Participation s (IAP2) Code of Ethics, and suggests that the Major Customer may wish to consider adopting a similar approach. IAP2 is available to assist interested persons in locating practitioners that can provide community engagement services. Generally, such engagement plans might involve: conducting an early community impact assessment; adopting an engagement strategy as part of the project planning and design process; and undertaking ongoing community engagement prior to acquisition and construction to mitigate community issues and inform stakeholders about activities in a timely and accurate manner. For Further Information Major Customers may contact their Project Sponsor to obtain further specific information. page 6