City of Owasso Public Work Department STATUS REPORT January 2, 2018

Similar documents
City of Owasso Public Work Department STATUS REPORT February 6, 2018

City of Owasso Public Work Department STATUS REPORT November 7, 2017

Final Plat Trails at Redwood Falls, Ph. 1 Hinckley Township EXECUTIVE SUMMARY

Planning Commission Preliminary Plan LRC Subdivision Montville Township

Due Diligence for Property Acquisitions

Appendix B Real Estate Plan

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM

L Provision of facilities for pedestrians and bicycles

HERON LANDING SUBDIVISION

Delaware River Basin Comprehensive Flood Risk Management Interim Feasibility Study and Integrated Environmental Assessment for New Jersey

TABLE OF CONTENTS General Legal Authority for Certification of Right of Way Control 24-2

INFORMATIONAL HANDOUT

YMCA Property Discussion. City Council Study Session April 10,

CITY OF FORT COLLINS NATURAL AREAS AND CONSERVED LANDS EASEMENT POLICY

PUBLIC HEARING. Loop 88 Segment 3 Thursday, October 12, 2017 Lubbock-Cooper Performing Arts Center at 6:00p.m. Date. Footer Text

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION

Task Central Office Real Estate Responsibilities District Responsibilities

PROJECT NH 0050(99)381 PCN 6926 YANKTON COUNTY. SD HWY 50 (4 th Street) from Broadway Ave to Archery Road in Yankton, SD

Frequently Asked Questions From the Certification of R/W Training Sessions

5. That the Owner shall agree that all development Blocks shown within the Draft Plan will be connected to full municipal services.

Pond Capacity Purchase Rates

Appendix G. Non-Federal Letters of Support and Draft Real Estate Plan

CHAPTER 3: IDENTIFYING SECTION 4(f) PROPERTIES

Right of Way Acquisition

GEODECA Land Surveying Company Projects

Memphis City Council Summary Sheet. S.D Roland Road Street Right-of-Way Dedication

PUBLIC FACILITIES REPORT. Triple Creek Community Development District. Hillsborough County, Florida

Planning Commission Preliminary Plan Hidden Lakes Estates Medina Township EXECUTIVE SUMMARY

7-3. Engineering and Operations Committee. Board of Directors. 7/11/2017 Board Meeting. Subject. Executive Summary

Section 4 Master Plan Framework

Purpose of the Public Hearing

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT AND TEXAS COMMISSION ON ENVIRONMENTAL QUALITY

ADOPT A RESOLUTION REGARDING

REQUEST FOR COUNCIL ACTION

SPANISH FORT PLANNING COMMISSION PRELIMINARY SUBDIVISION PLAT APPLICATION. Number of Lots (Units) Address. Address.

QUESTIONS AND ANSWERS FOR: RFP# 13-34, RFP for Engineering Services for Gas Distribution System Improvements

Order of Business. Board of Supervisors' Agenda Items

1340 Ogden Road Montrose, Colorado 81401

In Development. Property Acquisition. Design-Permitting. Construction Phase. Closeout Phase. Planning

Paintbrush North Siesta/Paintbrush Corridor Meeting. Saturday May 5, :00 4:00 PM

SUBJECT PARCEL(S) Property Owner(s) TMS Number Approximate Acreage Carolina Park Development, LLC

Burleigh County Water Resource District 1811 East Thayer Avenue Bismarck, North Dakota (701)

+/ ACRES - POOLER PARKWAY FRONTAGE

OFFICE OF REAL ESTATE

Facts on Metro Nashville s Development of a Hazard Mitigation Home Buyout Program in Response to the May 2010 Flood June 3, 2010

2012 COMMUNITY INFORMATION

Federal Aid Acquisition Guide. For Property Owners

LINCOLN COUNTY PLANNING & INSPECTIONS DEPARTMENT

DEVELOPMENT ACTIVITY AND DISCLOSURE REPORT

ZONING & LAND USE APPLICATION

CITY OF BATAVIA. DATE: September 23, 2016 Committee of the Whole-CD Drew Rackow AICP, Planner

Project Narrative Cherry Street Industrial Park Expansion - Subdivision and Street Extension

Appendix B Draft Real Estate Plan

Warren County, New Jersey

Objective: Approve an extension to development agreement between Gerrard Investments, LLC and Larimer County

Joint Public Notice. US Army Corps of Engineers Louisville District

WRITTEN DECISION OF THE HAYDEN CITY COUNCIL REGARDING MAPLE GROVE PRELIMINARY SUBDIVISION APPLICATION (SUB-0013) HAYDEN SIGNATURE, LLC

Locally Administered Projects Overview

Comprehensive Plan 2030


Athens Township Authority March 17, 2014

DESIGN PUBLIC HEARING

6.5 LAND AND WATER CONSERVATION FUND ACT SECTION

9.86 Acre Development Site Multifamily or Professional Office Moon Lake Road New Port Richey, FL

HUNTING BAYOU FLOOD RISK MANAGEMENT, HARRIS COUNTY, TEXAS DRAFT GENERAL REEVALUATION REPORT AND INTEGRATED ENVIRONMENTAL ASSESSMENT

AGENDA STATEMENT NO BUSINESS OF THE PLANNING COMMISSION City of Victoria, Minnesota STAFF REPORT. Casco Ventures (Developer)

5.5 Relocations and Displacements

3. Adopt the Preliminary Use and Management Plan for the property granted to the District.

Welcome to the Location Public Hearing for Highway 89 Improvements

PROJECT: P 0037(129)207 PCN: 039K BROWN COUNTY. S.D. Highway 37 From Aspen Ave to U.S. Highway 12 in Groton

REGULAR FINAL PLAT SUBDIVISION APPLICATION

DRIVEWAY REQUIREMENTS

Dane County Planning & Development Land Division Review

FACTS & HIGHLIGHTS. The community will attract young professionals and provide a housing option for empty nesters.

McGowin Park, LLC. B-3, Community Business District

Engineering Staff Report PHASE II REFERRAL

APPENDIX C REAL ESTATE PLAN BOULEVARD RESACA, BROWNSVILLE, TX CAMERON COUNTY, TEXAS

LYON COUNTY COMMUNITY DEVELOPMENT DEPARTMENT

Hank's Exchange Road Bridge Replacement Project

City of Ferndale CITY COUNCIL STAFF REPORT

RESOLUTION NO. R To Acquire Real Property Interests Required for the Lynnwood Link Extension

River Rock Estates Sketch Plan, a proposed major subdivision in S24, T35N R2W NMPM on County Rd 119 (PLN18-336)

ELECTRONIC PACKET JANUARY 9, 2017 POLICY, FINANCE, & PERSONNEL COMMITTEE MEETING. RELEASED: Tuesday, January 3, 2017

OAKGREEN AVENUE. Project Goals. (County Road 65) Corridor Improvement Project. Turn lanes Resurfacing Stormwater management

1.94 acres. Gwinnett Prado, L.P. c/o Brogdon Consulting Duluth, GA Contact: Ted Sandler

Investment Opportunity Rupley Site

PENNSYLVANIA TURNPIKE COMMISSION HIGHSPIRE, PENNSYLVANIA FORMAL MEETING FEBRUARY 21, :00 A.M.

March 12, The meeting was called to order at 7:00 p.m. by Mayor Docimo. The meeting was advertised in the following manner:

Variances & Preliminary Plan Hawks Ridge Montville Township EXECUTIVE SUMMARY

Land Value Analysis. Factors Affecting a Buyer s Value Opinion Lake Tahoe Conference Sacramento Sierra Chapter Appraisal Institute

CITY OF FERNDALE HEARING EXAMINER

SUB /CAR /PUD

JANUARY 2016 MAMARONECK & SHELDRAKE RIVERS NEW YORK FLOOD RISK MANAGEMENT GENERAL REEVALUATION REPORT FOR THE VILLAGE OF MAMARONECK APPENDIX E

February 20, 2017 LETTER OF INTENT

DISTRICT RESPONSIBILITIES: ASSIST WITH ACQUISITION ISSSUES AUDIT TO ASSURE THAT REQUIREMENTS ARE MET

A Guide to Good Applications

5.5 Relocations and Displacements

REGULAR AGENDA ITEM December 10, 2014 Commission Meeting Eagle Road and McMillan Road ( Project )

DESCRIPTION OF THE DISTRICT

FIMI CONSTRUCTION UPDATE

Transcription:

City of Owasso Public Work Department STATUS REPORT January 2, 2018 E 76 St N Widening (from U.S. Hwy169 to N 129 E Avenue) HDH - In 2010, federal funding was awarded for the engineering, right-ofway and utility relocation phase. In 2011, federal funding was awarded for the construction phase. Through the Surface Transportation Program, the city will be required to match the costs by 20% for each phase. - In February 2016, ODOT and Federal Highway Administration approved the environmental document. - Engineering design is approximately 95% complete. - The property owner of the remaining parcel has agreed and provided an approval of the Right to Entry. As a result, utility relocations should commence within the next 60-90 days. E 76 St N and Main Street Intersection Improvement Project HDH - In June 2015, City Council approved an engineering agreement with McClelland Engineering. In July 2016, City Council approved this project as eligible to receive - Construction commenced in May 2017. - Contractor is currently finishing up the final punch list items. - Project completion is scheduled to occur by mid-january 2018. Garnett Road Widening (from E 96 St N to E 106 St N) HDH - In November 2012, Council approved an engineering agreement with Dewberry. - In November 2013, federal funds were awarded through the Surface Transportation Program. A 20% fund match is required. - ODOT approved the environmental document in June 2015. The Federal Highway Administration (FHWA) approved the document in July 2015. - Right of way and easement acquisition is complete. - AEP/PSO is approximately 90% complete with the relocation of the utility poles and electric lines. - AT&T is scheduled to commence rel ocation in January 2018. - Unfortunately, ONG is behind schedule on other relocation projec ts, resulting in a 30-60 day delay on relocating utilities for the Garnett Roadway project. As a result, ONG is now scheduled to commence utility relocation in February or March 2018. - Private utility relocation is scheduled to be complete by June 2018; followed by construction.

Garnett Road Widening (E 106 St N to E 116 St N) HDH - In March 2016, City Council approved an engineering agreement with McClelland Consulting Engineers. Engineering design is 95% complete. - Right of way and easement acquisition commenced in January 2017. Of the 32 parcels, 15 have been obtained and staff continues negotiations with the remaining property owners. - Upon the acquisition of Right of Way and necessary easements, utility relocation will begin; followed by construction. E 106 St N and N 145 E Avenue Intersection Improvements HDH - In January 2016, Council approved an engineering agreement with Poe and Associates. - In February 2016, engineering design commenced with completion in September 2017. - 90% plans have been submitted, reviewed and returned to the engineer. - Right of Way and easement acquisition commenced in January 2017 with completion in December 2017. - Private utility companies are currently finalizing their relocation plans. Utility relocation is expected to commence within the next 60-90days. - Once utility relocation is complete, construction will follow soon after. E 116 St N & N 129 E Ave Intersection Improvements HDH - November 2014, funding for the construction phase of this project was approved to receive federal funds in the amount of $2,186,000. This matching grant is 80% ODOT funding, 10% Tulsa County funding and 10% City funding. - January 2016, the environmental study was approval by Federal Highway Administration. - Engineering design is 90% complete. - Right of way and easement acquisition commenced in September 2017. Of the 7 parcels, 1 has been obtained and staff continues negotiations with the remaining property owners. - Upon the acquisition of right of way, necessary easements and approvable utility relocation plans, utilities will begin relocation; followed by road construction. FY 2017 Street Rehabilitation Program HDH - In September 2016, City Council approved the proposed project list.

- The City Council awarded the bid to Becco Construction on August 15, 2017. - Construction commenced in October 2017. - Becco Construction continues work on N 123 rd E Ave and will commence with the base work in Southern Links during the month of January. Central Park / Lakeridge Stormwater Improvements HDH - In July 2015, Council approved an engineering agreement Meshek and Associates. - Army Corp of Engineers (USACE) has reviewed and approved the design plans. Staff anticipates receiving a permit to construct within the next 30-45 days. - Private utility companies are currently finalizing their relocation plans. Utility relocation is expected to commence within the next 60-90days. - Once utility relocation is complete ; construction will follow. Rayola Park / Elm Creek Tributary 5A Stormwater Improvements HDH - Meshek and Associates is modeling the stream to determine the needed improvements to satisfy the FEMA requirements. Results are expected in January 2018. South Sports Park Regional Detention Facility HDH - In July 2015, Council approved an engineering agreement Meshek and Associates. - Engineering design is complete. - On April 14, 2017, City staff met with the USACE to discuss the possibility of wetland mitigation required by the agency. The

USACE has claimed jurisdiction and wetland mitigation will be required offsite. - In June 2017, staff sent additional information to the USACE per their request. This information will be used to determine the final mitigation needed to permit the project, regarding wetlands, stream channel and pond removal. - On November 21, 2017, USACE issued the public notice for public comment. Governmental agencies such as EPA and ODEQ have provided comments. As a result, staff is in process of responding to the comments in reference to mitigation. - Lastly, environmental consultant is reviewing potential mitigation sites and will have a recommendation to City staff by mid-january 2018. Garrett Creek/Morrow Place Lift Station, Force Main, Gravity Sewer Line Improvements EF - In March 2016, City Council approved Garrett Creek/Morrow Place Sewer Improvement Assessment Area. - On March 21, 2017, OPWA approved the construction contract with Crossbo Construction and IRA Green Construction. - Lift Station and gravity sewer line improvements is schedule d to be complete by mid-january 2018. Mingo and E 116 St N Intersection/E 116 St N from Mingo to Garnett Road Imp rovement sh - In December 2016, City Council approved an engineering agreement with Garver LLC. - Engineering design is 90% complete. - Preliminary ROW documents submitted to the City for review, as well as the railroad permit. E 116 St N and Garnett Intersection/E 116 St N from Garnett to N 129 E Ave Improvements - In January 2017, City Council approved an engineering agreement with Guy Engineering. - E 116 St N roadway design is approximately 45% complete.

- E 116 St N and Garnett Intersection design is approximately 60% complete. - Remington Lift Station relief sewer line construction contract was awarded to Cross Bo Construction at the December 5, 2017, City Council meeting. Construction is scheduled to commence in January 2018. - ROW documents have been prepared and property owners have been notified from N 129 th E Ave to the Fire Training Facility (FTF) to obtain the ROW for the road project and the offsite water line to serve the FTF. E 116 St N from approximately N 129 E Ave to N 135 E Ave Improvements - In March 2017, City Council approved an engineering agreement with WP Moore. - Engineering design is approximately 80% complete. E 96 ST North from approximately N 119 E A ve to N 129 E Ave - In May 2017, City Council approved an agreement to perform a study and provide conceptual plans of the E 96 St N corridor from N 119 E Ave to N 129 E Ave. - Additional options were reviewed in November 2017 and at least one more option will be reviewed in January. Study will be finalized in February 2018. N 135 E Ave and N 140 E Ave Service Road Improvements - On February 7, 2017, Council approved an engineering agreement with Crafton Tull. - Land acquisition is complete. - Bid opening for the N 135 th E Ave improvements occurred on December 12, 2017, following with a proposal to award the construction contract on January 2, 2018. - Bid advertisement for N 140 th E Ave improvements is scheduled to occur in March 2018.