City of Owasso Public Work Department STATUS REPORT November 7, 2017

Similar documents
City of Owasso Public Work Department STATUS REPORT January 2, 2018

City of Owasso Public Work Department STATUS REPORT February 6, 2018

PROJECT NH 0050(99)381 PCN 6926 YANKTON COUNTY. SD HWY 50 (4 th Street) from Broadway Ave to Archery Road in Yankton, SD

Planning Commission Preliminary Plan LRC Subdivision Montville Township

DRIVEWAY REQUIREMENTS

Locally Administered Projects Overview

5. That the Owner shall agree that all development Blocks shown within the Draft Plan will be connected to full municipal services.

HERON LANDING SUBDIVISION

Purpose of the Public Hearing

May 21, ACHD Board of Commissioners Stacey Yarrington, Planner II DRH /DRH

SUBDIVISION & PLANNING APPROVAL STAFF REPORT Date: December 1, 2016

SHORE DRIVE CORRIDOR: PAST, PRESENT, & FUTURE APRIL 19, 2018 BAYFRONT ADVISORY COMMISSION

ARTICLE 7 UTILITIES AND EASEMENTS

Memphis City Council Summary Sheet. S.D Roland Road Street Right-of-Way Dedication

Due Diligence for Property Acquisitions

SPANISH FORT PLANNING COMMISSION PRELIMINARY SUBDIVISION PLAT APPLICATION. Number of Lots (Units) Address. Address.

BYRON TOWNSHIP ZONING APPLICATION

TOWN OF NEW SHOREHAM ZONING BOARD OF REVIEW APPLICATION PROCEDURE

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM

Final Plat Trails at Redwood Falls, Ph. 1 Hinckley Township EXECUTIVE SUMMARY

Committed to Service

LYON COUNTY COMMUNITY DEVELOPMENT DEPARTMENT

Appendix B Real Estate Plan

Executive Summary: This is a preliminary plat to construct 8 residential lots and 2 commons lots with a private road on 3.87-acres in Meridian, Idaho.

INFORMATIONAL HANDOUT

REQUEST FOR COUNCIL ACTION

SUB /CAR /PUD

YMCA Property Discussion. City Council Study Session April 10,

CITY OF FORT COLLINS NATURAL AREAS AND CONSERVED LANDS EASEMENT POLICY

McGowin Park, LLC. B-3, Community Business District

L Provision of facilities for pedestrians and bicycles

Section 4 Master Plan Framework

BAY FOREST PARK SUBDIVISION, RESUBDIVISION OF LOTS 6 & 7 AND BAY FOREST PARK SUBDIVISION LOT 10, OF THE RESUBDIVISON OF LOTS 9 & 10

In Development. Property Acquisition. Design-Permitting. Construction Phase. Closeout Phase. Planning

$28,145,000 THE COUNTY COMMISSION OF HARRISON COUNTY (WEST VIRGINIA) TAX INCREMENT REVENUE AND REFUNDING BONDS (CHARLES POINTE PROJECT NO

Sugar House Construction Projects

Paintbrush North Siesta/Paintbrush Corridor Meeting. Saturday May 5, :00 4:00 PM

March 12, The meeting was called to order at 7:00 p.m. by Mayor Docimo. The meeting was advertised in the following manner:

Order of Business. Board of Supervisors' Agenda Items

August 13, The meeting was called to order at 7:00 p.m. by Mayor Docimo. The meeting was advertised in the following manner:

PUBLIC FACILITIES REPORT. Triple Creek Community Development District. Hillsborough County, Florida

CHAPTER 3: IDENTIFYING SECTION 4(f) PROPERTIES

DAUPHIN CREEK ESTATES SUBDIVISION

Appendix G. Non-Federal Letters of Support and Draft Real Estate Plan

SITE PLAN REVIEW ADMINISTRATIVE REVIEW. Please Note: Once submitted to the County, all application materials become a matter of public record.

PUBLIC HEARING. Loop 88 Segment 3 Thursday, October 12, 2017 Lubbock-Cooper Performing Arts Center at 6:00p.m. Date. Footer Text

PROJECTS: P 0083(74)56; 036E; JONES COUNTY NH 0083(79)45; 04E7; MELLETTE COUNTY NH 0083(80)44; 04E8; MELLETTE COUNTY

BEFORE THE HEARING EXAMINER FOR THURSTON COUNTY

City of Palo Alto (ID # 4882) City Council Staff Report

ELECTRONIC PACKET JANUARY 9, 2017 POLICY, FINANCE, & PERSONNEL COMMITTEE MEETING. RELEASED: Tuesday, January 3, 2017

FIMI CONSTRUCTION UPDATE

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION

DIVISION 2 - CONSTRUCTION PLAN AND MISCELLANEOUS REQUIREMENTS

ZONING AMENDMENT & SUBDIVISION STAFF REPORT Date: March 1, 2018

FEASIBILITY REPORT FOR PROPOSED ROAD IMPROVEMENT PROJECT OF OLD VIKING BOULEVARD NOWTHEN, MINNESOTA DECEMBER 6, Prepared by:

PLANNING COMMISSION MINUTES OF MEETING Wednesday, December 12, :00 p.m.

HUNTING BAYOU FLOOD RISK MANAGEMENT, HARRIS COUNTY, TEXAS DRAFT GENERAL REEVALUATION REPORT AND INTEGRATED ENVIRONMENTAL ASSESSMENT

CITY OF PAPILLION PLANNING COMMISSION STAFF REPORT MAY 31, 2017 AGENDA SHADOW LAKE 2 FINAL PLAT FP

Committed to Service

PLANNED UNIT DEVELOPMENT CITY OF CHAMBLEE, GA

Appendix C. Real Estate. Brazos Island Harbor, Texas Channel Improvement Project Cameron County, Texas

Electric Transmission Right-of-Way Usage Policy

Tulsa Development Authority Board of Commissioners Meeting Executive Director s Report. March 2017

Frequently Asked Questions for: Drainage, Watershed and Water Quality Property Owners Near Creeks Developers and Engineers and Definitions of Terms

PROJECT: P 0037(129)207 PCN: 039K BROWN COUNTY. S.D. Highway 37 From Aspen Ave to U.S. Highway 12 in Groton

CHAPTER 10 Planned Unit Development Zoning Districts

Condominium Unit Requirements.

HENRICO COUNTY NOTICE OF SPECIAL MEETING BOARD OF SUPERVISORS

Dane County Planning & Development Land Division Review

GEODECA Land Surveying Company Projects

Administration and Calculation of Servicing Agreement Fees and Development Levies

In Development. Consultant Selection. Consultant - Scope of Work. Design-Permitting. Planning. Construction. Closeout

3. THAT the Mayor and Corporate Officer be authorized to execute all documents relating to this matter.

Appendix 4 Agency Approval Letters

DESCRIPTION OF THE DISTRICT

Date: March 16, Jake Centers ERD, LLC P.O. Box 1610 Eagle, ID Elevation Ridge Subdivision (SUB & PUD ) Street Address

Subdivision - Minor Plat Submittal

OFFICE OF REAL ESTATE

SECTION 7000 LAND DEVELOPMENT REQUIREMENTS

IH 35W Public Hearing CSJs: , , , and COMMENT AND RESPONSE REPORT

LINCOLN COUNTY PLANNING & INSPECTIONS DEPARTMENT

CITY OF EAU CLAIRE, WISCONSIN. SPECIAL ASSESSMENT POLICY (Dated: November 8, 2016)

DEVELOPMENT ACTIVITY AND DISCLOSURE REPORT

FINAL PLAT SUBMITTAL CHECKLIST

CITY OF PETALUMA HOUSING PROGRAM REQUEST FOR PROPOSALS FY

River Rock Estates Sketch Plan, a proposed major subdivision in S24, T35N R2W NMPM on County Rd 119 (PLN18-336)

Evaluating and Processing Road and Utility Easement Proposals on Corps Lands and Flowage Easements

Land Management Plan Fargo-Moorhead (FM) Area Flood Risk Reduction Project Version 1

MAPLETON CITY CORPORATION. Step 7: Upon final approval and prior to plat recording the applicant shall provide the following:

DEPARTMENT OF THE ARMY OFFICE OF THE CHIEF OF ENGINEERS WASHINGTON, D.C

Preliminary Subdivision Application (Major) (Four (4) lots or more)

Planning Commission Preliminary Plan Hidden Lakes Estates Medina Township EXECUTIVE SUMMARY

DETAILED GRADING PLAN CHECKLIST (TEARDOWN/REDEVELOPMENT) Updated: 12/12/2017

DATE: April 25, Mayor Buol and former Iowa DOT Director Paul Trombino Sign Memorandum of Understanding

CITY OF SARALAND FINAL SUBDIVISION PLAT REVIEW

SUBJECT: Application for Planned Unit Development and Rezoning 1725 Winnetka Road

ADMINISTRATORS REPORT - MAY 16, 2018.PDF

QUESTIONS AND ANSWERS FOR: RFP# 13-34, RFP for Engineering Services for Gas Distribution System Improvements

LEWISTOWN COMMERCE CENTER COMMUNITY DEVELOPMENT AUTHORITY (VIRGINIA) $37,675,000 Revenue Bonds, Series 2007

ADOPT A RESOLUTION REGARDING

Transcription:

City of Owasso Public Work Department STATUS REPORT November 7, 2017 E 76 St N Widening (from U.S. Hwy169 to N 129 E Avenue) HDH - In 2010, federal funding was awarded for the engineering, right-ofway and utility relocation phase. In 2011, federal funding was awarded for the construction phase. Through the Surface Transportation Program, the city will be required to match the costs by 20% for each phase. - In February 2016, ODOT and Federal Highway Administration approved the environmental document. - Engineering design is approximately 95% complete. - Right of Way and easement acquisition began in July 2016. Of the 24 parcels, 23 are complete and staff continues negotiations with the remaining property owner. - Upon the acquisition of Right of Way and necessary easements, utility relocation will begin, followed by construction. E 76 St N and Main Street Intersection Improvement Project HDH - In June 2015, City Council approved an engineering agreement with McClelland Engineering. In July 2016, City Council approved this project as eligible to receive - Construction commenced in May 2017. - Work on the remaining portion of E 76 th St N asphalt removal and concrete placement is expected the week of November 6 th. - Staff and contractors are working to get the roadway sections open by Thanksgiving (Weather Permitting). Dress up and work behind the curbs and at radius s will then continue throughout December 2017. Garnett Road Widening (from E 96 St N to E 106 St N) HDH - In November 2012, Council approved an engineering agreement with Dewberry. - In November 2013, federal funds were awarded through the Surface Transportation Program. A 20% fund match is required. - ODOT approved the environmental document in June 2015. The Federal Highway Administration (FHWA) approved the document in July 2015. - Right of way and easement acquisition is complete. - AEP/PSO is approximately 85% complete with the relocation of the utility poles. - ONG is scheduled to commence with relocation in December 2017.

- ATT and Cox will commence with relocation once AEP has completed transferring the electric lines to the new poles. - Private utility relocation is scheduled to be complete by April 2018; followed by construction. Garnett Road Widening (E 106 St N to E 116 St N) HDH - In March 2016, City Council approved an engineering agreement with McClelland Consulting Engineers. Engineering design is 95% complete. - Right of way and easement acquisition commenced in January 2017. Of the 32 parcels, 11 have been obtained and staff continues negotiations with the remaining property owners. - Upon the acquisition of Right of Way and necessary easements, utility relocation will begin; followed by construction. E 106 St N and N 145 E Avenue Intersection Improvements HDH - In January 2016, Council approved an engineering agreement with Poe and Associates. - In February 2016, engineering design commenced with completion in September 2017. - 90% plans have been submitted, reviewed and return to the engineer. - Right of Way and easement acquisition commenced in January 2017. Of the 6 parcels, 4 have been obtained and staff continues negotiations with the remaining property owners. - Upon the acquisition of right of way, necessary easements and approvable utility relocation plans, utilities will begin relocation; followed by road construction. E 116 St N & N 129 E Avenue Intersection Improvements HDH - November 2014, funding for the construction phase of this project was approved to receive federal funds in the amount of $2,186,000. This matching grant is 80% ODOT funding, 10% Tulsa County funding and 10% City funding. - January 2016, the environmental study was approval by Federal Highway Administration. - Engineering design is 90% complete. - Right of way and easement acquisition commenced in September 2017. Staff is currently negotiating with 7 property owners. - Upon the acquisition of right of way, necessary easements and approvable utility relocation plans, utilities will begin relocation; followed by road construction. FY 2017 Street Rehabilitation Program HDH

- In September 2016, City Council approved the proposed project list. - The City Council awarded the bid to Becco Construction on August 15, 2017. - Construction commence d on October 9, 2017. - Becco Construction is working on N 120 th E Avenue (North of 86 th ) replacing curb and gutter, patching street in preparation for new asphalt, repairing handicap ramps and installing concrete at intersection approaches. Brookfield Crossing Stormwater Improvements - In July 2016, City Council approved this project as eligible to receive - Engineering design was complete in December 2016. - Detention facility improvements commenced in October with completion scheduled by mid-november 2017. Central Park / Lakeridge Stormwater Improvements HDH - In July 2015, Council approved an engineering agreement Meshek and Associates. - Army Corp of Engineers (USACE) has reviewed the plans and has decided to require a scope reduction so that environmental impacts are reduced. - Once utility relocation is complete and permit is issued by the Corp; construction will follow. Rayola Park / Elm Creek Tributary 5A Stormwater Improvements HDH - Meshek and Associates is modeling the stream to determine the needed improvements to satisfy the FEMA requirements. Results are expected in November 2017. South Sports Park Regional Detention Facility HDH - In July 2015, Council approved an engineering agreement Meshek and Associates. - Engineering design is complete.

- On April 14, 2017, City staff met with the USACE to discuss the possibility of wetland mitigation required by the agency. The USACE has claimed jurisdiction and wetland mitigation will be required offsite. - In June 2017, staff sent additional information to the USACE per their request. This information will be used to determine the final mitigation needed to permit the project, regarding wetlands, stream channel and pond removal. - USACE is preparing to issue the public notice for the project. Once the notice is published, the public and governmental agencies will have 30 days to comment. The comments will be compiled and reviewed by the City of Owasso and USACE. Garrett Creek/Morrow Place Lift Station, Force Main, Gravity Sewer Line Improvements EF - In March 2016, City Council approved Garrett Creek/Morrow Place Sewer Improvement Assessment Area. - On March 21, 2017, OPWA approved the construction contract with Crossbo Construction and IRA Green Construction. - Construction commenced mid-may with completion scheduled to occur in December 2017. Mingo and E 116 St N Intersection/E 116 St N from Mingo to Garnett Road Imp rovement sh - In December 2016, City Council approved an engineering agreement with Garver LLC. - Engineering design is approximately 90% complete. - Right-of-way documents expected once AEP has reviewed the issued utility corridors. E 116 St N and Garnett Intersection/E 116 St N from Garnett to N 129 E Ave Improvements - In January 2017, City Council approved an engineering agreement with Guy Engineering. - Remington Lift Station relief sewer line has been permitted and advertised. Bids will be presented to City Council in December. - ROW documents have been prepared and property owners have been notified from 129 th East Ave to the Fire Training Facility

(FTF) to obtain the ROW for the road project and the offsite water line to serve the FTF. E 116 St N from approximately N 129 E Ave to N 135 E Ave Improvements - In March 2017, City Council approved an engineering agreement with WP Moore. - Engineering design is approximately 60% complete. E 96 ST North from approximately N 119 E A ve to N 129 E Ave - In May 2017, City Council approved an agreement to perform a study and provide conceptual plans of the E 96 St N corridor from N 119 E Ave to N 129 E Ave. - Draft of the conceptual plans were reviewed in October and additional information has been requested. Study will be finalized in February 2018. East and West Service Road Improvements - On February 7, 2017, Council approved an engineering agreement with Crafton Tull. - ROW negotiations are underway. - Bid advertisement for the west service road improvements will commence by mid-november 2017.