Copyright and Disclaimer

Similar documents
From: Gerard Reiter, EGM/Asset Management Date: 14 April 2015 Peter McIntyre, Managing Director

FACT SHEET: Tenure requirements for Major Customer Connections

Social Housing Initiative Review

THE VALUATION OF LAND UNDER ROADS

Electricity functions AEMO Final Budget and Fees. June Australian Energy Market Operator Limited

National Rental Affordability Scheme. Economic and Taxation Impact Study

NEM GENERATOR TRANSFER GUIDE

HIA Industry Recommendation - Private Certification

LOT 30 TREEBY ROAD ANKETELL WA 6167

Submission. Better Apartments Draft Design Standards

METHODOLOGY GUIDE VALUING LANDS IN TRANSITION IN ONTARIO. Valuation Date: January 1, 2016

MULTIPLE CHALLENGES REAL ESTATE APPRAISAL INDUSTRY FACES QUALITY CONTROL. Issues. Solution. By, James Molloy MAI, FRICS, CRE

Policy: Distribution Subdivision

ARCHITECTS BRIEF (development year to RIBA stage 3 with option to progress to 7)

Quarterly Review The Australian Residential Property Market and Economy

Consulted With Individual/Body Date Head of Finance Financial

Recommendation to Approve Dominion Virginia Power s Request for an Easement along Route 606 at Washington Dulles International Airport.

CORPORATE STANDARD FUNDING AND DELIVERY OF GROWTH INFRASTRUCTURE VERSION: 1.0

Information Memorandum

NSW Affordable Housing Guidelines. August 2012

Creswick Property Factsheet

DETACHED MULTI-UNIT APPROVALS

South East Queensland Growth Management Program

This decision is made under sections 130( 1 ) and 133 of the Environment Protection and Biodiversity Conservation Act 1999.

Kitchens and Bathrooms Report

VALUATION REPORTING REVISED Introduction. 3.0 Definitions. 2.0 Scope INTERNATIONAL VALUATION STANDARDS 3

FOREIGN PURCHASER AND ABSENTEE OWNER SURCHARGES. Costa Koutsis FTIA Partner, PwC

New Residential Zones their application and implications. Elizabeth Lewis David Vorchheimer

CONTENTS. Recommendation One Provision of Professional Development and Mentoring Opportunities

ATTACHMENT 1: Proposed Official Plan Amendment - Affordable Housing

Lochinvar Section 94 Contributions Plan 2014 VERSION 1 ADOPTED 26/08/14

Amendment C230 to the Greater Geelong Planning Scheme

REPORT ON: VALUATION APPROACH AND METHODOLOGY FOR SPECIALISED AIRFIELD ASSETS (RUNWAY, TAXIWAYS AND APRONS) BY PROFESSOR TERRY BOYD 3 AUGUST 2001

FORM F1 TECHNICAL REPORT TABLE OF CONTENTS

CoreLogic RP Data Property Market Indicator Summary All data to week ending 30 August 2015

Business and Property Committee

What can I do in PEXA? Date: 15 December 2015 Version 1.3

We deliver solutions that maximise the value of your real estate. JLL works with you to realise opportunities and reduce your risk.

FOR PL A N N ERS. Michael Forwood. Tuesday 11 July 2017

Chapter 3: A Framework for a National Land Information Infrastructure

Toowoomba Property Factsheet

DEVELOPMENT OPPORTUNITY LAND EAST OF NEW ROAD MELBOURN, CAMBRIDGESHIRE, SG8 6BX

Depreciation A QUICK REFERENCE GUIDE FOR ELECTED OFFICIALS AND STAFF

Strategic assessment scoping document - Solomon Heights, Vic

ADMINISTRATIVE GUIDANCE

Historic Environment Scotland

26 February 2013 FIRST HALF RESULTS PRESENTATION

TECHNICAL INFORMATION PAPER - VALUATIONS OF REAL PROPERTY, PLANT & EQUIPMENT FOR USE IN AUSTRALIAN FINANCIAL REPORTS

ACCOUNTING STANDARDS BOARD INTERPRETATION OF THE STANDARDS OF GENERALLY RECOGNISED ACCOUNTING PRACTICE

ENABLING AFFORDABLE HOUSING IN LOCAL GOVERNMENT AREAS. Discussion Paper COMMONEQUITY.COM.AU

Illinois Adjustable Block Program PV System Purchase Disclosure Form

shortfall of housing land compared to the Core Strategy requirement of 1000 dwellings per 1 Background

LSL New Build Index. The market indicator for New Builds March Political events

Lease Update. June 2017 Addison, Texas

Ashmore & Molendinar Property Factsheet

EXCELLENCE IN SURVEYING AWARD,

Standard for the acquisition of land under the Public Works Act 1981 LINZS15005

International Financial Reporting Standards (IFRS)

F R E QUENTLY AS K E D QUESTIONS

REQUEST FOR PROPOSAL FOR SERVICED APARTMENTS FOR: 1. CONCEPT DESIGN CONSULTATION AND/OR 2. OPERATION OF SERVICED APARTMENTS, FOR,

CoreLogic Quarterly Rental Review

South African Council for Town and Regional Planners

Capability Statement Town Planning, Cadastral & Development

GIS & GPS Applications in Valuation/Appraisal Assessments

DWGM and Victorian Gas FRC Final budget and Fees June Australian Energy Market Operator Limited

Exclusive Finance Broker Business Benchmarking Report One

Government Emergency Ordinance No. 54/2006 on the regime of the concession contracts for public assets ( GEO No. 54/2006 );

PPP Project Realization Roadmap for Public Entities. based on the PPP Act and the Act on Concessions for Construction Work or Services

Investigation into land and property acquisition for Phase One (London West Midlands) of the High Speed 2 programme

Presbyterian Church of Victoria

REQUEST FOR OFFERS. Tsubota Steel Site. ISSUE DATE: February 12, 2014

IAS Revenue. By:

RAPID ANALYTICS INTERACTIVE SCENARIO EXPLORER (RAISE) A tool for analysing and visualising land valuation in different development scenarios

Bargara Property Factsheet

DRAFT FEASIBILITY REPORT CENTRAL HILL ESTATE LONDON BOROUGH OF LAMBETH

Officers Report. Appendix 7. Colliers Valuation and Economic Feasibility Technical Report

RAPID ANALYTICS INTERACTIVE SCENARIO EXPLORER (RAISE) A tool for analysing and visualising land valuation in different development scenarios

PIP practice note 1 planning assumptions. How to use this practice note. Planning assumptions. What are planning assumptions? Type.

Business Combinations

Designing for transparency and participation in the Hellenic Cadastral Project

(b) a purpose directly related to such dealing provided that the purpose is not contrary to any Law; or

By Expressions of Interest. Under Instructions from Lockyer Quarry Pty Ltd. Approved Freehold High Quality BASALT QUARRY

An Overview of the eplan Journey with a Focus on the Victorian eplan 2025 Roadmap Dr Hamed Olfat

International Financial Reporting Standards (IFRS)

Alexandria Property Factsheet

RP Data Housing market update. October 2014

Housing as a Business (HaaB)

City of Surrey s Digital Plan Submission Process

REQUEST FOR PROPOSAL (RFP) RFP AS. Appraisal Services Valuation of DBHA Properties

Economic Impacts of MLS Home Sales and Purchases In The province of Québec and The Greater Montréal Area

The joint leases project change is coming

Information Memorandum FOR SALE

THE LOT A QUARTERLY BULLETIN ON DEVELOPMENT SECTOR ISSUES MAY 2017 EDITION ONE

PROPERTY DEVELOPMENT REPORT

Suburb Profile Report. Paddington, 2021 NSW

KPMG s CFO. Webcast. Administrative

Housing Need in South Worcestershire. Malvern Hills District Council, Wychavon District Council and Worcester City Council. Final Report.

Ingleburn Property Factsheet

The Profile for Residential Building Approvals by Type and Geography

The South Australian Housing Trust Triennial Review to

Transcription:

13 FEBRUARY 2019

Copyright and Disclaimer Copyright in this material is owned by or licensed to ElectraNet. Permission to publish, modify, commercialise or alter this material must be sought directly from ElectraNet. Reasonable endeavours have been used to ensure that the information contained in this report is accurate at the time of writing. However, ElectraNet gives no warranty and accepts no liability for any loss or damage incurred in reliance on this information. Revision Record Date Version Description Author Checked By Approved By 13 February 2019 1.0 First Issue William John Gichuhi ElectraNet internal review Rainer Korte Page 2 of 13

Contents 1. INTRODUCTION... 5 2. SUMMARY COST ESTIMATES... 5 3. ESTIMATING METHODOLOGY... 8 3.1 SUBSTATIONS... 8 3.2 TRANSMISSION LINES... 9 4. INDEPENDENT REVIEW OF TRANSMISSION LINE COSTS... 10 5. BASIS OF ESTIMATE... 11 5.1 PLANNING BASIS... 11 5.2 COST BASIS... 11 5.3 RISK BASIS... 11 5.4 CLASS 4 ESTIMATE... 11 5.5 COSTS FROM THIRD PARTIES... 12 5.6 GENERAL PROJECT DATA... 12 5.7 GENERAL PRICING ASSUMPTIONS... 12 5.8 COST ESCALATIONS... 13 5.9 LAND & EASEMENT COSTS... 13 5.10 EXCLUSIONS... 13 Page 3 of 13

Glossary of Terms Term AEMO JPB HVAC HVDC PACR PADR PSCR PV RIT-T SAET SPS SVC TNSP Description Australian Energy Market Operator Jurisdictional Planning Body High-Voltage Alternating Current High-Voltage Direct Current Project Assessment Conclusions Report Project Assessment Draft Report Project Specification Consultation Report Photovoltaic Regulatory Investment Test for Transmission South Australia Energy Transformation Special Protection Scheme Static VAR Compensator Transmission Network Service Provider Page 4 of 13

1. Introduction In June 2018, ElectraNet published a draft report on its SA Energy Transformation Regulatory Investment Test for Transmission (RIT-T) investigation of interconnector options between South Australia and the eastern states and alternative non-interconnector options. This Project Assessment Draft Report (PADR) was accompanied by a Basis of (Cost) Estimate report that sets out how the cost estimates of options considered in the economic assessment were derived. This Cost Estimate Report builds on this and sets out the cost estimates of the interconnector options considered in the Project Assessment Conclusions Report (PACR) that this report accompanies 1. In response to stakeholder submissions on the PADR, we commissioned Jacobs to undertake an independent review of the process by which the transmission line costs were derived and to recommend any changes. The outcomes of this review are described in Section 4 of this report. 2. Summary Cost Estimates Table 1 below summarises the cost estimates for the various interconnector options evaluated in the PACR. Table 1 Cost estimates of interconnector options evaluated in PACR SA Energy Transformation Estimates for PACR February 2019 Option Description Cost ($m 2018-19) B1 400 kv HVDC from Northern South Australia to Queensland (3 converter stations) 1,980 C3 C3ii C3iii 330 kv DC from Robertstown in Mid North SA to Wagga Wagga in Western NSW, via Buronga, plus Buronga to Red Cliffs 220 kv 330 kv line from Robertstown SA to Wagga Wagga in NSW, via Buronga, Red Cliffs, Kerang and Darlington Point 400 kv HVDC line from Robertstown SA to Darlington Point via Buronga, HVAC line from Darlington Point to Wagga Wagga, plus Buronga to Red Cliffs 220 kv (3 converter stations) 1,530 1,730 1,660 D 275 kv line from central SA to Victoria 1,200 1 Cost estimates of the non-interconnector option considered in the PACR are covered elsewhere and outside of the scope of this report Page 5 of 13

Table 2 provides a breakdown of these cost estimates by major cost components and by jurisdiction. Table 2 High level cost breakdown of interconnector options ($m 2018-19) Option Item SA QLD NSW VIC TOTAL Transmission lines 230 740 970 B 400 kv HVDC from northern SA to Qld Converter substations, including transformers Other costs, including reactive plant, SPS and delivery costs 300 570 870 60 80 140 Total Cost 590 1,390 2 1,980 Transmission lines 230 710 940 C.3 330 kv line from Robertstown SA to Wagga Wagga in NSW, via Buronga, plus Buronga to Red Cliffs 220 kv Substations, including transformers Other costs, including reactive plant, SPS and delivery cost 90 210 300 60 230 290 Total Cost 380 1,150 3 1,530 C.3ii 330 kv line from Robertstown SA to Wagga Wagga in NSW, via Buronga, Red Cliffs, Kerang and Darlington Point C.3iii 400 kv HVDC line from Robertstown SA to Darlington Point via Buronga; HVAC line from Darlington Point to Wagga Wagga, plus Buronga to Red Cliffs 220 kv Transmission Lines 230 820 1,050 Substations, including transformers Other costs, including reactive plant, SPS and delivery costs 90 260 350 60 270 330 Total Cost 380 1,350 4 1,730 Transmission lines 140 480 620 Substations, including transformers Other costs, including reactive plant, SPS and delivery costs 290 600 890 40 90 130 Total Cost 470 1,170 5 1,640 2 The cost of construction through NSW is included in the QLD cost 3 The cost of construction through Victoria is included in the NSW cost 4 The cost of construction through Victoria is included in the NSW cost 5 The cost of construction through Victoria is included in the NSW cost Page 6 of 13

Option Item SA QLD NSW VIC TOTAL Transmission lines 260 210 470 D 275 kv line from central SA to Victoria Substations, including transformers Other costs, including reactive plant, SPS and delivery costs 30 90 120 110 150 260 Network Hardening Costs 150 150 300 Total Cost 550 600 1,150 Table 3 provides a breakdown of the various transmission line route lengths by jurisdiction. Table 3 Breakdown of interconnector option line lengths (km) Option SA QLD NSW VIC TOTAL B 350 1,100 1,450 C.3 210 706 916 C.3ii 210 806 1016 C.3iii 210 706 916 D 270 240 510 Interconnector routes shown in Figure 1 are indicative only (straight-line) and have been included for illustrative purposes. The figure shows major transmission lines in the NEM but does not delineate between the capacities of these lines for simplicity. Additional variants of the SA-NSW interconnector option have been assessed, which include an HVDC option as well as a variant that runs via Kerang in Victoria (which was proposed in submissions). All variants of the SA-NSW interconnector now also include an augmentation between Buronga and Red Cliffs in Victoria. Page 7 of 13

Figure 1 - Overview of the options (and variants) assessed While a stylised straight-line representation of interconnector routes has been included in the figure above for simplicity, detailed desk-top assessments have been undertaken to identify notional routes for each option. Indicative estimated costs of land and easement acquisition have been factored into the cost estimates for the various interconnector options based on this analysis. 3. Estimating Methodology The cost estimating methodology for the various components of the interconnector options considered is described below. 3.1 Substations Substation costs were estimated by each Jurisdictional Planning Body (JPB) for the substations within its jurisdiction, based on defined technical requirements/ high level specifications. The relevant JPBs are ElectraNet in South Australia, AEMO in Victoria, Powerlink in Queensland and TransGrid in New South Wales. The cost estimates for special purpose equipment were derived as follows: (a) (b) For static var compensators (SVCs); shunt reactors/ shunt capacitors; synchronous condensers and series compensation, each JPB defined the size of equipment required for their networks (where needed) and sought high level estimates from reputable suppliers; For phase shifting transformers, AEMO and TransGrid defined the size required for their networks (Victoria, New South Wales) and sought high level estimates from reputable suppliers. Page 8 of 13

(c) (d) (e) For power transformers/ auto-transformers, each JPB defined the size of power transformers/ auto-transformers required for their networks (where needed) and sought high level estimates from reputable suppliers; For the HVDC converter stations Powerlink defined the size of HVDC converter stations required and sought high level estimates from ABB, Siemens and GE. The cost used in the PACR is derived from averaging the prices submitted by the three vendors. It is assumed that the cost estimates are applicable both for Queensland, New South Wales as well South Australia (for the relevant HVDC Option). For the System Protection Schemes, ElectraNet defined the scope and requirements and developed a high level estimate based on inputs from relevant vendors. 3.2 Transmission lines (a) ElectraNet developed a high level specification for potential interconnector transmission lines namely: Double circuit 275 kv AC; Double circuit 330 kv AC; and 400 kv HVDC. (b) (c) (d) (e) (f) (g) (h) The high level specifications were discussed and agreed with the relevant JPBs, in accordance with proposed interconnector links between South Australia and respective eastern states; The various transmission line routes (corridors) were developed by Mipela Geo Solutions. These form the basis for the route lengths used in the cost estimates of the various options. ElectraNet obtained cost estimates for each of the route options from the relevant host TNSPs (AEMO, Powerlink and TransGrid). Cost estimates were also sought from reputable Australian companies (vendors) with proven experience and capabilities in building transmission lines; The high level estimates received from external parties were reviewed by ElectraNet and some additional allowances (to cover the broader project scope, where such may not have been allowed by the vendor) were included in the overall cost estimates. In order to derive an appropriate cost rate that broadly captures the construction market price for the key transmission lines of 400 kv HVDC; 330 kv AC double circuit and the 275 kv AC double circuit lines, stochastic analysis/ simulations (PERT method) were conducted using the JPB and vendor construction data as inputs. The derived 50% probability of exceedance (P50) unit rates form the basis for the overall cost estimate for the relevant transmission lines. Estimates for transmission line components of different voltage levels or configuration (e.g. 220 kv DC and the 330 kv SC transmission line) were provided by the relevant JPB because these components constitute a relatively small portion of the overall transmission line works. Page 9 of 13

(i) The PERT simulations approach and use of P50-equivalent estimates was endorsed by the relevant JPBs as a plausible method for deriving statistically relevant average market prices. Table 3 sets out the cost rates/km for the various route options were developed for the purpose of the June 2018 draft report (PADR). Table 4 Transmission line $/km rates used in PADR ($m 2017-18) Option Description PERT $m/km NSW options 330 kv DC AC Line 1.013 Victoria option 275 kv DC AC Line 0.891 Queensland option 400 kv HVDC Line 0.716 4. Independent Review of Transmission Line Costs Following the publication of the PADR, ElectraNet received a number of submissions commenting on the underlying assumptions and approach used in deriving the resultant market cost rates. In response to submissions, ElectraNet engaged Jacobs to undertake an independent review of cost estimates, including: SA-QLD 400 kv HVDC line costs SA-NSW 330 kv HVAC line costs SA-VIC 275 kv HVAC line costs The Jacobs report is published alongside the PACR and this Cost Estimate Report and recommends the following line rates per km for the various transmission line components 6. Table 5 Jacobs recommended transmission line $/km rates ($m 2017-18) Line ElectraNet PADR PERT cost $m/km Jacobs adjusted PERT cost $m/km New South Wales 330 kv HVAC option 1.013 1.061 Victoria 275 kv HVAC option 0.891 0.964 Queensland 400 kv HVDC option 0.716 0.655 These line rates recommended by Jacobs have been escalated into $2018-19 and used for deriving the transmission line cost estimates in Table 2 used in the PACR. 6 ElectraNet Transmission Line Cost Review, Jacobs, February 2019. Page 10 of 13

5. Basis of Estimate This basis of estimate serves to clearly define the planning basis, cost basis, risk basis, assumptions informing the capital cost estimates together with exclusions to the capital cost estimates. 5.1 Planning Basis Contracting strategies for engineering, design, procurement, construction, resourcing and project execution plans, project schedule and key milestone dates are, at the time of writing, not fully established. However, ElectraNet has developed a project plan and a high level schedule, including preliminary planning as part of the PACR preparation. 5.2 Cost Basis The source of all pricing used in the estimate is from a range of cost intelligence resources including our own corporate cost database, industry vendors, industry subject matter experts in infrastructure and utilities sector, cost modelling, and our own capital infrastructure pricing experience. Prices are based on 2018-19 costs for labour, materials and equipment and no allowance for future price changes is included in the price estimate. 5.3 Risk Basis No allowance has been made for any risk related cost elements or contingency amounts. 5.4 Class 4 Estimate In line with AACE International Recommended Practice and Estimate Classification, this estimate is classified as Class 4, as it is preliminary in nature. Class 4 estimates are generally prepared based on limited information and subsequently have fairly wide accuracy ranges. They are typically used for concept studies, project screening; determination of feasibility; concept; evaluation; and preliminary budget approval. Typically, engineering design is from 1% to 15% complete. Capacities are preliminary. Plant location is approximate. Soils/hydrology/ground condition data not developed or assessed. Project plans are preliminary. Project schedule is preliminary. Work Breakdown Structure is preliminary or not existing. However, contracting strategy is stated such as separate design and construct contracts, turnkey design and construct contracts. The degree of Project scope definition is 1% to 15% of full project definition. End Usage: Class 4 estimates are prepared for a number of purposes, such as: concept studies; strategic planning; project screening; alternative scheme analysis; undertaking of economic and/or technical feasibility analysis; and preliminary budget approval. Page 11 of 13

Estimating Method: Class 4 estimates generally use stochastic estimating methods such as equipment factors (building blocks and schedules of rates), and other parametric and modelling techniques. We have engaged with industry partners for budget costing and verification or our estimates. Expected Accuracy Range: Typical accuracy ranges for Class 4 estimates are -15% to -30% on the low side, and +20% to +50% on the high side, depending on the complexity of the project, level of uncertainty of e.g. ground conditions, exchange rates, equipment/contractor availability and appropriate reference information. Accuracy ranges could exceed those indicated in unusual circumstances. 5.5 Costs from third parties Costs included from third parties, in particular the TNSP Jurisdictional Planning Bodies (JPBs) costs are included in good faith. 5.6 General Project Data Level of project definition is estimated at 15% Capacity of facility preliminary Plant location approximate Line routes - preliminary Soil & hydrology assumed Project Plan preliminary Project schedule preliminary Preliminary single line diagram and layout used Contracting Strategy - assumed 5.7 General Pricing Assumptions All costs are based on 2018/19 prices for labour, materials and equipment hire The following approvals and/or agreements are envisaged to be in place at project commencement: 1. necessary State and Commonwealth environmental approval for the project 2. necessary land access or easement agreements are in place with landholders or other third parties 3. necessary heritage agreements with traditional owners for access are in place and no Native Title issues Medium footings Reasonable ground conditions exact site locations TBA No access problems exact site locations TBA Page 12 of 13

Competitive tender process Reasonable market conditions Reasonably level sites Selected sites are close to roads say not more than 200 m distant 5.8 Cost escalations The Jurisdictional Planning Bodies agreed that requisite cost escalations, shall be based upon the Consumer Price Index (CPI) 5.9 Land & Easement costs ElectraNet engaged a consultant (Public Private Property) to provide indicative costs for land & easement acquisition for each of the proposed route options. 5.10 Exclusions The following are excluded from the cost estimates and could impact on the final project cost outcomes: GST Future cost escalation beyond Q2 2019 Deep network augmentation Unexpected poor ground conditions (no geotechnical tests/analysis has been conducted) Cost of decommissioning and site rehabilitation at end of life Civil works / trenching through rock Staging costs (assumed each project option carried out in one continuous effort) Control schemes (unless otherwise stated) Generation support (unless otherwise stated) System/critical spares (unless otherwise stated) Risk contingency allowance to cater for design and construction risks Maintenance costs (i.e. costs presented are CAPEX only) Page 13 of 13