Riverbank AAP, CA. Conveyance Progress Report

Similar documents
NWS Seal Beach Detachment Concord. Department of the Navy Base Realignment and Closure Program Management Office Laura Duchnak October 10, 2006

DRAFT FINAL FINDING OF SUITABILITY TO TRANSFER (FOST) Little Patuxent River Parcel. October 16, 2013

BRAC 2005: Cleanup Privatization

MEMORANDUM SUPPLEMENTAL INFORMATION REGARDING RLRA OPTIONS FOR THE DISPOSITION AND REUSE OF THE FORMER RIVERBANK ARMY AMMUNITION PLANT

A Regulator s Guide To Base Realignment and Closure

Institutional Controls at BRAC Sites: The Next Battleground

Technical Information Paper No

TRANSFER OF SURPLUS PROPERTIES USING NEW LEGISLATIVE AUTHORITIES

U.S. Department of Housing and Urban Development Office of Public and Indian Housing

Brownfields. Jere Trey Hess, Chief Groundwater Assessment & Remediation Division April 2015

FINDING OF SUITABILITY TO TRANSFER (FOST) TWIN CITIES ARMY AMMUNITION PLANT RAMSEY COUNTY, MINNESOTA


Tonawanda Brownfield Opportunity Area

OAKLAND OVERSIGHT BOARD MEMORANDUM

FLORIDA S BROWNFIELDS REDEVELOPMENT PROGRAM

FINDING OF SUITABILITY TO LEASE (FOSL)

FOR SALE SINGLE TENANT NET-LEASED PROPERTY

ALLEGANY COUNTY LAND BANK CORPORATION LAND ACQUISITION AND DISPOSITION POLICIES AND PRIORITIES

Form SF298 Citation Data

FINDING OF SUITABILITY TO TRANSFER NAVAL RESERVE CENTER DULUTH, MINNESOTA

Barbara County Housing Element. Table 5.1 Proposed Draft Housing Element Goals, Policies and Programs

THE REGULATIONS GOVERNING SOIL DISPLACEMENT AND DISPOSAL IN THE EAST HELENA SUPERFUND AREA IN LEWIS AND CLARK COUNTY, MONTANA.

FACT SHEET Brownfields Cleanup Program (BCP) KEY DEFINITIONS (see also ECL )

The Challenge of Brownfield Redevelopment: Addressing Contamination and Perception

APPROVED LONG RANGE PROPERTY MANAGEMENT PLAN MAJOR APPROVED DEVELOPMENT PROJECT HUNTERS POINT SHIPYARD/CANDLESTICK POINT

QUIT CLAIM DEED OF CONVEYANCE

ECONOMIC DEVELOPMENT AUTHORITY[261]

The Brownfields Program

PROCEDURES, RESPONSIBILITIES, AND GUIDELINES FOR THE EFFECTIVE CLOSING OF MILITARY INSTALLATIONS. Prepared By: Douglas McCutchen

Redevelopment Plan Feasibility Study Mile Lane Army Reserve Center Middletown, CT DRAFT JULY 29, 2008

rownfield redevelopment for housing

APPENDIX "B" STANISLAUS COUNTY FARMLAND MITIGATION PROGRAM GUIDELINES

No warranty or representation, expressed or implied, is made as to the accuracy of information contained herein, and same is submitted subject to

CURRENT THROUGH PL , APPROVED 11/11/2009

The Continuously Evolving Land Use Control Climate in FUSRAP

Real Estate Development and Reuse

CHAUTAUQUA COUNTY LAND BANK CORPORATION

Real Estate. Economic & Community Development. Real Estate Approved General Government Operating Budget. Real Estate. Heritage Land Bank

GUIDANCE FOR LEAD-BASED PAINT HAZARD MANAGEMENT DURING TRANSFER OF ARMY REAL PROPERTY

Meruelo Maddux Properties

METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN Phone (651) TDD (651)

Santa Barbara County Parks Department s Response to the Santa Barbara County Civil Grand Jury Report on: Jalama Beach County Park FINDINGS

Redevelopment Plan Feasibility Study Mile Lane Army Reserve Center Middletown, CT

Assessment. Guidance CLEANUP. Liability Release. Petroleum Brownfields Eligibility Letter Remediation Oversight. Project Endorsement

Environmental Management Chapter

ATTACHMENT 1 ENVIRONMENTAL PROTECTION PROVISIONS

Steffanie C. Dorn, Brownfields Coordinator City of Greenwood SC Council of Development Finance Agencies Project Marketplace November 4, 2015

CRS Report for Congress

Housing Commission Report

Hazardous Materials in Project Development Additional Guidance

The phasing schedule set forth in NJ.A.C. 5:93-5.6(d) is identical to that set forth in COAH's current rules at5:97-6.4(d).

Site Selection and Acquisition

Ohio EPA Guidance - VAP Environmental Covenants May 2005 Updated February 2012

developed industrial lots. They are expanding due to a current need. A developed

Sustainable development for the future of Arkansas

APPROVED LONG-RANGE PROPERTY MANAGEMENT PLAN MAJOR APPROVED DEVELOPMENT PROJECT MISSION BAY

Draft for Public Review -- June 23, 2014

9 Hanna Ave Establishment of Public Lane System

Project Area Tax Map. 94 Washington Street Hoboken, NJ (201) fax (201)

OFFICE OF THE CITY ADMINISTRATIVE OFFICER

Section 7: Plan Implementation Considerations As the Midcoast Regional Redevelopment Authority (MRRA) focuses on

North American Realty Advisory Services, L.P.

IOWA SOLID WASTE PROGRAM ENVIRONMENTAL COVENANT

CONCEPTUAL FRAMEWORK FOR DEVELOPMENT. (Mixed-Use Revitalization Project for Candlestick Point and Parcels A-3 and B-E of the Hunters Point Shipyard)

GENERAL PURPOSES OF ZONES

Division of Waste Management

Delaware River Basin Comprehensive Flood Risk Management Interim Feasibility Study and Integrated Environmental Assessment for New Jersey

MEMORANDUM OF AGREEMENT BETWEEN THE UNITED STATES DEPARTMENT OF THE ARMY AND THE JO-CARROLL DEPOT LOCAL REDEVELOPMENT AUTHORITY

Chapter XII BROWNFIELDS & BUSINESS TRANSACTIONS. A. Business Transactions

EVALUATION AND APPRAISAL REPORT OF THE CITY OF FELLSMERE COMPREHENSIVE PLAN APPENDIX D HOUSING ELEMENT

2014 ANNUAL REPORT. COMMERCIAL DEVELOPMENT p RESIDENTIAL DEVELOPMENT p. 5 RETAIL DEVELOPMENT p. 5

Preparing for Negotiations: The Environmental Lawyer s Checklist In Oil and Gas Transactions

04/19/2018 TITLE V, FEDERAL SURPLUS PROPERTY PROGRAM FEDERAL REGISTER REPORT FOR 04/20/2018 SUITABLE / AVAILABLE PROPERTIES BUILDING NEW YORK

McMULLIN AREA GROUNDWATER SUSTAINABILITY AGENCY

Office Development Annual Limit Program Status Update

REVISED REQUEST FOR REDEVELOPMENT PROPOSALS (RFP) 62 nd STREET INDUSTRIAL PARK IN THE UPPER LAWRENCEVILLE NEIGHBORHOOD OF THE CITY OF PITTSBURGH

THE COMMUNITY REDEVELOPMENT AGENCY OF THE CITY OF LOS ANGELES, CALIFORNIA M E M O R A N D U M

State of Florida Department of Transportation EXHIBIT A, SCOPE OF SERVICES

LEASE DISPOSITION AND DEVELOPMENT AGREEMENT

CHEROKEE PLACE APARTMENTS

DEPARTMENT OF THE ARMY U.S. Army Corps of Engineers Washington, DC Regulation No May 2015

ENVIRONMENTAL QUESTIONNAIRE AND DISCLOSURE STATEMENT

Public-Private Partnerships: A P3 Overview. bae urban economics

Goodwill donation express for sale

BRAC 05 LRA OUTREACH PROCESS

Prepared for Members and Committees of Congress

BRAC 05 LRA OUTREACH PROCESS

Guidelines and Procedures for the Disposal of Personal Property

Q: When will the first SID payment become due?

Case 1:17-cv REB Document 3 Filed 07/25/17 USDC Colorado Page 1 of 12 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLORADO

Base Realignment and Closure (BRAC): Transfer and Disposal of Military Property

Economic Effect of Brownfield Proximity to Branch Banking Deposit Trends

CONDITIONAL GRANT COMMITMENT AND SITE LEASE FOR REHABILITATION OF VERMONT HOUSE

Baldwin Park Successor Agency Long-Range Property Management Plan. Prepared for:

Amended Long Range Property Management Plan. Successor Agency to the Former Redevelopment Agency of the City of Stockton

Tejon Ranch Conservation and Land Use Agreement Executive Summary

Ohio EPA Guidance - VAP Environmental Covenants Updated July 2015

DONLON REALTY. KEVIN H. DONLON Land Broker CA License PHONE (209) FAX (209)

Promoting Redevelopment Projects with Environmental Barriers in Urban Communities

LAFCO APPLICATION NO LINDE CHANGE OF ORGANIZATION TO KEYES COMMUNITY SERVICES DISTRICT

Transcription:

Riverbank AAP, CA Conveyance Progress Report As of 1 October 2017

Page 2 1 October 2017 BRAC 2005 TABLE OF CONTENTS Summary 2 Environmental Cleanup 3 Reuse Plan 4 Programmatic Agreement 4 Property Conveyance Plan 5-6 Key Milestones Achieved 7 BRAC 2005 Recommendation The 2005 Base Realignment and Closure (BRAC) Commission recommended the closure of Riverbank Army Ammunition Plant, CA (RBAAP) and the relocation of the artillery cartridge case metal parts functions to Rock Island Arsenal, IL (RIA). History Riverbank Army Ammunition Plant was built in 1942. It began operation in 1943 as an aluminum reduction plant for military supplies and closed in 1944. It was used as a storage facility until 1952, when it was reopened as a Government-Owned, Contractor-Operated (GOCO) metal parts fabrication facility. Operated by Norris Industries via a Facilities Use Contract, RBAAP met surge requirements generated by the Korean, Vietnam, and Middle East wars, producing cartridge cases for land and naval artillery. Active plant workforce population varied from a few hundred to several thousand depending upon the military production requirements. In the 1990s, as production waned, the Army leased excess space to private tenants through the U.S. Army s Armament Retooling and Manufacturing Support (ARMS) program. Current Status BRAC law shifted RBAAP s military mission to RIA, and RBAAP was closed on 31 March 2010. The movement, relocation, refurbishment, and installation of the metal parts fabrication capability to RIA was completed in August 2011. To date, the former RBAAP acreage has not been transferred. Plans call for the transfer of an 80-acre parcel on the main plant plus a 28-acre parcel outside the fence, going to the Riverbank Local Reuse Authority (RLRA) via a no-cost Economic Development Conveyance (EDC). Other land parcels will be offered for public sale. Property Description RBAAP is located at the southeastern edge of the City of Riverbank, CA, five miles north of Modesto, placing it 75 miles east of the San Francisco Bay area and 75 miles south of Sacramento in the central San Joaquin Valley. The 172-acre complex is a mix of industrial and commercially zoned parcels. There is an 80-acre industrial park in the heart of the complex surrounded by 63 acres of undeveloped property and an additional 29-acre parcel along the Stanislaus River. The site contains 114 structures with 700,000 square feet of industrial buildings. Caretaking Status The Army has one Federal employee at RBAAP at this time. Former Riverbank Army Ammunition Plant, Modesto, CA

BRAC 2005 1 October 2017 Page 3 Main Plant Area Environmental Cleanup On 21 February 1990, RBAAP was listed as a Superfund site and placed on the Environmental Protection Agency (EPA) National Priorities List (NPL). Currently, the primary contaminants of concern are Polychlorinated Biphenyls (PCBs) (originating from decrepitating galbestos and oilbased PCBs in soil) and chromium in groundwater. Of the 13 sites requiring environmental cleanup, five have reached response complete or remedy in place status. Most of the work on the remaining eight sites is projected for FY17-FY25 with long-term monitoring requirements continuing after that. Munitions were not manufactured, tested, or assembled at RBAAP, and active firing conducted at the site was limited to a small, irregularly used pistol range. Therefore, there is no unexploded ordnance (UXO), munitions and explosives of concern (MEC), or leadbased contamination. In an effort to ensure the risk to human health and the environment is minimal, survey, characterization, and cleanup efforts continue. Environmental cleanup of PCBs due to galbestos will be accomplished via two Environmental Services Cooperative Agreements (ESCA). The first of these (Phase I) commenced 2 nd Quarter, FY2014. The second ESCA, awarded 29 April 2016, addresses the removal of PCB surface contamination within the structures and removal of galbestos panels on the exterior of the structures. Expected completion is in 2019.

Page 4 1 October 2017 BRAC 2005 Reuse Plan The RBAAP reuse plan was approved in November 2008. In summary, the plan envisions the 143- acre main RBAAP site will continue to function primarily as an industrial park, along with some limited convenience retail uses, while the 29-acre evaporation/percolation pond site will be sold by the Army for agricultural use. This approach is consistent with the vision, goals, and objectives of this Reuse Plan, which were developed through consultation with community members, stakeholders, and current tenants. It is also generally consistent with the land use designations proposed in Riverbank s Draft 2025 General Plan. With job creation and current tenant expansion being the top priorities for the community, no other significant land uses were considered viable in reaching the community goals. It is expected that new tenants will include a wide variety of manufacturing, storage, and repair businesses, similar to the businesses currently on the site. Some of these new tenants may require a limited amount of office space as well as space for research and development (R&D) activities to support their manufacturing operations. Limited retail uses are also proposed for two portions of the site. The figure below is annotated with types of new businesses for each sector. Programmatic Agreement, Section 106 There is no requirement for a Programmatic Agreement at the former Riverbank Army Ammunition Plant.

BRAC 2005 1 October 2017 Page 5 Parcel Name Property Conveyance Plan The former Riverbank Army Ammunition Plant consists of 172 acres, which includes a 143-acre industrial parcel and a separate 29-acre parcel. Currently, the former facility is occupied and operated by the Riverbank Local Redevelopment Authority (RLRA) via a lease administered by the Sacramento office of USACE. Plans are for the Army to convey the main plant area of 80 acres to the RLRA via a no-cost Economic Development Conveyance (EDC). Notably, this area has been sub-leased to various private commercial entities by the RLRA. In addition, 28-acre Parcel B will also convey via a no-cost EDC. Plans call for its use as a green industry business park. The Army plans to dispose of all remaining parcels (1, 1a, 2, 2a, and 4) via public sale. An earlier effort to market these parcels via the GSA failed; there were no bids. USACE is negotiating with a commercial broker in an effort to revitalize this effort. Although some interest has been expressed recently by possible buyers, the unanticipated discovery of contamination on Parcels 1 and 1a requires additional cleanup. This cleanup is expected to be completed in 2019. Property Conveyed (0 of 172 total acres) and Projected Parcel Acres Disposal Date Parcel Recipient Conveyance Authority B 27.7 1 st Qtr FY18 RLRA No-cost EDC 4 (Evaporation/Percolation Ponds) 28.9 3 rd Qtr FY18 TBD Public Sale Main Plant 79.9 3 rd Qtr FY18 RLRA No-cost EDC 2 19.6 2 nd Qtr FY19 TBD Public Sale 2a 3.3 2 nd Qtr FY19 TBD Public Sale 1 (End Cap) 8.5 2 nd Qtr FY19 TBD Public Sale 1a (End Cap) 4.4 2 nd Qtr FY19 TBD Public Sale

Page 6 1 October 2017 BRAC 2005 Property Conveyance Plan Main Plant area parcels (143 Acres) Parcel B (27.7 Acres) Parcel 4 (28.8 Acres) Main Plant (79.9 Acres) Parcel 4 (E/P Ponds) near Stanislaus River (28.8 Acres) Parcels 1 and 1a (both end cap parcels) - 12.9 acres. Conveyance by public sale has been delayed by the unanticipated discovery of oil-related PCB contamination. Testing for nature and extent is complete. The cleanup contract was awarded 5 September 2016 with completion expected in 2019. Parcels 2 and 2a (north of the main plant area) - 22.8 acres. Conveyance by public sale. Subsequent to the unexpected discoveries of oil-based PCB contamination in parcels 1 and 1a, confirm-or-deny testing of 2 and 2a was warranted. Sampling is complete with negative results. Parcel B (northernmost parcel of main plant area) - 27.7 acres. Conveyance by EDC in conjunction with Main Plant area. Currently used as pasture; there is no indication of contamination. Parcel 4 (Evaporation/Percolation Ponds) - 28.8 acres are located about 1 ½ miles north of the main plant area along the Stanislaus River. Originally part of the property planned to be conveyed to the RLRA, that body chose to excise the parcel from its development plans. As with the other parcels, the Army projects disposal via public sale. Private entities have expressed interest in purchasing this area. Testing has confirmed its suitability for transfer for agricultural use. Main Plant - 79.9 acres. Conveyance by no-cost EDC and FOSET. Site is contaminated with PCBs associated with decrepitating galbestos siding and roofing. Cleanup efforts are being conducted via two ESCAs. First ESCA (equipment) complete; second ESCA (siding, building surfaces, and grounds) was awarded 29 April 2016 with anticipated completion in 2019.

BRAC 2005 1 October 2017 Page 7 Key Milestones Achieved RBAAP closed 31 March 2010. The Riverbank Local Reuse Authority (RLRA) Reuse Plan was approved in 2008. Record of Decision (ROD) approved April 2010 Equipment transferred (rehabilitation en route) from RBAAP to RIA, IL and reported mission ready 1 September 2011. FOST/FOSET: Original Finding of Suitability of Transfer (FOST) signed April 2010; subsequent discoveries (currently undergoing testing) have required an amendment. DUSD approved a without consideration Economic Development Conveyance on 12 February 2013. The Finding of Suitability Early Transfer (FOSET) is undergoing detailed revisions IAW comments and requirements from the California regulators. The facility for relocation of metal parts fabrication line (shell casings for Army Stryker & USN artillery) at Rock Island Arsenal, IL met BOD on 18 April 2010 and SRD on 30 May 2010. Confirmatory tests and evaluations of production line and items was completed on 31 August 2011.