Community Development Department

Similar documents
Community Development Department

Community Development Department

Planning and Economic Development Department

AGENDA REGULAR VILLAGE BOARD MEETING

RESOLUTION NO. CONTAINING APPROXIMATELY 587 SQ.FT. RD:EEH:LCP

Explanation: Bids were opened and publicly read on February 13, 2018, for Project #1283 with the following results:

DIVISION 2 - CONSTRUCTION PLAN AND MISCELLANEOUS REQUIREMENTS

Planning & Economic Development Department

Planning and Economic Development Department

Planning Commission Staff Report

STAFF REPORT Administrative Subdivision Hearing West 150 South Street, Parcel # , and

Planning and Economic Development Department

CITY OF CIRCLE PINES SPECIAL ASSESSMENT POLICY

CITY OF EAU CLAIRE, WISCONSIN. SPECIAL ASSESSMENT POLICY (Dated: November 8, 2016)

DETAILED GRADING PLAN CHECKLIST (TEARDOWN/REDEVELOPMENT) Updated: 12/12/2017

REQUEST FOR PROPOSAL FOR ENGINEERING DESIGN SERVICES. Channel Reconstruction at Short Hills Garden Apartments Site Millburn, New Jersey

FOCUS ENGINEERING, inc.

S U B D I V I S I O N AGREEMENT

TOWN OF MAIDEN. July 17, 2017 MINUTES OF REGULAR MEETING

CHARTER TOWNSHIP OF CALEDONIA COUNTY OF KENT, MICHIGAN. at the Township and Village Hall, 8196 Broadmoor Avenue, Caledonia, Michigan on the

AGENDA ITEM EXECUTIVE SUMMARY

REQUEST FOR COUNCIL ACTION

CHAPTER 18 PUBLIC WORKS

February 11, The following Councilmembers were present: Brown, Dagg, Kajewski, Hahn and Sollom. Dagg chaired the meeting.

May 20, White Pines Civic Association 4N150 Pine Grove Bensenville, IL Dear Board of Directors,

ALBEMARLE COUNTY SERVICE AUTHORITY

ORANGE TOWNSHIP SIDEWALK CONSTRUCTION, REPAIR AND MAINTENANCE POLICY

COMMUNITY DEVELOPMENT AND RESOURCES COMMISSION OF THE CITY OF ATWATER

WRITTEN DECISION OF THE HAYDEN CITY COUNCIL REGARDING MAPLE GROVE PRELIMINARY SUBDIVISION APPLICATION (SUB-0013) HAYDEN SIGNATURE, LLC

RECOMMENDATION. TO: CITY COUNCIL Date: APRIL 10, 2006

Chapter 510 STREETS, SIDEWALKS AND OTHER PUBLIC PLACES

RFP # Request for Proposals Canyon Pointe Parking Lot Replacement

FEASIBILITY REPORT FOR PROPOSED ROAD IMPROVEMENT PROJECT OF OLD VIKING BOULEVARD NOWTHEN, MINNESOTA DECEMBER 6, Prepared by:

ORDINANCE NO BOROUGH OF ROSELAND COUNTY OF ESSEX, STATE OF NEW JERSEY AN ORDINANCE RESCINDING ORDINANCE NO

DETAILED GRADING PLAN CHECKLIST (TEARDOWN/REDEVELOPMENT)

Chapter 3 FINANCE, TAXATION, AND PUBLIC RECORDS

CHAPTER 620. [History: Repealed and Recreated by Ord ]

DEVELOPMENT AGREEMENT Jefferson Street Townhomes (SP 13-09) Jefferson Street Reconstruction

AGENDA ITEM SUMMARY BUSINESS OF THE CITY COUNCIL CITY OF GOLDEN, COLORADO. Quasi Judicial Matter

CITY OF WAUWATOSA 7725 WEST NORTH AVENUE WAUWATOSA, WI Telephone: (414) Fax: (414)

REGULATIONS OF WALLER COUNTY, TEXAS

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM

1. The reason provided for the opposing votes was that the two commissioners wanted something else to be developed on their parcel.

SECTION 7000 LAND DEVELOPMENT REQUIREMENTS

August 13, The meeting was called to order at 7:00 p.m. by Mayor Docimo. The meeting was advertised in the following manner:

FINAL SUBDIVISION AND LAND DEVELOPMENT PLAN CHECKLIST. Plan Name. Applicant's Name:

RIVERDALE CITY PLANNING COMMISSION APPLICATION FOR RESIDENTIAL SUBDIVISION SITE PLAN APPROVAL

MINUTES PLANNING AND ZONING COMMISSION FEBRUARY 9, 2016 REGULAR MEETING

COUNTY OF EL DORADO, CALIFORNIA COMMUNITY DEVELOPMENT SERVICES DEPARTMENT OF TRANSPORTATION NOTICE TO BIDDERS

City of Whittier Penn Street, Whittier, California (562) Fax (562)

RESOLUTION TO FORM THE REDSTONE PARKWAY BENEFIT DISTRICT

Condominium Unit Requirements.

VILLAGE BOARD MEETING STAFF REPORT

VILLAGE OF VILLA PARK 20 South Ardmore Avenue, Villa Park, Illinois 60181

Chapter 46 STREETS, SIDEWALKS AND OTHER PUBLIC PLACES*

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT

DATE: May 16, Honorable Mayor City Council Members. Laura Holey, Planner

Alvarez Engineers, Inc.

March 12, The meeting was called to order at 7:00 p.m. by Mayor Docimo. The meeting was advertised in the following manner:

Ordinance No. 94-~ AN ORDINANCE APPROVING THE PURCHASE OF BICYCLE PATH EASEMENTS

Plan and Zoning Commission Review Process

WORK SESSION October 9, 2018

DEVELOPMENT POLICY INFRASTRUCTURE GUIDELINES FOR NEW DEVELOPMENT

OAKLEY -~- STAFF REPORT CA LIFO RN I A. To: Agenda Date: 06/28/2016 Agenda Item: 3.3. Date: Tuesday, June 28, Bryan H. Montgomery, City Manager

PRELMINARY PLAT CHECKLIST

DECLARATION OF RESTRICITONS AFFECTING EWING PLACE SUBDIVISION SECTION 3

MEMORANDUM. TERESA McCLISH, COMMUNITY DEVELOPMENT DIRECTOR

Staff Report to the North Ogden Planning Commission

MEMORANDUM CITY COUNCIL TERESA MCCLISH, COMMUNITY DEVELOPMENT DIRECTOR ROBIN DICKERSON, CITY ENGINEER

ORDINANCE NO

PUD, HPUD, OSC Rezoning & Conceptual Plan Application (Planned Unit Development, Haggerty Road Planned Unit Development, Open Space Community)

City of Lafayette Staff Report

CHARTER TOWNSHIP OF KALAMAZOO KALAMAZOO COUNTY, MICHIGAN ORDINANCE NO. KALAMAZOO CHARTER TOWNSHIP SIDEWALK ORDINANCE

AGREEMENT. between the COUNTY OF SAN MATEO, a political subdivision of the State of Califoka,

ADMINISTRATIVE REGULATION AR: DATE APPROVED July 14, 2009 ORIGINATING DEPARTMENT:

RESOLUTION NO. R RESOLUTION APPROVING A STORM SEWER EASEMENT AGREEMENT

LETTER OF TRANSMITTAL

Community Development Department

10.a. Staff Report. Date: July 12, City Council. Valerie J. Barone, City Manager

Staff Report to the North Ogden City Council

Parkland-Spanaway-Midland LUAC - Agenda

STORMWATER MANAGEMENT SYSTEM AND FACILITIES

VERGENNES TOWNSHIP, KENT COUNTY, MICHIGAN ORDINANCE AMENDMENT Ordinance Adopted May 17, 2004

ARTICLE 13 CONDOMINIUM REGULATIONS

SECTION WATER SYSTEM EXTENSION

DECLARATION OF RESTRICITONS AFFECTING EWING PLACE SUBDIVISION SECTION 2

Chapter 115 SUBDIVISION OF LAND

2018 Street and Utility Improvement Project. Assessment Hearing Open House October 02, 2018

At Risk Building Permit (Revised 3/9/15)

City Projects Concepts, Costing & Construction

MEMORANDUM. 1. Approve additional expenses in the amount of $29,685 for additional work on the 2015 Street Repair project;

ARTICLE 7 UTILITIES AND EASEMENTS

CITY OF MARSHALL SPECIAL ASSESSMENT POLICY (Originally Adopted: October 18, 2004) (First Revision: August 1, 2005)

EASEMENT AGREEMENT. hereinafter called Grantor, (whether grammatically singular or plural) and the:

13-2 SUBDIVISION PLANS AND PLATS REQUIRED EXCEPTIONS Subdivision Plats Required To be Recorded

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM

VILLAGE OF ORLAND PARK

CITY COUNCIL AGENDA Monday, April 10, 2017 *********** 6:30 p.m. (Scheduled to be broadcast on Channel 16)

AGENDA BILL. Beaverton City Council Beaverton, Oregon BUDGET IMPACT

HARDYSTON TOWNSHIP MUNICIPAL UTILITIES AUTHORITY

Transcription:

Community Development Department SUBJECT: Consideration of a Resolution and a recommendation to (1) award a bid to DiMeo Brothers, Inc., of Elk Grove Village, Illinois, for the Happy Hollow & Rebecca Improvement Project ( Project ) in the amount of $2,473,125.00, plus an eight percent (8%) contingency, for a total budget of $2,670,974.00; (2) enter into an Easement Agreement with School District 30 for the Water Main Improvement as part of the Project. Project: E14-34/E15-55 AGENDA ITEM: 9.b.v. MEETING DATE: March 15, 2016 VILLAGE BOARD REPORT TO: Village President and Board of Trustees FROM: Joe Kenney, PE, Community Development Director, (847) 904-4313 THROUGH: Todd Hileman, Village Manager PURPOSE AND ACTION REQUESTED: Staff is requesting that the Village Board approve a Resolution and recommendation to award a contract to DiMeo Brothers, Inc. of Elk Grove Village, Illinois, in the amount of $2,473,125.00, plus an eight percent (8%) contingency, for a total budget of $2,670,974.00 to construct the Happy Hollow & Rebecca Improvement Project ( Project ). Staff is also requesting Village Board consideration of a Resolution and recommendation to enter into a Water Main Easement Agreement with School District 30 for the construction of water main piping located within a proposed easement on Willowbrook School ( School ) parking lot (District 30). BACKGROUND: The proposed project is located on: Happy Hollow Road from Maple Leaf Lane to Greenwood Road, Rebecca Lane from Happy Hollow Road to Greenwood Road, and along Lawson Road from the school parking lot to the south end (see Attachment 4-Location map). Happy Hollow Road, originally built in the late 1960 s, will be fully reconstructed including replacement of the utilities which are reaching the end of their expected service life. Due to the length of the project, it was divided into two phases. Phase I is scheduled for construction this year and includes construction on Lawson Road, Rebecca Lane, and Happy Hollow Road, from Greenwood Road to Lawson Road. Phase II is scheduled for construction in 1

2017 and includes the remaining section of Happy Hollow Road between Maple Leaf Lane and Lawson Road. The phasing is being coordinated to not impact traffic patterns during the school year. Scope of Work: The following major improvements are planned: A. Storm Sewer Improvements The proposed storm sewer improvements consist of the repair of, and/or addition of, approximately 800 linear feet of storm sewer pipes ranging in size from 12-inch to 27-inch in diameter to improve storm water conveyance within the existing storm sewer system on Happy Hollow Road and Rebecca Lane. The improvements also include the replacement of, and/or addition of, twenty (20) drainage structures. B. Sanitary Sewer Improvements The sanitary sewer improvements on Happy Hollow consist of replacement of the existing sanitary sewer manholes as well as lining of the existing sanitary sewer via trenchless repair methods as part of the FY 2016 Sewer Lining contract. C. Water Main Improvements Water main improvements consist of the installation of approximately 2,600 linear feet of eight (8) inch and 1,700 linear feet of twelve (12) inch Plastic Polyvinyl Chloride water pipe. The new water main will be looped and will replace the existing, deteriorated, approximately 50 year old, water main. The old water main will be abandoned and the new water main will be located along the edge of the roadway pavement, thereby improving future maintenance access and limiting damage to existing landscaping and private driveways. Currently, Willowbrook School is tied into the water main on Happy Hollow Road. This newly upsized and looped system will provide redundancy for the water system and improve fire flows adjacent to the school, meeting recommendations established in the Village s Water Master Plan. As part of the design, the improvements included looping of the water main system through the school parking lot and connecting it to the newly upsized water main system on Lawson. Since the work is within school property, a water main easement agreement is required as part of this project (refer to Attachment #3-Easement Agreement). District 30 approved the easement agreement on February 11, 2016. D. Pavement Improvements Pavement reconstruction on Happy Hollow consists of removal of approximately 7.5 inches of the existing concrete pavement and 4.5 inches of the existing failed base. The pavement will be replaced with an aggregate base material, a 7 inch thick hot-mix asphalt binder course, and 2 inch thick hot-mix asphalt surface course on Happy Hollow Road. The improvements also include the replacement of the existing curb and gutter as well as sidewalk where needed. Pavement improvements on Lawson road and Rebecca Lane consist of (1) pavement patching due to water main work and (2) resurfacing work by grinding of approximately 2 inches of the 2

existing asphalt pavement and placing 2 inches of new pavement surface course. TIMELINE OF PROJECT: Happy Hollow/Rebecca Project Bid notice published in local newspaper - Pioneer Press February 22, 2016 Bid opening date March 1, 2016 Bid award recommendation March 15, 2016 Preconstruction meeting March 28, 2016 Approximate starting date of construction April 1, 2016 Completion of construction August 17, 2017 DISCUSSION: On March 1, 2016, six (6) bids from responsive and responsible bidders for the above-referenced project were submitted to the Village. The contractors and the total bid amounts submitted were as follows: No CONTRACTOR TOTAL BID Phase I & II 1 DiMeo Brothers, Inc. of Elk Grove Village, Illinois $2,473,125.00 2 PirTano Construction Company, Addison, Illinois $2,529,944.30 3 R. A. Mancini, Inc., Lakemoor, Illinois $2,570,799.10 4 Patnick Construction, Inc., Franklin Park, Illinois $2,662,915.30 5 Martam Construction, Inc., Elgin, Illinois $2,850,922.25 6 Campanella & Sons, Inc., Wadsworth, Illinois $3,226,755.80 DiMeo Brothers, Inc. of Elk Grove Village, Illinois was the lowest bidder with a bid price of 2,473,300.00 for Phase I & II. REFERENCES: A. DiMeo Brothers, Inc. of Elk Grove Village, Illinois has a Certificate of Eligibility issued by IDOT for underground utility work. They have performed work in the capacity of the General Contractor and have successfully managed their subcontractors. B. DiMeo Brothers, Inc. of Elk Grove Village, Illinois, has previously worked in the Village of Glenview and all of their work has been satisfactory. BUDGET: This project is recommended by staff and was approved by the Village Board of Trustees during the FY 2016 CIP budget hearings. Since the Project will be constructed in phases, the requested contract approval for the Happy Hollow & Rebecca Lane Improvement Project is: Phase I (2016) - $1,641,170.00, plus an eight percent (8%) contingency, for a total budget of $1,772,463.00, and Phase II (2017) $831,955.00 plus an eight percent (8%) contingency, for a total budget of 3

$898,511.00. The total cost for the Project including contingency is $2,670.974.00. The proposed improvements are to be funded by the Village as follows: PHASE I (2016) Capital Projects Fund: 41080131-572016-WATER $273,147.00 Water Projects Fund: 51080851-572016-WATER $1,417,155.00 Sanitary Projects Fund: 54080851-572016-WATER $82,161.00 PHASE II (2017) Total (Phase I): $1,772,463.00 Capital Projects Fund: 41080131-572017-WATER $600,350.00 Water Projects Fund: 51080851-572017-WATER $240,899.00 Sanitary Projects Fund: 54080851-572017-WATER $57,262.00 Total (Phase II): $898,511.00 Grand Total (Phase I &II): $2,670,974.00 RECOMMENDATION: Staff recommends that the Village Board authorize the Village President to execute the attached Resolution and award a contract for the Happy Hollow & Rebecca Improvements to DiMeo Brothers, Inc., of Elk Grove Village, Illinois, in the amount of $2,473,125.00 plus an eight percent (8%) contingency, for a total budget of $2,670,974.00. Staff, also recommends that the Village Board authorize the Village President to execute the attached Resolution to approve the Water Main Easement Agreement between School District 30 and the Village of Glenview to facilitate the construction of water main piping within an easement on Willowbrook School property as part of the proposed Project. ATTACHMENTS: 1. Contract Resolution 2. Water Main Easement Resolution 3. Water Main Easement Agreement 4. Location Map 4

Attachment 1 Contract Resolution 5

RESOLUTION NO. WHEREAS, the Village of Glenview ( Village ), is a home rule municipality located in Cook County, Illinois; WHEREAS, a bid notice was issued by the Village on February 11, 2016 for construction services (the Services ) relating to the Happy Hollow & Rebecca Improvement Project (the Project ); WHEREAS, the corporate authorities have discussed and considered bids for the Services and DiMeo Brothers, Inc. of Elk Grove Village, Illinois ( DiMeo ), was the lowest qualified responsive and responsible bidder for the Project; and WHEREAS, the corporate authorities have determined that it is in the public interest to enter into a contract with DiMeo for the Services in the amount of $2,473,125.00, plus an eight percent (8%) contingency, for a total budget of $2,670,974.00. NOW, THEREFORE, BE IT RESOLVED, by the President and Board of Trustees of the Village of Glenview, as follows: That the President and Village Clerk are authorized to execute a contract by and between the Village of Glenview and DiMeo Brothers, Inc. of Elk Grove Village, Illinois, for the construction of the Happy Hollow & Rebecca Improvement Project in the amount of $2,473,125.00, plus an eight percent (8%) contingency, for a total budget of $2,670,974.00. PASSED this day of, 2016 AYES: NAYS: ABSENT: APPROVED by me this day of, 2016 ATTEST: Todd Hileman, Village Clerk of the Village of Glenview, Cook County, Illinois James R. Patterson, Jr., President of the Village of Glenview, Cook County, Illinois 6

Attachment 2 Water Main Easement Resolution 7

RESOLUTION NO. WHEREAS, the Village of Glenview ( Village ), is a home rule municipality located in Cook County, Illinois; WHEREAS, the corporate authorities have discussed and considered the Water Main Easement Agreement (the Agreement ) between School District 30 and the Village for the Happy Hollow & Rebecca Improvement Project ( Project ); and WHEREAS, the corporate authorities have determined that it is in the public interest to enter into an intergovernmental agreement with District 30 to facilitate this project. NOW, THEREFORE, BE IT RESOLVED, by the President and Board of Trustees of the Village of Glenview, as follows: That the President and Village Clerk are authorized to execute the Water Main Easement Agreement between the School District 30 and the Village of Glenview to facilitate the construction of the water main improvement that is part of the Happy Hollow & Rebecca Improvement Project. PASSED this day of, 2016 AYES: NAYS: ABSENT: APPROVED by me this day of, 2016 ATTEST: Todd Hileman, Village Clerk of the Village of Glenview, Cook County, Illinois James R. Patterson, Jr., President of the Village of Glenview, Cook County, Illinois 8

Attachment 3 Water Main Easement Agreement 9

10

11

12

13

14

15

16

17

Attachment 4 Location Map 18

ARI DR E 3638 Phase 1 Phase 2 Railroad Village Boundary Parcels 3637 3611 3610 ARI LN 3607 3608 3610 3606 3605 3541 3604 ² 3609 3609 3601 3602 3538 3537 3602 3616 3620 3630 3607 3550 3550 3550 3542 3538 3534 JANNEY RD LAWSON RD 2418 2415 2414 2410 2406 HALINA DR 2405 2440 2436 2422 2420 2418 KEENAN LN MAPLE LEAF DR 2444 2416 2500 3535 3529 3521 3515 3509 3501 3439 3431 3532 3610 3606 3602 3516 3512 3517 3513 3509 3505 3501 3522 3600 3508 3504 3500 3428 3518 3510 3502 3434 3519 3511 3503 2431 2427 2423 2439 2435 2419 2415 2503 2411 2412 2408 2507 2404 2405 3407 3425 3413 3419 3422 3418 3412 2436 2432 2428 2424 2420 2511 2440 3404 2523 2519 2515 REBECCA LN 2400 3346 E2014-0034 2444 2520 2524 STRAWBERRY LN 2312 3324 3330 3336 3340 2448 2437 2433 2429 2425 2421 2528 2532 2536 2540 HAPPY HOLLOW RD 2452 2445 2441 2401 3318 3349 2317 2426 GREENWOOD CT 2424 2430 2318 2312 2422 2350 2432 GREENWOOD RD 2436 2522 2527 2531 2535 2539 2543 3312 3323 3331 3337 3343 2311 2456 3317 2460 2464 2468 2472 2449 2453 2457 3306 3311 2461 2324 2325 2427 2423 2419 2349 2344 2345 2336 2337 2330 2331 2319 2313 2431 2443 MARY KAY LN 2439 2435 3230 3232 2521 2517 2513 2509 2505 2501 3228 3231 3239 3235 3231 3227 0 125 250 500 Feet Happy Hollow 1 inch = 250 feet Rebecca Lane 2340 BRANDE 2334 DR 2328 2322 2316 2310 PHILLIPS DR 3/8/2016 19