Vested Assets Deep Dive Report

Similar documents
Funding Auckland s greenfield infrastructure

Compulsory Land Acquisition Delegations

RESERVE REVOCATION FOR HUNDERTWASSER PROJECT Ruben Wylie - Manager - Infrastructure Planning

Housing Need in South Worcestershire. Malvern Hills District Council, Wychavon District Council and Worcester City Council. Final Report.

Changing a planning condition for delivery times January 2016

Depreciation A QUICK REFERENCE GUIDE FOR ELECTED OFFICIALS AND STAFF

RYEDALE SITES LOCAL PLAN MATTER 3 PROPOSED HOUSING SITE OPTION REF. 116 LAND AT MIDDLETON ROAD, PICKERING BARRATT HOMES & DAVID WILSON HOMES

DRAFT PROPOSED CHAPTER 21 SPECIFIC PURPOSE - FLAT LAND RECOVERY ZONE

Report to INFRASTRUCTURE SERVICES COMMITTEE for noting

RYEDALE SITES LOCAL PLAN MATTER 4 PROPOSED HOUSING SITE OPTION REF. 116 LAND AT MIDDLETON ROAD, PICKERING BARRATT HOMES & DAVID WILSON HOMES

State Highway Revocation: Policy and Guidance

PURPOSE This paper is to update the Audit and Risk Committee on a number of accounting issues that will impact the finalisation of the Annual Report

2017 ROAD ASSET VALUATION

FINANCIAL REPORTING STANDARDS IMPLEMENTATION COMMITTEE. FRSIC Consensus 28 Capitalisation of Borrowing Costs in a Township Development

Leasehold Management Policy

Wigan Core Strategy Examination Additional Hearing Sessions

REDAN CAPITAL LTD 13 Ikeja Close, Off oyo St, Area 2, Garki-, Abuja, Nigeria GUIDELINES FOR PREPARING PROJECT PROPOSALS

Cork Planning Authorities Joint Housing Strategy. Managers Joint Report on the submissions received and issues raised.

Strategic Housing Market Assessment South Essex. Executive Summary. May 2016

BUILDINGS, LAND AND LAND IMPROVEMENTS

KIWIBUILD: 100,000 MODERN AFFORDABLE HOMES FACTSHEET

Chapter 8 Transportation

Community Occupancy Guidelines

CASEY PLANNING SCHEME AMENDMENT C219

Issues in Applying Hong Kong Interpretations 5 September Hong Kong Interpretations Nelson 1

Rochford Core Strategy Schedule of Changes

Welsh Government Housing Policy Regulation

Hutt River City Centre Upgrade Project Preliminary Integrated Design

The cost of increasing social and affordable housing supply in New South Wales

Lease accounting 2019 IFRS and US GAAP Preparing for a smooth landing

QLDC Council 30 April Report for Agenda Item: 5. Land Transfer to facilitate replacement Kawarau Falls Bridge

Newlands Planning Application - Public Consultation Frequently Asked Questions

Council 20 December Midlothian Strategic Housing Investment Plan 2017/ /22. Report by Eibhlin McHugh, Joint Director, Health & Social Care

Leases. Asset to be abandoned or subleased Supplement to KPMG s Handbook, Leases US GAAP. June kpmg.com/us/frv

Housing New Zealand Investor Update

Report to ASSETS & INFRASTRUCTURE Committee for information

SPORTING AND COMMUNITY LEASING POLICY

Regulatory Impact Statement

Taking In Charge Policy For Housing Developments

TRIUMPH GULF COAST, INC. PRE-APPLICATION FORM

SOUTH TIPPERARY COUNTY COUNCIL

BUSI 330 Suggested Answers to Review and Discussion Questions: Lesson 10

IAG Conference Accounting Update Emerging issues in the public sector 20 November 2014 Michael Crowe Yannick Maurice

PLANNING COMMITTEE REPORT

INTRODUCTION OF CHARGES FOR STREET NAMING, HOUSE NUMBERING, AND CHANGING A HOUSE NAME

HOUSING ELEMENT Inventory Analysis

PROPOSED APARTMENT DEVELOPMENT 32 & 34 TENNYSON AVE TAKAPUNA INTEGRATED TRANSPORT ASSESSMENT

ACCOUNTING FOR CAPITAL ASSETS. Presented by: Joel Knopp, CPA Shareholder

The entity that obtains control of the acquiree. The business or businesses that the acquirer obtains control of in a business combination.

IFRS Project Insights Leases

Lease modifications. Accounting for changes to lease contracts IFRS 16. September kpmg.com/ifrs

Public Improvement District (PID) Policy

West Surrey Strategic Housing Market Assessment

Report of Meeting Date Item No. Brian Moran CCH

Community & Infrastructure Services Committee

DESIGN PUBLIC HEARING

What is a lease? asset for an agreed period of time.

Historic Environment Scotland

2. The Purpose of the Estates Strategy

Presentation to the Real Estate Institute of New Zealand 28 October 2016

ROTORUA LAKES COUNCIL

ROLE OF SOUTH AFRICAN GOVERNMENT IN SOCIAL HOUSING. Section 26 of the Constitution enshrines the right to housing as follows:

EX28.8 REPORT FOR ACTION. Community Space Tenancy Policy SUMMARY

First Experiences under the Tauranga Housing Accord

Framework for a Multi-Residential Rental Property Licence

18 Sale and Other Disposition of Regional Lands Policy

For the purposes of this policy, the following definitions apply:

File Reference No : Leases (Topic 842): a Revision of the 2010 Proposed Accounting Standards Update, Leases (Topic 840)

23 January To whom it may concern,

WEST MELBOURNE URBIS RESIDENTIAL MARKET OUTLOOK

Implementing GASB s Lease Guidance


Real estate industry sees highest annual volume increase in 23 months

BIRMINGHAM DEVELOPMENT PLAN EXAMINATION 2014 MATTER E: GREEN BELT POLICY & THE LANGLEY SUE

Housing Revenue Account Rent Setting Strategy 2019/ /22

PLANNED UNIT DEVELOPMENTS (Ordinance No.: 3036, 12/3/07; Repealed & Replaced by Ordinance No.: 4166, 10/15/12)

Materiële Vaste Activa. 27 September 2005 Pearl Couvreur

ST KILDA ROAD WORKS, DOMAIN PRECINCT

ASSURANCE AND ACCOUNTING ASPE - IFRS: A Comparison Investment Property

WYNYARD CENTRAL HOUSING POLICY

LEASES ICAEW REPRESENTATION 75/18

Paragraph 47 National Planning Policy Framework. rpsgroup.com/uk

MONTHLY HOUSE PRICE INDEX REPORT

EXPRESS LANES NORTHERN EXTENSION TECHNICAL REPORT SEPTEMBER 2016

PLANNED AND RESPONSIVE MAINTENANCE POLICY

Economic Significance of the Property Industry to the. OTAGO Economy PREPARED FOR PROPERTY COUNCIL NEW ZEALAND BY URBAN ECONOMICS

THAT Council receives for information the Report from the Planner II dated April 25, 2016 with respect to the annual Housing Report update.

State of Rhode Island. National Housing Trust Fund Allocation Plan. July 29, 2016

In December 2003 the Board issued a revised IAS 40 as part of its initial agenda of technical projects.

Land at East Bay Close, Cardiff. Planning Statement Proposed Redevelopment to Provide Student Accommodation.

INTERNAL AUDIT DIVISION REPORT 2017/062. Audit of oversight and support of property management in field missions by the Department of Field Support

Leeds City Region Statement of Common Ground. August 2018

METHODOLOGY GUIDE VALUING LANDS IN TRANSITION IN ONTARIO. Valuation Date: January 1, 2016

Starter Tenancy Policy

NORTH LEEDS MATTER 2. Response to Leeds Sites and Allocations DPD Examination Inspector s Questions. August 2017

Chapter 24 Saskatchewan Housing Corporation Housing Maintenance 1.0 MAIN POINTS

1.1 Mineral laws and concessions

Briefing Note. Voluntary Registration of Land in the Land Register of Scotland

DATE: August 9, 2017 TO:

Administration s Finance Office Approval Date: 4/10/12 Effective Date: 4/10/12 Capital Assets and Property Review Date:

Transcription:

Vested Assets Deep Dive Report Recommendation That the Board: i. Receive the report. Executive summary AT receives vested assets from developers and the NZ Transport Agency, with more than half a billion dollars worth received in the last five years. Whilst the largest portion is land, it also includes infrastructure within the road corridor. Issues have been raised with design and physical works carried out by developers, and several initiatives are underway to make improvements to the process. Vested assets arise when property developers undertake development in an area which requires them to build infrastructure. A design is agreed between Auckland Council (AC) and the developer and development contributions are paid. When the development is complete the infrastructure is vested to entities within the AC Group. They are recognised at fair value when control of the asset is transferred to the AC Group. Assets are also vested by the Transport Agency when the state highway status is revoked and they become local roads. They are then transferred to AT, adding to the local roading network. Vested assets bring associated consequential operating costs for AT. Historically it has been difficult to accurately forecast these costs. No additional funding has been received to manage vested assets. A study was completed for the Auckland Transport Alignment Programme (ATAP) that has ascertained the funding needs on a more robust basis. This data will be used for the next Long Term Plan (LTP). Background Vested assets are assets transferred from developers to meet their obligations under the building / resource consent issued for subdivisions. Other sources include the NZ Transport Agency, for assets no longer classified as state highways. They consist of land under roads, and all infrastructure within that roading corridor, including: Road Land Footpaths and cycle ways Street lighting Road Bridges Drainage associated with the road Street Gardens and Trees Bus Shelters Retaining Walls, Railings and fences Traffic signals, signs, road markings, Speed Humps, Traffic Islands and Bollards Value vested to Auckland Transport Ex Developers Ex NZTA Miscellaneous 1 Total

($000) 2016/17 (YTD) 40,338 40,338 2015/16 151,495 151,495 2014/15 162,483 444 162,926 2013/14 94,852 123 211 95,186 1 Occasionally other minor assets, such as CCTV cameras, are given to AT at no cost. The total value of vested assets depends on the development of subdivisions within the region. This is expected to increase in the foreseeable future. A budget was included in the last LTP for $140 million per annum ($100 million land and $40 million for associated assets). Vested Assets 2015/16 $000 Vested Land 112,453 Road - Formation 9,983 Roading Base, Surface, Footpaths and Drainage 22,051 Street lighting, Traffic Control and other associated assets 7,008 Total 151,495 Vested Assets from Developers AC Consent and Development Engineers regulate design and physical work carried out by developers. Road and associated work should be to AT s standards (known as ATCOP). On completion of the work, the developer is issued with a 224C certificate which confirms acceptance by AC. At this point, the roading component of the work becomes the responsibility of AT. A team of Development Engineers (AC), AT Quality Assurance Team representative and a Road Corridor Delivery team member will carry out a visual inspection of the work on completion. Issues arise where the work completed is: Below required standard Above required standards e.g. using asphalt on suburban roads Needing higher than normal ongoing opex e.g. managing vegetation There is limited leverage to do anything at the point of handover. Recent examples observed include:

Work not to specification - Urban design and street amenities high maintenance cost vs. new design - Raised pedestrian crossings and speed tables installed with varying designs, in some cases with little differentiation from decorative surface finishes - Footpaths that have been constructed with steeper longitudinal gradients than allowed in AT specifications - Vehicle crossings installed without the correct splays Lack of connectivity with existing infrastructure Visibility and safety issues As a consequence, AT is working with AC to improve the following: 1) AT should have a representative or project manager for project quality control 2) Identify to AC Consenting/Development Engineers what needs to be referred to AT for review (not all plans are sent to AT for approval) 3) A maintenance person should be sent development plans for review. The issue of limited resources within Road Corridor Delivery to carry out this work would need to be addressed. 4) AT staff should be notified in advance of all work that is to be carried out in the road corridor as a result of new developments 5) AT representatives (QA and RCD) should attend all final inspections where maintenance items are to be accepted by AT 6) The current turn-around times often do not allow for a good quality, comprehensive response back to AC (feedback to be provided in five days) Time constraints and resources appeared to be the main areas where improvements could be made. Liaison between AC and AT for the processing and approving of consented work has been improved, however, AT is not involved in all consent approvals that include roading, and issues such as those above continue to come through. Most of the issues above are of a practical nature, and might more readily be picked up before the construction phase by engineers with road construction or maintenance experience. Resourcing the specialists is the main challenge. Development Contributions (DC s) DC s are fees charged by the Council for residential and non-residential developments, to pay for their share of the extra community and network infrastructure required as a result of their development. AT does not set or receive DC s directly.

Auckland Council receives DC s for planned and historic growth infrastructure and vested assets for local works and services. Local works may be required as a condition of subdivision consent for the provision of water, parks and roads, and are in addition to the DC charge. DC s are proportionately calculated by AC, taking into account what AT has outlined as its required budget. The DC s are paid to AC as a cost recovery mechanism which is applied against part of the overall funding provided to AT. If infrastructure is no longer required for an activity in a specific funding area and no other project can provide the same requirements/needs the proportion of development contribution received may be required to be returned to the developer. Development contributions are one-off and do not cover ongoing opex. Rule changes recently require Councils to only charge developers for direct costs associated with developments (not downstream network impact or ancillary services like libraries). If AT need more funding for growth projects, a proposal through a budget refresh process (AP, LTP) may be accepted and added to the AP or LTP budget, the associated growth proportion will be included in the development contribution charge when the policy is reviewed.

Information Flow for Vested Assets from Land Developments Land Developer Auckland Council Development Engineers Auckland Council Consents Comments Auckland Transport Consents Asset Management / Road Corridor Delivery Comments Auckland Transport Asset Quality Assurance / Road Corridor Delivery Auckland Transport RAMM and FAR Upload

NZ Transport Agency Assets Vesting of highways is less frequent. The next significant vesting will be the existing State Highway between Puhoi and Warkworth when the new expressway is complete. AT is working with the Transport Agency to ensure asset condition is maintained through maintenance and renewals so that no backlog in maintenance is inherited on transfer. The associated Transport Agency activity classes will also need to be increased to ensure the 51% Transport Agency share of subsequent renewals and maintenance is funded. Consequential Opex The consequential operational and renewals needs (generally known as consequential opex) is an issue for vested assets due to both the quantum of extra work and lack of funding. The modelling of consequential opex is challenging due to: Difficulty in accurately predicting the quantum of assets to be added in any given year. AT s long term plans provide a good handle of future additions to the network but subdivision developments are governed by commercial imperatives which are beyond the control of AT. As a result, no accurate assessments are available for these projects. Historical trends are often used to overcome this issue, which are not always reliable. Unavailability of accurate life cycle cost needs at the inception. These needs are ideally to be ascertained before hand over of assets to AT but generally they are not available. Operational costs need to be catered for at the inception and includes activities such as power supply, cleaning, security, vegetation control and asset inspections etc. Sometimes these needs can be significantly high as demonstrated by the operational costs of the recently completed Northwest Shopping Centre. On the other hand, maintenance costs which are needed for asset repairs are minimal at the inception but will increase with time as assets age. These different requirements are generally not captured accurately at inception for most projects. Technology changes will increase the complexity of future infrastructure assets and their transfer will result in both increased maintenance and earlier renewal costs (e.g. smart lamp posts) Lack of additional funding provision. Additional opex has to be met from existing budgets. Further improvements to the current processes are being planned to capture the consequential opex needs more accurately. For the development of ATAP a study has been completed to ascertain consequential opex on a more robust basis. The following table estimates the consequential opex needs of ATAP.

Consequential Opex for growth within the road corridor Vested Assets First Decade of ATAP (2019-28) Maintenance Operations Renewal Consequential Consequential Consequential $M 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2019-28 Total Road Network 0.9 1.2 1.5 1.8 2.1 2.4 2.7 3 3.3 3.6 22.2 Total 0.9 1.2 1.5 1.8 2.1 2.4 2.7 3 3.3 3.6 22.2 Road Network 0.6 0.8 1 1.2 1.4 1.7 1.9 2.1 2.3 2.5 15.5 Total 0.6 0.8 1 1.2 1.4 1.7 1.9 2.1 2.3 2.5 15.5 Road Network 0 0 0 0 0.1 0.4 0.8 1.2 1.7 2.3 6.5 Total 0 0 0 0 0.1 0.4 0.8 1.2 1.7 2.3 6.5 Grand Total 1.5 2 2.5 3 3.6 4.5 5.4 6.3 7.3 8.4 44.2 This table assumes $150 million per annum of vested assets. Next Steps Process improvements are needed so that AT gets more say in design choices which impact amenity, safety, good design and ongoing cost. AC needs to acknowledge the ongoing opex associated with vested assets given the scale of these.

Document ownership Submitted by Karalee Squire Fixed Asset Accountant Recommended by Julian Michael Group Manager, Finance Richard Morris Chief Financial Officer Approved for submission David Warburton Chief Executive Officer