Delivering the defence estate

Similar documents
Investigation into land and property acquisition for Phase One (London West Midlands) of the High Speed 2 programme

Progress on the government estate strategy

Key findings from an investigation into low- and medium-value property sales. National Audit Office September 2017 DP

Managing the Defence Estate: Quality and Sustainability

The Ministry of Defence s arrangement with Annington Property Limited

Business and Property Committee

CROSSRAIL INFORMATION PAPER C10 - LAND DISPOSAL POLICY

POLICY BRIEFING. ! Disposal of public land for new homes NAO Report

BOROUGH OF POOLE BUSINESS IMPROVEMENT OVERVIEW AND SCRUTINY COMMITTEE 17 MARCH 2016 CABINET 22 MARCH 2016

Sale of Lands at the Former Lennox Castle Hospital

THE COPELAND CENTRE AND MORESBY PARKS DEPOT LEASE OF PART. Fiona Rooney, Director of Commercial and Corporate Resources. Manager.

Regeneration & Property Committee. 29 June Tankerton Football Club. Tricia Marshall - Director of Resources. This report is open to the public

Regulatory Impact Statement

Assets, Regeneration & Growth Committee 17 March Development of new affordable homes by Barnet Homes Registered Provider ( Opendoor Homes )

12. STAFF REPORT ACTION REQUIRED SUMMARY. Date: September 21, Toronto Public Library Board. To: City Librarian. From:

Consulted With Individual/Body Date Head of Finance Financial

APPENDIX A BABERGH AND MID SUFFOLK JOINT AFFORDABLE HOMES 3-YEAR ROLLING DEVELOPMENT STRATEGY COMMENCING 2017

CALL-OFF PROCUREMENT OF SALES AGENT FOR THE DISPOSAL OF THE SITE FORMING THE ROYAL MARINES MUSEUM NEAR EASTNEY BARRACKS, HAMPSHIRE

Extending the Right to Buy

Strategic assessment scoping document - Solomon Heights, Vic

Acquiring & Disposing Of Land

Accelerating housing supply A NATIONAL AGENCY WORKING LOCALLY. Colin Molton Executive Director, South and South West Homes and Communities Agency

Riverton Properties Ltd Proposed Special Housing Area

METHODOLOGY GUIDE VALUING LANDS IN TRANSITION IN ONTARIO. Valuation Date: January 1, 2016

Defence Site Maribyrnong Community Information Session. 20 August 2017

B.13. Our Statement of Performance Expectations

INVENTORY POLICY For Real Property

Minister s Function under the Public Works Act 1981

City of Wolverhampton Council Housing Company

City of Cardiff Council INVESTMENT ESTATE STRATEGY

Real Estate Reference Material

RYEDALE SITES LOCAL PLAN MATTER 3 PROPOSED HOUSING SITE OPTION REF. 116 LAND AT MIDDLETON ROAD, PICKERING BARRATT HOMES & DAVID WILSON HOMES

Assets, Regeneration & Growth Committee 11 July Development of new affordable homes by Barnet Homes Registered Provider ( Opendoor Homes )

MAKING THE MOST EFFECTIVE AND SUSTAINABLE USE OF LAND

Persimmon Homes Severn Valley comment St Cuthbert (Out) Neighbourhood Plan Pre-Submission Consultation

SELWYN HOUSING ACCORD

Facts and Figures 31 st December 2014

Swift Academies Assets & Disposal Policy

2. The Purpose of the Estates Strategy

RYEDALE SITES LOCAL PLAN MATTER 4 PROPOSED HOUSING SITE OPTION REF. 116 LAND AT MIDDLETON ROAD, PICKERING BARRATT HOMES & DAVID WILSON HOMES

Welsh Government Housing Policy Regulation

INVENTORY POLICY For Real Property

18 Sale and Other Disposition of Regional Lands Policy

At its 4 October 2002 meeting the Regulatory and Consents Committee resolved:

Managing the Defence Estate

Government Management Committee. P:\2011\Internal Services\Fac\Gm11008Fac- (AFS 10838)

Rutland One Public Estate

Agricultural land - farm sales framework

Council Policy. Council policy title: Lease and Licence Policy 2018

Innovation and Ambition The Hammersmith & Fulham Approach. Melbourne Barrett MBA MRICS Executive Director, Housing & Regeneration

abcdefghijklmnopqrstu

UK Housing Awards 2011

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL SELF-COMMISSIONED HOUSING AT ORCHARD PARK

Draft London Plan Review

The future of the Central Hill Estate

F.18 New Zealand. Railways Corporation HALF-YEARLY REPORT 1 JULY DECEMBER 2015

Voluntary Right to Buy Policy. Dan Gray, Executive Director, Property

ASSET TRANSFER REQUESTS Community Empowerment (Scotland) Act 2015 Guidance Notes

Vote Lands. APPROPRIATION ADMINISTRATOR: Land Information New Zealand

B8 Can public sector land help solve the housing crisis?

Scheme of Service. for. Housing Officers

Explanatory Notes to Housing (Scotland) Act 2006

LOT 30 TREEBY ROAD ANKETELL WA 6167

Evaluating your co-op manager

QUEENSTOWN-LAKES DISTRICT HOUSING ACCORD

The joint leases project change is coming

OLD TRELAI LIBRARY, BISHOPSTON ROAD, CARDIFF OPTIONS REPORT CONSIDERING: COMMUNITY ASSET TRANSFER (CAT), DISPOSAL OF BUILDING OR COMMERCIAL LEASE

Governing Body meeting (held in public)

Affordable Homes Service Plan 2016/17 and 2017/18


Room36 Aparthotel Bradford, England

SHEFFIELD TEACHING HOSPITALS NHS FOUNDATION TRUST EXECUTIVE SUMMARY REPORT TO THE BOARD OF DIRECTORS HELD ON 19 SEPTEMBER 2012

Inverness Area Planning Advisory Committee Inverness County Planning Advisory Committee Inverness County Council Planning Staff (EDPC)

Community Housing Federation of Victoria Inclusionary Zoning Position and Capability Statement

Town of Bristol Rhode Island

Lease modifications. Accounting for changes to lease contracts IFRS 16. September kpmg.com/ifrs

37 Wimpole Street redevelopment

Policy and Resources Committee Meeting 2 nd June 2015

Hurstpierpoint & Sayers Common Neighbourhood Plan. Habitats Regulations Assessment Screening Report. 4 th April 2014

Resettlement Policy Framework

Section 12A Purpose of Subdivision Provisions

Policy Response Budget 2017

NORTH LEEDS MATTER 2. Response to Leeds Sites and Allocations DPD Examination Inspector s Questions. August 2017

The Heygate Masterplan Elephant and Castle. Outline Planning Application. Equalities Impact Statement

KANSAS CITY, MISSOURI HOMESTEADING AUTHORITY POLICIES AND PROCEDURES

TANGIBLE CAPITAL ASSETS

BIRMINGHAM DEVELOPMENT PLAN EXAMINATION 2014 MATTER E: GREEN BELT POLICY & THE LANGLEY SUE

OTTAWA COMMUNITY LANDS DEVELOPMENT CORPORATION

Barratt Metropolitan Limited Liability Partnership

Land at East Bay Close, Cardiff. Planning Statement Proposed Redevelopment to Provide Student Accommodation.

RHLF WORKSHOP The National Housing Code

Charter for Housing Rights

Briefing paper A neighbourhood guide to viability

23 January To whom it may concern,

Council 20 December Midlothian Strategic Housing Investment Plan 2017/ /22. Report by Eibhlin McHugh, Joint Director, Health & Social Care

PLANNING REPORT. Prepared for: John Spaleta 159 Delatre Street Woodstock Ontario N4S 6C2

The cost of increasing social and affordable housing supply in New South Wales

End of fixed term tenancy policy

Effective housing for people on low incomes in the Welsh Valleys

Tenant s Scrutiny Panel and Designated Persons and Tenant s Complaints Panel

Transcription:

Ministry of Defence Delivering the defence estate Appendix Four NOVEMBER 2016

2 Appendix Four Delivering the defence estate Appendix Four 1 This document sets out our review of the disposals by the Ministry of Defence (the Department) of four selected estate sites, which we have used to inform the conclusions reached within our report on Delivering the defence estate 1. We selected these case studies to illustrate the range of issues the Department faces when disposing of its estate and to cover the various stages of disposal. 2 The facts contained within this Appendix have been agreed with the Department. 3 Our case studies: Ashchurch (disposal being considered). Old War Office (disposal complete). Lodge Hill (to be disposed, disposal ongoing). Waterbeach Barracks (to be disposed, disposal ongoing). 4 The Defence Infrastructure Organisation, a part of the Department, is responsible for managing the defence estate, including identifying sites for disposal and managing the disposal process. The Front Line Commands (the Commands) are the main users of the defence estate, using the defence estate to provide military capabilities. 2 1 Comptroller and Auditor General, Delivering the defence estate, Session 2016-17, HC 782, National Audit Office, November 2016. 2 Army, Navy, Air and Joint Forces Command.

Delivering the defence estate Appendix Four 3 Ashchurch Introduction to case study Ministry of Defence Ashchurch, Gloucestershire, is the Department s main vehicle support and storage site for all types of military vehicles. The site provides two main capabilities: Vehicle storage in temperature-controlled environments to prevent their condition deteriorating. Vehicle inspections, test, repairs and overhauls. The Army does not currently have a capability to enable it to keep vehicles at very high levels of readiness for deployment. The Defence Infrastructure Organisation (DIO) is investigating disposal of the Ashchurch site and re-providing, at a different site in closer proximity to Salisbury Plain, both the current capabilities provided by Ashchurch and a capability to support a new vehicle high readiness capability. At the time of our audit options include full and partial disposal. Justification for case study The issues that the Department has to consider in coming to a decision Ashchurch has been on the Department s disposal register since 2011 and is one of the longest running estate disposals still progressing. Delays have occurred because the forecast cost of re-providing the capability currently provided by Ashchurch when the site is disposed, and meeting Army s specifications for any new site, was not affordable at the time of our audit. DIO is seeking to balance the capability to be provided by any new site with the requirements of the Army. The DIO and Army have agreed some compromises, reducing forecast costs and affordability constraints and streamlining the process to check vehicles. This may increase the risk of faults on vehicles not being identified before they are deployed on operations. There are a limited number of sites meeting the Army s geographical requirements that can accommodate the capabilities currently provided by Ashchurch. Initial sites identified by DIO as suitable were eliminated as other government objectives were prioritised on these sites. This has delayed disposal and increased the costs associated with the disposal because each site was subject to detailed work by DIO. Contribution to the Department target to secure 1 billion receipts from land disposals by 2021 Contribution to the Department s target to release land to support 55,000 new homes by 2020 Contribution to reducing the running cost of the estate Costs of providing the capability offered by the site elsewhere The Department has estimated that receipts from selling the full Ashchurch site could reach 68 million. This assumes planning permission is secured prior to sale. The Department has also explored options for the partial or phased disposal which would alter the expected receipt. A final decision on the Ashchurch site had not been made by the time of our review and the exact contribution to this target is not yet known. In 2013, the Department identified that the full site could support up to 2,100 new homes. However, as release would need to be phased, the Department is assuming that land for around 500 homes could be secured during this parliament. DIO has not assessed the running cost savings that could be achieved by disposing of the Ashchurch site. DIO s initial estimate of the costs of re-providing the capability offered by Ashchurch at another site on a like-for-like basis, and a new vehicle high readiness capability, was 650 million. After detailed analysis and compromises being reached on the capability to be provided, DIO has reduced its estimate to 330 million. At the time of our review DIO s analysis was ongoing to bring the estimated cost within available budget. To inform its estimate of re-provisioning costs, DIO has undertaken a number of detailed assessment studies and option appraisals over the previous five years. Key risks to disposing of site 1 DIO and the Army are still to decide how to progress the disposal and at the time of our review there was uncertainty as to whether all or part of the site will be disposed of. 2 There is a lack of sites large enough that can accommodate both the capabilities currently offered by Ashchurch and the capabilities to keep vehicles at very high levels of readiness for deployment. 3 At the time of our review, the estimated cost of providing the capability currently provided by the Ashchurch site elsewhere is unaffordable within existing budgets. 4 DIO does not secure planning approval from the local authority for the Ashchurch site to be redeveloped, reducing the chances of a successful sale. Current position The Department expects to take a decision on how to progress the disposal of the Ashchurch site by the end of 2016. Key benefits from disposal The disposal is not the primary driver for the programme to optimise its vehicle storage and support facilities and determine the future of the Ashchurch site. The key benefit is the delivery of new capabilities so that vehicles can be kept at very high levels of readiness for deployment, which the Department is currently lacking.

4 Appendix Four Delivering the defence estate Old War Office Introduction to case study In August 2013, after a review of its central London estate the Department identified that the Old War Office building on Whitehall was surplus to it requirements. In March 2016, the Department sold the building on a long lease arrangement to the Hinduja Group in partnership with OHL Developments for 357 million. At the time of our review, plans included the building being restored and redeveloped as a luxury hotel and residential apartments. The civil servants working in the building have been moved to the Ministry of Defence s HQ in Whitehall. Justification for case study Reflecting its location on Whitehall, the sale was complicated by the security and heritage requirements of various government agencies. The proceeds from the sale accounted for the majority of the Department s asset disposal receipts in 2015-16. The issues that the Department had to consider in coming to a decision The building covers the equivalent of 580,000 sq. ft. and is grade II listed. Its layout is mostly small rooms that have not been modernised in a number of years. The Metropolitan Police and the Security Services placed a number of requirements on both how the building could be used in the future and the design of building features, including windows. DIO was required to balance these requirements with maximising sale proceeds from an open market bidding process. DIO agreed to dispose the building on a long lease, with a clause that would allow the Department to seek legal remedy through the Courts, including the potential for return of the building to the Department in the event that the purchasers do not act in accordance with the contract and security measures agreed before sale. Sale of the building attracted some opposition in the House of Lords. Contribution to the Department target to secure 1 billion receipts from land disposals by 2021 Contribution to the Department s target to release land to support 55,000 new homes by 2020 Contribution to reducing the running cost of the estate The sale contributed 357 million towards the target. However, HM Treasury retained 157 million of the proceeds, with the Department keeping 200 million. The Department estimates that the disposal will contribute 100 housing units against the target. At the time of our review the purchasers plan to develop the building into a luxury hotel, serviced apartments and apartments. The building was operated under a Private Finance Initiative arrangement. The Department estimated that between 8 million and 10 million of costs will be saved by vacating the Old War Office. Exiting the PFI did not incur any penalty or additional costs. DIO believed that the condition of the building was leading to relatively high running costs, particularly utilities. Costs of providing the capability offered by the site elsewhere DIO has not tracked the costs of moving the staff and equipment from the Old War Office to the Department s HQ in Whitehall. To accommodate those staff moving across, the Department undertook a reorganisation of its HQ. Key risks to disposing of site 1 Securing bids that complied with the strict security criteria of the Metropolitan Police and the Security Services. 2 Providing potential bidders with sufficient confidence that the site could be used for a range of purposes. Current position The sale of the Old War Office was completed in March 2016. The Department can seek to repossess the building through the Courts if the purchasers do not act in accordance with the contract and security measures agreed before sale. The movement of civil servants and equipment to the Department s HQ was completed in December 2015. Key benefits from disposal By disposing of the building the Department secured significant disposal receipts, which it can reinvest in its estate, and reduce its running costs. The disposals also secured indirect benefits by increasing the occupancy, and therefore efficiency, of its HQ building.

Delivering the defence estate Appendix Four 5 Lodge Hill Introduction to case study The Lodge Hill training area in Kent was used for training by the Royal School of Military Engineers and included training area, accommodation and military storage, and some areas were farmed by a tenant. In 2008, the site was declared surplus to requirements and remaining functions were gradually transferred to nearby Chatham Barracks. The overall condition of the built assets has deteriorated since 2009 when the Department decided to stop maintaining the site. Most buildings have been demolished. Justification for case study The issues that the Department has to consider in coming to a decision Although the site was declared surplus in 2008, the Department has not yet disposed of the site. A number of complications to the disposal process have arisen due to the complexity of the site, including environmental constraints imposed since the site was declared surplus. The area surrounding Lodge Hill is a Site of Special Scientific Interest (SSSI) owing to the presence of rare grasslands and nightingale birds. In 2013, the SSSI was extended to include the Lodge Hill site due to a significant presence of breeding nightingales. The Department unsuccessfully contested this extension. DIO developed a revised planning application in February 2014 with its then private sector partner, which included creating a suitable alternative habitat for the nightingales to be moved to. The local authority approved this revised plan in September 2014. Due to the issues and the scale of development, in February 2015 the revised planning application was subsequently called-in for a planning inquiry by the Department for Communities and Local Government. The Department is required to reassess the ecological impacts and these studies will need to be timed according to the nightingale nesting seasons. It is therefore unlikely that the planning inquiry will be completed before June 2017. Contribution to the Department target to secure 1 billion receipts from land disposals by 2021 Contribution to the Department s target to release land to support 55,000 new homes by 2020 The Department expects to make around 100 million of profit from the site, after development costs over a number of years. A final decision on the Lodge Hill site had not been made by the time of our review and the exact contribution to this target is not yet known. The 254 hectare site is proposed for development. The Department expects that full disposal of the site could support 5,000 new homes, subject to planning approval. The redevelopment plans include three primary schools, a secondary school, medical facilities and leisure and retail space, which are estimated to provide up to 5,000 jobs. The number of new homes that will score against the Department s target will not be known until the current public inquiry is complete, planning permission granted and the sale of the site complete. Due to planning complexity it was agreed that the site should transfer to the Homes and Communities Agency (HCA) to pursue disposal. Contribution to reducing the running cost of the estate Costs of providing the capability offered by the site elsewhere The Department no longer occupies the site and it estimates that running costs are minimal. However, DIO currently has a security contract for perimeter maintenance of the site, costing a total of 500,000 per annum. DIO has not tracked the costs associated with moving staff and equipment from Lodge Hill to Chatham Barracks because this was part of a wider programme to centralise training of military engineers, and the Lodge Hill elements happened on an ad hoc basis over a series of years. Key risks to disposing of site 1 Securing approval for the revised planning application. Some local stakeholders are opposed to the Department s plans. Any changes to the planning application as a result of the planning inquiry could add further time and cost to the disposal process. 2 The Department plans to secure a new private sector partner to manage the disposal and put in place enabling infrastructure (utilities, transport links, etc.) to support future development of the site. DIO anticipates securing a new partner will be challenging. The previous private sector partner withdrew due to the time taken to progress the disposal. Without a private sector partner, the Department does not have sufficient resources to develop the site to maximise its attractiveness for sale, either in parcels or in its entirety. Current position Due to the planning complexity of the site, at the time of our review the Department planned to transfer the freehold of the site to the HCA for disposal. Under the proposed transfer agreement, the HCA would use its land development expertise and resources to successfully dispose of the site. In return the Department would share disposal receipts with the HCA on a 80:20 basis (Department: HCA). Key benefits from disposal By disposing of this site the Department expects to receive significant disposal proceeds and a contribution to meeting its target to release land to support new housing.

6 Appendix Four Delivering the defence estate Waterbeach Barracks Introduction to case study The Waterbeach Barracks site is a 290.5 hectare former WWII RAF station situated in Cambridgeshire. It comprises an airfield with one remaining paved runway and accommodation for service personnel and their families. The site became vacant when an engineering unit moved to Kinloss Barracks. South Cambridgeshire District Council s Local Plan assumes the site, together with adjoining farmland to the north and east, which is owned by a local consortium, will become a new settlement to support approximately 6,500 new homes. The Department is selling the Waterbeach land independently, but is working in conjunction with the local consortium to package the two land sales together. Justification for case study Disposal of the Waterbeach site is the largest single contributor to the Government Housing Strategy, with potential to support 6,500 new homes. A ministerial statement declared the site would be vacated by 2014-15, but opposition to various elements of the local authority s plan have significantly delayed this. The Department has used a private sector agent to manage the disposal to maximise returns and mitigate the complications in dealing with multiple stakeholders on adjoining land, the local authority, and local opposition to the creation of a new settlement. The private sector agent is required to secure planning permission for the site before disposal. The issues that the Department has to consider in coming to a decision The key issue the Department faced was how to progress with disposal of the land. The two options were: Combining with a consortium of local landowners to dispose of a larger site; or Engaging a private sector partner who would manage the disposal and assume responsibilities for engagement with the multiple stakeholders. On the basis of an options appraisal completed by a commercial property adviser, the Department selected the second option as it was assessed to offer a better financial return and was lower risk. Contribution to the Department target to secure 1 billion receipts from land disposals by 2021 Contribution to the Department s target to release land to support 55,000 new homes by 2020 Contribution to reducing the running cost of the estate Costs of providing the capability offered by the site elsewhere Due to the size of the site DIO expects its agent will dispose of the site in parcels of land. It estimates that disposal of the site will secure approximately 87 million of sale proceeds over the period 2020 to 2037 (in 2016 prices). A final decision on the disposal of the site had not been made by the time of our review and the exact contribution to this target is not yet known. DIO has estimated that the site will support 6,500 new homes. A final decision on the disposal of the site had not been made by the time of our review and the exact contribution to this target is not yet known. DIO has not assessed the running cost savings that could be achieved by disposal of the Waterbeach site. The Department is unable to provide information regarding the cost of moving personnel from the Waterbeach site to Kinloss Barracks. Key risks to disposing of site 1 The local authority s plan is amended or rejected, requiring the Department s outline plans for the site to be changed. Current position Key benefits from disposal The Department is awaiting the outcome of the local planning inquiry. It expected the first disposal of land on the site to occur in late 2017. The Department estimates that disposal of the site will support 6,500 homes, forming the basis for the creation of a new settlement.

National Audit Office 2016 The material featured in this document is subject to National Audit Office (NAO) copyright. The material may be copied or reproduced for non-commercial purposes only, namely reproduction for research, private study or for limited internal circulation within an organisation for the purpose of review. Copying for non-commercial purposes is subject to the material being accompanied by a sufficient acknowledgement, reproduced accurately, and not being used in a misleading context. To reproduce NAO copyright material for any other use, you must contact copyright@nao.gsi.gov.uk. Please tell us who you are, the organisation you represent (if any) and how and why you wish to use our material. Please include your full contact details: name, address, telephone number and email. Please note that the material featured in this document may not be reproduced for commercial gain without the NAO s express and direct permission and that the NAO reserves its right to pursue copyright infringement proceedings against individuals or companies who reproduce material for commercial gain without our permission. Links to external websites were valid at the time of publication of this report. The National Audit Office is not responsible for the future validity of the links.