Cladding and Fire Safety Improvements Post-Grenfell. Matthew Fraser Landmark Chambers 30 October 2018

Similar documents
Technical e.xpertise. Post Grenfell: Impact of cladding on the valuation of high-rise residential blocks the current position.

Leasehold high-rise flats: who pays for fire safety work?

HAVEBURY HOUSING PARTNERSHIP

Factsheet 2. Good practice and factors for consideration in England and Wales

The Right to Manage A short guide

RESIDENTIAL LANDLORDS ASSOCIATION A RESPONSE TO THE HACKITT REVIEW FOR THE HOUSING, COMMUNITIES AND LOCAL GOVERNMENT SELECT COMMITTEE

EXPLANATORY MEMORANDUM TO THE HOUSING (SERVICE CHARGE LOANS) (AMENDMENT) (WALES) REGULATIONS 2011 SI 2011 No.

Fire Safety and Legal Obligations for Landlords

NON-EXCEPTED AREAS - POLICY AND GUIDANCE (January 2016 Edition)

T: (+44) F: (+44)

TACKLING UNFAIR PRACTICES IN THE LEASEHOLD MARKET RESPONSE OF ANTHONY COLLINS SOLICITORS LLP ( ACS )

Government Consultation in Tackling Unfair Practices in Leasehold. Response from Association of Retirement Housing Managers (ARHM)

Residential Management Disputes. Natasha Rees, Emma Gosling, Yvonne Hills and Sarah Heatley 25 February 2016

Tackling unfair practices in the leasehold market: A consultation paper Response from NAEA Propertymark September 2017

Right to Buy LEASE CONFERENCES. Disclaimer

Laceys Guide To Right To Manage

The project will be a wide-ranging review of residential leasehold law, focussing in the first instance on reform to:

Leasehold home ownership: buying your freehold or extending your lease. Law Commission Consultation Paper

Heathrow Expansion. Land Acquisition and Compensation Policies. Interim Property Hardship Scheme. Policy Terms

December Arbon House, 6 Tournament Court, Edgehill Drive, Warwick CV34 6LG T F

Leasehold Management

- 1 - Property Address:

A guide to buying your council or housing association home

Classification: Public. Heathrow Expansion. Land Acquisition and Compensation Policies. Interim Property Hardship Scheme 1.

Leasehold Management Policy

Property Notes. Self Invested Personal Pension

a short guide to The Right to Manage

Home owner handbook. Contents. 1. Our team Leasehold explained Insurance Ground rent, rent and service charges 3

Residential Flat Lease Extensions Information for Leaseholders on Extending Your Lease

Terms of Business, Landlord Insurances & Property Information (v2.0)

Date: July All Wards Affected

CJC response to the DCLG consultation on: TACKLING UNFAIR PRACTICES IN THE LEASEHOLD MARKET

CONTRACT OF SALE OF REAL ESTATE 1

Property notes for the AJ Bell Investcentre SIPP

Minimum Energy Efficiency Standards (MEES) How are you affected?

GUIDE TO SSAS PROPERTY PURCHASE

Contract of Sale of Real Estate

Minimum Energy Efficiency Standards Fact Sheet The Energy Efficiency (Private Rented Property) (England and Wales) Regulations 2015 introduce measures

RECOVERING COSTS IN THE FIRST-TIER TRIBUNAL. CIH Home Ownership & Leasehold Management Conference & Exhibition 5 and 6 February 2014

2 Marsham Street, London SWlP 3EB

19 September Tackling unfair practices in the leasehold market. Introduction

Buying the Freehold Interest in your Building with other flatowners (Leasehold Reform, Housing and Urban Development Act 1993)

HOME Scheme and Part Exchange. You ve found the Story Home of your dreams but you don t have a buyer for your current property...

POLICY BRIEFING. ! Tackling rogue landlords and improving the private rental sector

The Right to Acquire. Contents. Contents Making an informed decision Can you buy your home? How to buy your home 7. 4.

Mobility Scooter Storage Policy

Report. complaint no 03/B/13806 against Oxford City Council. on an investigation into. 31 May 2006

Fire safety: what s next? Jan Taranczuk CIHCM June 2018

Horsham District Council Empty Homes Strategy

Housing and Planning Bill + Welfare Reform and Work Bill

ESTATE AND LETTING AGENTS

CLACKMANNANSHIRE TENANTS AND RESIDENTS ASSOCIATION WRITTEN SUBMISSION

There are some fundamental principles which the Council will apply when regenerating estates:

Innovation and Ambition The Hammersmith & Fulham Approach. Melbourne Barrett MBA MRICS Executive Director, Housing & Regeneration

Some homes may not be eligible and in those cases we will try to find an alternative property that you can buy.

Section 21 Procedure

Royal Borough of Kensington and Chelsea Grenfell Rehousing Policy. Revision November 2017

Briefing. Energy efficiency and the Green Deal: Q&A for housing associations. Neighbourhoods. Tel:

WEST HENDON MANAGEMENT STRATEGY. June 2013 Revision A. Barratt Metropolitan LLP

Challenges of Shared Ownership. Steve Chapman

Response. Reinvigorating the right to buy. Contact: Adam Barnett. Investment Policy and Strategy. Tel:

Small Self Administered Scheme. Property Notes

Local Authority Housing Companies

The joint leases project change is coming

Buying a residential property in. England and Wales

2. The BSA welcomes the opportunity to respond to the Welsh Government s White Paper on the future of housing in Wales.

Recovering the Costs of Leasehold Management

Cladding loans to be offered to thousands of apartment owners

SSHA Tenancy Policy. Page: 1 of 7

Cabinet Meeting 4 December 2013

Leaseholder & Shared Ownership Handbook

Description of the RICS HomeBuyer (Survey & Valuation) Service

Group Company A together with its subsidiaries

1 Adopting the Code. The Consumer Code Requirements and good practice Guidance. 1.1 Adopting the Code. 1.2 Making the Code available

Guidance Notes for Solicitors

Voluntary Right to Buy

A Guide to Lease Extensions for the Barbican Estate

Overview Home Ownership Policy

ASSETS OF COMMUNITY VALUE. John Male QC and Thomas Jefferies. Community right to bid (assets of community value)

A home of your own SHARED OWNERSHIP (PART BUY/PART RENT)

Comment on the Exposure Draft Leases

1.4 The policy applies to all landlord organisations in the Group.

H M COURTS & TRIBUNALS SERVICE LEASEHOLD VALUATION TRIBUNAL

Community Empowerment and Renewal Bill A Consultation. Response from the Chartered Institute of Housing Scotland

equip yourself for the future

THAILAND S NEW TENANT PROTECTION LAWS CHALLENGE THE LUXURY CONDOMINIUM SECTOR

TERMS OF SALE. 3.2 Each order accepted constitutes a separate legally binding Contract between FAV and the Buyer.

APPENDIX 7. Housing Enforcement Policy V May 2003

Private Sector Housing Fees & Charges Policy

Housing: construction defects

Commonhold: A Call for Evidence Summary

SCOTTISH GOVERNMENT RESPONSE TO PRIVATE RENTED HOUSING (SCOTLAND) BILL STAGE 1 REPORT

NOISE KEY POINTS WHAT LESSEES CAN DO IF YOU HAVE A PROBLEM. Use the following stepped approach:

Residential Buy to Let Landlords Administration of Estates

Voluntary Right to Buy Policy. Dan Gray, Executive Director, Property

GUIDE TO SIPP PROPERTY PURCHASE

LEASEHOLD MANAGEMENT POLICY Responsible Officer Director of Customer Services

Explanatory Notes to Housing (Scotland) Act 2006

Conditions of Purchase FISCHER GmbH & Co. KG Lagertechnik + Regalsysteme, Stutensee

ASSURED SHORTHOLD TENANCY AGREEMENT

Transcription:

Cladding and Fire Safety Improvements Post-Grenfell Matthew Fraser mfraser@landmarkchambers.co.uk Landmark Chambers 30 October 2018

Latest MHCLG figures (12 October 2018) There are 457 high-rise (over 18 metres) residential buildings and publicly-owned buildings in England with Aluminium Composite Material (ACM) cladding systems unlikely to meet current Building Regulations guidance: 157 are social sector residential buildings, managed by local authorities or housing associations; 291 are private sector buildings, of which: 201 are private residential 28 are hotels 62 are student accommodation 9 are publicly-owned buildings, comprising hospitals and schools.

There are approximately 30 private sector residential buildings where the cladding status is still to be confirmed 22 of the 157 social sector buildings (14%) have finished remediation including receiving sign-off from building control where necessary, and a further 98 buildings (62%) have started the process of remediation. There are 33 buildings where a remediation plan is in place, and a further 4 buildings where the building owners intend to remediate and are developing plans. Interim fire safety measures are in place in all affected buildings to keep residents safe until the cladding has been replaced.

Of the 291 private sector buildings: 17 have finished remediation including receiving sign-off from building control where necessary; 21 have started remediation; remediation plans are in place for 92 buildings but remediation works haven t started on these buildings yet; there are 40 buildings where building owners intend to remediate and plans are being developed; and remediation plans remain unclear for 121 buildings

Total estimated bill The UK is facing an estimated 1bn bill to replace defective cladding on high-rise buildings.

Blocks owned by social landlords No cost will be borne by assured and secure tenants Long leaseholders who have exercised the right to buy may be liable depending on: The service charge provisions and landlord obligations in their leases; The nature and extent of the works being carried out.

CAM/38UC/LSC/2016/0064-5 tower blocks in Oxford - 54 RTB leaseholders - Major works by Oxford City Council as landlord, including cladding and fire safety improvements - Circa 50,000 service charge on each leaseholder - FTT held that the works (except for limited structural repairs and lift maintenance) did not fall within the landlord s covenant to maintain the properties - There was no scope in the leases for recovering a service charge for improvements - Result: 50,000 unreasonable, and replaced by circa 2,500

Central government commitment on cladding On 16 May 2018, the Government announced that it would meet the reasonable cost of the removal and replacement of unsafe cladding by councils and housing associations. It has estimated the cost at 400 million. This will not be means tested, and will be available regardless of whether work has been started, completed or not yet started, so that building owners do not have to worry about the cost of work displacing other activities. First tranche to twelve local authorities and 31 housing associations announced on 17 October 2018

Cladding Applications for 159 buildings have been received as at 17 October 2018 and 135 applications have been approved in this first tranche of funding. Twelve applications were not eligible for funding because they didn t meet the application criteria for example the buildings are below 18 metres, owned by commercial freeholders or the cladding is not ACM. Twelve applications have been deferred while building owners provide further information to confirm eligibility. Applications received after the 31 August deadline will still be reviewed. The government is paying 80% of the estimated eligible costs up front when work starts, with the remaining 20% when the work is complete and final costs are known. The funding allocated so far comes to 248 million.

What about other works? The government will also provide financial flexibilities to councils for other essential fire safety measures and is directing local authorities to take cladding-related issues into account when carrying out reviews of housing conditions in their areas. Financial flexibilities: more borrowing headroom or accessing other general funds that normal restrictions would not allow them to use in order to fund the work

Retro-fitting sprinklers? The government commissioned an independent, forward-looking review of the building regulations and fire safety system. The final report was published on 17 May 2018. The Housing, Communities and Local Government Select Committee s report on the independent review report was published on 18 July 2018. The SC recommended that: Where structurally feasible, sprinklers should be retrofitted to existing high-rise residential buildings to provide an extra layer of safety for residents. The Government should make funding available to fit sprinklers into council and housing association-owned residential buildings above 18 metres

Retro-fitting sprinklers (cont) The Government has refused to make a firm commitment on sprinklers. Their response to the SC recommendations on 18 September 2018 stated: An appropriate level of fire safety can be achieved without the need to retro fit sprinklers and, as the Committee notes, it may not be feasible to install a system, for example for structural reasons. It is for building owners to seek professional advice and decide whether to fit sprinklers, on the basis of their assessment of the particular risk faced in their building(s). The Government intends to undertake a technical review of Approved Document B and will publish a call for evidence in the autumn. Possible changes to the guidance in Approved Document B, including on the use of sprinklers, will be considered in this review. The Government will also consider financial flexibilities for local authorities concerned with funding other essential fire safety works in buildings which they own."

LB Wandsworth case study The London Borough of Wandsworth (LBW) is seeking to retro-fit sprinklers in all its blocks of 10 storeys or higher and has obtained legal advice to the effect that the cost, estimated to be around 3,000 to 4,000 per unit, is recoverable. Of the 6,401 properties that would benefit, 2,358 are leasehold. There are 1,315 resident leaseholders and 1,043 leaseholders living away from their property. LBW say that if the works are necessary and chargeable under the terms of the lease then it is under a strict fiduciary duty to recharge and that meeting leaseholders contributions from the Housing Revenue Account (HRA) or the General Fund is likely to be challengeable. A section 27A application has been made to the FTT by LBW.

Private sector Flats in affected residential blocks will be held on long leases It will depend on the terms of the lease who is liable to pay for cladding replacement and other fire safety measures Even if there is no express provision dealing with fire safety, freeholders might use a sweeping-up clause. This could allow freeholders to recover a service charge for: money spent for the benefit of the building money spent to enable good estate management

Case study Citiscape in Croydon Citiscape in Croydon is managed by Firstport on behalf of Proxima Properties. Landlord wanted to replace the ACM cladding and introduce a waking watch (permanent on-site fire marshal) after Grenfell. The estimated cost of removing and replacing the cladding on this block was between 1.8 and 2.5 million, with leaseholders facing average bills of 21,000 depending on the size of their flats. The waking watch would be circa 250k p.a. Firstport referred the question of the recoverability of the cost from leaseholders to the FTT who held on 13 March 2018 that the cost is recoverable from the block s leaseholders: LON/00AH/LSC/2017/0435.

FTT s decision Waking watch: recoverable within Inspecting rebuilding re-pointing repairing cleaning renewing or otherwise treating as necessary and keeping the Maintained Property comprised in the Block and every part thereof in good and substantial repair order and condition and renewing and replacing all worn or damaged parts therefore. Also within: Complying with the requirements and directions of any competent authority and with the provisions of all statutes and all regulations orders and bye-laws made thereunder relating to the Development insofar as such compliance is not the responsibility of the lessee of any of the Dwellings. All other reasonable and property expenses (if any) incurred by the Manager in and about the maintenance and proper and convenient management and running of the Development Providing and paying such persons as may be necessary in connection with the upkeep of the Maintained Property.

FTT s decision Removing and replacing cladding [58]: The words renewing or otherwise treating as necessary go beyond simple repair. Equally the words in good and substantial repair order and condition indicate an obligation that goes well beyond simple repair: if it did not the words order and condition in the phrase would be superfluous. We do not see how the two blocks can be said to be in good and substantial repair order and condition whilst the cladding remains a fire risk. Finally, and subject to Mr Ede s point considered below, the reference to rectifying or making good any inherent structural defects in paragraph 15 appears to us to encompass the removal of the defective cladding and its replacement with fire resistant cladding

At [62]: By granting 999 year leases the original freeholder was effectively relinquishing any capital interest in the flats. There is no prospect of the freeholder receiving other than nominal premiums either on enfranchisement or on individual lease renewals under the Leasehold Reform, Housing and Urban Development Act 1993. In such circumstances it is reasonable to conclude that the parties would have intended that all future costs associated with the blocks would be the responsibility of the tenants. That intention is reinforced by the use of identical words to define both the manager s obligation to undertake work and the tenant s obligation to pay for it.

66. It is foreseeable that the tenants may have claims against a number of parties: against the manufacturer of the cladding in particular if any warranties were given as to its suitability: against Barratt Homes if they were negligent as to the selection and installation of the cladding: against the Local Authority if there were errors in the certification process: against the DCLG if, as been suggested elsewhere, the relevant building regulations were not fit for purpose. 67. The difficulty with all these potential claims is that they are entirely speculative with uncertain outcomes.

After the FTT s decision On 19 April 2018, Barratt Developments, the original developers of the block, told leaseholders that they would cover future and backdated costs relating to employing a fire warden and the removal and replacement of unsafe cladding.

Another fire warden decision E & J Ground Rents No.11 LLP various leaseholders of Fresh Apartments, Salford: https://www.lease-advice.org/files/2018/01/doc019.pdf (24 January 2018) Reaches the same decision about the recoverability of costs for a waking watch, in the context of similar lease terms.

Latest voluntary action by developer On 16 October 2018 it was announced that Bellway has set aside 5.9m to carry out works to replace combustible cladding used on two of its apartment developments, Prospect Place in Cardiff and New Festival Quarter in east London.

Other remedies According to Inside Housing, the property management company in charge of New Capital Quay in Greenwich has launched a legal challenge against the National House-Building Council (NHBC) on the basis that the cladding complied with the building regulations in force at the time of construction and was signed off by the NHBC in their building control role: https://www.insidehousing.co.uk/news/news/nhbc-faces-liability-claims-fordangerous-cladding-on-tower-blocks-54198 Inside Housing has also reported on a block in Salford where surveys have revealed inadequate fire breaks in cladding panels, which may mean that insurers have a liability under the leaseholders warranties.

Central government funding? The Housing, Communities and Local Government Select Committee s report on the independent review report, published on 18 July 2018, recommended that The Government should fully fund the replacement of any cladding on existing buildings which had been permitted, but is subsequently banned as a consequence of the consultation. In those circumstances, this funding should be made available to both public and private sector landlords.

Government s response The Government has already provided funding for remediation of cladding in the social sector. In the private sector more and more firms are doing the right thing and replacing cladding themselves without the costs falling to leaseholders. The Government will consider what further steps may be appropriate as part of the detailed analysis of the consultation responses and the wider reforms proposed by the Independent Review.

Other recommendations some of these blocks do not have a single building owner, rather an owner of the modest freehold ground rent and the constituent long-leaseholders, the latter often being the only parties with a contractual obligation to carry out remedial works. We therefore recommend that the Government conduct an urgent review into responsibility and liability of such buildings to ensure the necessary work can be carried out for the safety of residents, which is paramount. The Government should then produce further subsequent guidance for building owners. While it is encouraging that an insurance company has recently accepted a claim to pay for remedial work on a private sector development in Greenwich, nevertheless, more needs to be done now to ensure that unsafe cladding is removed urgently. To avoid any further delay, we propose that the Government introduces a low-interest loan scheme for private sector building owners, to ensure that remedial work is carried out as quickly as possible and that costs need not immediately be passed on to leaseholders.

Government s response The Government has been clear that building owners are legally responsible for ensuring residents safety. They must undertake remediation action where potentially dangerous ACM cladding has been used and we have said that they should do all they can to protect leaseholders from incurring costs, either funding it themselves or looking at alternative routes such as insurance claims, warranties or legal action.

We are not persuaded that a review into responsibility for buildings is necessary; and would be concerned about the further delay that it could introduce into the process. We have written to the relevant building owners to remind them of their responsibilities and to highlight that, where building owners do not take action, local authorities have extensive enforcement powers to ensure that required remediation is undertaken. We welcome Mace s decision to cover the full costs of recladding two blocks at its Greenwich Square Project in south-east London. We also welcome the decision of developers such as Barratt Developments, Legal & General, Taylor Wimpey and Peabody to pay for work to remove cladding. We call on others to follow their example.

We have met leaseholders to understand their concerns, and industry to discuss the barriers to remediation and to work on solutions for individual building owners who cannot resolve building remediation themselves. We do not rule out any options if industry, individual building owners or developers do not come forward with their own solutions. Our new minister-chaired taskforce will be charged with ensuring that remediation plans are put in place swiftly across all private sector buildings with ACM cladding systems.

Government threats to private landlords James Brokenshire on 17 October 2018: In the private sector, I want to see landlords protect leaseholders from these costs. I am pleased that a number have stepped forward to do so, including Barratt Developments, Legal & General, Taylor Wimpey, Mace and Peabody. However, there are some who are not engaging in this process. If they don t, I have ruled nothing out In September 2018 the Minister wrote to around 60 building owners and developers threatening enforcement action if they do not strip unsafe material from their blocks, referring to a moral imperative. The threat may include preventing developers/owners from accessing government schemes. Plans for a two-pronged approach that would involve financial penalties on landlords and restricting access to housebuilding schemes for developers who refused to cover recladding costs: The Times, 20 October 2018

Legal challenges by private landlords On 20 October 2018, The Times reported that the government will face legal challenges to its plans to force private landlords to cover the cost of removing and replacing Grenfell Tower-style cladding from housing blocks

Dispensing with consultation requirements There have been two successful applications to the FTT under section 20ZA to dispense with the consultation requirements in view of the urgency of carrying out works considered necessary in light of the Grenfell incident. LON/00BC/LSC/2017/0086 LON/00BB/LDC/2018/0083 & LON/00BB/LDC/2018/0084

Conclusions In the public sector, the Government s position on funding beyond cladding replacement is uncertain and subject to change the question of what is considered an essential fire safety measure will likely hinge on the outcome of the inquiry. The Wandsworth fire-sprinkler case will test the RTB lease provisions as to whether leaseholders are liable. In the private sector, the Government is clear that it will not fund, and the dispute is between those with legal interests in the property. The FTT has so far found the service charge provisions to be wide enough to cover cladding replacement and waking watch measures. However, every lease is different and the dispute is only partly a legal question as to who is responsible under the lease. Some parties are voluntarily assuming responsibility, and legal/insurance/warranty claims will need to be considered.