VOLUNTARY LAND DONATION FRAMEWORK

Similar documents
SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS

Summary of Land Acquisition, Resettlement and Rehabilitation Policy for Infrastructure Development Project 2015

Social Screening and Impact Assessment for Sub Projects. B. Justification of project design and alternative analysis:

AFG: Water Resources Development Investment Program Tranche 1- Construction of Northern Basin Development Main Canals

FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATIONS OR WILLING BUYER/WILLING SELLER PROCESSES

Rural Reconstruction and Rehabilitation Sector Development Program

RESETTLEMENT POLICY FRAMEWORK AND PROCEDURAL GUIDELINES GAUNGXI ROADS DEVELOPMENT II PROJECT

SUMMARY LAND ACQUISITION PLAN. Supplementary Appendix to the. Report and Recommendation of the President to the Board of Directors.

Resettlement Planning Document

I U B Reddy The World Bank New Delhi, India

August 24, 2011 Ida Ayu Indira Dharmapatni World Bank Office Jakarta 1

Social Safeguards Due Diligence Report

Prepared by Nepal Electricity Authority and Tanahu Hydropower Limited of the Government of Nepal

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF PROJECT AFFECTED PERSONS. November 2000

RP1 85 November The Resettlement Policy Framework (RPF) Report on the GEF Hai Basin Project. (Final Version)

Land Acquisition and Resettlement Policy Framework

Expropriation. Recommended Policy Wordings (full): Lao National Land Policy. Context. Policy. Standard of Public Purpose

National Land Use Policy

Cambodia Health Equity and Quality Improvement Project (H-EQIP) (P157291) Resettlement Policy Framework (RPF) (DRAFT)

REPORT 2014/050 INTERNAL AUDIT DIVISION. Audit of United Nations Human Settlements Programme operations in Sri Lanka

In light of this objective, Global Witness is providing feedback on key sections of the 6 th draft of the national land policy:

Integrated Urban Development Project (IUDP)

Nepal: Emergency Flood damage Rahabilitation Project

B. Justification of project design and alternative analysis:

RP607. Summary of Land Acquisition & Resettlement Policy Framework JAMAICA: JM Hurricane Dean ERL Project. A. Introduction. B. Means of Obtaining Land

Mandatory Requirement for Certification Bodies in Assessing Free, Prior and Informed Consent (FPIC) in New Planting Procedures

LAND ACQUISITION AND RESETTLEMENT DUE DILIGENCE REPORT. ARMENIA: WATER SUPPLY AND SANITATION SECTOR PROJECT. Phase II

Republic of Turkey Additional Financing to Second Renewable Energy and Energy Efficiency Project Resettlement Policy Framework For TSKB and TKB

ERRA S RURAL LANDLESS PROGRAMME (PHASE - II FOR VIRTUALLY LANDLESS PEOPLE)

TONGA: Nuku alofa Urban Development Sector Project

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

TONGA: Nuku alofa Urban Development Sector Project. Core Subproject 1 (Water Supply)

LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK (LARPF)

Land Acquisition and Resettlement Framework. Date: May 2016 Status: Update. FIJI: Transport Infrastructure Investment Sector Project

Global Witness submission on Myanmar s draft national land policy

PAPUA NEW GUINEA. ROAD MAINTENANCE AND REHABILITATION PROJECT (RMRP) II Additional Financing

POYRAZ HEPP YESIL ENERJI ELEKTRIK URETIM SAN. TIC. A.S. REPORTING FORM FOR LAND ACQUISITION

LAND REFORM IN MALAWI

India: Madhya Pradesh Irrigation Efficiency Improvement Project. Subproject: Pipeline Distribution System for 500 Hectares of Command Area

Comparative Analysis of Afghanistan s Legal Framework and Involuntary Resettlement Safeguards in the ADB Safeguard Policy Statement

COMPLIANCE APPRAISAL: SUMMARY OF RESULTS

Indonesia: Neighborhood Upgrading and Shelter Project Phase 2

Mongolia: Western Regional Road Corridor Investment Program

JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK

Land Acquisition/Resettlement Framework. Proposed Loan and Administration of Grant Cook Islands: Renewable Energy Sector Project

BIOMASS-BASED DISTRICT HEATING PROJECT

Resettlement Policy Framework

PAPUA NEW GUINEA ROAD MAINTENANCE AND REHABILITATION PROJECT (RMRP) II

INDEX. of subrecipients, VIII -2 records, VI-1, 4, 13. OMB Circular A-122, VIII- 3 certification: I-28

Resettlement Framework 1 Primary Education Sector Development Program 3 (PEDP III): ADB TA NO BAN

Dhaka Water Supply and Sanitation Project Resettlement Policy Framework

Involuntary Resettlement Due Diligence Report. ARM: Water Supply and Sanitation Sector Project Additional Financing

Resettlement Policy framework for the Albania s Improvement of the Management and Conditions of the Secondary and Local Roads Project

Resettlement Plan. BHU: SASEC Road Connectivity Project. Phuentsholing Bypass Road. March 2014

RESSETTLEMENT POLICY FRAMEWORK

Resettlement Planning Document

Pakistan: Barani Integrated Water Resources Sector Project

PAK: Balochistan Water Resources Development Sector Project

DRAFT FOR PUBLIC COMMENT Guidance Note for ESS5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement

Port Moresby Power Grid Development Project.

LAND ACQUISITION FRAMEWORK

Democratizing Governance on Land towards Enhanced Access of the Poor to Land and Common Property Resources

NJ CDBG-Disaster Recovery Program (HURRICANE IRENE) Handbook. Section V Civil Rights

RESETTLEMENT FRAMEWORK. Transport Sector Development Project (RRP SOL 41171)

Integrated Safeguards Data Sheet (Updated)

Land Acquisition Framework

THE UNITED REPUBLIC OF TANZANIA PRESIDENT S OFFICE REGIONAL ADMINISTRATION AND LOCAL GOVERNMENT (PO-RALG) Tanzania Strategic Cities Project (TSCP)

Due Diligence Report on Social Safeguards. IND: Rural Connectivity Investment Program Projects I and II

Implementing Agency Department of Housing, Ministry of Local Government, Urban Development, Housing and Environment

GEO: Urban Services Improvement Investment Program Tranche 2 (Mestia Water and Sewerage Networks Project)

Socialist Republic of Vietnam POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT AND REHABILITATION OF DISPLACED PERSONS

Land for housing in African cities: are informal delivery systems institutionally robust and pro-poor?

Land Administration and Management in Nepal" Krishna Raj B.C. Joint Secretary Ministry of Land Reform and Management Nepal

Vietnam Land Administration - the Past, Recent and for the Future

Results Framework for LAPs Household-level Impacts

Upgrading and Construction of Chumateleti-Khevi Section of the E-60 Highway

HOUSING ELEMENT. 3. group and foster home construction. 1. increase the supply of new affordable housing with: a regional housing trust fund;

COAL MINE METHANE DEVELOPMENT PROJECT (SHANXI PROVINCE) RESETTLEMENT PLAN. CMM and CBM Production for Power Generation

Dhaka Water Supply and Sanitation Project

Scottish Social Housing Charter Indicators

Post Disaster Land Management Perspectives

Draft Land Acquisition and Resettlement Framework. Cambodia: National Solar Park Project

Draft Land Law (Special Regimen for Definition of Ownership of Immovable Property)

IND: Infrastructure Development Investment Program for Tourism - Tranche 1

NATIONAL GANGA RIVER BASIN AUTHORITY

Ex-Ante Evaluation (for Japanese ODA Loan)

Proposed Multitranche Financing Facility Georgia: Georgia Sustainable Urban Transport Investment Program

Scheme of Service. for. Housing Officers

Land acquisition and Resettlement Framework. Indonesia: Coral Reef Rehabilitation and Management: Coral Triangle Initiative Project (INO- COREMAP-CTI)

Government of Samoa. Ministry of Natural Resources and Environment

ABBREVIATED RESETTLMENT PLAN LEZHA MUNICIPALITY

Providing access to land: challenges and solutions Lessons learnt by members of the International Land Coalition

REPUBLIC OF MACEDONIA

LAND ACQUISITION BILL: THEN AND NOW

Land Acquisition Rehabilitation and Resettlement Act, 2013

LIVESTOCK WASTE MANAGEMENT IN EAST ASIA

Participants of the Ministerial Meeting on Housing and Land Management on 8 October 2013 in Geneva

UZB: Kashkadarya Regional Road Project

What You Can Plan For

Developing Land Policy in a Post-Conflict Environment: The Case of Southern Sudan

Transcription:

Community-Managed Irrigated Agriculture Sector Project Additional Financing (RRP NEP 33209) A. The Project and Context 1. Project Description VOLUNTARY LAND DONATION FRAMEWORK 1. The proposed Community Managed Irrigated Agriculture Sector Project Additional Financing (CMIASP-AF) aims to rehabilitate 77 farmer managed irrigation systems (FMIS) in 35 districts of the eastern and central development regions of Nepal. The project is also expected to finance the rehabilitation and partial management transfer of 5 agency-managed irrigation systems (AMIS). 2. The project will respond to requests from water User Associations (WUAs) in target areas where at least 40% households have landholdings less than 0.5 ha in the hills and 1.0 ha in the terai. The project will strengthen WUAs so they represent all water users within the command area, and improve WUA capacity in system management and equitable distribution of water across different reaches of the irrigation system. The project is expected to upgrade irrigation infrastructure to (i) enhance supplementary irrigation during the monsoon season, and (ii) where possible, provide irrigation for a second and/or third crop in the summer and/or winter season. Physical improvements of the systems will be supplemented by WUA training in effective water use and system maintenance, and the provision of irrigated agriculture extension to ensure improved water use efficiency and increased irrigated agriculture productivity. Improved irrigation efficiency is expected to lead to higher crop yields, better returns to farmers and lower prices of basic commodities. Where possible and feasible, groundwater use may supplement surface water resources, especially in water-short irrigation systems. 3. This Voluntary Land Donation Framework (VLDF) has been prepared to ensure that due diligence will be conducted on each subproject to assess the social safeguards status of a proposed subproject and confirm that the selection criteria had been met without triggering ADB s IR safeguard requirements. 2. CMIASP Experience in Land Acquisition through Voluntary Donation 4. The Community Managed Irrigated Agriculture Sector Project (CMIASP 2004) aimed to improve agriculture productivity and sustainability of existing FMIS suffering from low productivity and high incidence of poverty in the rural areas of the central and eastern development regions of Nepal. Its overall goal was to reduce poverty and improve the livelihoods of poor women and men in rural Nepal. 5. Subproject selection criteria required selection of subprojects with no resettlement or involuntary land acquisition. The project conducted due diligence on each subproject to assess the social safeguards status of the proposed subproject, and confirmed that the selection criteria had been met. When there was no involuntary resettlement (IR) effect a subproject was categorized C for the IR safeguard. No further action was required. 6. Subprojects with canal extensions, or that followed existing canal alignments but which required a small slice of private land along a canal, the project prepared resettlement plans following ADB guidelines. ADB s IR policy (OM Sections BP/F2 and Operational Procedure (OP)/F2, issued in October 2003) required preparation of a resettlement plan wherever one person or more lose more than 10% of their livelihoods. 7. For the project this meant registering losses of each affected person at the level of below or beyond 10%, the degree of vulnerability, and whether this is above or below a

2 predetermined level. Of the 111 subproject 20 subprojects had canal extensions (18%) and 2 subprojects required shifting the headwork upstream. 8. A review of 13 batch 1 and 2 subprojects (representing hill and terai from the central and eastern development regions) with canal extensions or which required widening provide census of land donors, percent of land loss, degree of vulnerability, and evidence of landowners (through whose land parcels the canal alignment passes) consent to donate land voluntarily for improving the canal alignment. Meaningful consultations are reported to have been undertaken with the land donors. 9. The project determined impacts on vulnerable people by assessing whether beneficiaries were above or below the project predetermined threshold of 10% land loss. However, in determining land loss, a beneficiary s total landholding within the command area was not taken into account. Farmers are reported to own several fragmented plots within a command area. Rather, land loss was calculated as a percent of only that land parcel(s) through which the canal alignment passed. Using this definition of land loss, the majority of beneficiaries fall in the category of losing less than 5% land. Only 5 subprojects have beneficiaries losing more than 10% land when measured only against the plot(s) through which the canal passed (Table 1). Compensatory measures provided for land donors include targeted assistance to Dalit and women headed households. Such assistance include exemption from WUA contribution, employment opportunities to at least one family member in construction activities, provision of livelihood improvement training, and priority access to water. There have not been any outstanding grievances regarding the voluntary donation of land. Table1. Land Voluntarily Donated by Beneficiaries # of APs losing > 10% land* No. ISP District Total # of APs # of APs losing 5-10% land* # of APs losing <5% land* 1. Akuwa Asine Bhojpur 25 5 7 12 2. Ghatte Khola Bhojpur 21 0 4 17 3. Kewa Khola Dhankuta 36 0 1 35 4. Talkhark Ilam 43 0 2 41 5. Ingla Khola Ilam 33 4 1 28 6. Sisneri-Chhahare Nuwakot 39 0 2 37 7. Tadi Khola Nuwakot 46 0 0 46 8. Shikhar Kateri Kavre 46 0 0 46 9. Terso kulo Kavre 33 0 0 33 10. Parwanipur Kalinjor Sarlahi 20 1 10 9 11. Balan Saptari 26 0 1 25 12. Shahutar Sankhuwasabha 10 1 2 7 13. Chharchhare Solukhumbu 19 1 5 13 Source: CMIASP consultants. List of Resettlement Plans. 2013. * calculated as a percent of only that land parcel(s) through which the canal alignment passes. 10. While the quantum of land donated is measured against the total landholding size of a donor household, the ground reality is that no farmer would be so transparent to declare his/her total landholdings in the country, and provide evidence of his/her landownership certificates for verification. Hence, upon consultation with project staff and consultants it was agreed that land donated would be measured as a percent of the donor household s total landholding in the command area. 11. To determine land loss against the total landholding in the command area three subprojects for which data were available was reviewed. The quantum of land donated by two marginal farmers was measured against their total landholdings in the command area. The percentage of land donated by a Dalit and a Brahmin beneficiary each was 3.2% and 3.9% respectively, less than the threshold of 10% land loss (Table 2).

3 12. Compensatory measures provided for land donors include targeted assistance to Dalits and women-headed households. These include exemption from WUA contribution, employment opportunities to at least one family member in construction activities, provision of training, and priority access to water. To date, no issues related to resettlement operations have been reported. Table 2. Voluntary Donation of Land as a % of Total Landholding in the Command Area No Name of Subproject Category Remarks 1 Akhuwa Asine Bhojpur 2 Shahutar, Sankhuwashabha 3 Chharchhare Sarlahi No & name of beneficiary donating >10% land* IP/Janajati** Caste Total land in CA (ha) 1. Ramesh K Pradhan Advanced 2.85 Less than 10% 2. Lila Bd. Pradhan Advanced 2.34 Less than 10% 3. Tek Bd. Pradhan Advanced 0.97 Less than 10% 4. Min Bd. Pradhan Advanced 1.02 Less than 10% 5. Bishnu Sarki Dalit 0.97 donated 3.2% of total land in command area 1.Devi Maya Adhakari Brahmin 0.97 donated 3.9% of total land in command area 1. Kamal Rai Disadvantaged -- Used HDPE during detail design, and hence donation of land was not required *calculated as a percent of only that land parcel(s) through which the canal alignment passes. ** NFIN defined categories. 2002 Source. NGO reports and ISPMC. 13. The project expected WUA members and beneficiaries to form a Grievance Redress Committee (GRC) in each subproject under the chairmanship of VDC Secretary. However, in lieu of a GRC the WUA and IDD have taken on the responsibility to resolve conflict, if any. 14. The CMIASP experience evidences landowners voluntarily contributing the canal land in rehabilitation construction in recognition of benefits, such as priority access to irrigation water and increased land price. 15. Field visits by CMIASP-AF Project Preparation team to CMIASP sites, and discussions with WUA, IDD, DADO and men and women farmers demonstrate that voluntary contribution is an acceptable option when agreed to by the concerned persons and confirmed by a third party. Since all required land acquisition will be strictly under voluntary land donation there is no issue of triggering the IR policy, and no need for preparing any resettlement plans. There is also no need to separately categorize each subproject for the IR safeguard. Due diligence will be conducted in line with the following voluntary land donation framework (VLDF) for the CMIASP-AF. B. Voluntary Land Donation Framework 1. Scope 16. The project will undertake medium farmer managed irrigation systems with no resettlement or involuntary land acquisition. It is categorized as C for the IR safeguard. The proposed subprojects will be screened for the IR impacts and only those that qualify to be

4 category C will be shortlisted. The subproject selection criteria require that the subproject is demanded by a community. Communities must submit applications for project benefits and indicate in their applications that they will voluntarily donate any necessary small parcels of land for rehabilitating irrigation infrastructure. By doing so, they become primary beneficiaries of enhanced water availability. 2. Due Diligence 17. The voluntary land donation due diligence will be documented in the subproject preparation report (SPPR) and will incorporate at a minimum the following: (i) (i) (ii) (iii) (iv) (v) Verification and documentation that land required for the project is given voluntarily and the land to be donated is free from any dispute on ownership or any other encumbrances; Verification that if more than 10% of agricultural land holding within the command area is donated the WUAs have negotiated livelihood restitution measures with the beneficiary land donors; Verification that land donation will not displace tenants or bonded labor, if any, from the land; Verification that land donated is not land used by indigenous peoples either traditionally or customarily; Meaningful consultation has been conducted with all potential landowners who may have to donate their land for irrigation subproject improvement. Documented verification that landowners donating land are in agreement with the subproject benefits. Separate discussions to be held with women and minority ethnic groups as required to facilitate meaningful participation; and Assurance that a fair system of grievance redress, as well as a system for project monitoring and reporting is operational. 3. Documentation 18. The Irrigation Development Division or Irrigation Development Subdivision (IDD) will screen for the IR safeguard during Scheme Verification by completing the land acquisition and resettlement (LAR) screening checklist (Annex1). Where subproject improvement requires canal extension or widening, IDD will document the voluntary land donation due diligence in each subproject preparation report (SPPR) that requires donation of private land. They will ensure completion of the written consent form for land donation (Annex 2). The donation will be verified by a representative of the ward or village development committee (VDC) and IDD to ensure that the land was voluntarily donated without any form of duress. The voluntary land donation due diligence information will be verified during scheme detailed design and updated as necessary. 4. Voluntary Land Donation Monitoring 19. Voluntary land donation issues will be monitored by the VDC, Department of Irrigation (through the Project Director and with support of the project implementation and management support consultants) and the Asian Development Bank (ADB) periodically through reviewing the land donation agreement forms and randomly interviewing the landowners who have donated land. During review missions, ADB will verify that land donation due diligence has been conducted in accordance with the above procedures. 5. Grievance Redress Mechanism 20. Anticipated grievances may relate to coercion for land donation or donation of more than 10% of one s agricultural land holding within the command area, leading to

5 impoverishment. A Grievance Redress Mechanism (GRC) will be established in each subproject area to receive, evaluate, and facilitate resolution of affected people s concerns, complaints, and grievances about the social and environmental performance of the project. Each GRC will be chaired by the relevant IDD chief. Members comprise two WUA representatives (a male and a female), the assigned IDD engineer, a member of the ward citizen s advisory group, and an elderly person from the subproject area (as independent member). The GRC can invite others to participate in its discussions as appropriate to the case. 21. The social mobilizer (consultant) assigned to the subproject will be responsible to form the GRC and advise subproject residents of its existence. A complainant can register grievances in the grievance register book kept in the WUA office. The register will document (i) date of grievance registered, (ii) name/address of complainant, and (iii) nature of grievance. The GRC will prepare a written assessment that describes the complaint and confirms whether the grievance is genuine. A response on the matter will be provided to the complainant within 7 days by the GRC. In case the GRC is unable to resolve the issue in 7 days, the matter will be forwarded to the office of chief district officer (CDO), who will investigate, assess and resolve the issue within 30 days of receiving the grievance. The corrective action will be carried out as agreed and documented in the grievance register book. The outcome shall also form part of the progress reports to ADB. During the entire process, the alternative to appeal at court will remain open if the complainant wishes. The details and information on use of this grievance redress mechanism will be communicated to the local stakeholders by social mobilizers and community organizers working in the subproject area.

6 ANNEX 1. VOLUNTARY LAND DONATION SCREENING CHECKLIST Name of Subproject District Brief description of the proposed subproject Region 1. Screening questions Likely Effects Yes No Remarks Will the subproject require widening or extension of the existing farmer managed irrigation system? Is the ownership status of land known? Is the current usage of land to be acquired known? Will there be loss of crops and/or trees? If yes, how much loss (%)? Will there be loss of incomes and If yes, how much loss (%)? livelihoods? 2. Information on the Beneficiary Households What is the estimated number of households likely to voluntarily donate land? What is the estimated number of households who may be required to donate more than 10% of agricultural landholding within the command area? What is the estimated number of female headed households who may donate land? What is the estimated number of Dalit households who may donate land? 3. Assessment based on the foregoing identification of impacts Are the beneficiaries willing to donate land voluntarily? (If YES conduct due diligence as per the Voluntary Land Donation Framework) Will the subproject involve involuntary land acquisition (If YES the subproject is dropped) *No involuntary resettlement (IR) impacts Yes No IR Category X X C: Due diligence required. A or B : Selection criteria not met.

7 ANNEX 2. SAMPLE VOLUNTARY LAND DONATION CONSENT Name of Irrigation Sub-Project (ISP): Location: Date of meeting and venue for voluntary land donation: We the following landowners of the above captioned ISP are fully aware that this canal is being rehabilitated at our request. We shall not claim any compensation or ownership against those voluntarily donated lands nor obstruct the construction process on the land in case of which he/she would be subject to sanctions according to law and regulations. As testimony to our voluntary donation of land for improving the irrigation infrastructure system for community benefit we the signatories below agree to provide the following land parcels: Details of voluntarily donated lands SN Name of Farmer Address Total Land area within Command Area Donated Land Area Plot No. % of land loss Location of donated land (ward/ tole) Signature Witness: WUA Executive NGO IDD/IDSD Signature: Name: Position: Date: