1 Project Procurement Management 1

2 Project Procurement Management Project need materials, equipment, consultants, training, and many other goods and services. Project procurement management is the process of purchasing the products necessary for meeting the needs of the project scope. It involves planning, acquiring the products or services from sources, choosing a source, administering the contract, and closing out the contract. It can be applied to internal work orders, formal agreements, and contracts between organizational units within a single entity. BUYERS POINT OF VIEW 2

3 Project Procurement Management When buying anything from a vendor, the buyer needs a contract, which becomes a key input to many of the processes within the project. The contract, more than anything else, specifies the rules and agreements for the project. The project manager should interact with a legal, contracting or procurement department to deal with contracts. When the seller is completing its obligations to supply a product, PMI treats those obligations as a project itself. 3

4 Project Procurement Management All the process in the Procurement Management will be performed for each items to be acquired or purchased. Centralized/Decentralized Contracting 4

5 Project Manager's Role in Procurement The project manager must be involved in the creation of contracts and fulfills the following key roles: Know the procurement process Understand contract terms and conditions Make sure the contract contains all the project management requirements such as attendance at meeting, reports, actions and communications deemed necessary Identify risks and incorporate mitigation and allocation of risks into the contract 5

6 Project Manager's Role in Procurement Help tailor the contract to the unique needs of the project Fit the schedule for completion of the procurement process into the schedule for the project Be involved during contract negotiation to protect the relationship with the seller Project the integrity of the project and the ability to get the work done Uphold the entire contract, not just the contract statement of work Work with the contract manager to manage changes to the contract 6

7 The Sequential Procurement Processes 1. Plan Procurements 2. Conduct Procurements 3. Administer Procurement 4. Close Procurements 7

8 Project Procurement Management Processes 1. Plan Procurements : the process of documenting project purchasing decisions, specifying the approach, and identifying potential sellers 2. Conduct Procurements : the process of obtaining seller responses, selecting a seller, and awarding a contract 3. Administer Procurements : the process of managing procurement relationships, monitoring contract performance, and making changes and corrections as needed 4. Close Procurements : the process of completing each project procurement 8

9 12.1 Plan Procurements Is the process of documenting project purchasing decisions, specifying the approach, and identifying potential sellers. Procurement planning is the process of identifying which part of the project should be procured from resources outside of the organization. It is concerned with determining what to procure, when, and how Generally, procurement decisions are made early on in the planning processes. Procurement planning centers on four elements: Whether or not procurement is needed? What to procure? How much to procure? When to procure? 9

10 12.1 Plan Procurements This process also includes consideration of potential sellers, particularly if the buyer wishes to exercise some degree of influence and control over acquisition decisions The requirements of the project schedule can significantly influence the strategy during this process. This process includes consideration of the risks involved with each make or buy decision. It also includes reviewing the type of contract planned to be used with respect to mitigating risks, sometimes transferring risks to sellers 10

11 12.1 Plan Procurements Inputs Tools & Techniques Outputs 1. Scope Baseline 2. Requirements Documentation 3. Teaming agreements 4. Risk register 5. Risk related contractual agreements 6. Activity Resource requirements 7. Project schedule 8. Activity cost estimates 9. Cost Performance baseline 10. Environmental factors 11. Organizational process assets 1. Make-or-buy analysis 2. Expert Judgment 3. Contract types 1. Procurement management Plan 2. Procurement Statements of work 3. Make-or-buy decisions 4. Procurement Documents 5. Source selection criteria 6. Change request 11

12 12.1 Plan Procurements : Inputs 1. Scope Baseline : Describes the need, justification, requirements and current boundaries for the project. It contains : The scope statement (The project scope statement defines the project work, and only the required work, to complete the project, it also defines the limitations of the project), WBS, and the WBS Dictionary 2. Requirements Documentation : may include : Imp information about project requirements that is considered during planning for procurements Requirements with contractual and legal implications that may include health, safety, security, performance, environmental,insurance,intellectual property rights,licenses,permits,etc all of which are considered when planning for procurements 3. Teaming Agreements : are legal contractual agreements between two or more entities to form a partnership or joint venture, or some other arrangement as defined by the parties.the agreement defines the buyer seller roles for each party. Whenever a teaming agreement is in place for a project, the roles of buyer and seller are predetermined 12

13 12.1 Plan Procurements : Inputs 4. Risk Register : Includes risk related information such as the identified risks, risk owners and risk responses 5. Risk related contract decisions 6. Activity Resource Requirements : contains information on specific needs such as people, equipment or location 7. Project Schedule : contains information on required timelines or mandated deliverable dates 8. Activity Cost Estimates : developed by the procuring activity are used to evaluate the reasonableness of the bids or the proposals received from potential sellers 9. Cost Performance Baseline : provides details of the planned budget overtime 10 Enterprise Environmental Factors : include but are not limited to : market place conditions,products,services,and results that are available in the marketplace,suppliers, including past performance and reputation, unique local requirements,typical terms and conditions for products, services or results or for the specific industry (Sole Sources, Single Source & Oligopoly) 11. Organizational Process Assets : How the procurement process work within the performing organization

14 12.1 Plan Procurements Tools & Techniques Make-or-buy analysis: general management technique used to determine whether an organization should make or perform a particular product or service inside the organization or buy from someone else Often involves financial analysis Experts, both internal and external, can provide valuable inputs in procurement decisions 14

15 12.1 Plan Procurements Tools & Techniques 1. Make-or-Buy Analysis 15

16 Make or Buy Decision Sample Question: You are trying to decide whether to lease or buy an item for your project. The daily lease cost is Dhs To purchase the item investment cost is Dhs and the daily cost is Dhs. 20. How long will it take for the lease cost to be the same as the purchase cost? 16

17 Make or Buy Decision Answer: Let D equal the number of days when the purchase and lease costs are equal. QR 120 D = QR QR 20 D QR 120 D - QR 20 D = QR 1000 QR 100 D = QR 1000 D = QR 1000 / QR 100 D = 10 The least cost will be the same as the purchase cost after ten days. 17

18 Make-or-Buy Example Assume you can lease an item you need for a project for $800/day; to purchase the item, the cost is $12,000 plus a daily operational cost of $400/day How long will it take for the purchase cost to be the same as the lease cost? 18

19 Make-or Buy Solution Set up an equation so both options, purchase and lease, are equal In this example, use the following equation; let d be the number of days to use the item: $12,000 + $400d = $800d Subtracting $400d from both sides, you get: $12,000 = $400d Dividing both sides by $400, you get: d = 30 If you need the item for more than 30 days, it is more economical to purchase it 19

20 12.1 Plan Procurements Tools & Techniques 2. Expert Judgment Expert judgment for procurement management planning can come from the following: Units or individuals within the performing organization Consultants and subject matter experts Professional, trade, or technical associations Industry groups 20

21 12.1 Plan Procurements Tools & Techniques 3. Contract Types Fixed Price Contract In this type of contract one price is agreed upon for all the work. The buyer has the least cost risk, provided the buyer has a completely defined scope, because the risk of higher costs is borne by the seller. The seller is most concerned with the contract statement of work in this type of contract. 21

22 12.1 Plan Procurements Tools & Techniques 3. Contract Types Firm Fixed Price Contracts (FFP ): The most commonly used contract type because price of the goods is set at the onset and not subject to change unless the scope of work changes. Any cost increase due to adverse performance is the responsibility of the seller. Under this type of contract the buyer must precisely specify the product or services to be procured, and any changes to the procurement specification can increase the costs to the buyer 22

23 Fixed Price Contract Variations Fixed Price Incentive Fee Contracts (FPIF) There are also incentives for fixed price contracts. Contract = Dhs. 1,100,000. For every month early the project is finished, an additional Dhs. 10,000 is paid to the seller. 23

24 Fixed Price Contract Variations Fixed Price Economic Price Adjustment (FPEPA) Sometimes a fixed price contract allows for price increases if the contract is for multiple years. Example Contract = Dhs. 1,100,00 but a price increase will be allowed in year two based on the Consumer Price Increase report for year one. Or the contract price is Dhs. 1,100,000 but a price increase will be allowed in year two to account for increases in specific material costs. 24

25 Purchase Order Purchase Order A purchase order is the simplest type of fixed price contract. This type of contract is normally unilateral (signed by one party) instead of bilateral. It is usually used for simple commodity procurements. Purchase orders are considered contracts when they are accepted either by performance ( Material is shipped by the seller ) or by signing a purchase order. Example Contract to purchase 30 linear meters of wood at Dhs. 40 per meter. 25

26 Cost-reimbursable Contract The seller's cost are reimbursed, plus an additional amount. The buyer has the most cost risk because the total costs are unknown. This form of contract is often used when the buyer can only describe what is needed, rather than what to do. The seller will therefore write the detailed contract statement work. 26

27 Cost-reimbursable Contract - Variations Cost plus Fixed Fee (CPFF) This is the most common type of cost reimbursable contract. In this type, the buyer pays all costs, but the fee (or profit) is fixed at a specific amount. This helps to keep the seller's costs in line because a cost overrun will not generate any additional fee or profit. Fees only change with approved change orders. Example Contract = Cost + Fee of Dhs 100,000 27

28 Cost-reimbursable Contract - Variations Cost Plus Fee (CPF) or Cost Plus Percentage of Costs (CPPC) This type of cost reimbursable contract requires the buyer to pay for all costs plus a percent of costs as a fee. Sellers are not motivated to control costs because the seller will get paid profit on every cost without limit. Example Contract = Cost + 10% of costs as fee. 28

29 Cost-reimbursable Contract - Variations Cost Plus Incentive Fee (CPIF) This type of cost reimbursable contract pays all costs and an agreed upon fee, plus a bonus for beating the performance objectives stated in the contract. 29

30 Cost-reimbursable Contract - Variations Cost Plus Award Fee Contracts ( CPAF) : The seller is reimbursed for all legitimate costs, but the majority of the fees is only earned based on the satisfaction of certain broad subjective performance criteria defined and incorporated into the contract. The determination of the fee is solely on the subjective determination of seller performance by the buyer, and is generally not subject to appeals 30

31 Time and Material (T&M) or Unit Price This type of contract is usually used for small amounts. The contract is priced on a per hour or per item basis and has elements of fixed price contract (in the fixed price per hour) and a cost reimbursable contract (in the material costs and the fact that the total cost is unknown). In this type of, the buyer has a medium amount of cost risks compared to CR and FP because the contract is usually for small amounts and for a shorter length of time. Example Contract = Dhs. 100 per hour + expenses or materials at cost or Dhs 10 per linear meter of wood. 31

32 Fixed-price contracts transfer the risk to the seller 32

33 33

34 12.1 Plan Procurements - Outputs 1. Procurement Management Plan How vendors will be selected, the type of contracts to be used The process of independent estimating (also known as should-cost estimates) The relationship between the project team and the procurement office within the performing organization (if one exists) The procurement forms, such as contracts, that the project team is required to use How multiple vendors will be managed to supply their contracted product The coordination between sellers and the project team and among project activities, project reporting, scheduling, business operations, and other project concerns Risk management issues etc 34

35 12.1 Plan Procurements - Outputs 2. Procurement Statements of Work A procurement statement of work (SOW) contains the details of the procurement item in clear, concise terms. It includes the following elements: The project objectives A description of the work of the project and any post-project operational support needed Concise specifications of the product or services required The project schedule, time period of services, and work location 35

36 Statement of Work (SOW) Template I. Scope of Work: Describe the work to be done to detail. Specify the hardware and software involved and the exact nature of the work. II. III. IV. Location of Work: Describe where the work must be performed. Specify the location of hardware and software and where the people must perform the work Period of Performance: Specify when the work is expected to start and end, working hours, number of hours that can be billed per week, where the work must be performed, and related schedule information. Deliverables Schedule: List specific deliverables, describe them in detail, and specify when they are due. V. Applicable Standards: Specify any company or industry-specific standards that are relevant to performing the work. VI. VII. Acceptance Criteria: Describe how the buyer organization will determine if the work is acceptable. Special Requirements: Specify any special requirements such as hardware or software certifications, minimum degree or experience level of personnel, travel requirements, and so on. 36

37 12.1 Plan Procurements - Outputs 3. Make-or-Buy Decisions Change Requests : change requests to the project management plan, its subsidiary plans, or other components may result from this process Procurement Documents : are used to solicit proposals from the prospective sellers. Request for Proposals: used to solicit proposals from prospective sellers A proposal is a document prepared by a seller when there are different approaches for meeting buyer needs Requests for Quotes: used to solicit quotes or bids from prospective suppliers A bid, also called a tender or quote (short for quotation), is a document prepared by sellers providing pricing for standard items that have been clearly defined by the buyer 37

38 4. Procurement Documents Procurement documents may include the following: Information for Sellers Background information Procedures for replying Guidelines for preparation of the response Form of response required Evaluation Criteria Pricing forms Contract Statement of work Proposed terms and conditions of the contract (legal and business) 38

39 Procurement Documents Non-Disclosure Agreement This is an agreement between the buyer and any prospective sellers stating what information or documents they will hold confidential and control, and who in their organization will gain access to the confidential information. Standard Contract Companies frequently have standard, preauthorized contracts for the purchase of goods or services. These types of standard contracts need no further legal review if used as they are. Special Provisions (Special Conditions) The project manager should determine what needs to be added, changed or removed from the standard provisions, so that the resulting contract addresses the particular needs of the project. 39

40 Procurement Documents Letter of Intent NOT a contract but a letter, without legal binding, that says the buyer Privity intends to hire the seller. Contractual relationship. Example Company A hires company B to do some work for them. Company B subcontracts to company C. The project manager for A is at the job site and tells company C to stop work. Generally, does company C have to listen? 40

41 Procurement Documents

42 12.1 Plan Procurements - Outputs 5. Source Selection Criteria : Source Selection criteria are included in the procurement document to give the seller an understanding of the buyer's needs and help them decide if they should bit or make a proposal on the work. During Select sellers, this criteria become the basis by which the bids or proposal are evaluated by the buyer. Selection criteria can be limited to purchase price if the procurement item is readily available from a number of acceptable sellers.

43 12.1 Plan Procurements - Outputs The following list includes some of the criteria you can consider using for evaluating proposals and bids: Comprehension and understanding of the needs of the project as documented in the contract SOW Technical ability of vendor and their proposed team and the technical approach Experience on projects of similar size and scope, including references, past performance of sellers Project management approach Management approach

44 12.1 Plan Procurements - Outputs The following list includes some of the criteria you can consider using for evaluating proposals and bids: Financial stability and capacity, production capacity and interest Intellectual and proprietary rights Overall or life cycle cost : will the selected seller produce the lowest total cost of ownership purchase cost plus operating cost) Risk Warranty Business Size and type, references

45 12.2 Conduct Procurements Is the process of obtaining seller responses, selecting a seller and awarding a contract. In this process the team will receive bids or proposals and will apply preciously defined selection criteria to select one or more sellers who are qualified to perform the work and acceptable as a seller 45

46 12.2 Conduct Procurements Inputs Tools & Techniques Outputs 1. Procurement management plan 2. Procurement Documents 3. Source Selection Criteria 4. Qualified seller list 5. Seller proposals 6. Project documents 7. Make or buy decisions 8. Teaming agreements 9. Organizational Process Assets 1. Bidder Conferences 2. Proposal evaluation techniques 3. Independent estimates 4. Expert judgement 5. Advertising 6. Internet search 7. Procurement Negotiations 1. Selected sellers 2. Procurement contract award 3. Resource calendars 4. Change requests 5. Project management plan 6. Project document updates 46

47 12.2 Conduct Procurements Procurement management plan Procurement Documents Source Selection Criteria Qualified seller list Seller proposals Project documents : risk register, risk related contract decisions Make or buy decisions Teaming agreements Organizational Process Assets : include, but are not limited to : listings of prospective and preciously qualified sellers, information on the relevant past experience with the sellers, good and bad 47

48 12.2 Conduct Procurements Tools & Techniques Bidder Conferences : Bidder conferences are meetings with prospective vendors or sellers that occur prior to the completion of their response proposal. Proposal evaluation techniques Independent estimates / Should-Cost Estimate : Comparing the cost to an estimate created inhouse or with outside assistance. Expert judgement Advertising : Advertising is letting potential vendors know that an RFP is available. Internet search Procurement Negotiations : The project manager may be involved during negotiations to clarify project requirements, and if for no other reason than to protect the relationship to clarify project requirements, and if for no other reason than to protect the relationship with the other side. Many projects go bad because of how negotiations were handled. The objectives of negotiation are to: Obtain a fair and reasonable price Develop a good relationship with the seller 48

49 12.2 Conduct Procurements Tools & Techniques Main Items to Negotiate Responsibilities Authority Applicable Law Technical and business management approaches Contract financing Schedule Payment and price 49

50 12.2 Conduct Procurements Outputs 1. Selected Sellers : A seller may simply be selected and asked to sign a standard contract A seller may be asked to make a presentation and then, if all goes well, go on to negotiations The list of sellers may be narrowed down to a few The short-listed sellers may be asked to make presentations and the selected seller then asked to go on to negotiations The buyer can negotiate with more than one seller Or some combination of presentations and negotiations

51 12.2 Conduct Procurements Outputs 2. Procurement Contract Award : Contracts are known by many names: Agreement, Subcontract, Purchase order, Memorandum of understanding Is awarded to each selected seller. A contract can be in the form of a simple purchase order or a complex document. A contract is a mutually binding legal agreement that obligates the seller to provide the specified products, services or results and obligates the buyer to compensate the seller What do you need to have a legal contract? An offer Acceptance Consideration - Something of value, not necessarily money Legal capacity - Separate legal parties, competent parties Legal purpose - You cannot have a contract for the sale of illegal goods

52 12.2 Conduct Procurements Outputs 3. Resource Calendars : the quantity and the availability of contracted resources and those dates on which each specific resource can be active or idle are documented 4. Change Requests 5. Project Management Plan Updates : components of the plan that may get updated include, but are not limited to : Cost baseline Scope baseline Schedule baseline Procurement Management Plan 6. Project Document Updates : docs that may get updated include, but are not limited to : Requirements documentation Requirements traceability documentation, and, Risk register

53 12.3 Administer Procurements This process consists of assuring that the performance of both parties to the contract meets contractual requirements. The Contract Administration process concerns monitoring the vendor s performance and ensuring that all the requirements of the contract are met. Contracts are legal relationships, so it is important that legal and contracting professionals be involved in writing and administering contracts 53

54 12.3 Administer Procurements Inputs Tools & Techniques Outputs 1. Contract 2. Project Management Plan - Contract management plan 3. Procurement Documents 4. Performance reports 5. Approved change requests 6. Work performance Information 1. Contract change control system 2. Procurement performance review 3. Inspections and audits 4. Performance reporting 5. Payment system 6. Claims administration 7. Records management system 1. Procurement documentation 2. Change Requests 3. Organizational process assets (updates) 4. Project management plan (updates). Procurement management plan. Contract management plan 54

55 12.3 Administer Procurements : Inputs Contract Project Management Plan - Contract management plan Procurement Documents : contain complete supporting records for administration of the procurement processes. This includes procurement contract awards and the statement of work Performance reports : seller performance related documentation includes : Seller developed technical documentation and other deliverable information provided in accordance with the terms of the contract Seller performance reports that indicate which deliverables have been completed and which have not 55

56 12.3 Administer Procurements : Inputs Approved change requests : can include modifications to the terms & conditions of the contract. Work performance Information : the extent to which the quality standards are being satisfied, what costs have been incurred, which seller invoices have been paid, etc 56

57 12.3 Administer Procurements Tools & Techniques 1. Contract change control system 2. Procurement performance reviews 3. Inspections and audits 4. Performance reporting 5. Payment system 6. Claims administration 7. Records management system 57

58 Contract change control system The contract change control system defines the procedures for how the contract may be changed. The system is part of integrated change control. It documents how to submit changes, establishes the approval process, and outlines authority levels. It includes a tracking system to number the change requests and record their status 58

59 Suggestions for Change Control in Contracts Changes to any part of the project need to be reviewed, approved, and documented by the same people in the same way that the original part of the plan was approved Evaluation of any change should include an impact analysis; how will the change affect the scope, time, cost, and quality of the goods or services being provided? Changes must be documented in writing; project team members should also document all important meetings and telephone phone calls 59

60 Procurement performance reviews Buyer conducted performance reviews examine the seller s performance on the contract to date. These reviews may be conducted at the end of the contract or at intervals during the contract period. Buyer reviews examine the contract terms and seller performance for elements such as these: Meeting project scope Meeting project quality Staying within project budgets Meeting the project schedule 60

61 Inspections and audits As the vendor completes the contracted work, the seller will need to inspect the work for progress, compliance with contract requirements, and adherence to agreed-to time, cost, and quality constraints. 61

62 Performance reporting This tool and technique entails providing your managers and stakeholders with information about the vendor s progress meeting the contract objectives. Performance reporting is part of communications and should be documented within the communications management plan. 62

63 Payment system Vendors submit seller invoices as an input to this process, and the payment system is the tool and technique used to issue payment. The organization may have a dedicated department, such as accounts payable, that handles vendor payments, or it might fall to the project manager. In either case, follow the policies and procedures the organization established regarding vendor payments. 63

64 Claims administration A claim is an assertion that the buyer did something that has hurt the seller and the seller asking for compensation. Another way of looking at claims is that they are a form of seller's change requests. Claims can get nasty. Imagine a seller that is not making as much profit as he hoped for, issuing claims for every action taken by the buyer. Claims administration involves documenting, monitoring, and managing changes to the contract. 64

65 Claims administration Changes that cannot be agreed upon are called contested changes. Contested changes usually involve a disagreement about the compensation to the vendor for implementing the change. You might believe the change is not significant enough to justify additional compensation, whereas the vendor believes they ll lose money by implementing the change free of charge. 65

66 Claims Administration Contested changes are also known as disputes, claims, or appeals. These can be settled directly between the parties themselves, through the court system, or by a process called arbitration. Arbitration involves bringing all parties to the table with a third, disinterested party who is not a participant in the contract to try to reach an agreement. The purpose of arbitration is to reach an agreement without having to go to court. 66

67 Records Management System A contract is a formal, legal document. Recording keeping can be critical if actions taken or situations faced during a project are ever in question after the work is completed. This can happen related to unresolved claims or legal actions, or even in order to satisfy insurance needs. A record management system can be quite extensive, with one person assigned just to manage these records. They can also include indexing systems, archiving systems and information retrieval systems for projects with extensive documentation. 67

68 12.3 Administer Procurements - Outputs 1. Procurement documentation 2. Change Requests 3. Organizational process asset updates : correspondence, payment schedules and requests, seller performance evaluation documentation 4. Project management plan updates : docs that can get updated include : but are not limited to : procurement management plan, baseline schedule, etc 68

69 Procurement documentation This output includes (but isn t limited to) all of the following: Contract Performance information Warranties Financial information (like invoices and payment records) Inspection and audit results Supporting schedules Approved and unapproved changes

70 12.4 Close Procurements This process consists of finishing all the loose ends of the contract. This process is part of the close project process described in integration. Contract closure is done: When a contract ends When a contract is terminated before the work is completed 70

71 12.4 Close Procurements This process is concerned with completing and settling the terms of the contract. It supports the Close Project process because the Contract Closure process determines if the work described in the contract was completed accurately and satisfactorily. This is called product verification. 71

72 12.4 Close Procurements Close Project verifies and documents the project outcomes just like the Contract Closure process. Keep in mind that not all projects are performed under contract so not all projects require Contract Closure. However, all projects do require the Close Project process. Since verification and documentation of the project outcomes occur in both of these processes, projects that are performed under contract need to have project results verified only one time. 72

73 12.4 Close Procurements Inputs Tools & Techniques Outputs 1. Project Management Plan Procurement management plan 2. Procurement Documentation 1. Procurement audits 2. Records management system 3. Negotiated Settlements 1. Closed Procurements 2. Organizational process assets (updates) 73

74 12.4 Close Procurements : Inputs The Contract Closure process has two inputs: Project Management Plan Procurement management plan Procurement Documentation 74

75 12.4 Close Procurements Tools & Techniques The Contract Closure process has three tools and techniques: 1. Procurement audits 2. Records management system. 3. Negotiated Settlements : In all procurement relationships the final equitable settlement of all outstanding issues, claims, and disputes by negotiations is a primary goal. Whenever settlement cannot be achieved by direct negotiation, some form of alternative dispute resolution (ADR) including mediation or arbitration may be explored. When all else fails, litigation in the courts is the least desirable option 75

76 Procurement audits Procurement audits examine the procurement process to determine areas of improvement and to identify flawed processes or procedures. The primary purpose of the procurement audit is to identify lessons learned during the procurement process. This allows you to reuse the successful processes on other procurement items for this project, on future projects, or elsewhere in the organization. It also alerts you to problems in the process so that you don t repeat them. 76

77 12.4 Close Procurements - Outputs 1. Closed Procurements : This is formal acceptance and closure of the contract. The buyer provides the seller with a formal written notice that the contract has been completed.requirements for formal procurement closure are usually defined in the terms and conditions of the contract and are included in the procurement management plan It s your responsibility as project manager to document the formal acceptance of the contract. Many times the provisions for formalizing acceptance and closing the contract are spelled out in the contract itself. 77

78 12.4 Close Procurements - Outputs 1. Organizational process assets (updates) : assets that may get updated, include but are not limited to : Procurement File : a complete set of indexed contract documentation, including the closed contract, is prepared for inclusion with the final project files Deliverable acceptance : the buyer provides the seller with a formal written notice that the deliverables have been accepted or rejected. Lessons learned documentation 78

PMP Exam Preparation Workshop. Chapter # 12 Project Procurement Management

PMP Exam Preparation Workshop. Chapter # 12 Project Procurement Management PMP Exam Preparation Workshop Chapter # 12 Copyright 2013 PMI SOC 1 Objective & Agenda Introduction to Understanding the processes of project procurement management in the four process groups: 1. 2. 3.

More information

Project Management Professional (PMP) Exam Prep Course 12 - Project Procurement Management

Project Management Professional (PMP) Exam Prep Course 12 - Project Procurement Management Project Management Professional (PMP) Exam Prep Course 12 - Project Procurement Management Slide 1 Project Procurement Management Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S.

More information

PM tutor CONDUCT PROCUREMENT. Presented by. Dipo Tepede, PMP, SSBB, MBA. Empowering Excellence

PM tutor CONDUCT PROCUREMENT. Presented by. Dipo Tepede, PMP, SSBB, MBA. Empowering Excellence PM tutor Empowering Excellence CONDUCT PROCUREMENT Presented by Dipo Tepede, PMP, SSBB, MBA www.pmtutor.org Powered by POeT Solvers Ltd PROCUREMENT PROCESSES PROCESSES BY PROCESS GROUP Planning Execu5ng

More information

Intent: To establish a policy and guidelines for all procurement activities in the city. SECTION I: Purpose of Purchasing Policies...

Intent: To establish a policy and guidelines for all procurement activities in the city. SECTION I: Purpose of Purchasing Policies... Policy Number: Appendix C Subject: Revised: 03/26/2012 Issued: 02/10/97 Page: 1 of 10 Intent: To establish a policy and guidelines for all procurement activities in the city. Applies to: All City Employees

More information

Contract Management Body of Knowledge, Acquisition Planning and Strategy, and Post- Award Competencies

Contract Management Body of Knowledge, Acquisition Planning and Strategy, and Post- Award Competencies Contract Management Body of Knowledge, Acquisition Planning and Strategy, and Post- Award Competencies Breakout Session #: B17 Presented by: Dr Mike Criss, CPCM, C.P.M., CSI Date: July 22, 2013 Time: 2:30

More information

Contract Law Basics and Standard Form Construction Contracts ENSC SFU. Presented by: Bob Gill, MEng, PEng, FEC

Contract Law Basics and Standard Form Construction Contracts ENSC SFU. Presented by: Bob Gill, MEng, PEng, FEC Contract Law Basics and Standard Form Construction Contracts ENSC 406 - SFU Presented by: Bob Gill, MEng, PEng, FEC Overview > Contract Law Basics > Construction Contracts > Typical Forms > Project Delivery/Contract

More information

Your guide to selling a home

Your guide to selling a home Your guide to selling a home Your guide to selling a home DISCLAIMER This booklet is an introductory guide. Buying property is a complex and sometimes fast-moving legal process. Every transaction is different,

More information

Stock Purchase Agreement Commentary

Stock Purchase Agreement Commentary Stock Purchase Agreement Commentary This is just one example of the many online resources Practical Law Company offers. PLC Corporate and Securities Commentary on key terms and conditions commonly found

More information

Central Kentucky Educational Cooperative

Central Kentucky Educational Cooperative Central Kentucky Educational Cooperative Name of Co-operative PROCUREMENT PLAN CHILD NUTRITION PROGRAM This procurement plan contained on the following pages 1 through 10 will be implemented on _April

More information

INFORMATION FOR VENDORS DOING BUSINESS WITH THE CITY OF CORAL SPRINGS, FLORIDA FINANCIAL SERVICES DEPT

INFORMATION FOR VENDORS DOING BUSINESS WITH THE CITY OF CORAL SPRINGS, FLORIDA FINANCIAL SERVICES DEPT Updated 11/21/2014 VENDOR HANDBOOK INFORMATION FOR VENDORS DOING BUSINESS WITH THE CITY OF CORAL SPRINGS, FLORIDA FINANCIAL SERVICES DEPT./PURCHASING DIVISION 9551 W SAMPLE RD CORAL SPRINGS, FL 33065 TABLE

More information

Prepared by Office of Procurement and Real Property Management. This replaces Administrative Procedure No. A8.215 dated November 2012 A8.

Prepared by Office of Procurement and Real Property Management. This replaces Administrative Procedure No. A8.215 dated November 2012 A8. Prepared by Office of Procurement and Real Property Management. This replaces Administrative Procedure No. A8.215 dated November 2012 A8.215 A8.215 Definitions A8.200 Procurement October 2013 The words

More information

TRIBAL CODE CHAPTER 13 PROCUREMENT AND PROPERTY MANAGEMENT

TRIBAL CODE CHAPTER 13 PROCUREMENT AND PROPERTY MANAGEMENT TRIBAL CODE CHAPTER 13 PROCUREMENT AND PROPERTY MANAGEMENT CONTENTS: 13.101 Definitions. 13.102 Compliance. 13.103 Financial Reporting and Recordkeeping. 13.104 Maintenance of Property. 13.105 Disposition

More information

The What, Why and How of Project Work Breakdown Structures (WBS)

The What, Why and How of Project Work Breakdown Structures (WBS) PM TUTORIAL The What, Why and How of Project Work Breakdown Structures (WBS) Purpose This document is a guide for understanding, preparing and using a Work Breakdown Structure (WBS) as a part of planning

More information

EAST BATON ROUGE REDEVELOPMENT AUTHORITY ADMINISTRATIVE POLICY PROCUREMENT CONTRACTING AND DBE POLICY FOR FEDERALLY FUNDED PROJECTS.

EAST BATON ROUGE REDEVELOPMENT AUTHORITY ADMINISTRATIVE POLICY PROCUREMENT CONTRACTING AND DBE POLICY FOR FEDERALLY FUNDED PROJECTS. EAST BATON ROUGE REDEVELOPMENT AUTHORITY ADMINISTRATIVE POLICY PROCUREMENT CONTRACTING AND DBE POLICY FOR FEDERALLY FUNDED PROJECTS February 5, 2013 East Baton Rouge Redevelopment Authority 801 North Blvd,

More information

REQUEST FOR PROPOSAL. SEEKING A MANAGEMENT AGENT for the CASA DE LOS ARCOS HOUSING PROJECT. RFP No

REQUEST FOR PROPOSAL. SEEKING A MANAGEMENT AGENT for the CASA DE LOS ARCOS HOUSING PROJECT. RFP No REQUEST FOR PROPOSAL SEEKING A MANAGEMENT AGENT for the CASA DE LOS ARCOS HOUSING PROJECT RFP No. 229-13-001 ARCHULETA COUNTY HOUSING AUTHORITY PAGOSA SPRINGS, CO Let Date: June 19, 2013 Response Deadline:

More information

PPP Project Realization Roadmap for Public Entities. based on the PPP Act and the Act on Concessions for Construction Work or Services

PPP Project Realization Roadmap for Public Entities. based on the PPP Act and the Act on Concessions for Construction Work or Services PPP Project Realization Roadmap for Public Entities based on the PPP Act and the Act on Concessions for Construction Work or Services 1. Identification of needs and possibilities to fulfil them by means

More information

City of Hays Request for Proposals

City of Hays Request for Proposals City of Hays Request for Proposals Sewer Camera Date of Issue: Proposal Due Date July 9, 2008 Table of Contents 1. INTRODUCTION...3 2. RULES OF PREPARATION...3 3. INQUIRIES...3 4. SUBMISSION OF PROPOSALS...3

More information

LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDERS UNDER

LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDERS UNDER LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDERS UNDER JSF LRIP 3 CONTRACT NUMBER N00019-08-C-0028 Generated using

More information

STATE OF MINNESOTA OFFICE OF THE STATE AUDITOR

STATE OF MINNESOTA OFFICE OF THE STATE AUDITOR REBECCA OTTO STATE AUDITOR STATE OF MINNESOTA OFFICE OF THE STATE AUDITOR SUITE 500 525 PARK STREET SAINT PAUL, MN 55103-2139 (651) 296-2551 (Voice) (651) 296-4755 (Fax) state.auditor@osa.state.mn.us (E-mail)

More information

APPRAISAL MANAGEMENT COMPANY

APPRAISAL MANAGEMENT COMPANY APPRAISAL MANAGEMENT COMPANY STANDARDS OF GOOD PRACTICE IN APPRAISAL MANAGEMENT JANUARY 6, 2010 POST OFFICE BOX 1196 WEXFORD, PA 15090 (P) 724-934-1420 (F) 724-934-0057 (W) WWW.TAVMA.ORG APPRAISAL MANAGEMENT

More information

Request for Proposals for Commercial Real Estate Brokerage Services Port Angeles, Washington. Issued June 6, 2016

Request for Proposals for Commercial Real Estate Brokerage Services Port Angeles, Washington. Issued June 6, 2016 Request for Proposals for Commercial Real Estate Brokerage Services Port Angeles, Washington Issued June 6, 2016 Proposal Due Date: June 13, 2016 RFP FOR PROPOSALS ( RFP ) COMMERCIAL REAL ESTATE BROKERAGE

More information

Town of Waldoboro ADMINISTRATIVE POLICY

Town of Waldoboro ADMINISTRATIVE POLICY Town of Waldoboro ADMINISTRATIVE POLICY Effective Date: December 1, 2010 Regulation No: 2010 001 Revision Date: None Supersedes: None Approved By: Board of Selectmen Subject: SECTION I. PURPOSE This policy

More information

Agenda Item 11. Fixed price contract : A contract that provides a price for each procurement item obtained under the contract.

Agenda Item 11. Fixed price contract : A contract that provides a price for each procurement item obtained under the contract. Agenda Item 11 Fixed price contract : A contract that provides a price for each procurement item obtained under the contract. Definite quantity contract a fixed price contract that provides for the supply

More information

Housing Authority of the County of Salt Lake Request for Qualifications. Professional Consulting Services for the Disposition of Public Housing

Housing Authority of the County of Salt Lake Request for Qualifications. Professional Consulting Services for the Disposition of Public Housing Housing Authority of the County of Salt Lake Request for Qualifications Professional Consulting Services for the Disposition of Public Housing Janice Kimball Executive Director Housing Authority of the

More information

CHAPTER 304 TOWN OF SCARBOROUGH PURCHASING POLICY

CHAPTER 304 TOWN OF SCARBOROUGH PURCHASING POLICY CHAPTER 304 TOWN OF SCARBOROUGH PURCHASING POLICY Adopted 4/20/94 Amended 04/18/01 Amended 09/17/03 Amended 11/01/17 Section 1. Purpose... 1 Section 2. Definitions... 1 1. Approved vendors.... 1 2. Bid

More information

In Conduct Procurements process negotiations occurs.

In Conduct Procurements process negotiations occurs. PMP Mock Questions Subject: Project Procurement Management No of Questions: 49 www.techfaq360.com Questions Question - 1 During what part of Procurement Management process does procurement negotiations

More information

Do I Need a Licence? Interpreting the Definition of Providing Condo Management Services.

Do I Need a Licence? Interpreting the Definition of Providing Condo Management Services. Do I Need a Licence? Interpreting the Definition of Providing Condo Management Services www.cmrao.ca info@cmrao.ca Condominium Management Regulatory Authority of Ontario Do I Need A Licence? Interpreting

More information

THE TOWN OF BANCROFT REQUEST FOR PROPOSAL (RFP) COMMERCIAL REAL ESTATE BROKERAGE SERVICES

THE TOWN OF BANCROFT REQUEST FOR PROPOSAL (RFP) COMMERCIAL REAL ESTATE BROKERAGE SERVICES THE TOWN OF BANCROFT REQUEST FOR PROPOSAL (RFP) 2016-02 COMMERCIAL REAL ESTATE BROKERAGE SERVICES Proposals will be received at the Town of Bancroft Municipal Office, 24 Flint Ave., Bancroft, Ontario,

More information

Prescribed Information and suggested clauses for tenancy agreements and terms of business

Prescribed Information and suggested clauses for tenancy agreements and terms of business Prescribed Information and suggested clauses for tenancy agreements and terms of business For Letting Agents Updated June 2016 Tel: 0300 037 1000 Email: deposits@tenancydepositscheme.com www.tenancydepositscheme.com

More information

Leasing guidance for schools

Leasing guidance for schools Leasing guidance for schools 1 Making the decision to lease Leasing can be a great way for schools to secure the equipment (and facilities) they need to provide students with a first-class education. The

More information

as Buyer(s) ("Buyer"), and

as Buyer(s) (Buyer), and EXCLUSIVE BUYER AGENCY AGREEMENT [Consult "Guidelines" (Form 201G) for guidance in completing this form] This EXCLUSIVE BUYER AGENCY AGREEMENT ("Agreement") is entered into (), between as Buyer(s) ("Buyer"),

More information

Prescribed Information and Clauses

Prescribed Information and Clauses Who should read this? How To (Pre-Tenancy) Tenants Agents Landlords Prescribed Information and Clauses Contents What has changed? 03 Guidance on issuing Prescribed Information for ASTs 04 Section A Prescribed

More information

For operating a community association, the general hierarchy of authority among governing documents consists of:

For operating a community association, the general hierarchy of authority among governing documents consists of: General Hierarchy of Authority for Governing Documents The general hierarchy of authority for governing documents is a loose one because not all documents address all issues involved in operating a community

More information

BUSINESS GUIDE. Resource Booklet

BUSINESS GUIDE. Resource Booklet BUSINESS GUIDE Resource Booklet Onsite Law practices in Conveyancing, Business Law and Wills. We provide advice in plain English in a cost efficient way. All client referrals to us are treated with courtesy

More information

Community Occupancy Guidelines

Community Occupancy Guidelines Community Occupancy Guidelines Auckland Council July 2012 Find out more: phone 09 301 0101 or visit www.aucklandcouncil.govt.nz Contents Introduction 4 Scope 5 In scope 5 Out of scope 5 Criteria 6 Eligibility

More information

REQUEST FOR PROPOSALS (RFP) SECTION 8 CONTRACT ADMINISTRATION SERVICES

REQUEST FOR PROPOSALS (RFP) SECTION 8 CONTRACT ADMINISTRATION SERVICES REQUEST FOR PROPOSALS (RFP) 09-331 SECTION 8 CONTRACT ADMINISTRATION SERVICES FOR THE HOUSING AUTHORITY OF THE CITY OF WINSTON-SALEM WINSTON-SALEM, NORTH CAROLINA 1 TABLE OF CONTENTS 1. Introduction 2.

More information

JOB DESCRIPTION MANAGEMENT EXCLUSION

JOB DESCRIPTION MANAGEMENT EXCLUSION 1. Position No. Various 2. Descriptive Working Title SENIOR DEVELOPMENT MANAGER JOB DESCRIPTION MANAGEMENT EXCLUSION 3. Present Classification Excluded Mgmt 4. Branch DEVELOPMENT AND ASSET 5. Department

More information

REQUEST FOR PROPOSAL FOR. Appraisal Services. Office of the Special Deputy Receiver

REQUEST FOR PROPOSAL FOR. Appraisal Services. Office of the Special Deputy Receiver REQUEST FOR PROPOSAL FOR Appraisal Services Office of the Special Deputy Receiver October 1, 2008 REQUEST FOR PROPOSAL ( RFP ) Appraisal Services BACKGROUND The Office of the Special Deputy Receiver (OSD),

More information

Request for Proposals

Request for Proposals Request for Proposals On Call Right-of-Way and Easement Acquisition and Related Services Requested by: Charter Township of Shelby Department of Public Works 6333 23 Mile Road Shelby Township, MI 48316

More information

REAL ESTATE INVESTING GUIDE. Combine IRA tax advantages with real estate investment opportunities.

REAL ESTATE INVESTING GUIDE. Combine IRA tax advantages with real estate investment opportunities. REAL ESTATE INVESTING GUIDE Combine IRA tax advantages with real estate investment opportunities. INTRODUCTION The IRS allows an IRA, Solo 401(k), or HSA to acquire real estate as an asset without penalty

More information

REPORT 2014/050 INTERNAL AUDIT DIVISION. Audit of United Nations Human Settlements Programme operations in Sri Lanka

REPORT 2014/050 INTERNAL AUDIT DIVISION. Audit of United Nations Human Settlements Programme operations in Sri Lanka INTERNAL AUDIT DIVISION REPORT 2014/050 Audit of United Nations Human Settlements Programme operations in Sri Lanka Overall results relating to the effective and efficient implementation of the UN-Habitat

More information

REQUEST FOR PROPOSAL (RFP) RFP AS. Appraisal Services Valuation of DBHA Properties

REQUEST FOR PROPOSAL (RFP) RFP AS. Appraisal Services Valuation of DBHA Properties REQUEST FOR PROPOSAL (RFP) RFP 2019-01AS Appraisal Services Valuation of DBHA Properties Daytona Beach Housing Authority (DBHA) 211 N Ridgewood Ave Suite 300 Daytona Beach, FL 32114 (386) 253-5653 Terril

More information

Acquisition of investment properties asset purchase or business combination?

Acquisition of investment properties asset purchase or business combination? Acquisition of investment properties asset purchase or business combination? Our IFRS Viewpoint series provides insights from our global IFRS team on applying IFRSs in challenging situations. Each edition

More information

Lease accounting scope & impacts

Lease accounting scope & impacts Leasing Lease accounting scope & impacts Scope What s in? All industries, all entities Arrangements that meet the definition of a lease Embedded leases within other arrangements What s out? Leases of:

More information

property even if the parties have no lease arrangement. This is often called an option contract.

property even if the parties have no lease arrangement. This is often called an option contract. In the farming community, lease-to-own refers to certain methods to achieve land ownership. Purchasing a farm with conventional financing is simply not an option (or the best option) for many. Lease-to-own

More information

Lawrenceville Housing Corporation

Lawrenceville Housing Corporation Lawrenceville Housing Corporation Request for Proposal: Licensed Real Estate Professionals Request for Proposals Licensed Real Estate Professionals Page 2 TABLE OF CONTENTS TABLE OF CONTENTS... 2 REQUEST

More information

Internal Audit Report

Internal Audit Report Internal Audit Report TxDOT Internal Audit Division Objective To determine if objectives are being met and are in compliance with current regulations. Opinion Based on the audit scope areas reviewed, control

More information

CALIFORNIA ASSOCIATION OF REALTORS. Buyer's and Seller's Guide to the California Residential Purchase Agreement

CALIFORNIA ASSOCIATION OF REALTORS. Buyer's and Seller's Guide to the California Residential Purchase Agreement CALIFORNIA ASSOCIATION OF REALTORS Buyer's and Seller's Guide to the California Residential Purchase Agreement (C.A.R. Form RPA-CA) 1 A publication of the CALIFORNIA ASSOCIATION OF REALTORS USER PROTECTION

More information

REQUEST FOR PROPOSAL FOR SERVICED APARTMENTS FOR: 1. CONCEPT DESIGN CONSULTATION AND/OR 2. OPERATION OF SERVICED APARTMENTS, FOR,

REQUEST FOR PROPOSAL FOR SERVICED APARTMENTS FOR: 1. CONCEPT DESIGN CONSULTATION AND/OR 2. OPERATION OF SERVICED APARTMENTS, FOR, REQUEST FOR PROPOSAL FOR SERVICED APARTMENTS FOR: 1. CONCEPT DESIGN CONSULTATION AND/OR 2. OPERATION OF SERVICED APARTMENTS, FOR, SERVICED APARTMENTS BRAND SPONSORED BY CYTONN INVESTMENTS MANAGEMENT LIMITED

More information

How do I use an architect? Frequently Asked Questions

How do I use an architect? Frequently Asked Questions How do I use an architect? Frequently Asked Questions Some of the most frequently asked questions about finding, appointing and working with an architect. Do I need an architect? Unless your project is

More information

CONTRACT RULES: ICE FUTURES GILT FUTURES CONTRACTS SECTION RRRR - CONTRACT RULES: ICE FUTURES GILT FUTURES CONTRACTS

CONTRACT RULES: ICE FUTURES GILT FUTURES CONTRACTS SECTION RRRR - CONTRACT RULES: ICE FUTURES GILT FUTURES CONTRACTS CONTRACT RULES: ICE FUTURES GILT FUTURES CONTRACTS RRRR SECTION RRRR - CONTRACT RULES: ICE FUTURES GILT FUTURES CONTRACTS RRRR.1 Interpretation RRRR.2 Contract Specification RRRR.3 List of Deliverable

More information

Home Buying Service. In this Guide: Finding an Agent. Finding the Right House. Applying for a Loan. Home Inspections.

Home Buying Service. In this Guide: Finding an Agent. Finding the Right House. Applying for a Loan. Home Inspections. 1 In this Guide: Home Buying Service Finding an Agent Finding the Right House Applying for a Loan Home Inspections and much more 2 Inside This Guide Thank You 3 Step 1: Finding the Right Agent 4-5 Step

More information

Chapter 16 PROCUREMENT. Procurement through NMSA Purchasing Discounts 13-1A-1 through 13-1A-4 NMSA 1978

Chapter 16 PROCUREMENT. Procurement through NMSA Purchasing Discounts 13-1A-1 through 13-1A-4 NMSA 1978 Chapter 16 PROCUREMENT No, this is not what it looks like. It is the purchasing of materials, supplies and services for use by a municipality. The procedures are outlined in the statutes. Procurement 13-1-1

More information

SSAP 14 STATEMENT OF STANDARD ACCOUNTING PRACTICE 14 LEASES

SSAP 14 STATEMENT OF STANDARD ACCOUNTING PRACTICE 14 LEASES SSAP 14 STATEMENT OF STANDARD ACCOUNTING PRACTICE 14 LEASES (Issued October 1987; revised February 2000) The standards, which have been set in bold italic type, should be read in the context of the background

More information

MOLDED FIBER GLASS COMPANIES Terms and Conditions of Sale (Custom Molding Products)

MOLDED FIBER GLASS COMPANIES Terms and Conditions of Sale (Custom Molding Products) MOLDED FIBER GLASS COMPANIES Terms and Conditions of Sale (Custom Molding Products) 1. Applicability - The following Terms and Conditions of Sale shall be applicable to all sales made by Molded Fiber Glass

More information

REQUEST FOR PROPOSALS Professional Engineering Services for Lift Station In the Rural Municipality of Wellington

REQUEST FOR PROPOSALS Professional Engineering Services for Lift Station In the Rural Municipality of Wellington REQUEST FOR PROPOSALS Professional Engineering Services for Lift Station In the Rural Municipality of Wellington Issue Date: March 2, 2018 Prepared By: Rural Municipality of Wellington Wellington, PEI

More information

REAL ESTATE TOPICS JUNE 1, 2008 NEGOTIATING AND STRUCTURING JOINT VENTURE AND LLC AGREEMENTS

REAL ESTATE TOPICS JUNE 1, 2008 NEGOTIATING AND STRUCTURING JOINT VENTURE AND LLC AGREEMENTS BENNETT VALLEY LAW REAL ESTATE TOPICS JUNE 1, 2008 NEGOTIATING AND STRUCTURING JOINT VENTURE AND LLC AGREEMENTS Parties negotiate joint venture agreements in the spirit of optimism. Anxious to combine

More information

ONTARIO S CONDOMINIUM ACT REVIEW ONCONDO Submissions. Summary

ONTARIO S CONDOMINIUM ACT REVIEW ONCONDO Submissions. Summary ONTARIO S CONDOMINIUM ACT REVIEW ONCONDO Submissions Summary PROCESS OVERVIEW As part of the first stage of Ontario s Condominium Act Review, the Ministry of Consumer Services invited the public to send

More information

QUESTIONS AND ANSWERS FOR IFBs , , , and Dec 2014

QUESTIONS AND ANSWERS FOR IFBs , , , and Dec 2014 QUESTIONS AND ANSWERS FOR IFBs 39 4603, 39 4006, 39 4604, and 39 4608 16 Dec 2014 Note: The following questions were presented to the Sales Contracting Officer (SCO) about the Invitation For Bid (IFB)

More information

Partnering To Develop Affordable Housing

Partnering To Develop Affordable Housing Partnering To Develop Affordable Housing Prepared by: Franke Consulting Group As part of the Development Seminar Series Under contract to: New York State Division of Housing & Community Renewal New York

More information

Second Land and Real Estate Registration Project. between KYRGYZ REPUBLIC. and INTERNATIONAL DEVELOPMENT ASSOCIATION

Second Land and Real Estate Registration Project. between KYRGYZ REPUBLIC. and INTERNATIONAL DEVELOPMENT ASSOCIATION Public Disclosure Authorized CONFORMED COPY GRANT NUMBER H380 KG Public Disclosure Authorized Financing Agreement Second Land and Real Estate Registration Project between Public Disclosure Authorized KYRGYZ

More information

ALLIED INTERNATIONAL SUPPORT, INC. TERMS AND CONDITIONS OF PURCHASE ORDER

ALLIED INTERNATIONAL SUPPORT, INC. TERMS AND CONDITIONS OF PURCHASE ORDER PLEASE READ THESE VERY CAREFULLY 1. ACCEPTANCE: These terms and conditions govern all Purchase Orders ("Orders") issued by Allied International Support, Inc. ( Buyer ) to the Seller identified on each

More information

CONDITIONS OF PURCHASE (GOODS AND SERVICES) DOMESTIC AND INTERNATIONAL

CONDITIONS OF PURCHASE (GOODS AND SERVICES) DOMESTIC AND INTERNATIONAL CONDITIONS OF PURCHASE (GOODS AND SERVICES) DOMESTIC AND INTERNATIONAL 1. DEFINITIONS For the purposes of these Conditions of Purchase: Agreement means the Order together with these Conditions of Purchase;

More information

Contract Risk Allocation Working Group. Recommended Practice for Managing Risks in Contracts Involving OWNER-FURNISHED PROPERTY

Contract Risk Allocation Working Group. Recommended Practice for Managing Risks in Contracts Involving OWNER-FURNISHED PROPERTY Contract Risk Allocation Working Group Recommended Practice for Managing Risks in Contracts Involving OWNER-FURNISHED PROPERTY INTRODUCTION This document is a guideline for managing risks in contracts

More information

General Brokerage Terms and Conditions for Consumers

General Brokerage Terms and Conditions for Consumers General Brokerage Terms and These are the general terms and conditions of the Dutch Association of Real Estate Brokers and Real Estate Valuers NVM (NVM). It sets out the rights and obligations of your

More information

CARRDAN TERMS AND CONDITIONS

CARRDAN TERMS AND CONDITIONS CARRDAN TERMS AND CONDITIONS Definitions: Purchaser means Carrdan Corporation Seller means the person or company to whom this document is addressed. 1. Offer, Acceptance and Notification. This Purchase

More information

CONDITIONS OF PURCHASE (GOODS AND SERVICES) DOMESTIC AND INTERNATIONAL

CONDITIONS OF PURCHASE (GOODS AND SERVICES) DOMESTIC AND INTERNATIONAL CONDITIONS OF PURCHASE (GOODS AND SERVICES) DOMESTIC AND INTERNATIONAL 1. DEFINITIONS For the purposes of these Conditions of Purchase: Agreement means the Order together with these Conditions of Purchase;

More information

Charleston County School District. Procurement Services

Charleston County School District. Procurement Services Vendor Guide Procurement Services July 2006 Vendor Guide Page 1 Table of Contents Introduction...2 About Charleston School District...2 About Procurement Servcies...2 District Procurement Code...3 Direct

More information

Right-of-Way Acquisition and

Right-of-Way Acquisition and Request for Proposals On Call Right-of-Way Acquisition and Appraisal Services Requested by: CityofElCentro Department of Public Works 307 W. Brighton Avenue El Centra, Ca. 92243 Phone: (760) 337-4505 Fax:(760)337-3172

More information

NEGOTIATING M&A ESCROW AGREEMENTS

NEGOTIATING M&A ESCROW AGREEMENTS CHECKLISTS NEGOTIATING M&A ESCROW AGREEMENTS This Checklist sets out the key negotiated issues between a buyer and seller in an escrow agreement entered into in connection with an M&A transaction. It also

More information

Sell Your House in DAYS Instead of Months

Sell Your House in DAYS Instead of Months Sell Your House in DAYS Instead of Months No Agents No Fees No Commissions No Hassle Learn the secret of selling your house in days instead of months If you re trying to sell your house, you may not have

More information

What Every New Zealander Should Know About Relationship Property

What Every New Zealander Should Know About Relationship Property What Every New Zealander Should Know About Relationship Property ARE YOU IN A RELATIONSHIP COVERED BY THE LAW OF RELATIONSHIP PROPERTY? The Property (Relationships) Act 1976 affects the lives of almost

More information

STANDARD DEVELOPER WORKS ENTRY ONTO THIRD PARTY PROPERTY SEPTEMBER 2016 VERSION: 1.0

STANDARD DEVELOPER WORKS ENTRY ONTO THIRD PARTY PROPERTY SEPTEMBER 2016 VERSION: 1.0 STANDARD DEVELOPER WORKS ENTRY ONTO THIRD PARTY PROPERTY SEPTEMBER 2016 VERSION: 1.0 TABLE OF CONTENTS Document Information... 3 Version History... 3 Summary of Changes in this Version... 3 Document Control...

More information

Office of the County Auditor. Broward County Property Appraiser Report on Transition Review Services

Office of the County Auditor. Broward County Property Appraiser Report on Transition Review Services Office of the County Auditor Broward County Property Appraiser Report on Transition Review Services January 14, 2005 Table of Contents BACKGROUND AND SCOPE...3 FINDINGS AND RECOMMENDATIONS...3 1. Financial

More information

Accounting for revenue is changing

Accounting for revenue is changing Accounting for revenue is changing What s the impact on housebuilders? March 2017 The new revenue standard effective from 1 January 2018 is likely to affect the way you account for revenue. But it is more

More information

SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS

SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS SCHOOL SECTOR PROGRAM (SSP) FRAMEWORK FOR LAND ACQUISITION THROUGH VOLUNTARY DONATION OR WILLING SELLER WILLING BUYER PROCESS MINISTRY OF EDUCATION GOVERNMENT OF NEPAL August 2011 2 A. Introduction 1.

More information

2017 BRAXTON COUNTY RFP GENERAL TERMS & CONDITIONS

2017 BRAXTON COUNTY RFP GENERAL TERMS & CONDITIONS 2017 BRAXTON COUNTY RFP GENERAL TERMS & CONDITIONS 1. Awards will be made in the best interest of the LEA. 2. The LEA may accept or reject in part, or in whole, any bid. 3. All quotations are governed

More information

The Buyer Consultation: Demonstrating & Articulating Value. Interactive Workshop. Student Workbook

The Buyer Consultation: Demonstrating & Articulating Value. Interactive Workshop. Student Workbook The Buyer Consultation: Demonstrating & Articulating Value Interactive Workshop Student Workbook The Buyer Consultation: Demonstrating and Articulating your Value What is a Buyer Consultation? What is

More information

This fact sheet covers:

This fact sheet covers: Legal information for community organisations This fact sheet covers: general principles of contract law reviewing a contract specific types of contracts, and approval processes for contracts. Contracts

More information

COOPERATION BETWEEN BUILDERS AND REAL ESTATE BROKER/AGENTS

COOPERATION BETWEEN BUILDERS AND REAL ESTATE BROKER/AGENTS COOPERATION BETWEEN BUILDERS AND REAL ESTATE BROKER/AGENTS This agreement supersedes and replaces the previous agreement outlining cooperation between REALTORS and Builders. CODE OF CONDUCT Builders Agree

More information

ROTOR CLIP PURCHASE ORDER GENERAL TERMS AND CONDITIONS

ROTOR CLIP PURCHASE ORDER GENERAL TERMS AND CONDITIONS ROTOR CLIP PURCHASE ORDER GENERAL TERMS AND CONDITIONS 1. ORDERS AND ACCEPTANCE: Any order placed or purchase order issued by Buyer (an Order ) for products and/or services described therein (collectively,

More information

Selling the Privately Held Company

Selling the Privately Held Company Selling the Privately Held Company Tuesday, January 15, 2013 Boston Bar Association Continuing Legal Education www.bostonbar.org/edu/cle SELLING THE PRIVATELY HELD COMPANY By: Steven C. Browne, Gitte J.

More information

EN Official Journal of the European Union L 320/373

EN Official Journal of the European Union L 320/373 29.11.2008 EN Official Journal of the European Union L 320/373 INTERNATIONAL FINANCIAL REPORTING STANDARD 3 Business combinations OBJECTIVE 1 The objective of this IFRS is to specify the financial reporting

More information

LWDB PROCUREMENT / PROPERTY MANAGEMENT POLICY

LWDB PROCUREMENT / PROPERTY MANAGEMENT POLICY NWPA WDB POLICY - 100 Rev. Level: C LWDB PROCUREMENT / PROPERTY MANAGEMENT POLICY The system of property and procurement management must have procedures to determine the actions of responsible parties

More information

PURCHASING, BIDS, CONTRACTS. Policy i

PURCHASING, BIDS, CONTRACTS. Policy i Table of Contents PURCHASING, BIDS, CONTRACTS Policy 560.1 PURPOSE... 1.2 GENERAL PROVISIONS... 1 2.1 WRITTEN CONTRACTS / WHEN REQUIRED... 1 (1) Written Contract Always Required for Certain Purchases...

More information

Broadstone Asset Management, LLC

Broadstone Asset Management, LLC Broadstone Asset Management, LLC 800 Clinton Square Rochester, NY 14604 Phone: 585-287-6500 www.broadstone.com Firm CRD#: 281847 Date: March 29, 2018 This brochure provides information about the qualifications

More information

Request for Proposal to Develop a Land Use Master Plan

Request for Proposal to Develop a Land Use Master Plan Request for Proposal to Develop a Land Use Master Plan PO Box 141, 400 Centre Road, Lions Bay, BC V0N 2E0 Phone: 604-921-9333 Fax: 604-921-6643 Email: office@lionsbay.ca Web: www.lionsbay.ca TABLE OF CONTENTS

More information

A Guide to Toronto Community Housing Tenant Representative Elections

A Guide to Toronto Community Housing Tenant Representative Elections A Guide to Toronto Community Housing Tenant Representative Elections Tenant Engagement Shaping Our Future Together Electing a Representative for your building and your new Neighbourhood Council Tenant

More information

Owners Association Management Services Asset & Facilities Management Services IT & Software Support Service

Owners Association Management Services Asset & Facilities Management Services IT & Software Support Service www.ownersunion.net Owners Association Management Services Asset & Facilities Management Services IT & Software Support Service Owners Union Community Manager was specifically created by Iong time strata

More information

H. UNIVERSITY PROCUREMENT CODE

H. UNIVERSITY PROCUREMENT CODE Page 1 H. UNIVERSITY PROCUREMENT CODE 3-801 General A. Applicability 1. This Article H ( University Procurement Code ) shall consist of rules prescribing procurement policies and procedures for the Arizona

More information

Headline Verdana Bold The evolutions of leases accounting under IFRS 16 Mariano Bruno, Carlo Laganà, Giuseppe Ambrosio, Deloitte & Touche S.p.A.

Headline Verdana Bold The evolutions of leases accounting under IFRS 16 Mariano Bruno, Carlo Laganà, Giuseppe Ambrosio, Deloitte & Touche S.p.A. SHIPPING AND THE LAW 7^ Edition 25-26 October 2016 NAPLES Headline Verdana Bold The evolutions of leases accounting under IFRS 16 Mariano Bruno, Carlo Laganà, Giuseppe Ambrosio, Deloitte & Touche S.p.A.

More information

Preparing for Acquisition Due Diligence

Preparing for Acquisition Due Diligence Preparing for Acquisition Due Diligence Carrie Keller, Partner, SmithAmundsen John Finger, Partner, SmithAmundsen The purpose of the due diligence process in an acquisition is to investigate the target

More information

Standard Terms & Conditions

Standard Terms & Conditions Please be sure to indicate Purchase Order # on such documents as an invoice, payment request details, shipping documents, etc. related to this Purchase Order. Standard Terms & Conditions This Standard

More information

Leases. (a) the lease transfers ownership of the asset to the lessee by the end of the lease term.

Leases. (a) the lease transfers ownership of the asset to the lessee by the end of the lease term. Leases 1.1. Classification of leases A lease is classified as a finance lease if it transfers substantially all the risks and rewards incidental to ownership. A lease is classified as an operating lease

More information

Answers to Questions Communities

Answers to Questions Communities Answers to Questions Communities may have about Floodplain Buyout Projects Is our community eligible to receive a mitigation grant for a floodplain buyout project? There are two key criteria for communities

More information

IND 205 LESSON #2 TITLE AND GOVERNMENT PROPERTY

IND 205 LESSON #2 TITLE AND GOVERNMENT PROPERTY IND 205 LESSON #2 TITLE AND GOVERNMENT PROPERTY PROPERTY TLO-2: Determine how the Government may take title to property under a contract. ELOs: 1. Define title and related terms 2. Determine who has title

More information

The President is authorized to delegate this authority to the Vice President for Administration and Treasurer.

The President is authorized to delegate this authority to the Vice President for Administration and Treasurer. PROCUREMENT AND MATERIALS HANDLING PROCUREMENT General Policy The President is the College s designated procurement authority with the right and responsibility to establish and oversee a procurement system,

More information

Applying IFRS. A closer look at the new leases standard. August 2016

Applying IFRS. A closer look at the new leases standard. August 2016 Applying IFRS A closer look at the new leases standard August 2016 Contents Overview 3 1. Scope and scope exceptions 5 1.1 General 5 1.2 Determining whether an arrangement contains a lease 6 1.3 Identifying

More information

IFRS Training. IAS 38 Intangible Assets. Professional Advisory Services

IFRS Training. IAS 38 Intangible Assets.  Professional Advisory Services IFRS Training IAS 38 Intangible Assets Table of Contents Section 1 Overview 2 Introduction to Intangible Assets 3 Recognition and Initial Measurement 4 Internally Generated Intangible Assets 5 Measurement

More information

TEXAS GENERAL LAND OFFICE PROCUREMENT GUIDANCE FOR RECIPIENTS AND SUBRECIPIENTS UNDER 2 CFR PART 200 (UNIFORM RULES)

TEXAS GENERAL LAND OFFICE PROCUREMENT GUIDANCE FOR RECIPIENTS AND SUBRECIPIENTS UNDER 2 CFR PART 200 (UNIFORM RULES) TEXAS GENERAL LAND OFFICE COMMUNITY DEVELOPMENT & REVITALIZATION PROCUREMENT GUIDANCE FOR RECIPIENTS AND SUBRECIPIENTS UNDER 2 CFR PART 200 (UNIFORM RULES) This checklist will assist the Texas General

More information