1 Grantee: Pinellas County, FL Grant: B-11-UN January 1, 2013 thru March 31, 2013 Performance Report 1

2 Grant Number: B-11-UN Grantee Name: Pinellas County, FL Grant Amount: $4,697, Estimated PI/RL Funds: Obligation Date: Contract End Date: 03/10/2014 Grant Status: Active Award Date: Review by HUD: Reviewed and Approved QPR Contact: Maggie Miles Total Budget: $4,697, Disasters: Declaration Number No Disasters Found Narratives Summary of Distribution and Uses of NSP Funds: Pinellas County will use the Neighborhood Stabilization Program 3 (NSP3) allocation of $4,697,519 for the acquisition and redevelopment of foreclosed and abandoned properties within the identified high priority areas of the County. It is anticipated that program income from these activities will occur and be utilized for additional NSP3 activities. Pinellas County will use NSP3 funds for the following activities: Acquisition Rehabilitation - Single Family - 5 units - $750,000 Acquisition Rehabilitation - Mulit-Family - 25 units - $678, and $1,174, (<50% set-aside) Acquisition Demolition - 5 units - $375,000 Redevelopment - 7 units - $1,000,000 Financing (Homeownership) - 10 units - $250,000 Administration - $469, In Pinellas County, the target areas for NSP3 were developed utilizing the HUD NSP3 Downloadable Data Files and identified properties with the Land Use Codes for the County. The identified neighborhoods had a risk score of 20, with 20 being the maximum possible. The target areas for NSP3 were developed by identifying the census tracts with the: Greatest percentage of home foreclosures; Highest percentage of homes financed by a sub-prime mortgage related loan; and Areas identified as the most likely to face a significant rise in the rate of home foreclosures. The analysis was based on the greatest percentage of foreclosures to determine that our focus would be on the socres that ranked 20. Our targeting then looked at the highest percentage of homes financed by sub-prime mortgages and foreclosures started over the past year. Pinellas County will also consider homes that meet the expanded definition of foreclosed which includes properties that have owners behind on their mortgage more than 60 days or delinquent on taxes. Pinellas County priority areas include Central and East Lealman. The Central Lealman neighborhood has a total of 4,272 housing units, with 63% of the persons having incomes less than 80% of Area Median Income (MI). According to the data provided with the HUD Mapping Tool, 31 properties will need either rehabilitation or redevelopment in order to have an impact on stabilizing the neighborhood. The East Lealman neighborhood has a total of 4,451 housing units in the neighborhood, with 60% of the persons having incomes less than 80% AMI. According to the data provided with the HUD Mapping Tool, 19 properties will need either rehabilitation or redevelopment to have an impact on stabilizing the neighborhood. Pinellas County will consider neighborhoods with Need Scores of 19 if we are not able to secure properties that have a Need Score of 20 within these census tracts. How Fund Use Addresses Market Conditions: Pinellas County will expend NSP3 funs through the following eligible activities to help address current market conditions. Single Family Acquisition Rehabilitation will help address the fact that Pinellas County has a high foreclosure rate, home values have dropped and neighborhoods are deteriorating as a result. Some areas are stabilizing; however, the Lealman area continues to be an area of need and requires assistance. The goal of Pinellas County is to revitalize the greatest need areas by improving the housing stock and stabilizing 2

3 declining market in the high priority areas. Once the homes have been purchased and rehabilitated, the Homeownership Financing activity will assist eligible homebuyers in the form of soft second financing, payment assistance to secure private mortgage insurance, loan loss reserves, shared equity and finance acquisition. Additionally, to help address neighborhood deterioration and declining values, the Acquisition Demolition activity will be used to remove blighted structures that are beyond repair. Properties acquired under the Acquisition Demolition activity will be redeveloped under the Redevelopment activity. Redeveloped housing will be sold or rented to income eligible households. Multi-Family Acquisition Rehabilitation will help address the fact that Pinellas County has seen home values decrease and the need for rental properties increase. Some of this is largely due to the high unemployment rate for the area, resulting in a need for affordable rental housing. Central and East Lealman areas continue to be areas of need and require assistance. The goal of Pinellas County is to revitalize the greatest need areas by preserving the number of rental units available to families below 120%of AMI. <!--[endif]--> Ensuring Continued Affordability: Pinellas County will ensure long term affordability through the use of Land Use Restriction Agreements (LURA) that will be recorded against the property. If an owner who has been assisted through this program transfers title to the property before the affordability period expires, the assistance provided by the County will be subject to recapture. The County will monitor the properties that are assisted with NSP3 funds during the affordabilityperiod to ensure that the specified units are affordable. This will be done utilizing the standards established with the HOME Program. In addition, all properties receiving NSP3 funding will be secured by a recorded mortgage on the property. The minimum threshold that will be used to ensure long term affordability will be consistent with the guidelines of the HOME Program as defined in 24 CFR (e). In some instances, the affordability requirements may be increased at the discretion of Pinellas County based on the amount of subsidy being provided to the recipient. Definition of Blighted Structure: For purposes of determining blighted structures to be assisted with NSP3 funding, blighted structure will be defined as any structure unfit for use, habitation, or dangerous to persons or other property. In addition, a structure is blighted when it exhibits objectively determinable signs of deterioration sufficient to constitute a threat to human health, safety, and public welfare. This includes structures showing evidence of physical decay or neglect, excessive use, or lack of maintenance. Definition of Affordable Rents: Affordable rents shall be defined as the standards established under the HOME Program and referenced in 24 CFR (a) (b) and (c). Projects identified to serve families at or below 50% AMI will have rents that do not exceed the established rents published annually by HUD. Housing Rehabilitation/New Construction Standards: Pinellas County will utilize the housing rehabilitation standards, which exceed the minimum code requirements, as described in the Pinellas County Community Development policies. Properties will be rehabilitated to standards that comply with applicable laws, codes and other requirements of 's Minimum Standards for Rehabilitation of Residential Properties. Pinellas County will incorporate modern, green building and energy-efficiency improvement standards, whenever feasible, to provide for longer-term sustainability. Vicinity Hiring: Pinellas County will identify and solicit contractors for participation in NSP3. Identification of potential contractors will be completed through the Request for Qualification process. Additional outreach methods, such as identifying contractors through local advertising and/or direct mailing to identify contracts that reside in our priority neighborhoods will be completed. Preference will be given to vicinity contractors to the extent that they are comparable bids. The contracts established with contractors include language that includes preference for utilizing vicinity contractors when soliciting sub-contractors or hiring new employees. Procedures for Preferences for Affordable Rental Dev.: Based on information provided by Pinellas County, and in order to make an impact on the identified areas, preference for NSP3 projects will be for the development of affordable rental housing. The data provided shows that the priority areas selected have 126 multi-family units with a land use code that signifies 4-9 units per structure. In addition, there are 630 duplexes and 176 triplexes within the neighborhood. There are also some larger developments which include 552 units with 50 or more units within the development and 244 units with units within the development. Although there are a large number of multi-family rental units in the Lealman area, it will be important to identify those rental units that are currently in foreclosure. The Mulit-Family Acquisition Rehabilitation activity, which focuses on rental developments, will be a priority of the County; however, single-family acquisition and rehabilitation will also be completed. Data collected from NSP acquisitions have indicated that although there are numerous duplexes and triplexes classified as rental property, investors are getting to the properties before we are able to secure them. 3

4 Grantee Contact Information: Sheri Harris, Compliance Manager 600 Cleveland Street, Suite 800 Clearwater, FL Overall Total Projected Budget from All Sources Total Budget Total Obligated Total Funds Drawdown Program Funds Drawdown Program Income Drawdown Program Income Received Total Funds Expended Match Contributed This Report Period To Date $4,697, $4,697, $1,835, $4,697, $2,582, $2,632, $2,582, $2,632, $2,352, $2,696, Progress Toward Required Numeric Targets Requirement Required Overall Benefit Percentage (Projected) Overall Benefit Percentage (Actual) Minimum Non-Federal Match Limit on Public Services $704, Limit on Admin/Planning $469, Limit on State Admin To Date 0.00% 0.00% $89, $89, Progress Toward Activity Type Targets Activity Type Target Actual Administration $469, $469, Progress Toward National Objective Targets National Objective Target Actual NSP Only - LH - 25% Set-Aside $1,174, $1,607, Overall Progress Narrative: During the quarter, Pinellas County continued property screening and evaluation reviews. One single-family property has been acquired during this quarter. Asbestos NESHAP Survey Reports were completed on two houses that will be demolished. Rehabilitation work write ups for two homes were completed and one has been sent out for bids. One home purchased with NSP 1 funds and located in the NSP3 eligible area is under contract for sale. NSP 3 funding will be used to finance the purchase in February. To date, a total of six single family properties have been acquired. 4

5 Project Summary Project #, Project Title This Report Period To Date Program Funds Drawdown Project Funds Budgeted Program Funds Drawdown ADMIN, Administration $57, $469, $89, AR Program, Acquisition & Rehabilitation $504, $520, $520, DEMO, Demolition $30, $375, $30, HO DPA, Financing Mechanism $113, $250, $113, REDEVELOPMENT, Redevelopment $1,874, $3,082, $1,877,

6 Activities Grantee Activity Number: Activity Title: Activitiy Category: Construction of new housing Project Number: REDEVELOPMENT Projected Start Date: 03/10/2011 Benefit Type: Direct ( HouseHold ) National Objective: NSP Only - LH - 25% Set-Aside C Magnolia Court 25% Activity Status: Under Way Project Title: Redevelopment Projected End Date: 03/10/2014 Completed Activity Actual End Date: Responsible Organization: Overall Total Projected Budget from All Sources Total Budget Total Obligated Total Funds Drawdown To Date $1,177, $1,177, $1,177, $1,113, Program Funds Drawdown $1,111, $1,113, Program Income Drawdown Program Income Received Total Funds Expended Jan 1 thru Mar 31, 2013 $1,111, $1,110, $1,110, $1,113, $1,113, Match Contributed Activity Description: This activity will address neighborhood stabilization with the redevelopment of demolished or vacant properties. Properties under the Rental Redevelopment Program may be redeveloped with housing that will become part of the Multi-Family Development Programs. Properties addressed under this activity that meet the NSP Plan's definition of blighted are exempt from the requirement that the property must be foreclosed or abandoned. This activity will serve households to meet the 25% set-aside requirement. Location Description: The activity will be completed in the Central and East Lealman neighborhoods, areas identified using the HUD Mapping Tool and designated as "20". Census tracts with a score of "19" that surround the neighborhoods will be considered if the area needs to be expanded for meeting the expenditure deadlines. Activity Progress Narrative: Pinellas County staff received an affordable housing development application requesting $3,905,000 in funding assistance for a 32 unit multi-family rental housing development project. The proposed project is located within the NSP3 eligible area. The application was reviewed by staff for overall NSP eligibility and potential funding analysis. Following a completion of the due diligence process, the project proposal was modified to include a total of only 26 units for a total development cost of $3,665,000. Staff recommended the approval of a financing package that provided funding from the following sources: >CDBG $ 360,000 6

7 HOME $1,664,961 NSP3 <50% $1,175,000 NSP3 <120% $ 465,039 Total $3,665,000 >This financing was closed on June 29, At that time the sight was acquired by the Pinellas Community Housing Foundation and subsequently leased to Contemporary Housing Alternatives of Florida Inc., the County's designated CHDO. Pre development plans and designs were completed and submitted for County BDRS review before the end of September, Building permits were issued and construction commenced during the first week of January, Through the end of March, 2013, $1,618,328 in NSP3 funds were spent on construction costs. Project construction is planned for completion by the end of July, Accomplishments Performance Measures No Accomplishments Performance Measures found. Beneficiaries Performance Measures No Beneficiaries Performance Measures found. Activity Locations No Activity Locations found. Other Funding Sources Budgeted - Detail No Other Match Funding Sources Found Other Funding Sources No Other Funding Sources Found Total Other Funding Sources Amount 7

8 Grantee Activity Number: Activity Title: Activitiy Category: Construction of new housing Project Number: REDEVELOPMENT Projected Start Date: 03/10/2011 Benefit Type: Direct ( HouseHold ) National Objective: NSP Only - LMMI D Magnolia Court Activity Status: Under Way Project Title: Redevelopment Projected End Date: 03/10/2014 Completed Activity Actual End Date: Responsible Organization: Overall Total Projected Budget from All Sources Total Budget Total Obligated Total Funds Drawdown To Date $475, $475, $465, $97, Program Funds Drawdown $97, $97, Program Income Drawdown Program Income Received Total Funds Expended Jan 1 thru Mar 31, 2013 $97, $97, $97, $99, $99, Match Contributed Activity Description: This activity will address neighborhood stabilization with the redevelopment of demolished or vacant properties. Properties under the Rental Redevelopment Program may be redeveloped with housing that will become part of the Multi-Family Development Programs. Properties addressed under this activity that meet the NSP Plan's definition of blighted are exempt from the requirement that the property must be foreclosed or abandoned. Location Description: The activity will be completed in the Central and East Lealman neighborhoods, areas identified using the HUD Mapping Tool and designated as "20". Census tracts with a score of "19" that surround the neighborhoods will be considered if the area needs to be expanded for meeting the expenditure deadlines. Activity Progress Narrative: Pinellas County staff received an affordable housing development application requesting $3,905,000 in funding assistance for a 32 unit multi-family rental housing development project. The proposed project is located within the NSP3 eligible area. The application was reviewed by staff for overall NSP eligibility and potential funding analysis. Following a completion of the due diligence process, the project proposal was modified to include a total of only 26 units for a total development cost of $3,665,000. Staff recommended the approval of a financing package that provided funding from the following sources: >CDBG $ 360,000 HOME $1,664,961 NSP3 <50% $1,175,000 NSP3 <120% $ 465,039 Total $3,665,000 8

9 >This financing was closed on June 29, At that time the sight was acquired by the Pinellas Community Housing Foundation and subsequently leased to Contemporary Housing Alternatives of Florida Inc., the County's designated CHDO. Pre development plans and designs were completed and submitted for County BDRS review before the end of September, Building permits were issued and construction commenced during the first week of January, Through the end of March, 2013, $1,618,328 in NSP3 funds were spent on construction costs. Project construction is planned for completion by the end of July, Accomplishments Performance Measures No Accomplishments Performance Measures found. Beneficiaries Performance Measures No Beneficiaries Performance Measures found. Activity Locations No Activity Locations found. Other Funding Sources Budgeted - Detail No Other Match Funding Sources Found Other Funding Sources No Other Funding Sources Found Total Other Funding Sources Amount 9

10 Grantee Activity Number: Activity Title: Activitiy Category: Construction of new housing Project Number: REDEVELOPMENT Projected Start Date: 03/10/2011 Benefit Type: Direct ( HouseHold ) National Objective: NSP Only - LMMI A Cypress Pointe Activity Status: Under Way Project Title: Redevelopment Projected End Date: 03/10/2014 Completed Activity Actual End Date: Responsible Organization: Overall Total Projected Budget from All Sources Total Budget Total Obligated Total Funds Drawdown $1,010, To Date $1,020, $1,020, $1,010, $240, Program Funds Drawdown $240, $240, Program Income Drawdown Program Income Received Total Funds Expended Jan 1 thru Mar 31, 2013 $1,010, $240, $242, $242, $242, $242, Match Contributed Activity Description: This activity will address neighborhood stabilization with the redevelopment of demolished or vacant properties. Properties under the Rental Redevelopment Program may be redeveloped with housing that will become part of the Multi-Family Development Programs. Properties addressed under this activity that meet the NSP Plan's definition of blighted are exempt from the requirement that the property must be foreclosed or abandoned. Location Description: The activity will be completed in the Central and East Lealman neighborhoods, areas identified using the HUD Mapping Tool and designated as "20". Census tracts with a score of "19" that surround the neighborhoods will be considered if the area needs to be expanded for meeting the expenditure deadlines. Activity Progress Narrative: Pinellas County staff received a funding application from Contemporary Housing Alternatives of Florida Inc., the County&rsquos designated CHDO, for this NSP3 eligible project in December, This project will include the acquisition of a former Mobile Home Park site that has been bank owned since December The site will be redeveloped as a 26 unit rental housing facility. Total project costs will be $3,672,000 of which $1,425,608 will be provided from Pinellas County&rsquos NSP3 allocation. Total project funding by source is as follows: SHIP 744, RHD HOME Production 1,501, NSP 3 Redevelopment 25% 424, NSP 3 Redevelopment 1,000, Total Funding Amount 3,672,

11 A closing on the financing for this project took place on February 4, The land was acquired by the Pinellas Community Housing Foundation and placed in the Community Land Trust established for this project. CHAF executed a 99 Year Land Lease on the property and immediately proceeded with the demolition of the remaining structures on the property. A required re-zoning of the property is scheduled to be finalized at the June 5, 2013 BCC meeting. Site and building plans are being developed, and construction is scheduled to commence in July, Accomplishments Performance Measures No Accomplishments Performance Measures found. Beneficiaries Performance Measures No Beneficiaries Performance Measures found. Activity Locations No Activity Locations found. Other Funding Sources Budgeted - Detail No Other Match Funding Sources Found Other Funding Sources No Other Funding Sources Found Total Other Funding Sources Amount 11

12 Grantee Activity Number: Activity Title: Activitiy Category: Construction of new housing Project Number: REDEVELOPMENT Projected Start Date: 03/10/2011 Benefit Type: Direct ( HouseHold ) National Objective: NSP Only - LH - 25% Set-Aside B Cypress Pointe 25% Activity Status: Under Way Project Title: Redevelopment Projected End Date: 03/10/2014 Completed Activity Actual End Date: Responsible Organization: Overall Total Projected Budget from All Sources Total Budget Total Obligated Total Funds Drawdown $430, To Date $430, $430, $430, $425, Program Funds Drawdown $425, $425, Program Income Drawdown Program Income Received Total Funds Expended Jan 1 thru Mar 31, 2013 $430, $425, $425, $425, $425, $425, Match Contributed Activity Description: This activity will address neighborhood stabilization with the redevelopment of demolished or vacant properties. Properties under the Rental Redevelopment Program may be redeveloped with housing that will become part of the Multi-Family Development Programs. Properties addressed under this activity that meet the NSP Plan's definition of blighted are exempt from the requirement that the property must be foreclosed or abandoned. This activity will serve households to meet the 25% set-aside requirement. Location Description: The activity will be completed in the Central and East Lealman neighborhoods, areas identified using the HUD Mapping Tool and designated as "20". Census tracts with a score of "19" that surround the neighborhoods will be considered if the area needs to be expanded for meeting the expenditure deadlines. Activity Progress Narrative: Pinellas County staff received a funding application from Contemporary Housing Alternatives of Florida Inc., the County&rsquos designated CHDO, for this NSP3 eligible project in December, This project will include the acquisition of a former Mobile Home Park site that has been bank owned since December The site will be redeveloped as a 26 unit rental housing facility. Total project costs will be $3,672,000 of which $1,425,608 will be provided from Pinellas County&rsquos NSP3 allocation. Total project funding by source is as follows: SHIP 744, RHD HOME Production 1,501, NSP 3 Redevelopment 25% 424, NSP 3 Redevelopment 1,000, Total Funding Amount 3,672,

13 A closing on the financing for this project took place on February 4, The land was acquired by the Pinellas Community Housing Foundation and placed in the Community Land Trust established for this project. CHAF executed a 99 Year Land Lease on the property and immediately proceeded with the demolition of the remaining structures on the property. A required re-zoning of the property is scheduled to be finalized at the June 5, 2013 BCC meeting. Site and building plans are being developed, and construction is scheduled to commence in July, Accomplishments Performance Measures No Accomplishments Performance Measures found. Beneficiaries Performance Measures No Beneficiaries Performance Measures found. Activity Locations No Activity Locations found. Other Funding Sources Budgeted - Detail No Other Match Funding Sources Found Other Funding Sources No Other Funding Sources Found Total Other Funding Sources Amount 13

14 Grantee Activity Number: Activity Title: Activitiy Category: Administration Project Number: ADMIN Projected Start Date: 03/10/2011 Benefit Type: ( ) National Objective: ADMIN NSP3 Administration Activity Status: Under Way Project Title: Administration Projected End Date: 03/10/2014 Completed Activity Actual End Date: Responsible Organization: Overall Total Projected Budget from All Sources Total Budget Total Obligated Total Funds Drawdown To Date $469, $469, $469, $89, Program Funds Drawdown $57, $89, Program Income Drawdown Program Income Received Total Funds Expended Jan 1 thru Mar 31, 2013 $57, $22, $22, $96, $96, Match Contributed Activity Description: NSP3 funds will be used to pay reasonable program administration costs related to the planning and execution of the identified activities being proposed for Pinellas County. This includes costs related to staffing for overall program management, coordination, monitoring, reporting, and direct and indirect costs. Location Description: Activity Progress Narrative: During the quarter, the Community Development Department continued to conduct program management and compliance activities. 14

15 Accomplishments Performance Measures No Accomplishments Performance Measures found. Beneficiaries Performance Measures No Beneficiaries Performance Measures found. Activity Locations No Activity Locations found. Other Funding Sources Budgeted - Detail No Other Match Funding Sources Found Other Funding Sources No Other Funding Sources Found Total Other Funding Sources Amount 15

16 Grantee Activity Number: Activity Title: Activitiy Category: Clearance and Demolition Project Number: DEMO Projected Start Date: 03/10/2011 Benefit Type: Area ( ) National Objective: NSP Only - LMMI DEMO Demolition Program Activity Status: Under Way Project Title: Demolition Projected End Date: 03/10/2014 Completed Activity Actual End Date: Responsible Organization: Overall Total Projected Budget from All Sources Total Budget Total Obligated Total Funds Drawdown To Date $191, $191, $375, $30, Program Funds Drawdown $30, $30, Program Income Drawdown Program Income Received Total Funds Expended Jan 1 thru Mar 31, 2013 $375, $30, $30, $30, $30, $30, Match Contributed Activity Description: This activity will address neighborhood stabilization within the identified target areas by removing blighted structures that are beyond repair. Properties will be redeveloped with affordable housing that will serve households below 120% of Area Median Income. Properties addressed under the Demolition Program that meet the NSP Plan's definition of blighted are exempt from the requirement that the property must be foreclosed or abandoned. Eligible costs under this activity include, but are not limited to, costs associated with acquisition, demolition, and clearance. Location Description: This activity will be completed in the Central and East Lealman neighborhoods, areas identified using the HUD Mapping Tool and designated as "20". Census tracts with a score of "19" that surround the neighborhoods will be considered if the area needs to be expanded for meeting the expenditure deadlines. Activity Progress Narrative: During the quarter, Pinellas County continued property screening and evaluation reviews. Four single-family properties were acquired during this quarter. Two previously acquired houses were demolished. Accomplishments Performance Measures No Accomplishments Performance Measures found. 16

17 Beneficiaries Performance Measures No Beneficiaries Performance Measures found. Activity Locations No Activity Locations found. Other Funding Sources Budgeted - Detail No Other Match Funding Sources Found Other Funding Sources No Other Funding Sources Found Total Other Funding Sources Amount 17

18 Grantee Activity Number: Activity Title: HO DPA Homeownership Financing Activitiy Category: Homeownership Assistance to low- and moderate-income Project Number: HO DPA Projected Start Date: 03/10/2011 Benefit Type: Direct ( HouseHold ) National Objective: NSP Only - LMMI Activity Status: Under Way Project Title: Financing Mechanism Projected End Date: 03/10/2014 Completed Activity Actual End Date: Responsible Organization: Overall Total Projected Budget from All Sources Total Budget Total Obligated Total Funds Drawdown To Date $113, $113, $250, $113, Program Funds Drawdown $113, $113, Program Income Drawdown Program Income Received Total Funds Expended Jan 1 thru Mar 31, 2013 $250, $113, $113, $113, $113, $113, Match Contributed Activity Description: This activity will address neighborhood stabilization within the identified high priority areas through direct assistance to eligible homebuyers of properties redeveloped under this plan. The assistance will be in the form of soft second financing, payment assistance to secure private mortgage insurance, loan loss reserves, shared equity, and finance acquisition. This activity will specifically provide homebuyer assistance not to exceed 50% of the value. This assistance will be provided in the form of a zero percent (0%) interest deferred loan. Loans will be deferred for a period not to exceed five (5) years. This activity also allows for the payment of all, or part of, costs required up front for the buyer to obtain necessary private mortgage insurance. Additionally, this activity will allow for the development of financing mechanisms designed to reduce the cost of acquisition to the buyer. Pinellas County has experience with operating numerous down payment programs and provides soft second mortgages to families through other funding sources. The assistance that is provided with this activity has been provided by the County with previous programs, so implementation will be similar and will target families with incomes less than 120% of Area Median Income. Location Description: The activity will be completed in the Central and East Lealman neighborhoods, areas identified using the HUD Mapping Tool and designated as "20". Census tracts with a score of "19" that surround the neighborhoods will be considered if the area needs to be expanded for meeting the expenditure deadlines. Activity Progress Narrative: During the quarter, one home purchased with NSP 1 funds and located in the NSP3 eligible area was sold. NSP 3 funding was used to finance the purchase in February. 18

19 Accomplishments Performance Measures No Accomplishments Performance Measures found. Beneficiaries Performance Measures No Beneficiaries Performance Measures found. Activity Locations No Activity Locations found. Other Funding Sources Budgeted - Detail No Other Match Funding Sources Found Other Funding Sources No Other Funding Sources Found Total Other Funding Sources Amount 19

20 Grantee Activity Number: Activity Title: Activitiy Category: Acquisition - general Project Number: AR Program Projected Start Date: 03/10/2011 Benefit Type: Direct ( HouseHold ) National Objective: NSP Only - LH - 25% Set-Aside M/F AR LH25 Multi-Family Development Program LH25 Activity Status: Under Way Project Title: Acquisition & Rehabilitation Projected End Date: 03/10/2014 Completed Activity Actual End Date: Responsible Organization: Overall Total Projected Budget from All Sources Total Budget Total Obligated Total Funds Drawdown ($532,340.75) To Date Program Funds Drawdown Program Income Drawdown Program Income Received Total Funds Expended Jan 1 thru Mar 31, 2013 Match Contributed Activity Description: This activity will address neighborhood stabilization within the high priority areas identified. Properties will be acquired, rehabilitated and made available as rental property for families that are below 50% of Area Median Income (AMI). Properties will be rehabilitated to standards that comply with the applicable laws, codes and other requirements of Pinellas County Community Development's Minimum Standards for Rehabilitation of Residential Properties. All rehabilitation must be performed by a licensed and insured contractor. Pinellas County has seen home values decrease and the need for rental properties has increased. Some of this is largely due to the high unemployment rate for the area, resulting in a need for affordable rental housing. Central and East Lealman areas continue to be areas of need and require assistance. The goal of Multi-Family Development Program LM25 is to revitalize the greatest need areas by preserving the number of rental units available to families below 50% AMI. Pinellas County has developed strong partnerships with our local nonprofit developers that have the capacity to acquire and rehabilitate multi-family developments. In addition, several of these nonprofit developers currently have units in close proximity to the target area that they are currently managing as affordable rental housing. Eligible properties include single-family homes and multi-family rental properties that are either abandoned or foreclosed. The continued affordability of the properties addressed under this activity will be ensured through land use restriction instruments. All properties acquired under this activity must meet the required purchase discount of at least 5% less than current market appraised value and must be as high as required to keep the total NSP portfolio within the required purchase discount level. The properties will be monitored for continued affordability requirements and affordable rents, consistent with the monitoring standards utilized for HOME funded multi-family properties. Location Description: 20

21 This activity will be completed in the Central and East Lealman neighborhoods, areas identified using the HUD Mapping Tool and designated as "20". Census tracts with a score of "19" that surround the neighborhoods will be considered if the area needs to be expanded for meeting the expenditure deadlines. Activity Progress Narrative: Accomplishments Performance Measures No Accomplishments Performance Measures found. Beneficiaries Performance Measures No Beneficiaries Performance Measures found. Activity Locations No Activity Locations found. Other Funding Sources Budgeted - Detail No Other Match Funding Sources Found Other Funding Sources No Other Funding Sources Found Total Other Funding Sources Amount 21

22 Grantee Activity Number: Activity Title: Activitiy Category: Acquisition - general Project Number: AR Program Projected Start Date: 03/10/2011 Benefit Type: Direct ( HouseHold ) National Objective: NSP Only - LMMI M/F AR LMMI Multi-Family Development Program LMMI Activity Status: Under Way Project Title: Acquisition & Rehabilitation Projected End Date: 03/10/2014 Completed Activity Actual End Date: Responsible Organization: Overall Total Projected Budget from All Sources Total Budget Total Obligated Total Funds Drawdown ($678,387.35) To Date Program Funds Drawdown Program Income Drawdown Program Income Received Total Funds Expended Jan 1 thru Mar 31, 2013 Match Contributed Activity Description: This activity will address neighborhood stabilization within the high priority areas identified. Properties will be acquired, rehabilitated and made available as rental property for families that are below 120% of Area Median Income (AMI). Properties will be rehabilitated to standards that comply with the applicable laws, codes and other requirements of Pinellas County Community Development's Minimum Standards for Rehabilitation of Residential Properties. All rehabilitation must be performed by a licensed and insured contractor. Pinellas County has seen home values decrease and the need for rental properties has increased. Some of this is largely due to the high unemployment rate for the area, resulting in a need for affordable rental housing. Central and East Lealman areas continue to be areas of need and require assistance. The goal of Multi-Family Development Program is to revitalize the greatest need areas by preserving the number of rental units available to families below 120% AMI. Pinellas County has developed strong partnerships with our local nonprofit developers that have the capacity to acquire and rehabilitate multi-family developments. In addition, several of these nonprofit developers currently have units in close proximity to the target area that they are currently managing as affordable rental housing. Eligible properties include single-family homes and multi-family rental properties that are either abandoned or foreclosed. The continued affordability of the properties addressed under this activity will be ensured through land use restriction instruments. All properties acquired under this activity must meet the required purchase discount of at least 5% less than current market appraised value and must be as high as required to keep the total NSP portfolio within the required purchase discount level. The properties will be monitored for continued affordability requirements and affordable rents, consistent with the monitoring standards utilized for HOME funded multi-family properties. Location Description: 22

23 The activity will be completed in the Central and East Lealman neighborhoods, areas identified using the HUD Mapping Tool and designated as "20". Census tracts with a score of "19" that surround the neighborhoods will be considered if the area needs to be expanded for meeting the expenditure deadlines. Activity Progress Narrative: Accomplishments Performance Measures No Accomplishments Performance Measures found. Beneficiaries Performance Measures No Beneficiaries Performance Measures found. Activity Locations No Activity Locations found. Other Funding Sources Budgeted - Detail No Other Match Funding Sources Found Other Funding Sources No Other Funding Sources Found Total Other Funding Sources Amount 23

24 Grantee Activity Number: Activity Title: Activitiy Category: Construction of new housing Project Number: REDEVELOPMENT Projected Start Date: 03/10/2011 Benefit Type: Direct ( HouseHold ) National Objective: NSP Only - LMMI REDEVELOPMENT OWNER Owner Redevelopment Program Activity Status: Under Way Project Title: Redevelopment Projected End Date: 03/10/2014 Completed Activity Actual End Date: Responsible Organization: Overall Total Projected Budget from All Sources Total Budget Total Obligated Total Funds Drawdown To Date Program Funds Drawdown Program Income Drawdown Program Income Received Total Funds Expended Jan 1 thru Mar 31, 2013 Match Contributed Activity Description: This activity will address neighborhood stabilization with the redevelopment of demolished or vacant properties. Properties under the Owner Redevelopment Program may be redeveloped with housing that will become part of the Homeownership Financing Program. Properties addressed under this activity that meet the NSP Plan's definition of blighted are exempt from the requirement that the property must be foreclosed or abandoned. Eligible homebuyers for the newly constructed homes will be required to complete an eight (8) hour HUD approved homebuyer counseling class. The tenure of the beneficiaries of this activity will be that of homeownership. Location Description: The activity will be completed in the Central and East Lealman neighborhoods, areas identified using the HUD Mapping Tool and designated as "20". Census tracts with a score of "19" that surround the neighborhoods will be considered if the area needs to be expanded for meeting the expenditure deadlines. Activity Progress Narrative: Accomplishments Performance Measures No Accomplishments Performance Measures found. 24

25 Beneficiaries Performance Measures No Beneficiaries Performance Measures found. Activity Locations No Activity Locations found. Other Funding Sources Budgeted - Detail No Other Match Funding Sources Found Other Funding Sources No Other Funding Sources Found Total Other Funding Sources Amount 25

26 Grantee Activity Number: Activity Title: Activitiy Category: Acquisition - general Project Number: AR Program Projected Start Date: 03/10/2011 Benefit Type: Direct ( HouseHold ) National Objective: NSP Only - LMMI S/F AR Single Family Acquisition & Rehabilitation Program Activity Status: Under Way Project Title: Acquisition & Rehabilitation Projected End Date: 03/10/2014 Completed Activity Actual End Date: Responsible Organization: Overall Total Projected Budget from All Sources Total Budget Total Obligated Total Funds Drawdown ($230,000.00) To Date $820, $820, $520, $520, Program Funds Drawdown $504, $520, Program Income Drawdown Program Income Received Total Funds Expended Jan 1 thru Mar 31, 2013 ($230,000.00) $504, $308, $308, $573, $573, Match Contributed Activity Description: Pinellas County has a high foreclosure rate, home values have dropped and neighborhoods are deteriorating as a result. Some areas are stabilizing; however, the Lealman area continues to be an area of need and requires assistance. The goal of the Single Family Acquisition & Rehabilitation Program is to revitalize the greatest need areas by improving the housing stock and stabilizing declining markets in the high priority areas. All properties acquired under this activity must meet the minimum 1% less than current market appraised value discount per property. Pinellas County has a strong system in place for completion of the activity and it will be accomplished through the Housing Finance Authority of Pinellas County. The County has established a successful model in NSP1 working with the Housing Finance Authority to purchase foreclosed single-family homes and rehabilitate them for resale to income eligible buyers. Intermediaries will be utilized to identify the most current inventory of foreclosed properties within the high priority areas. Negotiations with the lenders will meet the requirements established to obtain the maximum reasonable discount for the program. The purchase of specific foreclosed properties will be dependent upon the highest need within the neighborhood and the availability of foreclosed properties that can be obtained at a price consistent with the discount requirements of NSP3 funding. The minimum affordability requirements will be consistent with the requirements of HOME: $15,000-5 years $15,000-$40, years >$40, years 26

27 New Construction - 20 years If a home acquired through this activity is not able to be sold to an eligible homebuyer within a reasonable time, as determined by Pinellas County, the home may be considered for rental occupancy to an income qualified family. Location Description: The activity will be completed in the Central and East Lealman neighborhoods, areas identified using the HUD Mapping Tool and designated as "20". Census tracts with a score of "19" that surround the neighborhoods will be considered if the area needs to be expanded for meeting the expenditure deadlines. Activity Progress Narrative: During the quarter, Pinellas County continued property screening and evaluation reviews. Four single-family properties were acquired during this quarter. Two previously acquired houses were demolished. Rehab construction began on three houses, To date, a total of ten single family properties have been acquired. The expenditures for the acquisition of these 7 homes have been processed. Accomplishments Performance Measures No Accomplishments Performance Measures found. Beneficiaries Performance Measures No Beneficiaries Performance Measures found. Activity Locations No Activity Locations found. Other Funding Sources Budgeted - Detail No Other Match Funding Sources Found Other Funding Sources No Other Funding Sources Found Total Other Funding Sources Amount 27

October 1, 2012 thru December 31, 2012 Performance Report

October 1, 2012 thru December 31, 2012 Performance Report Grantee: Pinellas County, FL Grant: B-11-UN-12-0015 October 1, 2012 thru December 31, 2012 Performance Report 1 Grant Number: B-11-UN-12-0015 Grantee Name: Pinellas County, FL Grant Amount: $4,697,519.00

More information

July 1, 2017 thru September 30, 2017 Performance Report

July 1, 2017 thru September 30, 2017 Performance Report Grantee: Grant: Pinellas County, FL B-11-UN-12-0015 July 1, 2017 thru September 30, 2017 Performance Report 1 Grant Number: B-11-UN-12-0015 Grantee Name: Pinellas County, FL Grant Award Amount: $4,697,519.00

More information

April 1, 2013 thru June 30, 2013 Performance Report

April 1, 2013 thru June 30, 2013 Performance Report Grantee: Pinellas County, FL Grant: B-08-UN-12-0015 April 1, 2013 thru June 30, 2013 Performance Report 1 Grant Number: B-08-UN-12-0015 Grantee Name: Pinellas County, FL Grant Amount: $8,063,759.00 Estimated

More information

July 1, 2011 thru September 30, 2011 Performance Report

July 1, 2011 thru September 30, 2011 Performance Report Grantee: Pinellas County, FL Grant: B-08-UN-12-0015 July 1, 2011 thru September 30, 2011 Performance Report 1 Grant Number: B-08-UN-12-0015 Grantee Name: Pinellas County, FL Grant Amount: $8,063,759.00

More information

April 1, 2016 thru June 30, 2016 Performance Report

April 1, 2016 thru June 30, 2016 Performance Report Grantee: Grant: Orange County, FL B-11-UN-12-0012 April 1, 2016 thru June 30, 2016 Performance Report 1 Grant Number: B-11-UN-12-0012 Grantee Name: Orange County, FL Grant Award Amount: $11,551,158.00

More information

April 1, 2011 thru June 30, 2011 Performance Report

April 1, 2011 thru June 30, 2011 Performance Report Grantee: Pomona, CA Grant: B-11-MN-06-0516 April 1, 2011 thru June 30, 2011 Performance Report 1 Grant Number: B-11-MN-06-0516 Grantee Name: Pomona, CA Grant Amount: $1,235,629.00 Estimated PI/RL Funds:

More information

B-11-MN April 1, 2014 thru June 30, 2014 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-11-MN April 1, 2014 thru June 30, 2014 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Pomona, CA B-11-MN-06-0516 April 1, 2014 thru June 30, 2014 Performance Report 1 Grant Number: B-11-MN-06-0516 Grantee Name: Pomona, CA Grant Award Amount: $1,235,629.00 LOCCS Authorized

More information

January 1, 2016 thru March 31, 2016 Performance Report

January 1, 2016 thru March 31, 2016 Performance Report Grantee: Grant: Pompano Beach, FL B-11-MN-12-0024 January 1, 2016 thru March 31, 2016 Performance Report 1 Grant Number: B-11-MN-12-0024 Grantee Name: Pompano Beach, FL Grant Award Amount: $1,500,572.00

More information

Apr 1, 2015 thru Jun 30, 2015 Performance Report

Apr 1, 2015 thru Jun 30, 2015 Performance Report Apr 1, 2015 thru Jun 30, 2015 Performance Report Grant Number: B-08-UN-12-0015 Grantee Name: Pinellas County, FL Grant Award : $8,063,759.00 LOCCS Authorized : $8,063,759.00 Obligation Date: Award Date:

More information

July 1, 2014 thru September 30, 2014 Performance Report

July 1, 2014 thru September 30, 2014 Performance Report Grantee: Grant: Broward County FL B-11-UN-12-0002 July 1 2014 thru September 30 2014 Performance Report 1 Grant Number: B-11-UN-12-0002 Grantee Name: Broward County FL Grant Award Amount: $5457553.00 LOCCS

More information

B-08-MN October 1, 2015 thru December 31, 2015 Performance. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-08-MN October 1, 2015 thru December 31, 2015 Performance. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Pomona, CA B-08-MN-06-0516 October 1, 2015 thru December 31, 2015 Performance 1 Grant Number: B-08-MN-06-0516 Grantee Name: Pomona, CA Grant Award Amount: $3,530,825.00 LOCCS Authorized

More information

Reviewed and Approved

Reviewed and Approved Action Plan Grantee: Grant: Houston, TX B-11-MN-48-0400 LOCCS Authorized Amount: Grant Award Amount: $ 3,389,035.00 $ 3,389,035.00 Status: Reviewed and Approved Estimated PI/RL Funds: $ 1,250,664.11 Total

More information

January 1, 2015 thru March 31, 2015 Performance Report

January 1, 2015 thru March 31, 2015 Performance Report Grantee: Grant: Broward County, FL B-08-UN-12-0002 January 1, 2015 thru March 31, 2015 Performance Report 1 Grant Number: B-08-UN-12-0002 Grantee Name: Broward County, FL Grant Award Amount: $17,767,589.00

More information

July 1, 2013 thru September 30, 2013 Performance Report

July 1, 2013 thru September 30, 2013 Performance Report Grantee: Broward County, FL Grant: B-08-UN-12-0002 July 1, 2013 thru September 30, 2013 Performance Report 1 Grant Number: B-08-UN-12-0002 Grantee Name: Broward County, FL LOCCS Authorized Amount: $17,767,589.00

More information

January 1, 2016 thru March 31, 2016 Performance Report

January 1, 2016 thru March 31, 2016 Performance Report Grantee: Grant: Clark County, NV B-08-UN-32-0001 January 1, 2016 thru March 31, 2016 Performance Report 1 Grant Number: B-08-UN-32-0001 Grantee Name: Clark County, NV Grant Award Amount: $29,666,798.00

More information

October 1, 2014 thru December 31, 2014 Performance Report

October 1, 2014 thru December 31, 2014 Performance Report Grantee: Grant: Broward County FL B-08-UN-12-0002 October 1 2014 thru December 31 2014 Performance Report 1 Grant Number: B-08-UN-12-0002 Grantee Name: Broward County FL Grant Award Amount: $17767589.00

More information

July 1, 2015 thru September 30, 2015 Performance Report

July 1, 2015 thru September 30, 2015 Performance Report Grantee: Grant: Brevard County, FL B-08-UN-12-0001 July 1, 2015 thru September 30, 2015 Performance Report 1 Grant Number: B-08-UN-12-0001 Grantee Name: Brevard County, FL Grant Award Amount: $5,269,667.00

More information

January 1, 2017 thru March 31, 2017 Performance Report

January 1, 2017 thru March 31, 2017 Performance Report Grantee: Grant: Anderson, IN B-08-MN-18-0001 January 1, 2017 thru March 31, 2017 Performance Report 1 Grant Number: B-08-MN-18-0001 Grantee Name: Anderson, IN Grant Award Amount: $2,141,795.00 LOCCS Authorized

More information

Reviewed and Approved

Reviewed and Approved Action Plan Grantee: Grant: Orange County, FL B-11-UN-12-0012 LOCCS Authorized Amount: Grant Award Amount: $ 11,551,158.00 $ 11,551,158.00 Status: Reviewed and Approved Estimated PI/RL Funds: $ 11,700,000.00

More information

April 1, 2013 thru June 30, 2013 Performance Report

April 1, 2013 thru June 30, 2013 Performance Report Grantee: Prince William County, VA Grant: B-08-UN-51-0002 April 1, 2013 thru June 30, 2013 Performance Report 1 Grant Number: B-08-UN-51-0002 Grantee Name: Prince William County, VA Grant Amount: Estimated

More information

Grantee: Broward County, FL Grant: B-08-UN April 1, 2011 thru June 30, 2011 Performance Report

Grantee: Broward County, FL Grant: B-08-UN April 1, 2011 thru June 30, 2011 Performance Report Grantee: Broward County, FL Grant: B-08-UN-12-0002 April 1, 2011 thru June 30, 2011 Performance Report 1 Grant Number: B-08-UN-12-0002 Grantee Name: Broward County, FL Grant Amount: $17,767,589.00 Grant

More information

B-11-MN April 1, 2014 thru June 30, 2014 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-11-MN April 1, 2014 thru June 30, 2014 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Southfield, MI B-11-MN-26-0011 April 1, 2014 thru June 30, 2014 Performance Report 1 Grant Number: B-11-MN-26-0011 Grantee Name: Southfield, MI Grant Award Amount: $1,084,254.00 LOCCS Authorized

More information

Grantee: Broward County, FL Grant: B-08-UN April 1, 2012 thru June 30, 2012 Performance Report

Grantee: Broward County, FL Grant: B-08-UN April 1, 2012 thru June 30, 2012 Performance Report Grantee: Broward County, FL Grant: B-08-UN-12-0002 April 1, 2012 thru June 30, 2012 Performance Report 1 Grant Number: Obligation Date: Award Date: B-08-UN-12-0002 Grantee Name: Contract End Date: Review

More information

October 1, 2011 thru December 31, 2011 Performance Report

October 1, 2011 thru December 31, 2011 Performance Report Grantee: Pomona, CA Grant: B-08-MN-06-0516 October 1, 2011 thru December 31, 2011 Performance Report 1 Grant Number: B-08-MN-06-0516 Grantee Name: Pomona, CA Grant Amount: $3,530,825.00 Estimated PI/RL

More information

January 1, 2012 thru March 31, 2012 Performance Report

January 1, 2012 thru March 31, 2012 Performance Report Grantee: Elyria, OH Grant: B-08-MN-39-0007 January 1, 2012 thru March 31, 2012 Performance Report 1 Grant Number: B-08-MN-39-0007 Grantee Name: Elyria, OH Grant Amount: $2,468,215.00 Estimated PI/RL Funds:

More information

January 1, 2016 thru March 31, 2016 Performance Report

January 1, 2016 thru March 31, 2016 Performance Report Grantee: Grant: DuPage County, IL B-08-UN-17-0002 January 1, 2016 thru March 31, 2016 Performance Report 1 Grant Number: B-08-UN-17-0002 Grantee Name: DuPage County, IL Grant Award Amount: $5,176,438.00

More information

January 1, 2013 thru March 31, 2013 Performance Report

January 1, 2013 thru March 31, 2013 Performance Report Grantee: Osceola County, FL Grant: B-11-UN-12-0023 January 1, 2013 thru March 31, 2013 Performance Report 1 Grant Number: B-11-UN-12-0023 Grantee Name: Osceola County, FL Grant Amount: $3,239,646.00 Estimated

More information

B-08-MN April 1, 2016 thru June 30, 2016 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-08-MN April 1, 2016 thru June 30, 2016 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Savannah, GA B-08-MN-13-0004 April 1, 2016 thru June 30, 2016 Performance Report 1 Grant Number: B-08-MN-13-0004 Grantee Name: Savannah, GA Grant Award Amount: $2,038,631.00 Obligation

More information

B-11-MN April 1, 2016 thru June 30, 2016 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-11-MN April 1, 2016 thru June 30, 2016 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Tucson, AZ B-11-MN-04-0507 April 1, 2016 thru June 30, 2016 Performance Report 1 Grant Number: B-11-MN-04-0507 Grantee Name: Tucson, AZ Grant Award Amount: $2,083,771.00 LOCCS Authorized

More information

January 1, 2011 thru March 31, 2011 Performance Report

January 1, 2011 thru March 31, 2011 Performance Report Grantee: Southfield, MI Grant: B-08-MN-26-0011 January 1, 2011 thru March 31, 2011 Performance Report 1 Grant Number: B-08-MN-26-0011 Grantee Name: Southfield, MI Grant Amount: $3,241,457.00 Estimated

More information

January 1, 2017 thru March 31, 2017 Performance Report

January 1, 2017 thru March 31, 2017 Performance Report Grantee: Grant: Hillsborough County, FL B-08-UN-12-0006 January 1, 2017 thru March 31, 2017 Performance Report 1 Grant Number: B-08-UN-12-0006 Grantee Name: Hillsborough County, FL Grant Award Amount:

More information

October 1, 2015 thru December 31, 2015 Performance

October 1, 2015 thru December 31, 2015 Performance Grantee: Grant: Daytona Beach, FL B--MN-2-0032 October, 205 thru December 3, 205 Performance Grant Number: B--MN-2-0032 Grantee Name: Daytona Beach, FL Grant Award Amount: $,27,66.00 LOCCS Authorized Amount:

More information

January 1, 2014 thru March 31, 2014 Performance Report

January 1, 2014 thru March 31, 2014 Performance Report Grantee: Kern County, CA Grant: B-08-UN-06-0501 January 1, 2014 thru March 31, 2014 Performance Report 1 Grant Number: B-08-UN-06-0501 Grantee Name: Kern County, CA LOCCS Authorized Amount: $11,211,385.00

More information

B-08-UN April 1, 2015 thru June 30, 2015 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-08-UN April 1, 2015 thru June 30, 2015 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Lee County, FL B-08-UN-12-0009 April 1, 2015 thru June 30, 2015 Performance Report 1 Grant Number: B-08-UN-12-0009 Grantee Name: Lee County, FL Grant Award Amount: $18,243,867.00 LOCCS

More information

October 1, 2017 thru December 31, 2017 Performance

October 1, 2017 thru December 31, 2017 Performance Grantee: Grant: Hillsborough County, FL B-08-UN-12-0006 October 1, 2017 thru December 31, 2017 Performance 1 Grant Number: B-08-UN-12-0006 Grantee Name: Hillsborough County, FL Grant Award Amount: $19,132,978.00

More information

July 1, 2018 thru September 30, 2018 Performance Report

July 1, 2018 thru September 30, 2018 Performance Report Grantee: Grant: Broward County, FL B-11-UN-12-0002 July 1, 2018 thru September 30, 2018 Performance Report 1 Grant Number: B-11-UN-12-0002 Grantee Name: Broward County, FL Grant Award Amount: $5,457,553.00

More information

April 1, 2017 thru June 30, 2017 Performance Report

April 1, 2017 thru June 30, 2017 Performance Report Grantee: Grant: Orange County, FL B-08-UN-12-0012 April 1, 2017 thru June 30, 2017 Performance Report 1 Grant Number: B-08-UN-12-0012 Grantee Name: Orange County, FL Grant Award Amount: $27,901,773.00

More information

October 1, 2016 thru December 31, 2016 Performance

October 1, 2016 thru December 31, 2016 Performance Grantee: Grant: St Petersburg, FL B-08-MN-12-0026 October 1, 2016 thru December 31, 2016 Performance 1 Grant Number: B-08-MN-12-0026 Grantee Name: St Petersburg, FL Grant Award Amount: $9,498,962.00 LOCCS

More information

April 1, 2014 thru June 30, 2014 Performance Report

April 1, 2014 thru June 30, 2014 Performance Report Grantee: Grant: Prince Georges County, MD B-11-UN-24-0002 April 1, 2014 thru June 30, 2014 Performance Report 1 Grant Number: B-11-UN-24-0002 Grantee Name: Prince Georges County, MD Grant Award Amount:

More information

October 1, 2017 thru September 30, 2018 Performance

October 1, 2017 thru September 30, 2018 Performance Grantee: Hillsborough County, FL Grant: B-11-UN-12-0006 October 1, 2017 thru September 30, 2018 Performance 1 Grant Number: Obligation Date: Award Date: B-11-UN-12-0006 Grantee Name: Contract End Date:

More information

July 1, 2015 thru September 30, 2015 Performance Report

July 1, 2015 thru September 30, 2015 Performance Report Grantee: Grant: Hernando County, FL B-11-UN-12-0021 July 1, 2015 thru September 30, 2015 Performance Report 1 Grant Number: B-11-UN-12-0021 Grantee Name: Hernando County, FL Grant Award Amount: $1,953,975.00

More information

January 1, 2012 thru March 31, 2012 Performance Report

January 1, 2012 thru March 31, 2012 Performance Report Grantee: Indian River County, FL Grant: B-11-UN-12-0022 January 1, 2012 thru March 31, 2012 Performance Report 1 Grant Number: B-11-UN-12-0022 Grantee Name: Indian River County, FL Grant Amount: $1,500,428.00

More information

July 1, 2018 thru September 30, 2018 Performance Report

July 1, 2018 thru September 30, 2018 Performance Report Grantee: Grant: Clayton County, GA B-08-UN-13-0001 July 1, 2018 thru September 30, 2018 Performance Report 1 Grant Number: B-08-UN-13-0001 Grantee Name: Clayton County, GA Grant Award Amount: $9,732,126.00

More information

October 1, 2016 thru December 31, 2016 Performance

October 1, 2016 thru December 31, 2016 Performance Grantee: Grant: Babylon Township, NY B-08-MN-36-0101 October 1, 2016 thru December 31, 2016 Performance 1 Grant Number: B-08-MN-36-0101 Grantee Name: Babylon Township, NY Grant Award Amount: $2,170,909.00

More information

B-11-MN April 1, 2018 thru June 30, 2018 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-11-MN April 1, 2018 thru June 30, 2018 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Stockton, CA B-11-MN-06-0009 April 1, 2018 thru June 30, 2018 Performance Report 1 Grant Number: B-11-MN-06-0009 Grantee Name: Stockton, CA Grant Award Amount: $4,280,994.00 LOCCS Authorized

More information

January 1, 2012 thru March 31, 2012 Performance Report

January 1, 2012 thru March 31, 2012 Performance Report Grantee: Oakland, CA Grant: B-11-MN-06-0005 January 1, 2012 thru March 31, 2012 Performance Report 1 Grant Number: B-11-MN-06-0005 Grantee Name: Oakland, CA Grant Amount: $2,070,087.00 Estimated PI/RL

More information

April 1, 2017 thru June 30, 2017 Performance Report

April 1, 2017 thru June 30, 2017 Performance Report Grantee: Grant: St Petersburg, FL B-08-MN-12-0026 April 1, 2017 thru June 30, 2017 Performance Report 1 Grant Number: B-08-MN-12-0026 Grantee Name: St Petersburg, FL Grant Award Amount: $9,498,962.00 LOCCS

More information

January 1, 2016 thru March 31, 2016 Performance Report

January 1, 2016 thru March 31, 2016 Performance Report Grantee: Grant: Henderson, NV B-08-MN-32-0001 January 1, 2016 thru March 31, 2016 Performance Report 1 Grant Number: B-08-MN-32-0001 Grantee Name: Henderson, NV Grant Award Amount: $3,205,044.00 LOCCS

More information

January 1, 2012 thru March 31, 2012 Performance Report

January 1, 2012 thru March 31, 2012 Performance Report Grantee: Merced, CA Grant: B-11-MN-06-0012 January 1, 2012 thru March 31, 2012 Performance Report 1 Grant Number: B-11-MN-06-0012 Grantee Name: Merced, CA Grant Amount: $1,196,182.00 Estimated PI/RL Funds:

More information

October 1, 2017 thru December 31, 2017 Performance

October 1, 2017 thru December 31, 2017 Performance Grantee: Grant: Port St. Lucie, FL B-11-MN-12-0025 October 1, 2017 thru December 31, 2017 Performance 1 Grant Number: B-11-MN-12-0025 Grantee Name: Port St. Lucie, FL Grant Award Amount: $3,515,509.00

More information

January 1, 2013 thru March 31, 2013 Performance Report

January 1, 2013 thru March 31, 2013 Performance Report Grantee:, FL Grant: B-11-UN-12-0014 January 1, 2013 thru March 31, 2013 Performance Report 1 Grant Number: B-11-UN-12-0014 Grantee Name:, FL Grant Amount: $5,185,778.00 Estimated PI/RL Funds: Obligation

More information

October 1, 2009 thru December 31, 2009 Performance Report

October 1, 2009 thru December 31, 2009 Performance Report Grantee: Lancaster, CA Grant: B-08-MN-06-0510 October 1, 2009 thru December 31, 2009 Performance Report Grant Number: B-08-MN-06-0510 Grantee Name: Lancaster, CA Grant Amount: $6,983,533.00 Grant Status:

More information

B-11-UN April 1, 2016 thru June 30, 2016 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-11-UN April 1, 2016 thru June 30, 2016 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Lee County, FL B-11-UN-12-0009 April 1, 2016 thru June 30, 2016 Performance Report 1 Grant Number: B-11-UN-12-0009 Grantee Name: Lee County, FL Grant Award Amount: $6,639,174.00 LOCCS Authorized

More information

July 1, 2013 thru September 30, 2013 Performance Report

July 1, 2013 thru September 30, 2013 Performance Report Grantee: Kern County, CA Grant: B-08-UN-06-0501 July 1, 2013 thru September 30, 2013 Performance Report 1 Grant Number: B-08-UN-06-0501 Grantee Name: Kern County, CA LOCCS Authorized Amount: Estimated

More information

B-11-UN October 1, 2016 thru December 31, 2016 Performance. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-11-UN October 1, 2016 thru December 31, 2016 Performance. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Pasco County, FL B-11-UN-12-0014 October 1, 2016 thru December 31, 2016 Performance 1 Grant Number: B-11-UN-12-0014 Grantee Name: Pasco County, FL Grant Award Amount: $5,185,778.00 LOCCS

More information

B-11-MN April 1, 2015 thru June 30, 2015 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-11-MN April 1, 2015 thru June 30, 2015 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Orlando, FL B-11-MN-12-0020 April 1, 2015 thru June 30, 2015 Performance Report 1 Grant Number: B-11-MN-12-0020 Grantee Name: Orlando, FL Grant Award Amount: $3,095,137.00 LOCCS Authorized

More information

October 1, 2014 thru December 31, 2014 Performance Report

October 1, 2014 thru December 31, 2014 Performance Report Grantee: Grant: Boynton Beach FL B-11-MN-12-0002 October 1 2014 thru December 31 2014 Performance Report 1 Grant Number: B-11-MN-12-0002 Grantee Name: Boynton Beach FL Grant Award Amount: $1168808.00 LOCCS

More information

Oct 1, 2011 thru Dec 31, 2011 Performance Report

Oct 1, 2011 thru Dec 31, 2011 Performance Report Page 1 of 7 Oct 1, 2011 thru Dec 31, 2011 Performance Report Grant Number: B-11-MN-06-0511 Grantee Name: Long Beach, CA Grant Amount: $1,567,935.00 Estimated PI/RL Funds: $1,693,370.00 Obligation Date:

More information

January 1, 2012 thru March 31, 2012 Performance Report

January 1, 2012 thru March 31, 2012 Performance Report Grantee: Compton, CA Grant: B-08-MN-06-0505 January 1, 2012 thru March 31, 2012 Performance Report 1 Grant Number: B-08-MN-06-0505 Grantee Name: Compton, CA Grant Amount: $3,242,817.00 Estimated PI/RL

More information

October 1, 2013 thru December 31, 2013 Performance Report

October 1, 2013 thru December 31, 2013 Performance Report Grantee: Orlando, FL Grant: B-11-MN-12-0020 October 1, 2013 thru December 31, 2013 Performance Report 1 Grant Number: B-11-MN-12-0020 Grantee Name: Orlando, FL LOCCS Authorized Amount: $3,095,137.00 Estimated

More information

January 1, 2014 thru March 31, 2014 Performance Report

January 1, 2014 thru March 31, 2014 Performance Report Grantee: Lee County, FL Grant: B-08-UN-12-0009 January 1, 2014 thru March 31, 2014 Performance Report 1 Grant Number: B-08-UN-12-0009 Grantee Name: Lee County, FL LOCCS Authorized Amount: $18,243,867.00

More information

April 1, 2016 thru June 30, 2016 Performance Report

April 1, 2016 thru June 30, 2016 Performance Report Grantee: Grant: Sarasota County, FL B-11-UN-12-0017 April 1, 2016 thru June 30, 2016 Performance Report 1 Grant Number: B-11-UN-12-0017 Grantee Name: Sarasota County, FL Grant Award Amount: $3,949,541.00

More information

October 1, 2016 thru December 31, 2016 Performance

October 1, 2016 thru December 31, 2016 Performance Grantee: Grant:, MN B-08-UN-27-0003 October 1, 2016 thru December 31, 2016 Performance 1 Grant Number: B-08-UN-27-0003 Grantee Name:, MN Grant Award Amount: $3,885,729.00 LOCCS Authorized Amount: $3,885,729.00

More information

October 1, 2014 thru December 31, 2014 Performance Report

October 1, 2014 thru December 31, 2014 Performance Report Grantee: Grant: Miami, FL B-08-MN-12-0016 October 1, 2014 thru December 31, 2014 Performance Report 1 Grant Number: B-08-MN-12-0016 Grantee Name: Miami, FL Grant Award Amount: $12,063,702.00 LOCCS Authorized

More information

July 1, 2011 thru September 30, 2011 Performance Report

July 1, 2011 thru September 30, 2011 Performance Report Grantee: Hammond, IN Grant: B-08-MN-18-0006 July 1, 2011 thru September 30, 2011 Performance Report 1 Grant Number: B-08-MN-18-0006 Grantee Name: Hammond, IN Grant Amount: $3,860,473.00 Estimated PI/RL

More information

July 1, 2018 thru September 30, 2018 Performance Report

July 1, 2018 thru September 30, 2018 Performance Report Grantee: Grant: Illinois B-11-DN-17-0001 July 1, 2018 thru September 30, 2018 Performance Report 1 Grant Number: B-11-DN-17-0001 Grantee Name: Illinois Grant Award Amount: $5,000,000.00 LOCCS Authorized

More information

October 1, 2015 thru December 31, 2015 Performance

October 1, 2015 thru December 31, 2015 Performance Grantee: Grant: Butler County, OH B-08-UN-39-0001 October 1, 2015 thru December 31, 2015 Performance 1 Grant Number: B-08-UN-39-0001 Grantee Name: Butler County, OH Grant Award Amount: $4,213,742.00 LOCCS

More information

January 1, 2017 thru March 31, 2017 Performance Report

January 1, 2017 thru March 31, 2017 Performance Report Grantee: Grant: Rialto, CA B-08-MN-06-0518 January 1, 2017 thru March 31, 2017 Performance Report 1 Grant Number: B-08-MN-06-0518 Grantee Name: Rialto, CA Grant Award Amount: $5,461,574.00 LOCCS Authorized

More information

January 1, 2015 thru March 31, 2015 Performance Report

January 1, 2015 thru March 31, 2015 Performance Report Grantee: Grant: West Palm Beach, FL B-08-MN-12-0030 January 1, 2015 thru March 31, 2015 Performance Report 1 Grant Number: B-08-MN-12-0030 Grantee Name: West Palm Beach, FL Grant Award Amount: $4,349,546.00

More information

April 1, 2014 thru June 30, 2014 Performance Report

April 1, 2014 thru June 30, 2014 Performance Report Grantee: Grant: Canton Township, MI B-08-MN-26-0001 April 1, 2014 thru June 30, 2014 Performance Report 1 Grant Number: B-08-MN-26-0001 Grantee Name: Canton Township, MI Grant Award Amount: $2,182,988.00

More information

July 1, 2009 thru September 30, 2009 Performance Report

July 1, 2009 thru September 30, 2009 Performance Report Grantee: Lorain, OH Grant: B-08-MN-39-0010 July 1, 2009 thru September 30, 2009 Performance Report Grant Number: B-08-MN-39-0010 Grantee Name: Lorain, OH Grant : $3,031,480.00 Grant Status: Active Obligation

More information

January 1, 2016 thru March 31, 2016 Performance Report

January 1, 2016 thru March 31, 2016 Performance Report Grantee: Grant: Rialto, CA B-08-MN-06-0518 January 1, 2016 thru March 31, 2016 Performance Report 1 Grant Number: B-08-MN-06-0518 Grantee Name: Rialto, CA Grant Award Amount: $5,461,574.00 LOCCS Authorized

More information

B-08-MN October 1, 2015 thru December 31, 2015 Performance. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-08-MN October 1, 2015 thru December 31, 2015 Performance. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Stockton, CA B-08-MN-06-0009 October 1, 2015 thru December 31, 2015 Performance 1 Grant Number: B-08-MN-06-0009 Grantee Name: Stockton, CA Grant Award Amount: $12,146,038.00 LOCCS Authorized

More information

April 1, 2012 thru June 30, 2012 Performance Report

April 1, 2012 thru June 30, 2012 Performance Report Grantee: Elyria, OH Grant: B-08-MN-39-0007 April 1, 2012 thru June 30, 2012 Performance Report 1 Grant Number: B-08-MN-39-0007 Grantee Name: Elyria, OH Grant Amount: $2,468,215.00 Estimated PI/RL Funds:

More information

B-09-CN-CA April 1, 2014 thru June 30, 2014 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-09-CN-CA April 1, 2014 thru June 30, 2014 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Long Beach, CA B-09-CN-CA-0045 April 1, 2014 thru June 30, 2014 Performance Report 1 Grant Number: B-09-CN-CA-0045 Grantee Name: Long Beach, CA Grant Award Amount: $22,249,980.00 LOCCS

More information

April 1, 2011 thru June 30, 2011 Performance Report

April 1, 2011 thru June 30, 2011 Performance Report Grantee: Kokomo, IN Grant: B-11-MN-18-0008 April 1, 2011 thru June 30, 2011 Performance Report 1 Grant Number: B-11-MN-18-0008 Grantee Name: Kokomo, IN Grant Amount: Grant Status: Active Obligation Date:

More information

January 1, 2016 thru March 31, 2016 Performance Report

January 1, 2016 thru March 31, 2016 Performance Report Grantee: Grant: Middletown, OH B-08-MN-39-0011 January 1, 2016 thru March 31, 2016 Performance Report 1 Grant Number: B-08-MN-39-0011 Grantee Name: Middletown, OH Grant Award Amount: $2,144,379.00 LOCCS

More information

October 1, 2012 thru December 31, 2012 Performance Report

October 1, 2012 thru December 31, 2012 Performance Report Grantee: Lee County, FL Grant: B-08-UN-12-0009 October 1, 2012 thru December 31, 2012 Performance Report 1 Grant Number: B-08-UN-12-0009 Grantee Name: Lee County, FL Grant Amount: $18,243,867.00 Estimated

More information

October 1, 2011 thru December 31, 2011 Performance Report

October 1, 2011 thru December 31, 2011 Performance Report Grantee: San Joaquin County, CA Grant: B-11-UN-06-0005 October 1, 2011 thru December 31, 2011 Performance Report 1 Grant Number: B-11-UN-06-0005 Grantee Name: San Joaquin County, CA Grant Amount: $4,398,543.00

More information

October 1, 2011 thru December 31, 2011 Performance Report

October 1, 2011 thru December 31, 2011 Performance Report Grantee: Palm Beach County, FL Grant: B-08-UN-12-0013 October 1, 2011 thru December 31, 2011 Performance Report 1 Grant Number: B-08-UN-12-0013 Grantee Name: Palm Beach County, FL Grant Amount: $27,700,340.00

More information

October 1, 2014 thru December 31, 2014 Performance Report

October 1, 2014 thru December 31, 2014 Performance Report Grantee: Grant: Cincinnati OH B-08-MN-39-0003 October 1 2014 thru December 31 2014 Performance Report 1 Grant Number: B-08-MN-39-0003 Grantee Name: Cincinnati OH Grant Award Amount: $8361592.00 LOCCS Authorized

More information

October 1, 2012 thru December 31, 2012 Performance Report

October 1, 2012 thru December 31, 2012 Performance Report Grantee: Miami, FL Grant: B-08-MN-12-0016 October 1, 2012 thru December 31, 2012 Performance Report 1 Grant Number: B-08-MN-12-0016 Grantee Name: Miami, FL LOCCS Authorized Amount: $12,063,702.00 Estimated

More information

B-08-MN April 1, 2017 thru June 30, 2017 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-08-MN April 1, 2017 thru June 30, 2017 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Anaheim, CA B-08-MN-06-0501 April 1, 2017 thru June 30, 2017 Performance Report 1 Grant Number: B-08-MN-06-0501 Grantee Name: Anaheim, CA Grant Award Amount: $2,653,455.00 LOCCS Authorized

More information

April 1, 2018 thru June 30, 2018 Performance Report

April 1, 2018 thru June 30, 2018 Performance Report Grantee: Grant:, AZ B-11-UN-04-0503 April 1, 2018 thru June 30, 2018 Performance Report 1 Grant Number: B-11-UN-04-0503 Grantee Name:, AZ Grant Award Amount: $1,990,744.00 LOCCS Authorized Amount: $1,990,744.00

More information

Reviewed and Approved

Reviewed and Approved Action Plan Grantee: Grant:, FL B-11-UN-12-0011 LOCCS Authorized Amount: Grant Award Amount: $ 4,589,714.00 $ 4,589,714.00 Status: Reviewed and Approved Estimated PI/RL Funds: $ 2,500,000.00 Total Budget:

More information

July 1, 2013 thru September 30, 2013 Performance Report

July 1, 2013 thru September 30, 2013 Performance Report Grantee: San Joaquin County, CA Grant: B-11-UN-06-0005 July 1, 2013 thru September 30, 2013 Performance Report 1 Grant Number: B-11-UN-06-0005 Grantee Name: San Joaquin County, CA LOCCS Authorized Amount:

More information

Reviewed and Approved

Reviewed and Approved Action Plan Grantee: Grant: California B-11-DN-06-0001 LOCCS Authorized Amount: Grant Award Amount: $ 11,872,089.00 $ 11,872,089.00 Status: Reviewed and Approved Estimated PI/RL Funds: $ 6,000,000.00 $

More information

October 1, 2011 thru December 31, 2011 Performance Report

October 1, 2011 thru December 31, 2011 Performance Report Grantee: Kokomo, IN Grant: B-11-MN-18-0008 October 1, 2011 thru December 31, 2011 Performance Report 1 Grant Number: B-11-MN-18-0008 Grantee Name: Kokomo, IN Grant Amount: Estimated PI/RL Funds: Obligation

More information

October 1, 2012 thru December 31, 2012 Performance Report

October 1, 2012 thru December 31, 2012 Performance Report Grantee: Lee County, FL Grant: B-11-UN-12-0009 October 1, 2012 thru December 31, 2012 Performance Report 1 Grant Number: B-11-UN-12-0009 Grantee Name: Lee County, FL Grant Amount: $6,639,174.00 Estimated

More information

B-08-UN October 1, 2015 thru December 31, 2015 Performance. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-08-UN October 1, 2015 thru December 31, 2015 Performance. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Anoka County, MN B-08-UN-27-0001 October 1, 2015 thru December 31, 2015 Performance 1 Grant Number: B-08-UN-27-0001 Grantee Name: Anoka County, MN Grant Award Amount: $2,377,310.00 LOCCS

More information

October 1, 2011 thru December 31, 2011 Performance Report

October 1, 2011 thru December 31, 2011 Performance Report Grantee: San Joaquin County, CA Grant: B-08-UN-06-0005 October 1, 2011 thru December 31, 2011 Performance Report 1 Grant Number: B-08-UN-06-0005 Grantee Name: San Joaquin County, CA Grant Amount: $9,030,385.00

More information

B-08-MN April 1, 2016 thru June 30, 2016 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR)

B-08-MN April 1, 2016 thru June 30, 2016 Performance Report. Community Development Systems Disaster Recovery Grant Reporting System (DRGR) Grantee: Grant: Hesperia, CA B-08-MN-06-0509 April 1, 2016 thru June 30, 2016 Performance Report 1 Grant Number: B-08-MN-06-0509 Grantee Name: Hesperia, CA Grant Award Amount: $4,590,719.00 LOCCS Authorized

More information

July 1, 2012 thru September 30, 2012 Performance Report

July 1, 2012 thru September 30, 2012 Performance Report Grantee: Lee County, FL Grant: B-11-UN-12-0009 July 1, 2012 thru September 30, 2012 Performance Report 1 Grant Number: B-11-UN-12-0009 Grantee Name: Lee County, FL Grant Amount: $6,639,174.00 Estimated

More information

Reviewed and Approved

Reviewed and Approved Action Plan Grantee: Grant: Grand Rapids, MI B-08-MN-26-0006 LOCCS Authorized Amount: Grant Award Amount: $ 6,187,686.00 $ 6,187,686.00 Status: Reviewed and Approved Estimated PI/RL Funds: $ 1,203,715.00

More information

January 1, 2016 thru March 31, 2016 Performance Report

January 1, 2016 thru March 31, 2016 Performance Report Grantee: Grant: Hammond, IN B-11-MN-18-0006 January 1, 2016 thru March 31, 2016 Performance Report 1 Grant Number: B-11-MN-18-0006 Grantee Name: Hammond, IN Grant Award Amount: $1,243,934.00 LOCCS Authorized

More information

January 1, 2017 thru March 31, 2017 Performance Report

January 1, 2017 thru March 31, 2017 Performance Report Grantee: Grant:, FL B-11-UN-12-0006 January 1, 2017 thru March 31, 2017 Performance Report 1 Grant Number: B-11-UN-12-0006 Grantee Name:, FL Grant Award : $8,083,062.00 LOCCS Authorized : $8,083,062.00

More information

Reviewed and Approved

Reviewed and Approved Action Plan Grantee: Grant: Lakeland, FL B-11-MN-12-0013 LOCCS Authorized Amount: Grant Award Amount: $ 1,303,139.00 $ 1,303,139.00 Status: Reviewed and Approved Estimated PI/RL Funds: $ 578,484.85 Total

More information

January 1, 2016 thru March 31, 2016 Performance Report

January 1, 2016 thru March 31, 2016 Performance Report Grantee: Grant: Idaho B-08-DN-16-0001 January 1, 2016 thru March 31, 2016 Performance Report 1 Grant Number: B-08-DN-16-0001 Grantee Name: Idaho Grant Award Amount: $19,600,000.00 LOCCS Authorized Amount:

More information

Neighborhood Stabilization Program

Neighborhood Stabilization Program Neighborhood Stabilization Program Neighborhood Stabilization Program What is the Neighborhood Stabilization Program? NSP was funded in 3 rounds to provide assistance to state and local governments to

More information

July 1, 2011 thru September 30, 2011 Performance Report

July 1, 2011 thru September 30, 2011 Performance Report Grantee: Volusia County, FL Grant: B-11-UN-12-0019 July 1, 2011 thru September 30, 2011 Performance Report 1 Grant Number: B-11-UN-12-0019 Grantee Name: Volusia County, FL Grant Amount: $3,670,516.00 Grant