Cressingham Gardens Estate, Brixton. DRAFT Masterplan Objectives for discussion. September 2015

Size: px
Start display at page:

Download "Cressingham Gardens Estate, Brixton. DRAFT Masterplan Objectives for discussion. September 2015"

Transcription

1 Cressingham Gardens Estate, Brixton DRAFT Masterplan Objectives for discussion September 2015

2 Contents Introduction 1 Project objectives 2 Masterplan objectives 4 Draft masterplan objectives for the Cressingham Gardens Estate: Summary 5 Draft masterplan detailed objectives for the Cressingham Gardens Estate 6 Design Engagement Principles 10 Tibbalds Planning and Urban Design 19 Maltings Place 169 Tower Bridge Road London SE1 3JB Telephone mail@tibbalds.co.uk Cressingham Gardens Estate

3 Introduction Tibbalds Planning and Urban Design was commissioned by Lambeth Council to help develop these initial masterplan objectives for the redevelopment of the Cressingham Gardens Estate in Brixton. This is in anticipation of the next stage of work that will see proposals developed for the estate under a development management led team appointed by the Council to work with residents and stakeholders. In undertaking this work we have reviewed much of the earlier project information produced over the past 2-3 years. This includes: We have also reviewed: Work prepared by Cressingham Gardens TRA, (including the Cressingham Gardens Estate Analysis Questionnaire Results 8th Sep 2013 and Engagement Statement by residents June 2013) Issues identified by residents as documented on the Save Cressingham Gardens website; and Issues raised by others in press releases about the estate and its residents available online. As part of this work, we have prepared an initial high level design assessment of the estate in an attempt to better understand the way that the estate works now. Work carried out by Social Life from June 2013 to February 2014 Living on Cressingham (report on conversations with over 100 residents on Cressingham Gardens Estate Developing a cooperative approach to engagement for Lambeth s estate regeneration programme (Lessons learnt from Social Life s work, June 2013-February 2014) Summary of results of workshop on 7th November 2014 Briefing Pack for Developing options for Cressingham Garden Estate Workshop 1, Nov 7th 2014 Understanding well-being on Cressingham Gardens 29th January 2012 Work carried out by Karthaus Design Ltd Massing options Reports prepared by LBL Acuity Household Needs Survey March 2015 Dwelling Stock 7 Residents Report 19 July Garage Stoke Report 5 July

4 Project objectives The rebuilding of Cressingham Gardens Estate is part of a wider programme of estate rebuilding being progressed by Lambeth to deliver More and Better Homes for the people of Lambeth. There are various programme level objectives that have been defined through Lambeth s Cabinet Decisions, which are applicable to all estate regeneration projects. These provide the context in which Masterplan Objectives for individual estates are formulated. The changes that are being made to Lambeth s estates through this programme needs to create places that: are sustainable; create desirable, high quality residential neighbourhoods that provide a good quality of life for residents and enable the formation and continuation of cohesive and supportive communities; are cost effective to manage and maintain into the future, that enable the formation of mixed communities with a variety of income profiles; and that provide good quality environments, are resource efficient and provide good local amenity. These strategic aspirations can be interpreted on individual projects as follows: to maximise the number of new homes in response to housing demand, taking into consideration planning constraints and expectations and local social and physical infrastructure; to meet the housing needs of the residents on the estate; to achieve the best possible viable balance of tenures for the additional new homes, with an aspiration to secure up to 60% homes for council rent and 40% private sale/ private rent; to harness the process of estate regeneration to deliver positive benefits to the local area; and In working together with residents to seek to achieve these objectives, it has to be recognised that design proposals for projects must adhere to the following constraints: Development strategies for estate regeneration projects must be both viable and practicably deliverable. They must be feasible; projects must deliver the re-provision of existing homes in line with the Key Guarantees to residents; and projects must meet as a minimum Council planning policy and Council tenancy strategy on affordable housing for the net additional new homes. In parallel with the feasibility work on estates within the estate regeneration programme, Lambeth has been developing its own Lambeth Design Standards that will apply to all new homes within the programme. The Council will be consulting more widely with residents on these new Standards in parallel with early work on masterplanning of estates. In addition to the project level objectives noted above, Lambeth has made commitments to residents through its Key Guarantees: The Council will make every effort to ensure that people only have to move once by phasing development so that some new homes are built before existing homes are demolished: those households, who require adaptations to their property due to their disability or to the disability of a family member, will have this carried out before they are required to move into a new property. Any necessary adaptations will be carried out in consultation with the user and with relevant professionals e.g. Occupational Therapists or Social Workers. to seek to minimise the disruption caused to existing residents during both the decant and construction processes. 2

5 The Council has further developed consultation principles, which will guide the process by which the Council engages with residents on the development of masterplans for each estate. These are: Keep uncertainty for residents to a minimum; ensure residents have an understanding of the bigger picture; make it clear to residents that their voices have been heard by decision makers; and ensure that residents have the information they need to make the best choices about their families futures. Photographs from within the Cressingham Gardens Estate 3

6 Masterplan objectives Introduction The overarching objective for the regeneration of the Cressingham Garden Estate is to provide more and better homes for the benefit of current and future residents. This includes providing additional affordable homes for residents of the Borough in housing need. It is important that in developing plans for its redevelopment the qualities of the current estate are properly understood in terms of both its social and physical characteristics. As well as well-documented problems with existing buildings there are a number of positive qualities that should strongly inform whatever is planned to replace it. Understanding these positive qualities and the process of integrating them into the masterplanning should be undertaken alongside residents and key stakeholders. Residents within the Cressingham Gardens Estate feel they have a strong sense of ownership and form part of a local community Cressingham Gardens is a strong community and all efforts should be taken to preserve this. New proposals should enable residents who wish to remain in the estate the possibility to do so. In doing so, residents should be clearly explained the financial and other consequences of this. Proposals as much as possible should allow for residents of current blocks to stay close together as the strongest social networks are currently mainly within blocks. This is particularly important since a lot of people on the estate are in ill-health and reliant on their current immediate neighbours. New proposals will avoid the segregation of residents and will aim for a real mixed community where everyone s new homes are given the same consideration regardless of their tenancy, age, family size, background, health and economic means. The Rotunda community centre is of importance to the community The new masterplan will retain a community centre to provide activities to serve all residents. This space could also be rented out to generate income and assist with the cost of running activities. 4

7 Draft masterplan objectives for the Cressingham Gardens Estate: Summary 1 Deliver a minimum 50% increase in the number of homes on the estate to increase the amount of affordable homes within the borough. 2 Redevelop the estate to provide all new homes to high standards of construction, size and energy consumption, as defined by the emerging Lambeth Design Standards (on which the Council will be consulting with residents in the near future). 3 Minimise the impact of the new development on the Brockwell Park conservation area. The central open space is at the heart of the estate 4 Integrate the new development with surrounding development and open spaces. 5 Work closely with residents and stakeholders to understand those qualities of the estate that should be used to inform the future masterplan/redevelopment proposals. 6 Create a strong masterplan with a distinct and coherent identity. 7 Plan the new development around the desire to keep existing resident groups together. 8 Re-provide the rotunda community facility in consultation with the TRA and local residents. 9 Retain a central open space within the heart of the estate. The estate s strong design qualities should inform future proposals 10 Create robust new buildings that will remain in good condition into the future There are strong social connections within blocks, which should be encouraged and preserved where possible 5

8 Draft masterplan detailed objectives for the Cressingham Gardens Estate 1 Deliver a minimum 50% increase in the number of homes on the estate to increase the amount of affordable homes within the borough. This means going from 306 to more than 464 homes, a number which has been subject to initial testing and is considered a reasonable but not excessive increase given the estate s strong landscape character, heritage context and the housing needs of existing residents. Pocket Pocket 2 Redevelop the estate to provide all new homes to the new Lambeth Design Standard (in development) of construction, size and energy consumption. For Cressingham Gardens, this will also mean: Pocket Pocket Park Edge 2.1 Provide a good mix of types and sizes of accommodation in an integrated way across the estate. 2.2 Ensure that kitchens and living rooms overlook streets and arrival spaces to help ensure they are active and that good levels of interaction is supported between residents. 2.3 Develop an approach to movement and car parking on the estate that allows it to retain its calm and quiet character, not dominated by traffic and roads. 2.4 Address aspects or areas of the estate that do not work well at present, including safety concerns in some areas and poor overlooking of some routes. Gateway Space Tulse Hill Elevation Central Space Pocket Pocket 3 Minimise the impact of the new development on the Brockwell Park conservation area. In assisting with this, the future masterplanning will need to ensure: 3.1 New development takes into account its setting (adjacent to Brockwell Park conservation area) and minimises any negative impact on the views from the park. 3.2 The massing and scale of new buildings is broken up, and as much as possible shaped by existing mature trees on site. Community Hall Main pedestrian route Pedestrian links Private gardens Pocket The estate has limited vehicular routes, this creates a peaceful and quiet environment 6

9 4 Integrate the new homes with surrounding development and open spaces. The estate should retain a strong identity but needs to relate well to its neighbours. New development should acknowledge existing neighbouring buildings and routes of movements. 4.1 The form and density of new development should respond to its context. Tallest buildings should be located along Tulse Hill Road and the north west corner of the site and lower density more modest in scale buildings should address Trinity Rise and the edge with Brockwell Park. 4.2 The new masterplan should provide an improved route between Tulse Hill and Brockwell Park. This could be a more direct, better overlooked route that also allows for some visual connection. 4.3 New proposals should better address Tulse Hill Road by providing an active frontage at ground floor level. Current tallest building fronts onto Tulse Hill Road 5 Work closely with existing residents and stakeholders in understanding those qualities of the existing estate that should be used to inform the future masterplan/redevelopment proposals and to engage with them as it is developed. Learning from what works now, positive physical characteristics in the replacement scheme could include: 5.1 A thorough assessment of the current design of the estate to understand the aspects of the current design that support the social interaction of residents, and have a positive impact upon people s lives; 5.2 Maximising the number of new homes that are able to have their own front door onto a street or external entrance space; New proposals should make the most of the views of Brockwell Park 5.3 Recreating the gently stepping village character of the pedestrian ways; 5.4 Retaining a central green space as the heart of the development; 5.5 Maintaining strong links with Brockwell Park, including maximising the number of homes with views of the park and the central green space; 5.6 Shaping the development around existing mature trees and a strong overall landscape character; Existing mature trees - retaining this will assist in preserving the green character of the estate 7

10 5.7 Maintaining the strong sense of overlooking provided across the estate; 5.8 Clustering homes into small neighbour groups; 5.9 Creating façades that step in and out, are well articulated and with softened, broken up rooflines; 5.10 Variation in scale with the tallest buildings along the western edge of the site; 5.11 Giving opportunities for residents to look after, garden and care for the areas around where they live; and 5.12 Include a range of types of private, communal and shared open spaces that encourage social interaction and communal activity. 6 Create a strong masterplan with a distinct and coherent identity. As well as being responsible to the positive qualities of the existing estate, the masterplan should enable legible movement with a clear structure, distinct sub-areas and a safe and enjoyable place to live. 7 Plan the new development around the desire to keep existing resident groups together, wherever this is possible. This will allow existing support networks and groups to continue and help support both long term and new residents. This could be achieved by: Well overlooked spaces is a current design quality of the estate 7.1 Avoiding large monolithic blocks and arranging buildings as small clusters of units around a more intimate communal space/street; and 7.2 Clustering different dwelling types together or within blocks. This will also encourage a more diverse community. 8 Re-provide the rotunda community facility in consultation with the TRA and local residents, ideally in such a way as it does not need to close for construction i.e. the replacement is constructed before the existing facility needs to close. It is important that the new community centre: 8.1 Is located in close proximity to the central open space and easily accessible to all residents; There are accessibility issues within the estate, new proposals should avoid this 8

11 8.2 Continues to be a feature building. This could be designed as part of a larger building but clearly expressing its use and function. Or it could be a free-standing pavilion type building. Either approach should ensure the new community centre building brings vitality and strong character to the estate; Brockwell Park 8.3 Is flexible enough to be able to accommodate different range of activities for different types and numbers of users (e.g. be able to sub-divide etc); and 8.4 The brief for the new community facility should be developed with existing user groups. 9 Retain a central green space within the estate as amenity space and consult with residents over its design or arrangement. 9.1 The relationship with Brockwell Park is of great importance, existing and new green spaces should be designed to feel like an extension of the park. Gateway Space Central Space Gardens back onto open space Central Space pulls the park into the masterplan 9.2 Existing trees should be retained (as far as possible) and new routes and spaces should be well landscaped to assist maintain the green character of the estate. 10 Create robust new buildings that will remain in good condition into the future and that minimise on going or difficult maintenance regimes for buildings and spaces. This means considering from the very early stages creating buildings that work well for the occupants as well as those who will own and maintain them over time The Council and housing providers should ensure a better system for reporting and dealing with repairs are in place as part of the new project Future repairs and planned maintenance should be carried out on time and using high quality workmanship and materials. Main entrance to estate. Vehicle routes lead to parking garages under Block A types Tulse Hill Higher 3.5 storey Block A types create a strong edges to the site along Tulse Hill Buildings front on to pedestrian routes Main pedestrian route links open spaces and the community hall 10.3 The estate management team should acknowledge and support existing gardening clubs set up by residents and involve them in the design and maintenance of open spaces. A thorough assessment of the current design of the estate will help to understand the design qualities that currently support the strong social interaction of residents 9

12 Design Engagement Principles This section covers important development principles that are set out to form part of the masterplan process and that will assist with: moving the masterplan/project forward; keep uncertainty for residents to a minimum; ensure residents have an understanding of the bigger picture so that informed decisions can be made; make it clear to residents that their voices have been heard by decision makers; and ensure that residents have the information they need to make the best choices about their families futures. 1 Agree a process for working up a masterplan for the replacement homes that is based on good up to date information and clear communication with residents. This should be based on: Up to date survey information about the estate gathered at the start of the process, including mapping the location and importance of existing trees, heritage issues related to the park, key views, and other site constraints information e.g. services, rights of way etc. The most recent housing needs survey of existing residents that gives a reasonable indication of the likely housing need at the time the project is expected to be completed. This should include understanding the specific requirements of residents with particular accessibility requirements. Providing clear design information and mapping in a way that residents can easily understand what is proposed, so that they can contribute to the process of providing useful information about the estate. Keeping residents updated with project progress and the current status of the project, as a minimum every 4 weeks (confirm). 2 Communicate regularly with residents and keep them informed and updated about the project and engaged in the scheme as it is developed. This includes: Involving residents in the selection of the consultant and design team. Providing consistent named contacts and contact points (web pages, address and phone numbers) throughout the duration of the project for both Council Officers and the development management team, once appointed. Making information available to residents in a broad variety of ways that allows different people to access it. e.g. printed maps, models, online, , SMS, social media, posters etc. Use digital channels to provide rapid updates if required rather than waiting for print deadlines. Keeping residents informed of any changes to the project drivers or changes to the project objectives. Explaining planning policy considerations and guidance to residents and how this will impact on the scheme. Consider offering residents the support of an independent advisor who can help them with their engagement with the masterplanning and design process. Working to engage with the full range of residents on the estate, including both those who regularly or occasionally attend events and those who do not. Supporting the TRA in their role of communicating with and engaging with residents on the estate and providing an important link between residents and the Council. Explaining the timescales, process and programme for the masterplanning project and any other related work to residents and keeping them regularly informed of any changes. 10

13 Explain the masterplanning process and to engage residents in key decisions at the appropriate times, to offer training that may help residents engage with the design process more effectively and to understand what is proposed and what it may mean for them. Sharing information with residents about viability and trade offs within the project i.e. where to invest money to get the best outcomes e.g. larger community facility versus additional affordable homes, or the additional costs associated with particular development options or delivery arrangements. Explaining the constraints that control what the Council is able to do and what it cannot. Sharing in a timely manner any emerging plans for temporary re-housing, construction phasing, delivery timescales or other aspects of the project where they will be affected as part of the redevelopment, giving them the opportunity to comment and input to those proposals. Provide residents with access to financial planning information that will help them work out how they will be able to afford to stay on the estate once redeveloped, or to move away if that is what they want to do. Share and develop details of a local lettings policy with residents in the lead up to construction. 11

14

FENWICK ESTATE Q&A Issued: 18th February 2016

FENWICK ESTATE Q&A Issued: 18th February 2016 As we go through the engagement process the Council will try to answer residents' questions. One of the ways that we will try to do this is by publishing Q&A documents. This is a record of questions that

More information

Briefing paper A neighbourhood guide to viability

Briefing paper A neighbourhood guide to viability Briefing paper A neighbourhood guide to viability 2 Introduction Community Led Design and Development is a programme funded by the Department for Communities and Local Government s Tenant Empowerment Programme

More information

Tenancy Policy Introduction Legal Framework Purpose Principles Policy Statement Tenancy Statement...

Tenancy Policy Introduction Legal Framework Purpose Principles Policy Statement Tenancy Statement... 1 Tenancy Policy January 2014 Table of Contents Tenancy Policy... 1 Introduction... 2 Legal Framework... 2 Purpose... 3 Principles... 3 Policy Statement... 4 Tenancy Statement... 4 Tenancy Types... 5 Assured

More information

Qualification Snapshot CIH Level 3 Certificate in Housing Services (QCF)

Qualification Snapshot CIH Level 3 Certificate in Housing Services (QCF) Qualification Snapshot CIH Certificate in Housing Services (QCF) The Chartered Institute of Housing (CIH) is an awarding organisation for national qualifications at levels 2, 3 and 4. CIH is the leading

More information

Together with Tenants

Together with Tenants Together with Tenants Our draft plan Your feedback needed by 19 April 20 February 2019 About this plan The National Housing Federation is the membership body for housing associations in England. Our housing

More information

Report summary: This report provides an up-date on the whole estates regeneration and housing projects programme.

Report summary: This report provides an up-date on the whole estates regeneration and housing projects programme. 2 Better Homes Board Report title: Estates Regeneration Programme Update Report Authorised by: Rachel Sharpe, Commissioning Director Report Author: Neil Vokes, Programme Director Contact for enquiries:

More information

Cabinet Meeting 11 March 2015

Cabinet Meeting 11 March 2015 Cabinet Meeting 11 March 2015 Agenda Item No: 11 Report title Decision designation Cabinet member with lead responsibility Key decision In forward plan Wards affected Accountable director Originating service

More information

Funding and Delivery Strategies for New Housing

Funding and Delivery Strategies for New Housing Funding and Delivery Strategies for New Housing Steve Cox Corporate Director, Environment & Place Chair of Gloriana Ltd March 2017 An appetite for Growth Need for c20-30,000 homes over 20 years to support

More information

WELCOME TIMESCALES. Thank you for attending Anthology s final public exhibition on the emerging plans for Kennington Stage. ANTHOLOGY S COMMITMENTS

WELCOME TIMESCALES. Thank you for attending Anthology s final public exhibition on the emerging plans for Kennington Stage. ANTHOLOGY S COMMITMENTS WELCOME Thank you for attending Anthology s final public exhibition on the emerging plans for Kennington Stage. Since the second consultation in October 2018, which asked your views on the preferred approach,

More information

LITTLE MOUNTAIN ADJACENT AREA REZONING POLICY

LITTLE MOUNTAIN ADJACENT AREA REZONING POLICY LITTLE MOUNTAIN ADJACENT AREA REZONING POLICY JANUARY 2013 CONTENTS 1.0 INTENT & PRINCIPLES...1 2.0 APPLICATION...2 3.0 HOUSING TYPES, HEIGHT & DENSITY POLICIES...3 3.1 LOW TO MID-RISE APARTMENT POLICIES...4

More information

On: 20 April Report by: Director of Development and Housing Services. Heading: Paisley West End - Regeneration Masterplan. 1.

On: 20 April Report by: Director of Development and Housing Services. Heading: Paisley West End - Regeneration Masterplan. 1. To: Council On: 20 April 2017 Report by: Director of Development and Housing Services Heading: Paisley West End - Regeneration Masterplan 1. Summary 1.1 This report sets out proposals for the regeneration

More information

MAKING THE MOST EFFECTIVE AND SUSTAINABLE USE OF LAND

MAKING THE MOST EFFECTIVE AND SUSTAINABLE USE OF LAND 165 SOC146 To deliver places that are more sustainable, development will make the most effective and sustainable use of land, focusing on: Housing density Reusing previously developed land Bringing empty

More information

Planning Application 16/4008/F Rockwell 771 units off Anchor and Hope Lane SE7

Planning Application 16/4008/F Rockwell 771 units off Anchor and Hope Lane SE7 Annex (6 pages) Planning Application 16/4008/F Rockwell 771 units off Anchor and Hope Lane SE7 Evidence from Charlton Riverside Masterplan Summary (NB This is the Short Annex see also Long Annex for more

More information

Tenancy Policy. 1 Introduction. 12 September Executive Management Team Approval Date: Review date: September 2018

Tenancy Policy. 1 Introduction. 12 September Executive Management Team Approval Date: Review date: September 2018 Tenancy Policy Originator: Executive Management Team Approval Date: Policy and Strategy Team 12 September 2017 Review date: September 2018 1 Introduction 1.1 1.2 This Policy sets out how One Vision Housing

More information

PROJECT INITIATION DOCUMENT

PROJECT INITIATION DOCUMENT Project Name: Housing Futures Phase Two Project Sponsor: Steve Hampson Project Manager: Denise Lewis Date Issued: 15 February 2008 Version No: 1 Background: At Full Council on 31 January 2008 the following

More information

Member consultation: Rent freedom

Member consultation: Rent freedom November 2016 Member consultation: Rent freedom The future of housing association rents Summary of key points: Housing associations are ambitious socially driven organisations currently exploring new ways

More information

DRAFT FOR DISCUSSION PURPOSES ONLY. Port Credit Local Area Plan Built Form Guidelines and Standards DRAFT For Discussion Purposes

DRAFT FOR DISCUSSION PURPOSES ONLY. Port Credit Local Area Plan Built Form Guidelines and Standards DRAFT For Discussion Purposes Port Credit Local Area Plan Built Form Guidelines and Standards DRAFT For Discussion Purposes 1 Local Area Plan - Project Alignment Overview Directions Report, October 2008 (General Summary Of Selected

More information

Communal Areas Policy

Communal Areas Policy Communal Areas Policy Originator: Executive Management Team Approval Date: Review date: Policy and Strategy Team 24 th October 2017 October2020 1 Introduction 1.1 1.2 One Vision Housing s (OVH) mission

More information

SSHA Tenancy Policy. Page: 1 of 7

SSHA Tenancy Policy. Page: 1 of 7 POLICY 1. Overall Policy Statement 1.1 South Staffordshire Housing Association (SSHA) will work with all customers to develop and maintain sustainable communities and sees a range of tenancy products and

More information

TENANT PARTICIPATION STRATEGY

TENANT PARTICIPATION STRATEGY TENANT PARTICIPATION STRATEGY 2016-2020 Section Operations Date Policy Approved by Board 16 March 2016 Review Period Annual Review Due 16 March 2017 Version 3.00 Table of Contents... 0 STRATEGY CHANGE

More information

DRAFT FEASIBILITY REPORT CENTRAL HILL ESTATE LONDON BOROUGH OF LAMBETH

DRAFT FEASIBILITY REPORT CENTRAL HILL ESTATE LONDON BOROUGH OF LAMBETH DRAFT FEASIBILITY REPORT For the Project At Prepared On Behalf Of LONDON BOROUGH OF LAMBETH Date: 6 th July 2016 Reference: 14/124 Central Hill Version 5 Version Control Version Date Author Page No(s)

More information

TEE FABIKUN. Document Ref: REP.LP Matter 3 Housing

TEE FABIKUN. Document Ref: REP.LP Matter 3 Housing TEE FABIKUN Document Ref: REP.LP.145-01 Matter 3 Housing 1. Bearing in mind the recent Inspector s report following the Further Alterations to the London Plan (FALP) examination (see paragraphs 31-35 of

More information

2. The Purpose of the Estates Strategy

2. The Purpose of the Estates Strategy Royal National Orthopaedic Hospital NHS Trust Trust Board - December 2012 Estates Strategy 2012 to 2017 - Executive Summary 1. Purpose of the Report The purpose of this report is to advise the Trust Board

More information

Consider retention of existing low-rise family housing where this does not prevent the achievement of wider regeneration objectives

Consider retention of existing low-rise family housing where this does not prevent the achievement of wider regeneration objectives Site Allocation SA3.4 Greater Carpenters District This note is prepared in response to the Inspector s additional questions of 24 th March 2015 in relation to Site Allocation 3.4 Greater Carpenters District.

More information

Bridgeland-Riverside Area Redevelopment Plan (ARP)

Bridgeland-Riverside Area Redevelopment Plan (ARP) Bridgeland-Riverside Area Redevelopment Plan (ARP) The current Bridgeland-Riverside Area Redevelopment Plan (ARP) was approved in 1980. Since then, a lot of changes have taken place in the city and the

More information

NORTH LEEDS MATTER 2. Response to Leeds Sites and Allocations DPD Examination Inspector s Questions. August 2017

NORTH LEEDS MATTER 2. Response to Leeds Sites and Allocations DPD Examination Inspector s Questions. August 2017 NORTH LEEDS MATTER 2 Response to Leeds Sites and Allocations DPD Examination Inspector s Questions August 2017 CLIENT: TAYLOR WIMPEY, ADEL REFERENCE NO: CONTENTS 1.0 INTRODUCTION 2.0 TEST OF SOUNDNESS

More information

HOUSING REGENERATION LAND ACQUISITION STRATEGY. Strategy for the acquisition of land for estates undergoing redevelopment

HOUSING REGENERATION LAND ACQUISITION STRATEGY. Strategy for the acquisition of land for estates undergoing redevelopment HOUSING REGENERATION LAND ACQUISITION STRATEGY Strategy for the acquisition of land for estates undergoing redevelopment Prepared for London Borough of Lambeth by Ardent with contributions from BDB and

More information

Secure tenants. Our Key Guarantees to secure tenants

Secure tenants. Our Key Guarantees to secure tenants Secure tenants Our Key Guarantees to secure tenants A secure tenant is a tenant of Lambeth Council, who has signed a tenancy under the 1985 Housing Act. A better home for you and your family Rebuilding

More information

PROGRAM PRINCIPLES. Page 1 of 20

PROGRAM PRINCIPLES. Page 1 of 20 PROGRAM PRINCIPLES Page 1 of 20 DEVELOPMENT OF THE PROGRAM PRINCIPLES The Program Development Project The Program Principles have been developed as part of the Planning Our Future Program Development Project

More information

Managing Change in the Historic Environment: Demolition of Listed Buildings

Managing Change in the Historic Environment: Demolition of Listed Buildings Background Managing Change in the Historic Environment: Demolition of Listed Buildings Managing Change is a series of guidance notes issued by Historic Environment Scotland in our role as lead public body

More information

National Standards Compliance Tenancy Standard Summary Report Quarter /15

National Standards Compliance Tenancy Standard Summary Report Quarter /15 National s Compliance Tenancy 1.1.1 Registered providers shall let their homes in a fair, transparent and efficient way. They shall take into account the housing needs and aspirations of tenants and potential

More information

DCLG consultation on proposed changes to national planning policy

DCLG consultation on proposed changes to national planning policy Summary DCLG consultation on proposed changes to national planning policy January 2016 1. Introduction DCLG is proposing changes to the national planning policy framework (NPPF) specifically on: Broadening

More information

RYEDALE SITES LOCAL PLAN MATTER 4 PROPOSED HOUSING SITE OPTION REF. 116 LAND AT MIDDLETON ROAD, PICKERING BARRATT HOMES & DAVID WILSON HOMES

RYEDALE SITES LOCAL PLAN MATTER 4 PROPOSED HOUSING SITE OPTION REF. 116 LAND AT MIDDLETON ROAD, PICKERING BARRATT HOMES & DAVID WILSON HOMES RYEDALE SITES LOCAL PLAN MATTER 4 PROPOSED HOUSING SITE OPTION REF. 116 LAND AT MIDDLETON ROAD, PICKERING BARRATT HOMES & DAVID WILSON HOMES REPRESENTOR ID: 1064 INTRODUCTION 1.1 We write on behalf of

More information

Assets, Regeneration & Growth Committee 11 July Development of new affordable homes by Barnet Homes Registered Provider ( Opendoor Homes )

Assets, Regeneration & Growth Committee 11 July Development of new affordable homes by Barnet Homes Registered Provider ( Opendoor Homes ) Assets, Regeneration & Growth Committee 11 July 2016 Title Report of Wards Status Urgent Key Enclosures Officer Contact Details Development of new affordable homes by Barnet Homes Registered Provider (

More information

Affordable Homes Service Plan 2016/17 and 2017/18

Affordable Homes Service Plan 2016/17 and 2017/18 Report To: Housing Portfolio Holder 15 March 2017 Lead Officer: Director of Housing Purpose Affordable Homes Service Plan 2016/17 and 2017/18 1. To provide the Housing Portfolio Holder with an update on

More information

Homeowners. Our Key Guarantees to homeowners

Homeowners. Our Key Guarantees to homeowners Homeowners Our Key Guarantees to homeowners A better home for you and your family Rebuilding your estate will mean that you and your family will be able to move into a better home. While we work together

More information

5.0 Development Strategy 32

5.0 Development Strategy 32 5.0 Development Strategy 32 Objectives To ensure the long term future of the Bazaar Market building by giving it a higher order retail use, reflecting the development of retail on the Guy s site To ensure

More information

Housing White Paper Summary. February 2017

Housing White Paper Summary. February 2017 Housing White Paper Summary February 2017 On Tuesday 7 February, the government published the Housing White Paper, aimed at solving the housing crises in England through increasing the supply of homes

More information

ROLE OF SOUTH AFRICAN GOVERNMENT IN SOCIAL HOUSING. Section 26 of the Constitution enshrines the right to housing as follows:

ROLE OF SOUTH AFRICAN GOVERNMENT IN SOCIAL HOUSING. Section 26 of the Constitution enshrines the right to housing as follows: 1 ROLE OF SOUTH AFRICAN GOVERNMENT IN SOCIAL HOUSING Constitution Section 26 of the Constitution enshrines the right to housing as follows: Everyone has the right to have access to adequate housing The

More information

C Secondary Suite Process Reform

C Secondary Suite Process Reform 2018 March 12 Page 1 of 9 EXECUTIVE SUMMARY On 2017 December 11, through Notice of Motion C2017-1249 (Secondary Suite Process Reform) Council directed Administration to implement several items: 1. Land

More information

RYEDALE SITES LOCAL PLAN MATTER 3 PROPOSED HOUSING SITE OPTION REF. 116 LAND AT MIDDLETON ROAD, PICKERING BARRATT HOMES & DAVID WILSON HOMES

RYEDALE SITES LOCAL PLAN MATTER 3 PROPOSED HOUSING SITE OPTION REF. 116 LAND AT MIDDLETON ROAD, PICKERING BARRATT HOMES & DAVID WILSON HOMES RYEDALE SITES LOCAL PLAN MATTER 3 PROPOSED HOUSING SITE OPTION REF. 116 LAND AT MIDDLETON ROAD, PICKERING BARRATT HOMES & DAVID WILSON HOMES REPRESENTOR ID: 1064 INTRODUCTION 1.1 We write on behalf of

More information

OVERVIEW PROJECT SUMMARY

OVERVIEW PROJECT SUMMARY OVERVIEW Good terraced house development that creates an excellent edge to the street while accommodating the car via rear lane access. PROJECT SUMMARY The six terraced houses at Buckley Avenue are part

More information

Assets, Regeneration & Growth Committee 17 March Development of new affordable homes by Barnet Homes Registered Provider ( Opendoor Homes )

Assets, Regeneration & Growth Committee 17 March Development of new affordable homes by Barnet Homes Registered Provider ( Opendoor Homes ) Assets, Regeneration & Growth Committee 17 March 2016 Title Report of Wards Status Urgent Key Enclosures Officer Contact Details Development of new affordable homes by Barnet Homes Registered Provider

More information

City Plan Sub- Committee Report

City Plan Sub- Committee Report AGENDA ITEM: Date: 21 st July 2016 City Plan Sub- Committee Report Classification: Title: Report of: Cabinet Member Portfolio: Wards Affected: City for All Key Decision: Financial Summary: Report Author

More information

A mix of uses. Housing:

A mix of uses. Housing: 7 Massing and uses Page 79 7:1. A mix of uses % Total Habitable Occ/ People Rooms HR Studio 6.8% 308 1 0.90 277 1 bed 32.0% 1442 2 0.90 2,595 2 bed 37.6% 1691 3 0.90 4,567 3 bed 21.2% 955 4 0.90 3,438

More information

Jasper 115 Street DC2 Urban Design Brief

Jasper 115 Street DC2 Urban Design Brief Jasper 115 Street DC2 Urban Design Brief Greenlong Construction Ltd. Stantec Consulting Ltd. 2017 Overview The proposed rezoning application supports the development of two mixed-use high-rise buildings

More information

APPENDIX 7. Housing Enforcement Policy V May 2003

APPENDIX 7. Housing Enforcement Policy V May 2003 Housing Enforcement Policy V1.2 9 May 2003 INTRODUCTION This policy provides guidance on the aims and objectives of the Housing department to make homes on the Island fit and available for occupation.

More information

BEP 2: What you need to know

BEP 2: What you need to know Revitalising Redfern & Waterloo Draft Built Environment Plan Stage 2 (BEP 2) JANUARY 2011 Draft BEP 2: to create a safer and more sustainable environment BEP 2: What you need to know The Draft Built Environment

More information

Community Housing Federation of Victoria Inclusionary Zoning Position and Capability Statement

Community Housing Federation of Victoria Inclusionary Zoning Position and Capability Statement Community Housing Federation of Victoria Inclusionary Zoning Position and Capability Statement December 2015 Introduction The Community Housing Federation of Victoria (CHFV) strongly supports the development

More information

Rented London: How local authorities can improve the capital s private rented sector. January 2018

Rented London: How local authorities can improve the capital s private rented sector. January 2018 Rented London: How local authorities can improve the capital s private rented sector January 2018 As Londoners go to the polls in May, housing will continue to be at the top of their minds. More than two

More information

9.3.5 Dual occupancy code

9.3.5 Dual occupancy code 9.3.5 Dual occupancy code 9.3.5.1 Application (1) This code applies to accepted development and assessable development identified as requiring assessment against the Dual occupancy 1 code by the tables

More information

What does Social Housing

What does Social Housing What does Social Housing Reform mean for Practitioners? Jennie Donald, Deputy Chief Executive, NIFHA Background 2011 Review of NI Housing Executive by PwC & mature conversation 2013 Social Housing Reform

More information

Choice-Based Letting Guidance for Local Authorities

Choice-Based Letting Guidance for Local Authorities Choice-Based Letting Guidance for Local Authorities December 2016 Contents Page 1. What is Choice Based Lettings (CBL) 1 2. The Department s approach to CBL 1 3. Statutory Basis for Choice Based Letting

More information

How do I Object to Flats and Apartments in my Area?

How do I Object to Flats and Apartments in my Area? Guide How do I Object to Flats and Apartments in my Area? January 2017 Background This is an introduction to objecting to proposals for flats or apartments in your area. For more detailed information and

More information

Key principles for Help-to-Rent projects. February 2017

Key principles for Help-to-Rent projects. February 2017 Key principles for Help-to-Rent projects February 2017 1 Crisis and the private rented sector Crisis is the national charity for single homeless people. We are dedicated to ending homelessness by delivering

More information

2. Draft Settlement Boundaries Planning Policy and local principles

2. Draft Settlement Boundaries Planning Policy and local principles Housing Information 1. Cornwall Local Plan policy position: Cornwall Local Plan sets down key targets for the provision of homes where they can best meet need and sustain the role and function of local

More information

London Tenant s Federation. Reclaiming social rent

London Tenant s Federation. Reclaiming social rent London Tenant s Federation Reclaiming social rent Target rent Southwark Council Cabinet report Dec 2014 12. Rent convergence is no longer applicable from April 2015. However, since there are proposals

More information

TENANCY SUSTAINMENT STRATEGY

TENANCY SUSTAINMENT STRATEGY LANGSTANE HOUSING ASSOCIATION TENANCY SUSTAINMENT STRATEGY 2017-2020 C:\Users\ayesha.reid\AppData\Local\Microsoft\Windows\Temporary Internet Files\Content.Outlook\GSBPYVBK\Tenancy Sustainment Strategy

More information

For and on behalf of Redrow Homes Ltd

For and on behalf of Redrow Homes Ltd For and on behalf of Redrow Homes Ltd Sheffield Additional Site Allocations Document Local Development Framework Consultation Representations Prepared by DLP Planning Ltd February 2012 Contents Page 1.0

More information

SCHEDULE 8 TO THE DESIGN AND DEVELOPMENT OVERLAY RESIDENTIAL AREAS SURROUNDING ACTIVITY CENTRES AND ALONG MAIN ROADS

SCHEDULE 8 TO THE DESIGN AND DEVELOPMENT OVERLAY RESIDENTIAL AREAS SURROUNDING ACTIVITY CENTRES AND ALONG MAIN ROADS 23/07/2009 C74 SCHEDULE 8 TO THE DESIGN AND DEVELOPMENT OVERLAY Shown on the planning scheme map as DDO8 RESIDENTIAL AREAS SURROUNDING ACTIVITY CENTRES AND ALONG MAIN ROADS 1.0 Design objectives 08/03/2007

More information

The Scottish Social Housing Charter

The Scottish Social Housing Charter The Scottish Social Housing Charter April 2017 2 The Scottish Social Housing Charter Table of contents page 1. Introduction 2 2. Charter outcomes and standards 5 3. A note about language 12 3 1. Introduction

More information

Cressingham Gardens - Resident Engagement Panel (REP)

Cressingham Gardens - Resident Engagement Panel (REP) Cressingham Gardens - Resident Engagement Panel (REP) Venue: St Martin s Scout Hut, 18-28 High Trees, Tulse Hill, SW2 3PX Time: 7pm-9pm Minutes of the meeting: Monday 2 nd October 2017 Present: Cllr Mary

More information

Rawlinson House, Lewisham, London SE13 5EL

Rawlinson House, Lewisham, London SE13 5EL Rawlinson House, Lewisham, London SE13 5EL Client: Lewisham Homes Old Town Hall Catford London SE6 4RU Date: 18 February 2016 Job No: 2540-MA-N-RP-0001-D00 Martin Arnold Ltd 4 Gunnery Terrace The Royal

More information

JOINT CORE STRATEGY FOR BROADLAND, NORWICH AND SOUTH NORFOLK EXAMINATION MATTER 3A GENERAL STRATEGY FOR THE GROWTH LOCATIONS

JOINT CORE STRATEGY FOR BROADLAND, NORWICH AND SOUTH NORFOLK EXAMINATION MATTER 3A GENERAL STRATEGY FOR THE GROWTH LOCATIONS Matter 3A General Strategy for the Growth Locations Representor No. 8826 JOINT CORE STRATEGY FOR BROADLAND, NORWICH AND SOUTH NORFOLK EXAMINATION MATTER 3A GENERAL STRATEGY FOR THE GROWTH LOCATIONS SUBMISSION

More information

Tenure and Tenancy management. Issue 07 Board approved: February Responsibility: Operations/C&SH Review Date: February 2019

Tenure and Tenancy management. Issue 07 Board approved: February Responsibility: Operations/C&SH Review Date: February 2019 Operational Manual Tenure and Tenancy management Corporate Policy Issue 07 Board approved: February 2017 Responsibility: Operations/C&SH Review Date: February 2019 1.0 Introduction 1.1 Hightown provides

More information

Note on housing supply policies in draft London Plan Dec 2017 note by Duncan Bowie who agrees to it being published by Just Space

Note on housing supply policies in draft London Plan Dec 2017 note by Duncan Bowie who agrees to it being published by Just Space Note on housing supply policies in draft London Plan Dec 2017 note by Duncan Bowie who agrees to it being published by Just Space 1 Housing density and sustainable residential quality. The draft has amended

More information

Scottish Social Housing Charter Indicators

Scottish Social Housing Charter Indicators Scottish Social Housing Charter Indicators Briefing Paper July 2012 Introduction This joint Tenants Information Service (TIS) / Tenant Participation Advisory Service (TPAS) briefing paper has been produced

More information

Multi-unit residential uses code

Multi-unit residential uses code 9.3.11 Multi-unit residential uses code 9.3.11.1 Application (1) This code applies to assessable development identified as requiring assessment against the Multi-unit residential uses code by the tables

More information

Leasehold Management Policy

Leasehold Management Policy Author(s): Simon McCracken and Liz Evans Leasehold Management Policy Approved by: The Board Date: 3 rd December 2015 Date Published: 1 st January 2016 Version: Live 3.0 Review Date: December 2019 Contents

More information

London Borough of Lewisham Response to Achilles Street Stop and Listen Campaign FACT SHEET

London Borough of Lewisham Response to Achilles Street Stop and Listen Campaign FACT SHEET London Borough of Lewisham Response to Achilles Street Stop and Listen Campaign FACT SHEET 1. The Achilles Street Stop and Listen Campaign say: Lewisham Council wants to demolish decent council homes The

More information

Strategic Housing Market Assessment South Essex. Executive Summary. May 2016

Strategic Housing Market Assessment South Essex. Executive Summary. May 2016 Strategic Housing Market Assessment South Essex Executive Summary May 2016 Executive Summary 1. Turley in partnership with specialist demographic consultancy Edge Analytics were commissioned by the Thames

More information

Proposals for the Redevelopment of the Magistrates Court & Police Station, Normandy Street / Orchard Lane, Alton

Proposals for the Redevelopment of the Magistrates Court & Police Station, Normandy Street / Orchard Lane, Alton THE SITE THE SITE The Site in Context WELCOME Welcome to our public exhibition in connection with our draft proposals ahead of a planning application being proposals for the redevelopment of the magistrates

More information

BUSINESS PLAN Part 1

BUSINESS PLAN Part 1 BUSINESS PLAN 2016-17 Part 1 Contents Executive Summary... 1 Objectives... 2 Company Formation... 3 Governance and Management Structure... 4 Decision Making... 6 Operational Management... 7 Market Overview...

More information

Multi- Storey Tower Blocks: Options Appraisal

Multi- Storey Tower Blocks: Options Appraisal NORTH AYRSHIRE COUNCIL Cabinet 20 March 2018 Title: Purpose: Recommendation: Multi- Storey Tower Blocks: Options Appraisal To advise Cabinet of future investment options for the seven multistorey blocks

More information

Welsh Government Housing Policy Regulation

Welsh Government Housing Policy Regulation www.cymru.gov.uk Welsh Government Housing Policy Regulation Regulatory Assessment Report August 2015 Welsh Government Regulatory Assessment The Welsh Ministers have powers under the Housing Act 1996 to

More information

REPORT BY THE CHAIRPERSON OF THE LYTTELTON/MT HERBERT COMMUNITY BOARD 28 SEPTEMBER 2010

REPORT BY THE CHAIRPERSON OF THE LYTTELTON/MT HERBERT COMMUNITY BOARD 28 SEPTEMBER 2010 31. 3. 2011 REPORT BY THE CHAIRPERSON OF THE LYTTELTON/MT HERBERT COMMUNITY BOARD 28 SEPTEMBER 2010 PART A - MATTERS REQUIRING A COUNCIL DECISION 1. 47 DUBLIN STREET, LYTTELTON ADDITIONAL INFORMATION REPORT

More information

Residential Intensification in Established Neighbourhoods Study (RIENS)

Residential Intensification in Established Neighbourhoods Study (RIENS) Residential Intensification in Established Neighbourhoods Study (RIENS) EXECUTIVE SUMMARY In December 2015, the City of Kitchener retained Meridian Planning Consultants to undertake the Residential Intensification

More information

Tenancy Policy. Director of Operations. Homes and Neighbourhoods. 26 March Page 1 of 10

Tenancy Policy. Director of Operations. Homes and Neighbourhoods. 26 March Page 1 of 10 Tenancy Policy Lead Director Director of Operations EMT Review Pol Ref No POL 19 Committee Review Homes and Neighbourhoods Board Approval 26 March 2018 Review Date March 2021 Page 1 of 10 Page 2 of 10

More information

Leeds City Region Statement of Common Ground. August 2018

Leeds City Region Statement of Common Ground. August 2018 Leeds City Region Statement of Common Ground August 2018 1.0 Introduction 1.1 The Leeds City Region partner councils have prepared this Statement of Common Ground in response to the requirement as set

More information

NSW Affordable Housing Guidelines. August 2012

NSW Affordable Housing Guidelines. August 2012 August 2012 NSW AFFORDABLE HOUSING GUIDELINES TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 DEFINITION OF KEY TERMS... 1 3.0 APPLICATION OF GUIDELINES... 2 4.0 PRINCIPLES... 2 4.1 Relationships and partnerships...

More information

Representation re: Sullivans Cove Planning Scheme /2015 Amendments - Macquarie Point Site Development: Affordable housing

Representation re: Sullivans Cove Planning Scheme /2015 Amendments - Macquarie Point Site Development: Affordable housing General Manager, Hobart City Council, GPO Box 503, Tas 7001 16 November, 2015 Representation re: Sullivans Cove Planning Scheme 1997-2/2015 Amendments - Macquarie Point Site Development: Affordable housing

More information

P. H. Robinson Consulting Urban Planning, Consulting and Project Management

P. H. Robinson Consulting Urban Planning, Consulting and Project Management PLANNING RATIONALE REPORT FOR SITE PLAN AND DRAFT PLAN OF CONDOMINIUM APPLICATIONS 73-75 HARVEY STREET CITY OF OTTAWA PREPARED BY: P H ROBINSON CONSULTING AUGUST 2012 1 This report has been prepared on

More information

CONCEPT NOTE EFFECTIVE LAND ADMINISTRATION IN AFRICA TRAINING WORKSHOP

CONCEPT NOTE EFFECTIVE LAND ADMINISTRATION IN AFRICA TRAINING WORKSHOP CONCEPT NOTE EFFECTIVE LAND ADMINISTRATION IN AFRICA TRAINING WORKSHOP Innovative Concepts, Tools and Practices for Effective Land Administration Land Conference Pre-Conference Workshop Advocating & Implementing

More information

Re: Social Housing Reform Programme, Draft Tenant Participation Strategy

Re: Social Housing Reform Programme, Draft Tenant Participation Strategy 30th March 2015 Tenant Participation Strategy Consultation Social Housing Reform Programme Ground Floor Lighthouse Building Gasworks Business Park Belfast BT2 7JB Dear Sir/Madam, Re: Social Housing Reform

More information

PUBLIC OPEN HOUSE September 19, 2018

PUBLIC OPEN HOUSE September 19, 2018 PUBLIC OPEN HOUSE September 19, 2018 Board 1 BACKGROUND Council direction was given to develop a The is looking at new housing in mature and recent communities, as outlined in the City of Winnipeg s planning

More information

New Marrickville Library

New Marrickville Library 1 New Library Precinct C Heritage Cottages Commericial Use Precinct C New Residential Building 2 & 8 storeys Precinct D New Residential Building 6 storeys Precinct D Possible Refurbishment of Existing

More information

Tenancy Policy. Document control

Tenancy Policy. Document control Tenancy Policy Document control 2018 2021 Policy approval April 2018 EDT Updating Tenancy Policy 2017-2018 Next review date April 2021 Author Neighbourhoods & Income Business Manager Responsible Executive/

More information

Date Date Date Date Date Date Date Name of GSO

Date Date Date Date Date Date Date Name of GSO 1507 DELEGATED POWERS REPORT NO. SUBJECT: West Hendon Regeneration Scheme Discretionary Home Loss Payments Control sheet All of the following actions MUST be completed at each stage of the process and

More information

Stephen Davy Peter Smith Architects

Stephen Davy Peter Smith Architects Stephen Davy Peter Smith Architects Stephen Davy Peter Smith Architects 21 Stephen Davy Peter Smith Architects Stephen Davy Peter Smith Architects 23 FIFTH FLOOR FOURTH FLOOR FIFTH FLOOR FOURTH FLOOR THIRD

More information

Submission July 2014 Response to the City of Cockburn Draft Housing Affordability and Diversity Strategy

Submission July 2014 Response to the City of Cockburn Draft Housing Affordability and Diversity Strategy Submission July 2014 Response to the City of Cockburn Draft Housing Affordability and Diversity Strategy Chantal Roberts Organisation Email Executive Officer Shelter WA eo@shelterwa.org.au About Shelter

More information

TOWN PLANNING: RESIDENTIAL

TOWN PLANNING: RESIDENTIAL TOWN PLANNING: RESIDENTIAL OUR CAPABILITIES The UK housing challenge The famous saying that an Englishman s home is his castle is under threat with the significant housing crisis that continues to grip

More information

Paradigm Housing Group Tenure Policy

Paradigm Housing Group Tenure Policy Paradigm Housing Group Tenure Policy April 2017 Policy Title Tenure Policy Policy statement Objective Background As a Private Registered Provider of homes, Paradigm is committed to letting our properties

More information

Paragraph 47 National Planning Policy Framework. rpsgroup.com/uk

Paragraph 47 National Planning Policy Framework. rpsgroup.com/uk To boost significantly the supply of housing, local planning authorities should use their evidence base to ensure that their Local Plan meets the full, objectively assessed needs for market and affordable

More information

Building more and better homes. Looking after you and your new home

Building more and better homes. Looking after you and your new home Building more and better homes Looking after you and your new home Issued September 2017 Looking after you and your new home While each of the estates that will be rebuilt is at different stages, we want

More information

Kensington Legion redevelopment: a case of NIMBY versus YIMBY

Kensington Legion redevelopment: a case of NIMBY versus YIMBY Kensington Legion redevelopment: a case of NIMBY versus YIMBY RICHARD WHITE More from Richard White (HTTP://CALGARYHERALD.COM/AUTHOR/RICHARD-WHITE) Published on: October 30, 2015 Last Updated: October

More information

SD00. Westbury Estate. Introduction and Summary to the Planning Application

SD00. Westbury Estate. Introduction and Summary to the Planning Application SD00 Westbury Estate Introduction and Summary to the Planning Application December 2017 Westbury Estate Team Tibbalds Planning and Urban Design Lead Consultant, Design Management and Planning Campbell

More information

KIDBROOKE VILLAGE PHASES 3, 5 & 6 A PLACE IN THE MAKING... MARCH 2015

KIDBROOKE VILLAGE PHASES 3, 5 & 6 A PLACE IN THE MAKING... MARCH 2015 KIDBROOKE VILLAGE PHASES 3, 5 & 6 A PLACE IN THE MAKING... MARCH 2015 1 EXECUTIVE SUMMARY WORKING WITH OUR PARTNERS, THE ROYAL BOROUGH OF GREENWICH & THE MAYOR OF LONDON, OUR ACHIEVEMENTS AT KIDBROOKE

More information

BIRMINGHAM DEVELOPMENT PLAN EXAMINATION 2014 MATTER E: GREEN BELT POLICY & THE LANGLEY SUE

BIRMINGHAM DEVELOPMENT PLAN EXAMINATION 2014 MATTER E: GREEN BELT POLICY & THE LANGLEY SUE BIRMINGHAM DEVELOPMENT PLAN EXAMINATION 2014 MATTER E: GREEN BELT POLICY & THE LANGLEY SUE STATEMENT BY SAVILLS ON BEHALF OF THE LANGLEY SUE CONSORTIUM SEPTEMBER 2014 Question 1.Does policy TP10 set out

More information

Urban Design Brief Dundas Street. London Affordable Housing Foundation. November Zelinka Priamo Ltd.

Urban Design Brief Dundas Street. London Affordable Housing Foundation. November Zelinka Priamo Ltd. Urban Design Brief 1039-1047 Dundas Street London Affordable Housing Foundation November 2017 Zelinka Priamo Ltd. TABLE OF CONTENTS Page No. INTRODUCTION... 3 SECTION 1 LAND USE PLANNING CONTEXT... 3 1.1

More information

Allocations and Lettings Policy

Allocations and Lettings Policy Date approved TBC Date of Next Review May 2016 Date of Last Review May 2015 Review Frequency Annually Type of document Policy Owner Name Jenny Spoor, Group Head of Neighbourhoods Job Title Approved by

More information